ARGYLL AND BUTE COUNCIL                     OBAN LORN AND THE     
ISLES AREA COMMITTEE 
ROADS AND INFRASTRUCTURE                    12 JUNE 2024
SERVICES                     
TOBERMORY PLAY PARK – UPDATE REPORT No 2 
1.0 EXECUTIVE SUMMARY 
1.1 In August 2022, the Scottish Government confirmed a full 5 year funding package
to all Scottish Local Authorities from 2020/21 through to 2025/26.  Argyll and Bute
Council will receive a total of £938k for Play Park funding. 
1.2 A report was presented to the December 2022 EDI Committee outlining the Play
Park budget from the Scottish Government and the criteria which covered all of
Argyll and Bute’s 30 Council managed Play Parks. The Committee noted the
available funding for play park equipment and agreed the budget split for each of
the 4 administration areas which did not include the Lochgilphead Play Park and
Atlantis Play Park as they were relatively new and at that time needed no funding. 
1.3 Oban Lorn and the Isles (OLI) Area Committee received an update report in
September 2023 which noted the breakdown of engagement and consultation
responses across the Argyll and Bute area with the majority of responses
focusing on new/replacement equipment and agreed the relevant spend on
Tobermory Play Park at £33,500. All work must be completed by 31 March 2026
to ensure full funding is received. 
1.4 Previously in June 2016 a constituted group of local residents formed the
Tobermory Play Park Committee and entered into a formal agreement with the
Council whereby they raised money to replace old equipment and the Council
took on a 10 year maintenance agreement. This agreement runs out on 1 June
2026. 
RECOMMENDATIONS 
It is recommended that the Oban Lorn and the Isles Area Committee: 
• Note the engagement process and supportive work from local residents in
the Tobermory Area. 
• Note the suggestion that local residents will continue with a constituted
group with the option to take on the play park replacement works locally.

Page 2

• Note the Community Benefit work which has agreed a further £24k can be
added to the funding for the play park.

Page 3

ARGYLL AND BUTE COUNCIL                               OBAN LORN AND THE    
ISLES AREA COMMITTEE 
ROADS AND INFRASTRUCTURE                              12 JUNE 2024
SERVICES                     
TOBERMORY PLAY PARK – UPDATE REPORT No 2   
2.0 INTRODUCTION 
2.1 This report provides an update regarding the Tobermory Play Park engagement
work for the Oban Lorn and the Isles Area Committee. 
2.2 The report further outlines options available to potentially take the works
forward either in-house by the Council or, as per previous agreement, with the
local Tobermory Play Park Committee. 
2.3 Previously Argyll and Bute Council carried out an engagement survey across the
whole Council area in relation to play parks. This was well answered, however
feedback from the Tobermory area was that locally the community felt that they
could have been more involved. Subsequent meetings have taken place with local
residents which included a further survey which supported the initial findings as
well as a site visit where the local residents agreed to look at whether they would
take the play works on from the Council to replace and improve the area. At the
time of writing this report this is still being considered locally. 
2.4 There are however potential procurement issues as previous work in the Oban
area where a similar agreement was entered into proved costly for the Council
when materials were found to be substandard. This will require prolonged
discussions and agreements with the group to satisfy the Council that no
likelihood of extra post-delivery costs will be encountered. 
2.5 Whilst this is being considered as an option to allow the constituted group to take
on the works, it may be preferrable and more prudent to allow the group to have
a full say on what they want for the play park locally and go through the Council
tender. 
2.6 As part of tender processes for any works carried out across the Council,
community benefits are actively pursued by Officers within the Council. It was
highlighted that there are building works being carried out near to the Tobermory
play park and as part of this contract management process it was agreed that
£24k funding would also be allocated to support the Scottish Government play
park funding for the Tobermory play park. This brings a total of £57.5k which can
be used to replace equipment or if using the £24k build new equipment.

Page 4

3.0 RECOMMENDATIONS 
3.1  It is recommended that the Oban Lorn and the Isles Area Committee: 
• Note the engagement process and supportive work from local residents in
the Tobermory Area. 
• Note the suggestion that local residents will continue with a constituted
group with the option to take on the play park replacement works locally.
• Note the Community Benefit work which has agreed a further £24k can be
added to the funding for the play park. 
4.0 IMPLICATIONS 
4.1 Policy – This project will be delivered within the Procurement tendering process
however, as we have had two unsuccessful processes already as well as a
direct award failure members should note that this may well delay matters and
officers. 
4.2 Financial – funded from grant funding from Scottish Government and
community benefit funding of £24k. 
4.3  Legal – None known. 
4.4  HR – None known. 
4.5  Fairer Scotland Duty: None known 
4.5.1   Equalities - protected characteristics – engagement will take place with
appropriate groups, including the disability forum, to provide a positive impact
on our young people. 
4.5.2   Socio-economic Duty – None known. 
4.5.3 Islands – elements of renewal on all play parks, which therefore will not
adversely affect islands. 
4.6. Climate Change – we will endeavour to minimise carbon footprint of this project. 
4.7  Risk – Failure to deliver within the allotted Scottish Government timescales may
result in losing the budget allocated. 
4.8  Customer Service – the intention of this funding is to provide better facilities for
our customers. 
4.9  The Rights of the Child (UNCRC) – None known.

Page 5

Executive Director with responsibility for Roads and Infrastructure Services,
Kirsty Flanagan 
Policy Lead for Roads, Transport and Amenity Services
Councillor John Armour 
22 May 2024                                                  
For further information contact: 
Jim Smith, Head of Roads and Infrastructure Services
Jim.Smith@argyll-bute.gov.uk 
Hugh O’Neill, Network and Standards Manager 
Hugh.ONeill@argyll-bute.gov.uk