To:  Finance, Resources and Customer Services Policy Board
On:  11 June 2026 
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure  
___________________________________________________________________
Heading: Contract Authorisation Report for Maintenance and Refurbishment
Works – Void Properties (RC-CPU-24-247)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance,
Resources and Customer Services Policy Board to award a Measured
Term Contract for Maintenance and Refurbishment Works – Void
Properties (RC-CPU-24-247) to City Gate Construction (Scotland)
Limited (Co. No. SC244614).   
1.2 The recommendation to award the Contract follows a procurement
process that was conducted in accordance with the Open Procedure
under the Public Contracts (Scotland) Regulations 2015, as amended
for an above Government Procurement Agreement (GPA) Threshold
Works Contract and the Renfrewshire Council Standing Orders
Relating to Contracts.   
1.3 A Contract Strategy was approved by the Corporate Procurement
Manager on 19 March 2026 and the Head of Housing Services on 24
March 2026.  
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services
Policy Board:

Page 2

PUBLIC 
2.1 Authorises the Head of Corporate Governance to award a Measured
Term Contract for Maintenance and Refurbishment Works – Void
Properties (RC-CPU-24-247) to City Gate Construction (Scotland)
Limited (Company no. SC244614). 
2.2 Authorise the approved total contract value of up to a maximum value
of £15,000,000, excluding VAT.    
2.3 Notes the Contract Period will be 24 months with the Council having
the option to extend for up to 12 months on one occasion, with the
Contract commencing on 18 July 2026.  In the event that the Contract
does not commence on 18 July 2026, the Contract Period shall run
from the date as stated in the Award Schedule to the Letter of
Acceptance.  
_________________________________________________________
3. Background
3.1 The Council has a requirement to appoint a suitably experienced and
qualified Contractor to carry out Maintenance and Refurbishment
Works to Void Council Properties within the Renfrewshire Council
housing estate. 
3.2 To initiate this procurement process a Contract Notice was published
on Find a Tender Service via the Public Contracts Scotland portal on
24 March 2026 with the tender documentation available for
downloading from the Public Contracts Scotland – Tender Platform on
the same day.  
3.3 During the live tender period, 63 organisations expressed an interest in
the tender.  By the closing date set 12 noon, 27 April 2026 for return of
electronic tender submissions, 10 organisations had submitted a tender
response, 45 organisations did not respond, and 8 organisations
declined to respond.  
3.4 As required by Regulation 60 of the Public Contracts (Scotland)
Regulations 2015, as amended, each Tenderer was required to
complete a Single Procurement Document (“SPD”), which was to be
submitted with their tender submission. All 10 tender submissions were
evaluated against a pre-determined set of criteria within the SPD by
representatives from the following Council services: Housing Services,
the Corporate Procurement Unit, Corporate Risk and Corporate Health
and Safety.
3.5 All 10 tender submissions complied with the minimum selection criteria
of the SPD and progressed to evaluation against the published Award

Page 3

PUBLIC
Criteria which were based on a weighting of 65% Price and 35%
Quality. 
3.6 During the evaluation process, three tenderers failed to comply with the
pricing instructions and were therefore treated as irregular bids in
accordance with Regulation 27 (6)(a) of The Public Contracts
(Scotland) Regulations 2015 and those bids were not considered.
3.7 The remaining 7 tender submission scores relative to the award criteria
are noted below: 
Company Price
(65%)
Quality
(35%)
Total
(100%)
City Gate Construction (Scotland) Limited
(Co. No. SC244614) 65.00% 35.00% 100.00%
CRD Property Renovations &
Reinstatements Ltd (Co. No. SC533267) 47.26% 29.25% 76.51%
Consilium Contracting Services Ltd (Co. No.
SC472396)  40.74% 31.75% 72.49%
Procast Building Contractors Ltd. (Co. No.
SC407400)  41.93% 30.00% 71.93%
McConnell Construction Services Limited
(Co. No. SC625250)  42.85% 29.00% 71.85%
C Hanlon Facilities Management Ltd (Co.
No. SC246704)  39.35% 31.25% 70.60%
A C Whyte & Co Limited (Co. No.
SC054565) 24.53% 33.00% 57.53% 
3.8 The evaluation of the tender submissions identified that the tender
submission by City Gate Construction (Scotland) Limited was the most
economically advantageous to the Council.  
3.9 The form of contract is SBCC Measured Term Contract for use in
Scotland (MTC/Scot 2011) amended by the Employer’s Amendments.  
3.10 The costs for this Measured Term Contract will be met from the
Housing Revenue Account Capital and Revenue Budgets.  
3.11 Mandatory Community Benefits were included as a condition of this
contract which City Gate Construction (Scotland) Limited confirmed
they would adhere to.  This commitment was to deliver three
Employment Opportunities each year of the Contract; these
Employment Opportunities will be delivered without any spend on the
Contract.  The mandated Community Benefits are detailed below:

Page 4

PUBLIC 
3.12 In addition to the mandatory Community Benefits requirements, the
quality criteria specified that 40 community benefits points must be
delivered for every £2,000,000 of contract spend. City Gate
Construction (Scotland) Limited have committed to deliver the following
for their first £2m of contract spend:   
___________________________________________________________________
Implications of the Report
1. Financial – The total approved contract value will be up to a maximum
value of £15,000,000, excluding VAT, for the Contract Period, including
the full 12-month extension (3 years in total).  The costs will be met
from the Housing Revenue Account Capital and Revenue Budgets. 
The breakdown of work between the budgets is:
- Capital – Void kitchen and bathroom work 
- Revenue – Maintenance of houses and void repairs.   
2. HR & Organisational Development - None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – Making sure the infrastructure is in
place to support growth in local economy and population (such as
housing, transport and schools)
Mandated Community Benefits Requested   No of People
/ Activity
Year 1 - Job for a young person (age 16-24) from a
recognised priority group e.g. from the councils'
most deprived data zones.
1
Year 2 - Job for a young person (age 16-24) from a
recognised priority group e.g. from the councils'
most deprived data zones.
1
Year 3 - Job for a young person (age 16-24) from a
recognised priority group e.g. from the councils'
most deprived data zones.
1
Community Benefit Description  No of People
/ Activity
Work Experience Placement for an individual 16+
years of age 2
Industry Awareness Events 2
Industry Skill Transfer to Schools 1

Page 5

PUBLIC
• Our Renfrewshire is well - Developing strong community-based
services that respond to local need
• Our Renfrewshire is safe - Protecting vulnerable adults and
children, ensuring they can live safely and independently
• Place - Working with partners to ensure our neighbourhoods are
safe, vibrant and attractive places to live 
4. Legal - The procurement of this Measured Term Contract has been
conducted as an above GPA (Works) Open Procedure in accordance
with the Renfrewshire Council Standing Orders Relating to Contracts
2026 and the Public Contracts (Scotland) Regulations 2015, as
amended.   
5. Property/Assets – This Measured Term Contract will allow the Council
to carry out Void Housing maintenance and repair work, including
kitchen and bathroom upgrades.   
6. Information Technology - None directly arising from this report.
7. Equality & Human Rights - None directly arising from this report.
8. Health & Safety – City Gate Construction (Scotland) Limited Health &
Safety credentials were evaluated by the Council’s Corporate Health &
Safety team and met the requirements regarding Health & Safety.  
9. Procurement – This Measured Term Contract was tendered in
compliance with the Renfrewshire Council’s Standing Orders Relating
to Contracts 2026 and statutory requirements in respect of procurement
procedures, efficiency and modern government.
10. Risk – City Gate Construction (Scotland) Limited has been assessed
and evaluated by the Council’s Risk team to confirm they meet the
Council’s minimum requirements regarding insurance risk.  
11. Privacy Impact - None directly arising from this report
12. Climate Risk – The level of impact associated with provision of this
service has been assessed using the Scottish Government
Sustainability Test and is considered to be high risk.  Tackling Climate
Change and working towards Net Zero are addressed throughout this
Contract.  The environmental impacts considered are broad and range
from the disposal of waste generated from the works being carried out
to the type of vehicles and machinery being used on site.  City Gate
Construction (Scotland) Limited will be required to consider the
emissions from their vehicles when working onsite and to switch
engines off when not using them to prevent unnecessary emissions.

Page 6

PUBLIC 
Another mitigation included was the mandatory requirement to provide
a Waste Management Plan Template that will be used in the delivery of
the Contract.  
13. Children’s Rights – None directly arising from this report
14. Cosla Policy Position – No COSLA Policy Position implications have
arisen or are anticipated.
_________________________________________________________
List of Background Papers 
(a)  None  
___________________________________________________________________ 
Author:          Kevin Milliken, Senior Procurement Specialist,