Minute of Special Meeting
Finance, Resources and Customer Services Policy Board 
Date Time Venue
Thursday, 23 May 2024 09:30 Microsoft Teams Meeting, 
Present: Councillor Fiona Airlie-Nicolson, Councillor Jacqueline Cameron, Provost Lorraine
Cameron, Councillor Graeme Clark, Councillor Audrey Doig, Councillor Chris Gilmour,
Councillor Edward Grady, Councillor Neill Graham, Councillor Robert Innes, Councillor Alec
Leishman, Councillor Bruce MacFarlane, Councillor Sam Mullin, Councillor Iain Nicolson,
Councillor John Shaw 
Chair
Councillor Shaw, Convener, presided. 
In Attendance
A MacArthur, Director of Finance & Resources; C Dalrymple, Head of Facilities and Property
Services,F Farrell, Technical Unit Programme Manager, and P MacIver and A Pearson,
both Project Managers (all Environment, Housing & Infrastructure); and C McCourt, Head
of Finance & Procurement, J Bowles, Corporate Procurement Manager, M Dunbar, Solicitor
and E Gray, Senior Committee Services Officer (all Finance & Resources). 
Webcasting of Meeting
Prior to the commencement of the meeting the Convener intimated that this meeting of the
Policy Board would be filmed for live or subsequent broadcast on the Council's internet site. 
Apology
Councillor Ann-Dowling. 
Declarations of Interest and Transparency Statements
There were no declarations of interest or transparency statements intimated prior to the
commencement of the meeting.

Page 2

Adjournment
The meeting adjourned at 9.40 am to due to technical issues. The meeting reconvened
at 12.30 pm.  
Sederunt
Councillor Mullin did not rejoin the meeting following the adjournment. 
1 Paisley Grammar School Community Campus (PGSCC) – Principal
Contractor (PC) Main Works (RC-CPU-21-247)
There was submitted a joint report by the Directors of Finance & Resources and
Environment, Housing & Infrastructure relative to the award of a main works package
for Paisley Grammar School Community Campus – Principal Contractor (PC) Main
Works (RC-CPU-21-247) to Galliford Try Construction Limited, T/A Morrison
Construction Scotland.  
DECIDED:  
(a) That the Head of Corporate Governance be authorised to award a Design & Build
Contract for the Paisley Grammar School Community Campus (PGSCC) – Principal
Contractor (PC) Main Works (RC-CPU-21-247) to Galliford Try Construction Limited,
T/A Morrison Construction Scotland;  
(b) That the award of the contract for the Contract Sum of £67,762,340.10 excluding
VAT be authorised;  
(c) That a contingency spend of £6,979,521, which equated to 10.3% of the Contract
Sum, be authorised;  
(d) That a total Approved Contract Value up to £74,741,861.10 excluding VAT, (which
was the total of the Contract Sum plus the contingency spend) be authorised;  
(e) That it be noted that the Date of Possession was anticipated to start on 17 June
2024, with the Date for Completion of the Works anticipated to be 12 June 2026 and
that the actual dates would be confirmed in the Council’s Letter of Acceptance to
Galliford Try Construction Limited, T/A Morrison Construction Scotland; and 
(f) That it be noted that the Contract included caps on liability for the following: (i) public
liability (in respect of property damage only) at the level of £25 million for each and
every claim; (ii) professional indemnity at the level of £10 million in the aggregate with
an automatic annual reinstatement; and (iii) for uninsurable risks, in the absence of any
Council or project metric to use, liability was capped at the contract sum.