Notice of Meeting and Agenda
Finance, Resources and Customer Services Policy Board 
Date Time Venue
Thursday, 23 May 2024 09:30 Microsoft Teams Meeting, 
Membership 
Councillor John Shaw (Convener):     Councillor Fiona Airlie-Nicolson (Depute Convener):    
Councillor Alison  Ann-Dowling:  Councillor Jacqueline Cameron:  Provost Lorraine Cameron: 
Councillor Graeme Clark:  Councillor Audrey Doig:  Councillor Chris Gilmour:  Councillor Edward
Grady:  Councillor Neill Graham:  Councillor Robert Innes:  Councillor Alec Leishman:  Councillor
Bruce MacFarlane:  Councillor Sam Mullin:  Councillor Iain Nicolson:   
Further Information - online meetings only
This meeting is on-line only but is a meeting which is open to members of the public by prior
arrangement. A copy of the agenda and reports for this meeting will be available for inspection
prior to the meeting at the Customer Service Centre, Renfrewshire House, Cotton Street, Paisley
and online at http://renfrewshire.cmis.uk.com/renfrewshire/CouncilandBoards.aspx 
For further information, please email democratic-services@renfrewshire.gov.uk 
Webcasting of Meeting
This meeting will be filmed for live or subsequent broadcast via the Council’s internet site – at
the start of the meeting the Convener will confirm if all or part of the meeting is being filmed.  To
find the webcast please navigate to 
https://renfrewshire.public-i.tv/core/portal/home 
MARK CONAGHAN
Head of Corporate Governance
Page 1 of 10

Page 2

17/05/2024 
Items of business      
Apologies
Apologies from members. 
Declarations of Interest and Transparency Statements
Members are asked to declare an interest or make a transparency
statement in any item(s) on the agenda and to provide a brief
explanation of the nature of the interest or the transparency statement. 
1 Paisley Grammar School Community Campus (PGSCC) –
Principal Contractor (PC) Main Works (RC-CPU-21-247)
Joint report by the Directors of Finance & Resources and Environment,
Housing & Infrastructure. 
3 - 10 
Page 2 of 10

Page 3

___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board 
On: 23 May 2024
___________________________________________________________________
Report by: Report by the Director of Finance and Resources and the Director
of Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Contract Award: Paisley Grammar School Community Campus
(PGSCC) – Principal Contractor (PC) Main Works (RC-CPU-21-247)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to obtain authority from the Finance,
Resources and Customer Services Policy Board to award a Main
Works package for Paisley Grammar School Community Campus
(PGSCC) – Principal Contractor (PC) Main Works (RC-CPU-21-247) to
Galliford Try Construction Limited, T/A Morrison Construction Scotland. 
1.2 On 15 June 2022, a report was taken to the Finance, Resources and
Customer Services Policy Board following a tender exercise to appoint
a contractor for pre-construction services and a Design and Build
Contract in respect of the Paisley Grammar School Community
Campus.  The report to that board set out that Galliford Try
Construction Limited, T/A Morrison Construction Scotland was the most
economically advantageous tenderer. At that Board the
recommendation was approved to award the Pre-Construction Services
Agreement for PGSCC to Galliford Try Construction Limited, T/A
Morrison Construction Scotland. It was noted that a further report would
be brought back to the Board once a more definite cost had been
established in respect of the build element of the PGSCC Project. 
Item 1
Page 3 of 10

Page 4

1.3 An option, at the Council’s discretion, to split the build element of the
contract into two contracts, an Enabling Works Contract followed by a
design and build contract, was permitted within the original
procurement exercise.  The Enabling Works Contract (ground
improvement works), was awarded on 15 March 2024, following
approval at this board on 8 February 2024. 
1.4 A Contract Strategy addendum was approved by the Strategic
Commercial and Procurement Manager and the Head of Property
Services on 5 November 2021, this was to amend and update the
Contract Strategy approved on 7 September 2021 for Paisley Grammar
Community Campus Principal Contractor.  This strategy set out the
procurement approach to procure a Principal Contractor for the Paisley
Grammar School Community Campus project for both pre-construction
services and the construction itself.
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Finance, Resources and Customer Services
Policy Board: 
(a) Authorises the Head of Corporate Governance to award a Design &
Build Contract for the Paisley Grammar School Community Campus
(PGSCC) – Principal Contractor (PC) Main Works (RC-CPU-21-247) to
Galliford Try Construction Limited, T/A Morrison Construction Scotland; 
(b) Authorises the award of the Contract for the Contract Sum of
£67,762,340.10 excluding VAT; 
(c) Authorises a contingency spend of £6,979,521 which equates to 10.3%
of the Contract Sum; 
(d) Authorises a total Approved Contract Value up to £74,741,861.10
excluding VAT, (which is the total of the Contract Sum plus the
contingency spend); 
(e) Notes that the Date of Possession is anticipated to start on 17 June
2024, with the Date for Completion of the Works anticipated to be 12
June 2026. The actual dates will be confirmed in the Council’s Letter of
Acceptance to Galliford Try Construction Limited, T/A Morrison
Construction Scotland.
 
(f) Notes that the Contract includes caps on liability for the following:
a. public liability (in respect of property damage only) at the level of
£25 million for each and every claim.
Page 4 of 10

Page 5

b. professional indemnity at the level of £10 million in the aggregate
with an automatic annual reinstatement.
c.   for uninsurable risks, in the absence of any Council or project metric
to use, liability is capped at the contract sum.
__________________________________________________________________
3. Background
3.1  Renfrewshire Council requires to replace the existing Paisley Grammar
School and seeks to integrate the school with both the local community
and enterprise organisations to form a new Paisley Grammar School
Community Campus.
On 15 June 2022 the Finance, Resources and Customer Services
Policy Board approved the recommendation to award a Contract for
Pre-Construction Services Agreement for Paisley Grammar School
Community Campus (PGSCC).  The report noted that a further report
would be brought to the Finance, Resources and Customer Services
Policy Board seeking approval to enter into the Design and Build
Contract with Galliford Try Construction Limited T/A Morrison
Construction Scotland.
3.2 At the time of the original tender, the tender exercise was being carried
out against a background of a very challenging market place with
fluctuating costs in labour and material both post COVID and post
Brexit.  There was recognition therefore that it would be unreasonable
to expect Contractors to tender a fixed price for construction works that
were not yet designed and would not commence until 2 years post-
contract award.  This was balanced against a very real benefit of early
contractor engagement in respect of buildability and delivery of the
school. 
3.3 The original tender exercise was carried out on the basis that
Tenderers submit a defined price for Pre-Construction Services and
that they also tendered a selection of key preliminaries items,
overheads and profit in respect of the construction works which would
be applied to an estimated construction cost.  This ensured that these
elements were competitively tendered.  As per the rules of the Pre-
Construction Services contract, the Contractor had to competitively
tender the various work packages to their supply chain to ensure best
value for the Council.    
Page 5 of 10

Page 6

This was conducted as an open book procurement process with the
Council’s Property Services and the externally appointed cost manager 
reviewing and confirming the costs.  Pricing of remaining preliminaries
items was assessed by the externally appointed cost manager by
benchmarking against other similar projects to verify value for money. 
The procurement process undertaken by the Contractor produced the
actual construction cost to which preliminaries, overheads and profit
derived from the original procurement exercise are applied to identify
the Contract Sum for the main works. 
3.4 As the board will be aware, the PGSCC is being delivered against a
challenging funding programme and it was established that instead of
awarding one Design and Build Contract, utilising the Council’s option
to instruct an Enabling Works Contract in advance of the full design and
build contract would assist in meeting that programme.  The Enabling
Works Contract, largely ground improvement works, was awarded on
15 March 2024, following approval at this board on 8 February 2024.
3.5 This recommendation is to enter the final phase of this project, a
Design and Build Contract with Galliford Try Construction Limited, T/A
Morrison Construction Scotland to construct the new Paisley Grammar
School Community Campus.  The appointed Multi-Disciplinary Design
Team (MDDT) contract will be novated to Galliford Try Construction
Limited, T/A Morrison Construction Scotland.  The appointed
Contractor and their design team will deliver Renfrewshire’s first school
building to be constructed to Passivhaus standard.  This methodology
was adopted to comply with the Scottish Futures Trust’s requirement
for LEIP Phase 2 funded schools to be constructed to a high level of
quality with low levels of energy consumption during its life cycle.  
3.6   The form of Design and Build Contract will be SBCC Design and Build
Contact for use in Scotland 2016 edition, accompanied with bespoke
Employer’s Amendments and Preliminaries. 
___________________________________________________________________
Implications of the Report
1. Financial – The value of the Main Works Contract will be up to
£74,741,861.10, including a contingency allowance of £6,979,521, and
exclusive of VAT.  This is part-funded by the Scottish Futures Trust
within the Stage 2 Learning Estate Investment Programme (LEIP) and
the Council’s Non-Housing Capital Programme. 
Page 6 of 10

Page 7

2. HR & Organisational Development - None arising directly from this
report. 
3. Community/Council Planning –  
 Our Renfrewshire is fair - Tenderers were assessed within Award
Criteria regarding their approach to ensuring fair working practices
throughout their organisation and supply chain, i.e., payment of the
living wage, training and development opportunities, etc. 
 Reshaping our place, our economy and our future - The work from
the design to the main works will create many employment
opportunities across Renfrewshire.  The Community Campus itself
will redevelop an empty space and it will provide a base for learning
and development for current and future generations.    
 Building strong, safe and resilient communities - The new Paisley
Grammar not only operates as a school; it will also provide facilities
for use by the community and partner organisations. This will help
nurture and bring communities together.   
 Tackling inequality, ensuring opportunities for all - The work and
objectives of this project have the power to tackle inequalities that
exist in Renfrewshire throughout all communities.  It has the ability
to deliver opportunities for all, through Community Benefits and the
wider work of the project.   
 Creating a sustainable Renfrewshire for all to enjoy - The new
Paisley Grammar School Community Campus will provide a fresh
new learning base for over a thousand young people with internal
environmental quality of a high standard.  It will give back to the
communities that it serves by providing space for public use in a
sustainably designed, low energy building.
 Working together to improve outcomes - The new Paisley Grammar
School Community Campus will deliver many outcomes throughout
its lifetime through the strengthening of the partnership working
between school and community, providing good quality services,
and new ICT developments and opportunities.   
4. Legal - The procurement of this contract was conducted in accordance
with the Competitive Procedure with Negotiation under the Public
Contracts (Scotland) Regulations 2015 and the Council’s Standing
Orders Relating to Contracts.  
Page 7 of 10

Page 8

The original procurement was for a single Principal Contractor for both
pre-construction services and the construction itself.   The appointed
Multi-Disciplinary Design Team contract will be novated to the
Contractor. 
5. Property/Assets – The Council identified the construction of a new
Paisley Grammar Community Campus as its learning estate investment
priority in May 2019. The Council’s investment in its learning estate
offers the opportunity for a place-based approach to local outcomes,
integrating local services to support communities. 
6. Information Technology - None arising directly from this report. 
7. Equality & Human Rights - The recommendations contained within
this report have been assessed in relation to their impact on equalities
and human rights. No negative impacts on equality groups or potential
for infringement of individuals’ human rights have been identified
arising from the recommendations contained in the report.   If required
following implementation, the actual impact of the recommendations
and the mitigating actions will be reviewed and monitored, and the
results of the assessment will be published on the Council’s website.   
8. Health & Safety – Galliford Try Construction Limited, T/A Morrison
Construction Scotland’s health and safety credentials were assessed in
the original procurement exercise and met the Council’s requirements
regarding health and safety.
9. Procurement – The original procurement was for a single Principal
Contractor for both pre-construction services and the construction itself.  
10. Risk – Galliford Try Construction Limited, T/A Morrison Construction
Scotland insurances were assessed in the original procurement
exercise and met the requirements regarding insurable risk, including
noted liability caps.   
There is an interface with the Advanced Manufacturing Innovation
District Scotland (AMIDS) South contract and this project.  This is
currently being managed through regular meetings of the respective
teams delivering each project to mitigate associated risks. 
11. Privacy Impact – None arising directly from this report. 
12. Cosla Policy Position – None have arisen or are anticipated.  
Page 8 of 10

Page 9

13. Climate Risk - Tackling Climate Change and working towards Net Zero
have been addressed throughout the Paisley Grammar School
Community Campus Project.  This will be the first Passivhaus School in
Renfrewshire, which is supporting the Councils vision and work of
becoming net zero by 2030.  
The environmental impacts considered are broad and range from the
disposal of waste generated from the works being carried out to the
types of vehicles and machinery that will be used on site.  The
Contractor will be required to consider emissions from their vehicles
when working on site and to switch engines off when not in use to
prevent unnecessary emissions.   
Galliford Try Construction Limited, T/A Morrison Construction Scotland
set out in their tender response an aligned approach to Renfrewshire
Council’s Net Zero Strategy with opportunities that include:
 “Reduction in Emissions – Using One Click LCA we can report on
embodied carbon for the project, and our strategy to invest and
promote the use of a local supply chain will help to keep the
projects carbon footprint down. 
 We propose to explore opportunities with the Advanced
Manufacturing District Scotland (AMIDS) to understand any current
and future opportunities to connect to their district heating network
(BHN). 
 Waste Reduction - following our Design for Manufacture and
Assembly (DfMA) approach this will reduce the amount of
construction waste;
 Reduction in Energy Use and Business Travel – our strategy to
invest and promote the use of a local Supply Chain will help to
reduce our carbon footprint; and
 Climate Change Sub-Committee – We will offer up our skilled team
to be involved in your Climate Change Sub-Committee and support
your Youth Assembly through active participation.” 
The level of impact associated with provision of these works has been
assessed using the Scottish Government Sustainability Test and is
considered to be overall low risk. 
Page 9 of 10

Page 10

___________________________________________________________________
List of Background Papers 
1) Contract Authorisation Report - Paisley Grammar School Community Campus
Principal Contractor, approved by the Finance, Resources and Customer
Services Policy Board on 15 June 2022. 
2) Contract Award: Paisley Grammar School Community Campus (PGSCC) –
Principal Contractor (PC) Enabling Works, approved by the Finance,
Resources and Customer Services Policy Board on 8 February 2024.
___________________________________________________________________ 
Author:         Laura Gillan, Strategic Category Manager, Corporate procurement unit,