Renfrewshire Council 
Environment, Housing & Infrastructure 
Internal Service Provider 
Building Services 
Three Year Business Plan 
2026/7 (year 1) to 2028/9 (Year 3)

Page 2

Page 2 of 33 
PUBLIC 
Contents          Page(s) 
Executive Summary         4 
Section 1.0 – Overall Business Context 
1.1 The Council’s Commitment to Building Services      5 
1.2 Building Services Mission Statement and Key Service Standards   7 
1.3 How do we achieve the Key Standards?            9 
1.4 Building Services core functions, services provided and not provided  10 
1.5 Building Services Key Performance Indicator (KPI) Priorities   12 
Section 2.0 – Service Improvement Activities and Outcome Updates  15 
2.1 Trade Operative Productivity Analysis                                                               16 
2.2 Financial Productivity level Analysis                    16 
2.3 Cost per job Housing and Non-Housing                                                             17 
2.4 Work Portfolio Demand and Delivery Profiling                                                   18 
2.5 Housing Repairs Diagnosis, Categorisation and Scheduling             19       
2.6 Building Services Staff Support                                                        20
2.7 Building Services Management Structure/s                                                        22 
2.8 Business Unit 1 - Planned and Responsive Repairs     23 
2.9 Business Unit 2 - Void House Repairs                                                               23 
2.10 Business Unit 3 – Compliance       24
2.11 Business Unit 4 – Contracts and Planned works     24 
2.12 Building Services Subcontractor Subcontractors                                             24 
2.13 Internal Customer Service Centre                                                                    25

Page 3

Page 3 of 33 
PUBLIC 
Section 3.0 – Building Services Financial Projections   
3.1 Expenditure           25
3.2 Income           26 
Section 4.0 – Building Services Hourly Labour Recharge Rates in 2025/26  
4.1 Charging Mechanism         27
4.2 Recharge Rates 2026/27        28 
Section 5.0 – Workforce 
5.1  Workforce Composition, progression and planning    29
5.2  Adult Apprentice programme       31
5.3  Further and Higher Education        31
5.4  Working with local Colleges and other agencies.      32
5.5    Upskilling and re-skilling        32 
Section 6 – Conclusion         33

Page 4

Page 4 of 33 
PUBLIC
Executive Summary 
Renfrewshire Council’s Building Services is a vital internal provider, delivering
responsive, planned, and compliance-based property maintenance across the
Council’s housing and public building estate. This three-year Business Plan (2026–
2029) sets out a clear roadmap for service delivery, improvement, and
transformation, aligned with the Council’s strategic objectives and values.
Key Achievements to Date
• Delivered over 103,000 jobs in 2025/26 with a turnover of £25.25 million
(excluding Kitchens and Boiler programme) 
• Maintained productivity above the national average (4.8 jobs/per operative per
day vs. industry average of 4.5).
• Achieved high compliance in gas and electrical safety, with 99.9% of gas
certificates issued on time.
• Embedded a strong culture of workforce development, with 24 apprentices
currently on the apprenticeship programme.
Strategic Priorities (2026–2029)
• Service Excellence: Improve customer satisfaction through better
diagnostics, appointment systems, and first-time fix rates.
• Workforce Planning: continue to address an ageing workforce through
succession planning, apprenticeships, and upskilling.
• Digital Transformation: Upgrade the WorkHub system to enhance
scheduling, reporting, and performance tracking.
• Financial Sustainability: Maintain cost-effective operations through strategic
and timeous budget monitoring.
• Sustainability: Support the Council’s Net Zero agenda through energy-
efficient repairs wherever possible.
Challenges Ahead
• High volumes of emergency repairs. For 2025/26 - 34% of Housing repairs
17% of public buildings repairs) which in turn limits planned work efficiency.
• System limitations affecting KPI expansion and real-time performance
analytics.
• Introduction of Awaab’s Law in October 2026 (should Building Services be
required to assist Housing Services).

Page 5

Page 5 of 33 
PUBLIC
Our Commitment
Building Services remains committed to delivering a high quality, customer focused,
and value for money service. This plan outlines how we will adapt to future demands,
invest in our people, and continue to provide essential services that keep
Renfrewshire’s homes and public buildings safe, compliant, and resilient. 
1.0 Overall Business Context 
1.1 The Council’s Commitment to Building Services 
Renfrewshire Council is committed to ensuring that it provides a high quality, internal
service provider with regards to the repairs and maintenance service across both
council houses and the wider public building portfolio. 
This commitment comes from the highest levels of the organisation including the
Chief Executive, Director of Environment, Housing and Infrastructure (EH&I) and the
wider Corporate Management Team (CMT). This includes Corporately for issues like
ICT, Finance and HR. 
Gordon McNeil, Director of Environment, Housing and Infrastructure outlined his
commitment by stating: 
“An Internal Service provider is essential to allow Renfrewshire Council to
react quickly to emergencies, take ownership of problems and to react swiftly
and decisively in the face of challenge. As the Director, I have committed to
maintaining this service, growing it as required and ensuring we deliver a high
level of service and “right first time” approach to repairs, maintenance and
compliance work.” 
Whilst this is noted to be a large commitment, this is required to allow the Council to
provide Best Value, align with the Corporate Objectives, fulfil the Council values and
more importantly to allow Renfrewshire Council to react swiftly in the time of a crisis. 
Within Environment, Housing and Infrastructure, there is a commitment from
Housing Services to continue to use the internal service provider as the main
contractor for the repairs and maintenance service. This will ensure a steady flow of
appropriate work (reactive and capital) to allow appropriate planning within the 3-
yearly business plan in relation to trades/workload and workforce planning. This will
tie in and align with the Housing Services 30-year plan. 
Senior Management within Building Services will continue to commit to delivering a
high level of service for clients and stakeholders. This will include the continued
recruitment of staff, “growing our own” staff via apprenticeships and delivering the
continued training as legislation and maintenance requirements continue to evolve.

Page 6

Page 6 of 33 
PUBLIC 
We will continue to strive for improvement and monitor this via the EH&I Service
Improvement Plan (SIP), through productivity monitoring and by ensuring
appropriate Key Performance Indicators (KPIs) are implemented and met. 
One of the key commitments is to keep residents, communities and members of the
public safe, therefore we will continue to visit emergencies and make safe anything
that is deemed as dangerous. 
Building Services are essential to Renfrewshire Council, especially during a crisis
e.g. Storm Eowyn in January 2025 which brought the whole country to a complete
standstill and led to severe damage across the Renfrewshire estate. Building
Services worked throughout the weekend/nights to ensure the safety of the residents
and that the schools and public buildings could open safely on the Monday morning.
This shows the commitment and value that Building Services provides to the local
community of Renfrewshire. 
In addition, it is highly unlikely that any private contractor could have responded as
quickly with sufficient resources to cover all of the works required within the
timescales. It is also true that the costs of an external contractor for emergency
works at very short notice over a weekend would have been extremely expensive.   
Finally, there is a strong commitment across EH&I that Housing Services, Soft FM,
Technical Services and Building Services will work together, collaborate, and deliver
a high-quality repairs and maintenance service for Renfrewshire Council. 
1.2  Building Services’ Mission Statement and Key Service Standards 
To provide a high quality, customer focused and cost-effective property
repairs and maintenance service for Renfrewshire residents and visitors.
1.2.1 Building Services organisational values are:
• To strive for high quality service delivery,
• To ensure a “right first time” approach where possible 
• Provide our customers with a flexible responsive repairs service which reflects
their needs and expectations,
• Commit to achieving continuous improvement across all areas of service
delivery.
• Support and encourage our employees by providing development opportunities
such as adult and youth apprenticeships, up-skilling and multi-skilling, toolbox
talks and training courses.
1.2.2  Our business aims and objectives are derived from our values and
incorporate three main themes:

Page 7

Page 7 of 33 
PUBLIC
• Improving customer service and quality, 
• Increase productivity, efficiency, and value for money,
• Enhance employee development, communication, and safety.
Building Services is an integral part of the comprehensive Facilities and Property
Services Division within Renfrewshire Council. Building Services mission statement
and key service standards detailed above are aligned to the overall aims and
objectives of the Facilities and Property Service and Renfrewshire Council’s mission
and values as detailed in the diagram below.

Page 8

Page 8 of 33 
PUBLIC 
Renfrewshire Council’s Mission  
We will achieve our vision by showing that we are proud to work for Renfrewshire Council and for making
decisions based on what is best for people who live and work in Renfrewshire. We are committed to
creating a sustainable economy, society and environment that will benefit future generations. 
Renfrewshire Council Values   
- We are fair. We treat each other and everyone we deal with respectfully and work hard to build trust in
Renfrewshire Council.  
- We are helpful. We care about getting things right and are always approachable.    
- We are great collaborators. We work as one team and with people who care about this place.    
- We value learning to help us innovate, improve, and deliver better services. 
The vison and priorities of Facilities and Property Services reflect the needs at a departmental level.         
“We work together to create, build, repair, maintain, open/close, clean and improve the built
environment for the communities and residents of Renfrewshire”. 
Overarching priorities for Facilities and Property Services in 2025/26: 
- Focus on the recruitment and retention of staff. 
- Focus on absence management, PDP’s and workforce planning/succession planning cross Facilities and
Property Services. 
Building Services priorities for 2026/27: 
- provide stability across Building Services through staff retention, workforce flexibility and succession
planning whilst growing the workforce of the future. 
- Complete and ratify a robust business plan that looks at the short medium and long term for Building
Services. 
- To increase the overall volume of work by carrying out works for Technical Services, Hard FM, Social Work,
and Children’s Services.

Page 9

Page 9 of 33 
PUBLIC
1.3 How do we achieve the Key Standards? 
Building Services aims to achieve the key Service Standards by
comprehensively looking at the individual aspects of the service and to aspire to
achieve the following: 
1.3.1  To improve customer service and quality we will:
• Work with our partners to deliver works programmes that reflect their business
needs – Programmed repairs (P/P9, D/9)
• Undertake repairs using the correct trade skills and materials on a first visit
basis - Emergencies (E), Right to Repair (Q same day), Right to repair (Q),
Urgent (U5), 
• Provide a flexible customer appointment system that provides options such as
AM or PM, school run flexibility, text reminders - Routine repair (A), % of
appointment kept. 
Section 1.5 provides more details of the KPI performance tracking across all
categories of repairs. Additional categories of repairs maybe required in the future to
better suit the type of future work in conjunction with the ambition to move to a more
planned repairs service. We will continue to work with our colleagues in Housing
Services and Hard FM as the systems development moves forward to explore the
additional KPI category. This will allow repairs that take longer than 15 days but
would not be appropriate to extend out to 90 days to be measured more accurately.
As an example, this would include roofing works that may contain scaffolding. 
KPIs have been introduced for compliance works in the Public Building environment. 
1.3.2  We will increase productivity, efficiency, and value for money by: 
• Continually reviewing our resource inputs, business operating costs and
outputs to ensure value for money in service delivery,
• Increasing productivity by using modern working practices and effective job
scheduling,
• Maximising the use and benefit of technology across the business,
• Benchmarking Building Services with similar service providers and seeking
efficiencies, 
The Service continuously reviews costs across all of the business areas and ensure
that they are correct and pursue any cost reductions to ensure best value across all
service delivery aspects. More detail is provided in section 2.3. 
Productivity is being monitored weekly and has been in place since November 2023.
The tracking across the whole financial year has shown that the productivity
fluctuates across the year due to public holidays, annual leave, weather, seasons etc

Page 10

Page 10 of 33 
PUBLIC
but the average across 2025/26 was 4.8 jobs per operative per day which is above
the industry average of 4.5. 
1.3.3  We will enhance employee development, communication, and safety by:
• Supporting our employees in learning and development,
• Supporting and embracing change by encouraging employee involvement,
• Promoting and encouraging effective communication with employees and their
representatives,
• Providing a safe working environment for our employees. 
1.3.4  Building Services stakeholders and Partners are: 
• Residents and council House tenants
• Public Buildings users
• Council employees
• Housing Services
• Hard FM
• Technical Services 
• Children’s Services
• Social Work 
1.4 Building Services core functions, services provided and not provided. 
Building Services core business is the repair and maintenance of council owned
properties in Renfrewshire. To ensure full compliance with legislation and includes all
council houses, schools, public halls, libraries and offices. 
The service undertook approximately 103,000 individual jobs in 2025/26 and its
budgeted turnover was £25.25m (excluding Kitchens and boilers) and for 26/27 the
number of jobs is not anticipated to reduce, and the budgeted turnover be around
£28.5m. This includes the kitchen and boiler replacement capital programme
estimated to provide an additional turnover of circa £3m per year during 26/27 and
up to £3m annually in the coming years.   
As a repairs and maintenance service, there is a wealth of skills that may also
undertake and manage refurbishment works and capital programme works across
the Renfrewshire Council portfolio. In 2025/26 Building Services secured a 5-year
programme of kitchen and boiler replacement across the housing estate which
commenced in July 2025 and will continue to 2030. In addition, Building Services
have also secured 3 further school toilet refurbishments in 2026/27, and some larger
commercial gas works across the public building estate due to our increase skills
and resources in this area.

Page 11

Page 11 of 33 
PUBLIC
1.4.1 Core Competences
Building Services core competences is in the provision of a multi-trade property
repairs, maintenance and refurbishment service covering both housing and non-
housing (public buildings) properties.
These key activities can be summarised as:
Housing repairs, maintenance, and refurbishment
• Providing council house tenants with a multi trade responsive repairs service on
an appointment-based system (from 8am to 4pm) allowing flexibility of
appointments during the working day.
• Provide the same responsive repairs service for public buildings (schools etc).
• Having a multi trade emergency repairs service which operates on a 24hr/7 day
a week basis for both council tenants and public buildings. This is a make safe
service only any works required will be carried out within working hours. 
• Responding to other emergencies such as the effects of inclement weather,
police call outs and major incidents.  
• Repairs and refurbishment of empty/void properties to a specified re-let
standard.
• Planned cyclical maintenance works such as gas, electrics, and window
servicing.
• Work associated with improvement projects which can include including
bathrooms, kitchens, rewires and central heating.
• Aids and adaptations to assist tenants with physical challenges to remain in
their homes.
• Undertake fire damage and insurance repairs. 
• Provide a common repairs facility to owner occupied properties.
• Mobile key cutting service and cosmetic repair service. 
Non-housing repairs and maintenance
• Provide a repairs and maintenance service and emergency call out service for
non-residential properties such as schools and public buildings.
• Undertake specific project work including refurbishments on behalf of the other
teams in the Facilities and Property Service. 
• Provide a comprehensive compliance service for all public buildings including
gas, electrics, water management, air conditioning and emergency lighting. 
1.4.2  Building Services do not carry out the following Services: 
• Repairs to intercoms/aerials in houses or public buildings. 
• Control the kitchen replacement or window replacement programmes.
• Carry out pre inspections to determine if a repair is required.

Page 12

Page 12 of 33 
PUBLIC
• Carry out all repairs and maintenance across Renfrewshire. 
• Flat roofing
• Carry out cleaning of road gullies.
• Environmental cleaning/ clearing works. 
• Garden Maintenance.
• Tenanted house glazing. 
• Graffiti removal. 
• Streetlighting. 
1.5  Building Services’ Key Performance Indicator (KPI) Priorities 
1.5.1  Housing  
% OF REPAIRS WITHIN TARGET Target 2023/24 2024/25 2025/26
Emergency Completed (E/E4) 99% 97.05% 97.79%  98.04%
Right to Repair Completed (Q
Same Day) 99% 99.04% 99.01%  99.17%
Right to Repair Completed (Q) 97% 98.10% 99.89%  99.14%
Urgent Completed (U5) 97% 62.59%  80.83% 82.25%
Routine Completed (A) 97% 88.54% 89.25%  92.88%
Programmed Completed (P/P9
D D/9) 97% 98.23% 99.33%  99.53%
OVERALL REPAIRS
COMPLETE WITHIN
TARGET
94% 92.42% 93.59%  95.73% 
The categorisation of repairs requires to be reviewed as part of the Housing Repairs
Policy review (see section 2.5). In addition, it is proposed that the targets and
category of repairs will be reviewed with Housing to ensure they remain valid and if
additional categories are required, they can be introduced and monitored in future
years.  
APPOINTMENTS  Target 2023/24 2024/25 2025/26
% of repairs made by
appointment  82% 99%  100% 99.85%
% of non emergency
repairs kept  99% 93%  81.94% 86.05% 
Gas Service / Inspections Target 2023/24 2024/25 2025/26
Number of Services Carried
Out  9,479 10,469  10,736
Gas Certificates Obtained
Before Previous Expiry
(%) 
100.00% 99.81% 99.95%  99.90%

Page 13

Page 13 of 33 
PUBLIC
Compliance within the housing environment has been much more closely monitored
within the last 3 years and therefore the development of KPIs to specifically track
and monitor the progress across the compliance categories should be further
developed. Potential additional categories are highlighted below. Building Services
will work with the Housing compliance colleagues to develop these as official KPIs
over the coming months. Consideration should also be given to the level of remedial
works that are required following an EICR inspection as this would be anticipated to
fall over time due to the regular inspections now in place. 
Forced smoothing of the annual number is now being carried out to prevent large
numbers of renewals being due all at the same time. This equates to 2500 – 3000
house per year moving forward.  
ELECTRICAL Target 2024/25 2025/26 2026-27
Number of EICR’s completed    1935 4001* 
Number of forced entries for EICR   600 737 
Electrical paperwork inspected   100% 100% 100% 
Properties physically inspected  10% N/A N/A 
Number of properties with remedial
works following EICR  900 900 
The total number of EICR’s carried out is 3264+737 forced accesses. 
1.5.2  Non-Housing KPI Development
Working with our colleagues in Hard FM Services we are continuing to develop
meaningful and measurable KPIs and targets areas moving forward. We have
mirrored the same criteria as Housing for consistency and the data will be populated
from the Workhub and CAMIS systems. 
% OF REPAIRS COMPLETED
WITHIN TARGET 
New Target 2024/25 2025/26 2026/27    
Emergency Completed (E) 
24 hours  99% 94.63% 99% 
Urgent Completed (U5) 
5 days  95% 48.68% 58%* 
Routine Completed (A) 
15 days  90% 73.11% 83% 
Programmed Completed 
90 days   100% 92.63% 100% 
Planned 247 days  100% 100% 100% 
*The U5 Category has improved but works on going to make further improvements.

Page 14

Page 14 of 33 
PUBLIC
Compliance categories 
Element of compliance    Target
% carried out
within
anniversary
25/26
% carried out
within
anniversary
26/27
% carried out
within
anniversary
27/28
Electrical (including MUGA's)   90% 90%  
Emergency lighting   90% 92%  
Water Management (including
showers and swimming pools)   90% 97%  
Gas    90% 100%  
HVAC 90% 100%  
Canopies   90% 100%   
1.5.3  Building Services Targets
• Productivity –the industry average is noted to be 4.5 jobs per operative/per day.
Building Services will strive to ensure the productivity stays at or above 4.5 for
the average no of jobs per operative per day within the responsive repairs
section. Work hub will be able to produce more statistics when it is upgraded,
and this will be kept under review by Senior Managers.   
• Absence – target of 6.37%
• Voids - number per week currently averaging 11-15. Timescale targets based
on work content. The average number of hours per void property has increased
steadily to 141 hours per property in 25/26. The average turn around days has
reduced to an average of 13.3 days for 25/26 (including exemptions).  
Section 2.0 – Service Improvement Activities and Outcome Updates 
Service reviews and improvements over the last 5 years have been instrumental in
driving service re-designs, data monitoring improvements and increasing
accountability. This is the Council's commitment to ensuring that the very best
services are being delivered to its residents. 
In 2021 following a review it was recommended that: 
• Processes and procedures were to be detailed in writing including roles and
responsibilities of the data management. 
• The reintroduction of a 3-year business plan. 
• The reintroduction of service level agreements. 
• The reintroduction of targeted and detailed financial information. 
• The reintroduction of a productivity monitoring process at the trade level. 
• The review of deployment and SOR codes.

Page 15

Page 15 of 33 
PUBLIC
• The review of increasing responsive repairs especially within the emergency
category. 
In 2022 following a further review it was recommended:
• To complete the review of the asbestos policy. 
• Review KPIs
• Review void process and create a single voids team. 
• Review the stores provision within Building Services. 
• Structured monthly review and performance meetings.
• Review and refresh of the current fleet. 
• Review the current electronic repairs and deployment systems. 
• Review central charges. 
In 2023 it was recommended:
• Development of a suite of KPIs for Public Buildings.
• Develop a new sub-contractor supply chain.  
In 2024 it was recommended:
• Review the structure of Building Services. 
• Create a commercial team to assist across Housing, Public Buildings and
Building Services. 
• Continue to develop commercial report and provide accurate forecasting. 
• Review productivity and value for money. 
• Look to deliver more capital programme works. 
• Review the support services provided, reporting lines and adequacy of service
provision. 
Throughout this intense review period Building Services have worked to carry out as
many of the recommendations as possible and have achieved a much greater level
of information and proof that Building Service are providing an invaluable service to
Renfrewshire Council and its residents. These reviews have also shown that Building
Services are providing a strong, robust service contrary to previous reporting and
beliefs. 
2.1 Trade Operative Productivity Analysis  
From a review in 2023/4, a new process was put in place to measure productivity
across the responsive service within Building Services. This is approximately 65 – 70
operatives who carry out responsive repairs for Housing Services. This
encompasses gas engineers, electricians, joiners, plasterers, painters, bricklayers,
plumbers, slaters, drainage operatives, and general maintenance operatives. They
confirmed that the national industry average is 4.5 jobs per operative for responsive
repairs services. The chart below shows that the tracking of the productivity in
Building Services has shown that the service is operating above the industry
average. N.B. Caution must be made when interpreting these figures over time as
the move from less responsive work to more planned work may lead to lower jobs
per day.

Page 16

Page 16 of 33 
PUBLIC 
Productivity analysis 
Productivity levels must be measured by area of work and by trade to be comparable
and realistic. The chart shown above is only currently available in responsive repairs
through the manual job tracking sheet introduced as part of the consultant review.
The current IT system Work Hub will be able to provide additional reports on all of
the areas and trades across Building Services when it is upgraded. 
2.2 Financial Productivity level Analysis.  
In order to calculate the hourly rate for each trade within Building Services we must
first calculate the physical available hours per year per operative. 
If we start from 100% and deduct annual leave, training, sick leave and non-
productive time (vehicle breakdowns, stores collections etc) the resulting percentage
would be the available hours that can be worked. It is hoped that over the next 3
years this can be increased annually, and the proposed improvement is indicated
below. This will be measured quarterly to ensure increases in productivity are being
realised. Continued work is required with colleagues in HR to ensure there are
modern, clear policies in relation to absence and Occupational Health. There is
currently a corporate focus on this and remains a challenging area. 
• 2025/26 – 75.94% 7.01% sickness – achieved a better productivity result and a
lower sickness. 
• 2026/27 – 76.45% 6.37% sickness assuming a 10% improvement of 25/26. 
• 2027/28 – 76.95% 6.0% sickness
• 2028/29 – 77.45% 5.5% sickness
2.3 Cost per job Housing and Non-Housing

Page 17

Page 17 of 33 
PUBLIC
As part of the review the costs per job for both housing and non-housing were
calculated to provide visibility on the value for money the service is providing. It has
been confirmed that the average cost across the industry is in the region of £150 per
job. As can be seen from the graph the average costs per job is consistently lower
across the whole year. 
2024/25 average cost £125
2025/26 average cost £124 
For non-housing work it is more difficult to provide an industry average as it depends
on the portfolio of properties being maintained and what condition they are being
maintained to.  However, the consultant agreed that the average costs being tracked
across the year were within the normal limits anticipated for this category of repairs. 
2024/25 average cost £220
2025/26 average cost £209

Page 18

Page 18 of 33 
PUBLIC 
* December 25 - It should be noted that there is a 2 week shut down in December when only emergencies and a
small amount of compliance are carried out therefore the number of jobs carried out over this period will be lower and
the costs for delivering during holidays increases. 
2.4 Work Portfolio Demand and Delivery Profiling 
Working in partnership with Housing Services it has been possible to secure more
detailed work profiles. However, we will look to work together to move away from the
current substantial responsive repairs to a more planned work approach as this
allows for increased efficiency and better service delivery. 
In the short term, the volume of voids remains lower than in previous years,
however, the large-scale demolition and build programme may be influencing these
numbers. However, the volume of work content within the current void houses has
been increasing which negates any savings in time or resources. It is also
anticipated that the volume of responsive repairs will also remain high as stated
above until a full review of the Council’s housing policies are undertaken. After
discussions with Housing Services, all works to Homeless Person Units (HPU)
properties will also now be passed to Building Services with a view to extending this
to some of the SHQS voids as required. 
Building Services will undertake a considerable amount of boiler and kitchen
replacements over the next 5 years which commenced in July 2025. This has
allowed a more planned rather than a reactive approach to workload ensuring
continuity of work. 
Further discussions will be ongoing with regards to new and emerging technologies
to ensure that Building Services have the correct skills and sufficient resources to
take forward future installations and maintenance in areas such as solar panel
maintenance, ground source heat pump maintenance and electric charging points in
housing premises

Page 19

Page 19 of 33 
PUBLIC 
2.5 Housing and non-housing repairs diagnosis, categorisation and
scheduling 
The categorisation of housing repairs is a combination of Housing Regulator and
Housing policy. This can only be reviewed by Housing Services to see if there are
any areas that the current very high level of responsive repairs can be modified.
Below is the overview of volume of repairs for 2025/26 and these are only repairs
carried out for Housing. 
34% of all repairs are in the emergency category requiring Building Services to
respond within 24 hours. This is a 1% drop from 2024/25 but there have also been
few adverse weather events in 25/26 which may account for the slight decrease.
This has been consistently high over the last 5 years and prevents the service from
planning the workforce resources efficiently. It is also sessional and severely
affected if there are adverse weather conditions. 
29% of the emergency repairs are out of hours. The provision of the out of hours
services is compulsory via Housing Services policy, but the volume of repairs made
out of hours remains consistently high. The calls to this service are triaged and more
than 40% do not result in an operative visit. 
In addition to the above number of repairs we have to add in additional repair visits
not included. These are removed from the overall numbers by housing as they do
not form part of the repairs reported to the housing regulator. 
Housing Other categories not included in the figure above  8948
*Assists (Two Operative Visit)      3023

Page 20

Page 20 of 33 
PUBLIC
For the total number of repairs that Building Services carry out we also need
to add in the repairs carried out in public buildings, community centers,
schools and leisure facilities.   
Public Buildings repairs      15,168 
Therefore, the total number of repairs that Building Services operatives have
been deployed to in 25/26 is 102,973. 
Looking closely at the overall numbers for Public Buildings it can be seen that 15%
of all repairs are currently categorised as an emergency with 29% classified as
urgent with 29% being designated as a routine repair. This is an improvement of 5%
on the combined emergency and urgent repairs (44%). While this is an improvement
it is still relatively high and does affect the ability to effectively plan resources. We
will continue to work with our colleagues to identify the miscoding of repairs and look
for further improvements in the classification of works. 
2.6 Building Services Staff Support 
2.6.1  IT support 
Building Services currently uses the WorkHub system which is an electronic repairs
management system. This has been functioning at a basic level for 4 years and a
new version of the product was hoped to be introduced in late 2025 which should
allow greater monitoring and analysis of the business however this did not
materialise. Therefore, Building Services relies on the specialist team to provide
detailed reports across many important areas of the business to ensure we do have
consistent monitoring.   
29%
15%27%
29%
Public Building Repairs 25-26
A - Appointments within 15
days
E - Emergency within 1 day
P - Planned within 247 Days
U5 - Urgent within 5 days

Page 21

Page 21 of 33 
PUBLIC
Building Services and the Support team are working with colleagues in Housing
Services to design and implement a new repairs system through the replacement
product for the Housing OHMS system. 
2.6.2  Stores support 
The stores provision within Building Services for 25/26 had a turnover of
approximately £3.2 million per annum and a stock holding of approximately £500,000
which is a reduction in both areas through a review of stock. This has improved the
stock turnover ratio from 5.25 to 6.4 which is now above the industry average of
between 4 and 6. Building Services are working with procurement to get the best
prices for all materials required across the business and the price paid for the
materials used on any job are charged at cost only. The staffing and operational
structure of Stores will be reviewed within the next 12 months to ensure it continues
to be fit for purpose and robust for any workload changes. 
2.6.3 Transport support 
Building Services have permission to procure a new fleet, however an options paper
is required from Transport colleagues in order that strategic and financial decisions
can be made on the future direction of the procurement and the make-up of the fleet. 
This may be a combination of purchasing and leasing in order to get the best
provision possible. 
An options appraisal is required to get the right blend of vehicles for staff and this
should include electric vehicles wherever possible, however, this comes with distinct
challenges. 
For efficiency and practicality, most operatives take their works vehicles home so
they can deploy directly to their 1st job in the morning. Therefore, if more electric fleet
were to be introduced there would be a requirement for operatives to potentially
charge their vehicle at their home address. 
Development of usable reports from the vehicle tracking system has been extremely
difficult and work continues with colleagues to create a dashboard (potentially via AI)
to assist Officers in overseeing staff movements. 
2.6.4 Office Provision 
Building Services will move to dedicated offices within Unit 5 in mid-September
2026. This allows all Building Services staff to be in one location and also satisfies
the recommendations within both the external and internal audit reports. In addition,
there is also a potential opportunity to install two large solar arrays on the roof of unit
5 that could generate a large volume of electricity for the whole depot which will have

Page 22

Page 22 of 33 
PUBLIC
a payback period of 3 years and considerably contribute to the Councils’ green
targets. 
2.6.5 Office and non-technical support 
The repairs support team are now fully integrated into Building Services. The
structure of the team was revised so that there was a clear structure including a
manager and two senior officers overseeing the daily support teams. The team was
also increased to meet the growing demand for record management, specialised
compliance tasks and day to day operations. 
The team are working to use AI for as many tasks as possible to ultimately reduce
the large amount of manual inputting. The new Housing repairs system that should
come on-line in 2027 should also help to streamline the processes. 
2.7 Building Services Management Structure/s 
The trade workforce is supported by a management and supervisory structure
covering areas such as operational management, contract & commercial
management, technical & productivity supervision. 
After additional workload and contracts were added in June of 2025, the service is
now a 4-division operation and re-designed the teams within each area to match the
type of workload and the ambitious programme of review and development over the
next 3 years. Each unit had its own dedicated Senior Facilities Manager and
Facilities Technical and Productivity Supervisors allowing increased flexibility within
the service and the service will be more able to adaptable to future developments
and changes. The structure will be monitored annually taking into account current
resources, future resources, workforce planning and new business development

Page 23

Page 23 of 33 
PUBLIC
areas. The FTE numbers are the number of direct employees, however, the
business units are also supplemented with Agency staff and sub-contractor as the
work profiles dictate. 
2.8 Business Unit 1 - Void House Repairs
2.81 This business unit employs circa 66 FTE (mixed trades) to undertake works on
properties which have been vacated and are empty. 
2.82 When a property becomes vacant the Housing Client function decides what
each property requires in terms of repairs to meet the letting standard. Currently if
void houses require new kitchens, bathroom or rewired they are passed to an
external contractor who are managed directly by Housing Services, however, this is 
to be reviewed to allow some of the work to be given to Building Services. The
volume and flow of work to the void team is unpredictable on a weekly basis but
averages over the year. In 2025/26 they completed 556 full void packs and 123 gas
heating installations. While this is approximately 70% of all void houses the time with
Building Services only equates to less than 2% of the total rent loss. 
2.83 Previously Homeless Persons Units (HPUs) were passed to external
contractors to carry out remedial works and some of the timescales for return were
extensive, however in February 2026 they were passed to Building Services. The
number and timescales will remain under review as these homes have the largest
rent loss amounts attached to them. 
2.9 Business Unit 2 - Responsive Repairs 
2.91 This business unit undertakes repairs for both Housing Services and Public
Buildings. Responsive and contract repairs can be defined as “maintenance repairs
arising from a landlord’s obligation to carry out repairs to a property as per a tenants
request (emergency, urgent or routine) and unanticipated works such as fire flood or
other weather damage”[1]. 
2.92 This is the principal business unit within Building Services as it provides a
service directly to tenants and users of public buildings and must be resourced to
meet the demand. This business unit employs circa 53 full time tradespersons
(mixed trades) to undertake these repairs. The flow, volume and value of responsive
work is based on tenant and customer demand mainly via the customer contact
centre. When the workload fluctuates significantly, e.g. responding to storm damage,
management increase the employee resources in the Responsive Unit by moving
operatives from other business units.  
2.93 This business unit must be highly experienced in dealing with all types of tenant
groups as achieving high customer satisfaction requires a service to demonstrate
timeliness, quality, cleanliness and cost effectiveness in providing a responsive
repairs service. Customer surveys are used to gauge satisfaction with Housing
Repairs Services across the Council.

Page 24

Page 24 of 33 
PUBLIC
[1] Chartered Institute of Housing 
2.10 Business Unit 3 - Compliance
2.10.1 Circa 49 FTE (mixed trades) and specialist support staff are employed in this
business unit.  Compliance is a large part of the legal responsibility of a landlord.
Building Services carry out many of these requirements for both Housing Services
and Public Buildings. 
2.10.2 There is a timetable for all types of compliance which varies across disciplines
depending on the legislation. Areas that this will cover are, water management,
electrical testing and certification and gas certification. 
2.11 Business Unit 4 – Contracts and planned 
2.11.1 Circa 41 FTE (mixed trade and support staff) are currently employed in this
business unit. A large part of their workload is the management and delivery of the
two major investment programmes Kitchens installations and boiler renewal.
However, the staffing level will increase as demand for more programmed and
project work increases. 
2.11.2 They also carry out the capital investment works for the public buildings
including 3 major bathroom refurbishments across the learning estate. 
2.11.3 The business unit is also expanding their workload by carrying out project
work for both hard FM and Technical Services. 
2.12 Building Services Subcontractors 
Building Services currently use different procurement options including the use of
existing frameworks via the local government procurement frameworks and their
processes. At times, this can be restrictive, does not allow for much deviation and
does not current allow for local SMEs to work with the Council. A new local company
repairs and maintenance framework was developed to try to ensure that more small
local businesses SMEs are able to work alongside the Council. This is a key Council
challenge to help support and grow the local economy and is being kept under
review. 
2.13 Internal Customer Service Centre 
The Customer Service centre operatives work through and implement the policies
set out by our colleagues in Housing Services. This dictates the workflow to Building
Services.

Page 25

Page 25 of 33 
PUBLIC
It is anticipated that the replacement of the Housing management system to a more
integrated system will help align the frontline contact with the deployment of
resources by providing better diagnostics tools. 
Section 3.0 – Building Services’ Financial Projections   
3.1 Expenditure
Building Services has worked extremely hard to be able to provide a greater level of
financial detail and understanding. Working with colleagues in finance over the last 2
years, we are now able to provide a much more comprehensive analysis of finances
and continue to develop reports and processes to improve all aspects of the
finances. 
The financial details are set out below to show the definitions and complexity of the
financial model that Building Services operates within. 
Expenditure incurred by Building Services can be categorised as a direct cost for
providing a specific task rechargeable to the client or as part of the overall overhead
cost of operating as a distinct service area.  
Staffing costs can be broken down over these two categories with the direct staff
being the craftsmen, manual operatives and agency staff who carry out tasks on
behalf of clients and can attribute costs directly to a workstream as an allocation of
time. The indirect staff costs are the managers, stores staff and administration staff
who ensure that the services can be delivered and function appropriately.  
Overhead costs that are not staff, include the depot running costs, commercial
waste not directly allocated to a workstream, ICT overheads, small tools and
equipment for the workforce, administration costs, insurance, central administration
costs for support services (payroll, personnel, accountancy, call centre, audit, legal,
procurement etc) amongst others.  
Transport is another overhead cost associated with operating the business while
this will have an element of variability depending on the work requirements and the
volume of staff and agency employed this on the whole is treated as a fixed
overhead cost.  
Apprentices - since 2024/25 the allocation of apprentice costs has been included as
a direct overhead for the business and this is linked to the long-term workforce
planning requirements. Apprenticeships are a positive practice to enhance workforce
planning approaches - a ‘grow your own’ opportunity for the service which enables
access to employment and a career in Building Services for young people. The

Page 26

Page 26 of 33 
PUBLIC
current establishment allows for around 24 apprentices across a multi trade and
training profile. The recruitment of youth apprentices is restricted to Renfrewshire
Council residents only therefore providing direct benefits to the local economy and
local residents.    
Materials - in terms of other direct costs which are variable in nature and will depend
on the type of work, volume of work and the timing of the workload received from
clients. These include the cost of materials used to deliver the work – this is a
combination of materials utilised from the internal store within Building Services or as
direct material allocated to the individual job. 
Sub-contractors – is a direct variable cost is in relation to the utilisation of
subcontractor’s procured by Building Services; this will again vary depending on the
workload and the capabilities internally to deliver specific services. An example of
this may be in the sub-contracting of specialised drainage works out with the internal
workforces’ capabilities or skills.  
The budget for Building Services is proposed as follows for 2025/26 – 2027/28
across the categories and based on historical budget levels. 
Category 2026/27 2027/28 2028/29
Direct Staffing 11,272,332 11,610,502 11,842,712
Overhead Staffing 4,199,108 4,325,081 4,411,583
Overhead Costs 4,393,448 4,481,317 4,570,944
Variable Costs 8,581,100 8,752,722 8,927,776
Full Year Budget * 28,445,988 29,169,622 29,753,015
In future years have assumed the same inflation as the HRA BP with CPI of 2.0% for all costs in 27/28+28/29 except using
3.0% for staffing inflation in 27/28 as per the HRA BP assumption  
This budget is an area that is under review and will remain under constant review to
ensure that Building Services can adapt to future and changing priorities and to
ensure that the budget reflects the changing environment. 
3.2 Income
Historically, Building Services can allocate the majority if not all of its income across
4 main income stream categories. HRA Revenue, HRA Capital, General Services
Revenue and General Services Capital.  
HRA Revenue Income  
This includes income for the provision of services / contracts for Void Repairs,
Reactive Repairs, Planned Maintenance, and other repairs for HRA revenue. This
includes work on compliance for gas, electrical and water safety in the 12k council

Page 27

Page 27 of 33 
PUBLIC
properties. At present an element of the overall void works for the HRA based on the
existing staffing levels within Building Services. 
HRA Capital Income  
This is work classed as major investments with the HRA and historically has included
income for workstreams such as Heating Works, Kitchen and Bathrooms, Disabled
Adaptations, rewiring, legislative compliance such as the smoke and heat detector
programme. Again, this is an area that Building Services at present can deliver within
the existing staffing levels.  
General Services Revenue Income  
This is work carried out on behalf of the non-housing properties owned by the
Council such as the school estate, community centres, town halls, operational offices
and also properties managed by OneRen via the Public Buildings workstream. This
includes work on compliance testing and emergency and planned repairs and
maintenance.  
General Services Capital Income  
This is work carried out on behalf of the non-housing properties owned by the
Council as noted above but of a Capital investment nature. This is an area where the
historical levels of income have reduced reflective of the financial constraints within
the General Services Capital budget. 
Section 4.0 – Building Services Hourly Labour Recharge Rates in 2025/26  
4.1 Charging Mechanism
The direct staffing and overhead costs will form part of an hourly labour rate for each
trade type to be charged to each workstream via the manual timesheet process or
via the PDA process directly.  
A calculation of the productive time for trades and craft staff will be carried out on a
regular basis to ensure full recover of direct and overhead costs as part of the
charging mechanism. 
The variable costs such as stock materials, direct materials and sub-contractors will
be recharges at cost to the client budgets based on workstreams received. 
4.2 Recharge Rates 2026/27
The hourly recharge rate reflects a combination of fixed and variable cost elements,
including pay, national insurance, pension contributions and overheads. These
assumptions are regularly reviewed to reflect inflationary pressures, workforce

Page 28

Page 28 of 33 
PUBLIC
changes and legislative impacts, and are aligned with the Medium-Term Financial
Plan.
The methodology underpinning recharge rates and cost allocations is subject to
periodic review to ensure it remains robust, equitable and compliant with best
practice. This supports the delivery of Value for Money, ensuring that charges are
transparent, appropriate and reflective of efficient service delivery. 
The review of recharge rates is ongoing to ensure full cost recovery and compliance
with statutory requirements. It has been agreed, with appropriate financial oversight,
that any over- or under-recovery will be addressed in-year, with a year-end
adjustment where required between Building Services, the Housing Revenue
Account (HRA) and the General Fund, ensuring no cross-subsidy. 
Performance against recharge rates is monitored throughout the year to identify and
address variances at an early stage. This approach reduces the risk of material year-
end adjustments and supports robust financial management. A materiality threshold
is applied to ensure focus remains on significant variances, enabling proportionate
and effective financial control 
Section 5 – Workforce 
5.1  Workforce Composition, progression and planning. 
The total workforce of Building Services, as of April 2026, consisted of 277 full and
part time staff.  The tradespersons cover 10 different building and maintenance
related trades and include 24 apprentices (within the business at various stages of
qualification) and 4 close cleaners.

Page 29

Page 29 of 33 
PUBLIC
As the workload evolves, we will continually review the skill sets we require to deliver
to our customers and it is likely that in the future Building Services will recruit from
alternative trades and undertake internal training to upskill some of our existing
employees to undertake alternative works, to meet the long term demands from our
customers. 
73.65% of the existing Building Services staff live within the Renfrewshire area.
Building Services provide a good working environment as well as job security for
many Renfrewshire residents. 
The age profile of the workforce has been analysed to look at the current distribution
of ages across all the trade, management and support staff. Looking forward in the
short term (within the next 12 months) we have a number of trades people and
management who will be looking for options such as reduced hours, flexible
retirement, ill health retirement or full retirement. The service remains flexible with all
staff on trying to accommodate options to suit both the employee and the service.
This can be evidenced by the 1.3% shift from fulltime to part time within the last year
and this figure is expected to rise. 
Overall, just under 37% of the workforce is over 50 years old. Many of the
employees around and above 55 years have extremely long service and have
expressed an interest to pursue flexible retirement or leave well before the national
retirement age.  
However, Building Services continue to work hard to attract and retain new and
existing employees to ensure we have the workforce to deliver the service required.
This can be evidenced in the 2.2% rise in the number of employees under 25 years
old. The trade wages are now only just below standard external commercial wages,

Page 30

Page 30 of 33 
PUBLIC
however, with the addition of pension benefits, flexible working, further and higher
education access it is being seen as a good option by tradesperson and the number
of applicants for trade jobs has seen a marked increase over the last year. 
As part of succession planning and in order to be able to provide the level of service
in the future, we need to look very carefully at how we create the workforce of the
future, retain the existing staff and attract new employees. 
Short term – 12 months 
• five trade apprentices annually now agreed for next 3 years.
• One adult trade apprentice from within the existing employees of
Renfrewshire Council. 
• Flexible retirement as an option instead of full retirement for eligible staff so
they can remain part of the workforce, pass on their knowledge and skills.  
• Employee development programme open to all employees– HNC/ CMI/
Degree.  
• Support and mentor employees going through their degree courses.   
• Trainee Supervisor programme –has been developed further with strict
outcomes and timelines for training.  
• Personal Development Plans (PDP) – completed for all office based staff but
to be developed for operatives.   
Medium term 2-3 years 
• Extension of the youth and adult apprenticeship programme to match future
skills needs. 
• Review of age profile matching trade profile to future trade skills needs. 
• Review existing skills within workforce and look to plan for retraining. 
• Continue to encourage further and higher education. 
• Continue to improve and develop the Trainee Supervisor Programme. 
• Have a comprehensive training plan for all employees. 
Long-term 5 years +. 
• Review youth and adult apprenticeship programme to match future skills
needs.
• Review trade skills and future technologies and plan for change.
5.2 Adult Apprentice programme
Building Services started the Adult Apprentice programme in 2011 where any
existing Renfrewshire employee can apply to train in various trades and qualify as a
tradeperson. This has been extremely successful with candidates training in trades
such as plumbing, joinery, painting and plastering.

Page 31

Page 31 of 33 
PUBLIC
5.3  Further and Higher Education 
Building Services, over the last 12 years, has actively encouraged and supported its
employees to participate in Higher and Further Education training. The table below
details the Courses undertaken and what role they have moved from and to. Many
have progressed to higher positions within the Council, and this has shown existing
employees there is progression within both Building Services and the Council and
has increased the overall retention rate as employees see a career within the
Council and not just a job. 
Graduate apprenticeship places were recently offered out to the whole workforce as
part of the selection process, they were asked to write 500 words on why they should
be given this opportunity. The responses were extremely good with many saying that
they had not considered that they would ever be offered this chance but could see
others who had participated and gone on to other better positions. Three new
candidates will commence university in September 2026. 
HNC Degree Original Job Role Current Job Role
person 1  x x Apprentice Joiner Senior Facilities Manager
person 2 x x Apprentice Joiner Senior Facilities Manager
person 3 x x Apprentice Joiner Facilities Technical Supervisor
person 4 x x Apprentice Plumber Facilities Coordinator
person 5 x x Electrician Facilities Technical Supervisor
person 6 x x Apprentice Electrician Facilities Technical Supervisor
person 7 x x Apprentice Joiner Senior Facilities Manager
person 8 x x Apprentice Painter Repairs & Maintenance Officer
person 9 x x Estimator / Surveyor Development Manager
person 10 x x Apprentice Electrician Lead Facilities Manager
person 11 x x Apprentice Joiner Quantity Surveyor
person 12 x x Joiner Facilities Technical Supervisor
person 13 x   Apprentice Electrician Electrician
person 14 x   Joiner Facilities Technical Supervisor
person 15 x  x Apprentice Electrician Electrical QS
Person 16 x  Apprentice Joiner Joiner
Person 17 x  apprentice Joiner Joiner 
5.4  Working with local Colleges and other agencies 
Building Services works with the local college to provide work experience for school
and college students throughout the year. In addition, we also provide on-site work

Page 32

Page 32 of 33 
PUBLIC
experience for a local gas training company to ensure the students can achieve the
requirements of the course. 
5.5  Upskilling and re-skilling
Building Services has over the last 15 years looked to provide opportunities to the
workforce to upskill and reskill, over and above the offer of adult apprenticeships and
further and higher education. 
• Cosmetic repairs – Building Services invested in specialist training in order to
be able to repair rather than replace many elements within houses and public
buildings. The service is widely used in the void houses as saves both time
and money. The repairs offered are extensive but include repairing scratched
sanitary ware, repairing damaged kitchen doors and worktops, repairing
UPVC doors and windows. 
• Gas engineers – 1-year intensive training to upskill to a gas engineer. The
staff upskilled were a labourer, a store person, a painter and an asset co-
ordinator. 
Under consideration is a potential opportunity to add value to our current service
provision. The certified manufacture of modified timber fire doors within our
workshop in conjunction with certified installers from within our frontline operatives.
The current workshop has all of the required equipment necessary to make and
manufacture fire doors especially for Public Buildings where they are often bespoke.
Additional training for the bench hands is all that is required for Building Services to
become a certified manufacturer. Along with additional training for our joiners to
become certified installers this would then provide a quick responsive service that
will satisfy fire regulations and insurers. 
There will be more opportunities for skills development of the workforce as
technology changes. We need to be adaptable and flexible to ensure we are ready
and able to deliver these future requirements by being open to reskilling and
upskilling. 
6.0  Conclusion 
Building Services has had to adapt to many changes over recent years and has
shown that it is able to be flexible and modify to all aspect of change. It is well known
that when you are making changes, that it is important to have support from leaders,
a good communication process and get employees engaged in the process. 
In 2026-27 Building Services aims to: 
• Reduce sickness levels across the service by a minimum of 10%

Page 33

Page 33 of 33 
PUBLIC
• Restructure the Stores section to reflect the on-going needs and changes of
the business 
• Improve the KPIs across the emergency and U5 categories
• Have a comprehensive transport strategy for the next 3-5 years
• Increase the volume of works carried out for other departments of the Council 
Building Services has the support of the Elected Members and the Directorate to
continue to provide the invaluable services that it delivers. However, it requires to
think more strategically in the short, medium and long term to plan the future
direction of the business. The three-year rolling business plan developed and
updated by Building Services provides that annual scrutiny that can be updated to
include future changes. The Business plan will be reported alongside the KPIs to the
Finance and Resources Policy Board. 
Finances within Local Government remain challenging and will not get any easier in
the future. We must ensure we are able to provide cost effective solutions that
provide best value and the robust monitoring processes put in place are continuing
to provide that evidence but have to also adapt and change going forward. By
working closely with our colleagues across the Council we will be able to better
identify potential savings and solutions. 
We need to ensure that we continue to develop and improve the productivity and
service delivery to meet the key performance indicators and expectations of all of our
stakeholders. This can only be done by ensuring we have robust measures in place.
The Business plan sets out where we are at the present time and the developments
that have to be realised to ensure we continue to progress and improve. 
The structure of Building Services has changed to be able to adapt to future changes
as the business develops and modifies to future requirements. The staff are
dedicated to succeeding and are a major part of the successful future changes that
will be required. By continuing to encourage employee development at all levels and
keeping open lines of communication we will ensure that we have the workforce and
skills for the future. 
This Business Plan sets out where Building Services are currently in their
development journey and a pathway to where they want to be over the next 3 years.
There will be challenges as change is not an easy process, and there are risks in
many areas that are not always within the control of Building Services, but Building
Services is able to adapt and step up to those challenges and deliver successful
outcomes.