Page 1

PUBLIC 
___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board 
On:  10 September 2026
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure 
___________________________________________________________________
Heading: Contract Authorisation Report: New Build Housing Design and Build at
Foxbar Rivers, Paisley (RC-CPU-24-226)
___________________________________________________________________
1. Summary
1.1  The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Works
Contract for New Build Housing Design and Build at Foxbar Rivers,
Paisley (RC-CPU-24-226) to A.S. Homes (Scotland) Limited (Company
Number SC371651).  
1.2 The recommendation to award the Contract follows a procurement
exercise which was conducted as a Mini Competition under Lot 4 –
Development of 36-80 Units of the Scotland Excel New Build
Residential Construction Framework Agreement (Reference 2121). 
1.3 A Contract Strategy was approved by the Corporate Procurement
Manager on 19 February 2026 and Head of Housing Services on 24
February 2026.
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

PUBLIC
2.1 Authorises the Head of Corporate Governance to award a Contract for
New Build Housing Design and Build at Foxbar Rivers, Paisley
reference RC-CPU-24-226 to A.S. Homes (Scotland) Limited following
a Mini Competition under Lot 4 (Development of 36-80 Units) of the
Scotland Excel New Build Residential Construction Framework
Agreement (Reference 2121), which is subject to the Council receiving
a sufficient offer of Scottish Government Affordable Housing Grant
funding that Council officers determine is sufficient to support the
business plan for the development; 
2.2 Authorises a Contract Sum of £9,774,003.63 excluding VAT; 
2.3 Notes the Date of Possession of the Site will be confirmed in the
Council’s Letter of Acceptance.  The Date for Completion of Works is
105 weeks (40 weeks for design and 65 weeks for Construction). 
2.4 Notes the award of this Contract requires the provision of the Sub
Consultant/Contractor Collateral Warranty as indicated within the
tender documentation.
_________________________________________________________
3. Background
3.1 The aim of the Contract is to provide high quality new build housing for
social rent within the Foxbar Rivers area of Paisley.  The Contract will
be compliant with the Scottish Government affordable housing grant
criteria.  Renfrewshire Council seeks to appoint a Design and Build
Contractor to carry out the design and construction of a residential
development at Foxbar Rivers, Paisley consisting of 45 units.  The site
for this residential development is Foxbar Rivers, Paisley.  The
appointed Contractor will be responsible for the Design and Build of 24
cottage flats and 21 houses with associated landscaping and fencing
within the development.   
3.2 The costs for this project will be partly met by grant funding from the
Scottish Government (as provided for in Renfrewshire’s Strategic
Housing Investment Plan 2026/2027 – 2030/2031 and draft Local
Housing Strategy Plan 2023 – 2028) and partly from the Council’s
Housing Revenue Account Capital Investment Plan.  The minimum
benchmark grant is based on the proposed number of bedspaces and
is £5,187,375. The Council has applied for additional grant funding,
based on the construction cost and the rental income. The Scottish
Government is carrying out an appraisal, and it is anticipated the grant
awarded will be above the minimum benchmark grant.

Page 3

PUBLIC
This contract will only be awarded if Council officers determine that the
grant provided by the Scottish Government Affordable Housing Grant
funding is sufficient to support the business plan.
3.3 The Scotland Excel New Build Residential Construction Framework
Agreement (Reference 2121) (Framework) was identified as a suitable
route for this procurement.      
3.4 The Council invited all 11 Contractors appointed to Lot 4 Development
of 36-80 Units of the Framework to participate in the Mini Competition
for 45-unit development via the Public Contracts Scotland – Tender
Portal (PCS-T) on Tuesday 24 February 2026 with the tender
documentation available for downloading from the PCS-Tender portal
from the same date.  
3.5 By the closing date for the return of electronic tender submissions, 12
noon, Tuesday 26 May 2026, 4 Contractors submitted a response, 5
Contractors Declined and 2 Contractors failed to reply.    
3.6 The 4 Tender Submissions continue to meet the requirements of the
Single Procurement Document (SPD) they completed when applying
for a place on the Framework. 
3.7 The Tender Submissions were then evaluated against the mini
competition Award Criteria of 55% Quality and 45% Price.  
3.8 The scores relative to the Award Criteria for this Tender are noted
below: 
Price
(45%)
Quality
(55%)
Total
(100%)
1 A.S. Homes (Scotland) Limited
(Company Number SC371651) 45.00% 54.00% 99.00%
2 JR Construction (Scotland) Limited
(Company Number SC534950) 42.35% 53.00% 95.35%
3 Ogilvie Construction Limited
(Company Number SC069644) 42.94% 49.05% 91.99%
4 Clark Contracts Limited (Company
Number SC088490) 41.59% 50.20% 91.79% 
3.9 Following the tender evaluation in accordance with the criteria set out in
the procurement documents, the bid received by A.S. Homes
(Scotland) Limited was within the benchmark forecasts of the Scottish
Government Grant funding mechanism and was therefore deemed to
be value for money.

Page 4

PUBLIC
3.10 In accordance with the Framework requirements for Call-off Contracts,
the Terms and Conditions being utilised are SBCC Design and Build
Contract for Use in Scotland 2016 Edition (DB/Scot) supplemented by
Employer’s Amendments.
3.11  Mandatory Community Benefits were included as a condition of this
Contract which A.S. Homes (Scotland) Limited confirmed they would
adhere to. The commitment was to deliver five Employment
Opportunities.  The mandated Community Benefits are detailed below: 
3.12 In addition to the Mandatory Community Benefits requested, evaluated
Community Benefits were requested and A.S. Homes (Scotland)
Limited confirmed that the following Community Benefits would be
made available to the Council for this Contract: 
Mandated Community Benefits   No of people
/ activity
Job for an unemployed individual from a Priority Group 5
Job for an unemployed individual 4
Modern Apprenticeship 3
Graduate  2
Community Benefit Description  No of
People /
Activity
Work Experience Placement for an individual 16+ years
of age (who is not currently in employment, education or
training) and preferably from an identified priority group. 
10
Work Experience Placement for an individual aged 14+
years of age (and currently in full-time education) and
preferably from an identified priority group. 
8
S/NVQ (or equivalent) for    
•  New Tenderer Employee working on this contract  
•  New Supply Chain Employee working on this contract 
5
Industry Awareness Events 
•  Schools  
•  Invest in Renfrewshire – Employability  
•  Further Education 
5
Industry Skill Transfer to Schools. 4
Business advice/support to an SME /Social Enterprise/
Voluntary organisation
6
Event to promote supply chain opportunities 4
Financial Support for a Social Enterprise within
Renfrewshire
3
Non-financial support for a Social Enterprise within
Renfrewshire
2

Page 5

PUBLIC
___________________________________________________________________
Implications of the Report
1. Financial – The total approved contract value is £9,774,003.63. The
cost of this Contract will be partly met by the Housing Revenue Account
(HRA) and partly from Grant funding as follows:
Grant Funding (minimum) £5,187,375
Housing Revenue Account (HRA) (maximum) £4,586,628 
The contract will only be awarded if Council officers determine that the
grant provided by the Scottish Government Affordable Housing Grant
funding is sufficient to support the business plan. 
2. HR & Organisational Development – None directly arising from this
report.   
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable
• Our Renfrewshire is well – supporting the wellness and resilience
of our citizens and communities 
• Our Renfrewshire is fair - addressing the inequalities which limit life
chances
• Our Renfrewshire is safe – protecting vulnerable people and
working together to manage the risk of harm. 
• Place
- Ensuring Renfrewshire has the supply of green, high-quality
cross-tenure homes in the right places to meet current and
future demand.
- Working together to ensure our neighbourhoods are safe,
vibrant, and attractive places to live.
- Demonstrating that Renfrewshire is a great place to live, work
and visit. 
- Developing our relationship with and working alongside
communities on the decisions that affect them. 
• Economy
- Linking opportunities to enhance economic benefits for
Renfrewshire.
- Creating sustainable employment opportunities, ensuring that all
people can benefit from the inclusive growth in Renfrewshire.
- Supporting people into Fair Work.

Page 6

PUBLIC
- Matching skills and opportunities across Renfrewshire with the
opportunities available in Renfrewshire.
• Fair
- Reducing inequalities in Renfrewshire. 
• Green 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.  
- Integrating climate considerations into our long-term strategic
planning as an organisation.   
• Living Our Values
- Delivering Best Value for our citizens and customers 
4. Legal - The procurement of this Contract was conducted in accordance
with the requirements following a Mini Competition under Lot 4 of the
Scotland Excel New Build Residential Construction Framework
Agreement (Reference 2121) and the Renfrewshire Council Standing
Orders Relating to Contracts. The award is also subject to sufficient
Grant Funding being made available to support the development. 
5. Property/Assets - This Contract will ensure that the Council fulfils its
investment in the area as part of the Council’s New Build Housing
Programme: 
• Renfrewshire’s Draft Local Housing Strategy 2022-2027, and 
• Renfrewshire’s Strategic Housing Investment Plan 2022 – 2027. 
6. Information Technology – None directly arising from this report.    
7. Equality & Human Rights - None directly arising from this report.  
8. Health & Safety - A.S. Homes (Scotland) Limited health and safety
credentials were evaluated by Corporate Health and Safety and met
the Council’s requirements regarding health and safety.  
9. Procurement – The procurement procedures outlined within this report
ensures that the Council meets its statutory requirements in respect of
procurement procedures, efficiency, and modern Government.  
10. Risk - A.S. Homes (Scotland) Limited insurances have been assessed
and evaluated to confirm that they meet the requirements regarding
insurance risk.
11. Privacy Impact - None directly arising from this report.

Page 7

PUBLIC
12. Climate Risk – The level of impact associated with the provision of
these works have been assessed using the Scottish Government
Sustainability Test and is considered High Risk: 
To mitigate against the High Risk, the Contractor will: 
• Introduce a no-idling policy for all deliveries, subcontractors and
plant. 
• Replace 20% of small plant/tools with electric alternatives. 
• Switch site compound and A. S. Homes (Scotland) Limited office
to a green electricity tariff. 
• Begin monthly carbon monitoring (fuel, waste, transport).  
• Include carbon reduction clauses in all major subcontract
packaging. 
• Begin annual staff training on low-carbon construction and PAS
2080 principles.  
13. Children’s Rights – None directly arising from this report.
14. Cosla Policy Position – None directly arising from this report.
_________________________________________________________
List of Background Papers 
(a)  None 
___________________________________________________________________ 
Author:          Kevin Milliken, Senior Procurement Specialist,
kevin.milliken@renfrewshire.gov.uk