RC-CPU-24-026 Board Report - External Works Ferguslie Green Line Neighbourhood Centre

Renfrewshire Council · 11 December 2024
Back to Finance, Resources and Customer Services Policy Board — 11 December 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board
On:  11 December 2024
___________________________________________________________________
Report by: Director of Finance and Resources and the Chief Executive Services
___________________________________________________________________
Heading: Contract Award: External Works Ferguslie Green Line –
Neighbourhood Centre (RC-CPU-24-026)  
___________________________________________________________________
1. Summary
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract for External Works Ferguslie Green Line – Neighbourhood
Centre (RC-CPU-24-026) to P1 Solutions Ltd. 
1.2  The recommendation to award the Contract follows a procurement
exercise conducted in accordance with the Council’s Standing Orders
Relating to Contracts 1 January 2024 for a below Regulated (Works)
Contract using the below GPA Open Procedure. 
1.3 A Contract Strategy was approved by the Corporate Procurement
Manager and Head of Economy & Development Services on 5
November 2024.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board: 
2.1 Authorises the Head of Corporate Governance to award a Works
Contract in the form of SBCC Standard Building Contract with
Quantities for use in Scotland (SBC/Q/Scot), 2016 Edition, as
supplemented by the Employer’s Amendments, for External Works

Page 2

Ferguslie Green Line – Neighbourhood Centre (RC-CPU-24-026) to P1
Solutions Ltd; 
2.2 Authorises the Tendered Contract Sum (approved contract value) of
£588,389.12 excluding VAT.
2.3 Authorises the Date of Possession of the site for 20 January 2025 and
the Date for Completion of the works of 23 June 2025. Any changes to
these dates will be confirmed in the Council’s Letter of Acceptance.  
_________________________________________________________
3. Background
3.1 This procurement exercise is for the appointment of a contractor to
carry out the provision of a new and improved path network throughout
the site, with key gateway links; installation of an activity space; site
drainage; street lighting; site furniture; improvements to existing soft
landscaping and introduction of trees and shrubbery at a vacant site at
Bankfoot Road, Ferguslie Park.
3.2 A Prior Information Notice (PIN) was issued on the Public Contracts
Scotland portal on 9 August 2024 to gauge interest in the requirement. 
3.3                To initiate this procurement process, a Contract Notice was published
on the Public Contracts Scotland advertising portal on 5 November
2024. 
3.4 During the live tender period, twenty organisations expressed interest
in the tender.  By the closing date set for return of electronic tender
submissions, 10am on 27 November 2024, six organisations submitted
a response, two organisations declined to respond, and twelve
organisations failed to submit a response. 
3.5 In accordance with the Council’s Standing Order relating to Contracts
standing order 11.5, Tenderers were required to complete a Single
Procurement Document (SPD) to be submitted with their tender
submission. All six tender submissions were evaluated against a pre-
determined set of Criteria in the form of the SPD by representatives
from the following Council services: Chief Executive Service, the
Corporate Procurement Unit, Corporate Risk and Corporate Health &
Safety.
3.6  One tenderer submitted a qualified bid; however, the Council was not
willing to accept the qualifications to the bid and that tenderer
subsequently withdrew from the tender process.  The remaining five
tender submissions received complied with the minimum selection

Page 3

criteria of the SPD. The five tender submissions were each evaluated
against the Award Criteria of 60% Quality and 40% Price.
3.7 The scores relative to the Award Criteria for each of the five tender
submissions are noted below:
Tenderer Price
(40%)
Quality
(60%)
Total
(100%)
P1 Solutions Ltd 40.00% 47.25% 87.25%
Landscapes and Contracts
Limited 38.27% 41.25% 79.52%
Landcare Solutions
(Scotland) Limited 37.13% 33.75% 70.88%
MacKenzie Construction
Limited  32.52% 31.25% 63.77%
JH Civil Engineering
Limited 27.16% 34.25% 61.41% 
3.8 The evaluation of tender submissions received identified that the
submission by P1 Solutions Ltd was the most economically
advantageous tender.
3.9 The form of Contract is SBCC Standard Building Contract with
Quantities for use in Scotland (SBC/Q/Scot) 2016 Edition, as
supplemented by the Employer’s Amendments.
3.10 The funding for this Contract has been secured from the UK
Government's Shared Prosperity Fund and Scottish Government's
Place Based Investment Programme.
3.11 Community benefits were requested as part of the contract and P1
Solutions have offered the following community benefits: 
Community Benefit Outcome Description  No of People
/ Activity
S/NVQ (or equivalent) for  
• New Employee
• Existing Employee  
• Supply Chain Employee 
3
___________________________________________________________________
Implications of the Report
1. Financial – The Contract value of £588,389.12 for the 22 week
Contract will be funded through the secured funding from the UK

Page 4

Government's Shared Prosperity Fund (SPF) and Scottish
Government's Place Based Investment Programme and from the
Housing Revenue Account (HRA).   
Funding  Amount
Shared Prosperity Fund (SPF) £200,000
Scottish Government’s Place
Based Investment Programme. 
£280,000
Housing Revenue Account (HRA) £120,000 
The SPF funding was approved at the 23rd August 2022 Economy and
Regeneration Policy Board, an update to this paper was approved at
the 19th March 2024 Economy and Regeneration Policy Board. The
funding for the Place Based Investment Programme was approved at
the Economy and Regeneration Policy Board on the 5th November
2024. The anticipated Date of Possession of the site is 20th January
2025. 
2. HR & Organisational Development – None arising directly from this
report. 
3. Community/Council Planning –  
Place:
• Adopting a 'placeshaping' approach to developing our
communities - working together to maximise our collective
impact and influence across economic, social, physical, cultural
and environmental policies and practices.
• Demonstrating that Renfrewshire is a great place to grow up, a
place of opportunity for those that live and work here, and a
brilliant place for a day out.
Economy:
• Improving lives and securing wellbeing through a stronger,
inclusive and sustainable economy, being creative, imaginative
and linking opportunities to enhance the benefits for
Renfrewshire.
Living Our Values:
• Ensuring Renfrewshire Council delivers Best Value for our
citizens and customers, that we are a well governed, effective
organisation.

Page 5

4. Legal - The Procurement of this Contract was conducted as a below
Regulated (Works) Open Procedure in accordance with the Council’s
Standing Orders Relating to Contracts 1 January 2024.   
5. Property/Assets – This contract relates to a vacant site at Bankfoot
Road, Ferguslie Road. The contract will provide a new and improved
path network throughout the site, with key gateway links; installation of
an activity space; site drainage; street lighting; site furniture;
improvements to existing soft landscaping and introduction of trees and
shrubbery. 
6. Information Technology - None directly arising from this report.
7. Equality & Human Rights - None arising directly from this report.  
8. Health & Safety – P1 Solutions Ltd health and safety credentials were
evaluated by Corporate Health and Safety and met the Council’s
minimum requirements regarding health and safety.  
9. Procurement – The procurement procedures outlined within this report
ensure that the Council meets its statutory requirements in respect of
procedures, efficiency, and modern Government.
10. Risk – P1 Solutions Ltd insurances have been assessed and evaluated
to confirm that they meet the requirements regarding insurance risk.
11. Privacy Impact - None directly arising from this report.
12. Climate Risk – The level of impact associated with the External Works
– Ferguslie Green Line Neighbourhood Centre has been assessed
using the Scottish Government Sustainability Test and are considered
to be high risk.  P1 Solutions Ltd will be required to carry out the works
in a manner that minimises the impact their activities will have on the
environment. To mitigate the high risk P1 Solutions will:
• implement waste management plans to reduce, reuse and
recycle construction waste. 
• Establish monitoring programmes to track environmental
parameters and ensure there is regular reporting to promptly
address any adverse environmental impacts. 
13. Children’s Rights – None directly arising from this report.
14. Cosla Policy Position - None arising directly from this report.
_______________________________________________________

Page 6

List of Background Papers 
(a) Report by the Chief Executive to the Leadership Board on the 1st
December 2021: “The Making of Ferguslie – framework report and
place plan”. 
(b) Report by the Chief Executive to the Economy and Regeneration
Policy Board on the 23 May 2023: “The Making of Ferguslie –
Update”. 
(c) Report by the Chief Executive to the Economy and Regeneration
Policy Board on the 23rd May 2023: “Place Based Improvement
Programme 2024/25”. 
(d) Report by Chief Executive to the Economy and Regeneration Policy
Board on the 14th June 2022: “UK Shared Prosperity Fund”. 
(e) Report by Chief Executive to Economy and Regeneration Policy
Board on the 23rd August 2022 on the “UK Shared Prosperity Fund
Update”. 
(f) Report by the Chief Executive to the Economy and Regeneration
Policy Board on the 5th November 2024: “Placed Based
Improvement Programme 2024/2025”. 
(g) Report by the Chief Executive to the Economy and Regeneration
Policy Board on the 19th March 2024: “Regeneration Funding Bids
Update”. 
___________________________________________________________________ 
Author:          Aileen Ross, Procurement Adviser, aileen.ross@renfrewshire.gov.uk