Board Report - Notification of award of Contract for Construction of Red Smiddy to Erskine Active Travel Routes

Renfrewshire Council · 23 April 2026
Back to Finance, Resources and Customer Services Policy Board — 23 April 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
___________________________________________________________________
To:  Finance, Resources and Customer Services Policy Board
On:  23 April 2026
___________________________________________________________________
Report by: The Director of Finance and Resources and the Director of
Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Notification of the award of a Contract for Construction of Red Smiddy
to Erskine Active Travel Route Phases 4 and 5 (RC-CPU-25-158) 
Notification of the award of a Contract for Construction of Red Smiddy
to Erskine Active Travel Route Phase 6 (RC-CPU-25-159)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to notify the Finance, Resources and
Customer Services Policy Board of the award of: 
• A Contract for Construction of Red Smiddy to Erskine Active
Travel Route Phases 4 and 5, reference RC-CPU-25-158 to
John McGeady Limited; and
• A Contract for Construction of Red Smiddy to Erskine Active
Travel Route Phase 6, reference RC-CPU-25-159 to John
McGeady Limited. 
1.2 The Council was offered a grant from Transport Scotland’s Tier 2
Active Travel Fund for Construction on the condition that the associated
spending commenced  before 31 March 2026. In order to meet the
condition, the Head of Finance and Procurement approved the use of
standing order 9.1k of the Council Standing Orders Relating to
Contracts with the requirement for retrospective reporting to this Policy
Board.

Page 2

PUBLIC
1.3 In accordance with the authority granted by the Head of Finance and
Procurement as noted in 1.2 above, the Head of Climate, Public
Protection and Roads authorised the award of these two Contracts on 7
January 2026. The Letters of Acceptance were issued on the same
date.
___________________________________________________________________ 
2. Recommendations 
The Finance, Resources and Customer Services Policy Board is asked
to note:
2.1 The Contract for Construction of Red Smiddy to Erskine Active Travel
Route Phases 4 and 5, reference RC-CPU-25-158, was awarded to
John McGeady Limited (SC080553); and  
2.2 The Contract for the Construction of Red Smiddy to Erskine Active
Travel Route Phase 6, reference RC-CPU-25-159, was awarded to
John McGeady Limited (SC080553).
2.3 The detail provided in section 3 of this report in connection with the
Contract for Construction of Red Smiddy to Erskine Active Travel Route
Phases 4 and 5 and the Contract for Construction of Red Smiddy to
Erskine Active Travel Route Phase 6. 
2.4 The Contract for the Construction of Red Smiddy to Erskine Active
Travel Route Phases 4 and 5, reference RC-CPU-25-158, was
awarded for an approved contract value of £811,095 (excluding VAT). 
This was from a Total Tendered Contact Sum of £737,359 excluding
VAT plus a 10% contingency spend of £73,736 (excluding VAT).
2.5 The Contract for the Construction of Red Smiddy to Erskine Active
Travel Route Phase 6, reference RC-CPU-25-159, was awarded for an
approved contract value of £351,358 (excluding VAT).  This was from a
Total Tendered Contract Sum of £319,416 plus a 10% contingency
spend of £31,942 (excluding VAT).
2.6 The cost of these Contracts will be wholly met from funding provided by
Transport Scotland’s Tier 2 Active Travel Infrastructure Fund for
Construction.
2.7 The starting date for both Contracts was 19 January 2026 with the
completion date for both Contracts being 26 weeks from the starting
date. 
2.8 Note that the Council required Tenderers to appoint a supported
business as a subcontractor to provide the signage required for this

Page 3

PUBLIC
Contract. John McGeady Limited have nominated a supported
business for this requirement. 
_________________________________________________________
3. Background
3.1 The Council was offered a grant from Transport Scotland’s Tier 2
Active Travel Fund for the construction of an active travel route in 2
stages:
• Phases 4 and 5 are for the construction of 1.4 kilometres of shared
footway and cycleway from the end of the existing shared footway
and cycleway on Greenock Road, round Red Smiddy Roundabout,
north onto Southbar Road to Southholm Roundabout; and
• Phase 6 is for the construction of 0.616 kilometres of shared
footway and cycleway from Southholm Roundabout to the
overbridge on the A726 on the northbound verge.
A stipulation of the grant required the Council to commence work on
the Contracts at the earliest opportunity so most of the funding could be
utilised during the 2025/2026 financial year with the remaining being
provided during the 2026/2027 financial year.
3.2 To meet the grant conditions, the Head of Finance and Procurement
approved the use of 9.1k Council Standing Orders Relating to
Contracts to enable the work to commence before 31 March 2026. The
Contract awards were authorised by the Head of Climate, Public
Protection and Roads on 7 January 2026 and issued on the same date.
3.3 The tendering procedure for these below Regulated threshold Works
Contracts followed the Open Procedure in accordance with
Renfrewshire Council’s Standing Orders Relating to Contracts.
3.4 A Contract Notice was published on the Public Contracts Scotland
advertising portal on Thursday 13 November 2025 and the tender
documentation was available for downloading from the Public Contracts
Scotland – Tender platform from this date. 
3.5 During the tender live period, 27 organisations expressed an interest in
the Contracts. By the closing date for return of electronic Tenders, 12
noon on Friday 19 December 2025, 8 companies submitted a
response, 6 declined to respond and 13 showed no further interest. 
3.6 In accordance with Standing Order relating to Contracts 11.5, each
Tenderer was required to submit a completed Single Procurement
Document (SPD) as part of their Tender Submission. The completed
SPD documents were evaluated against a pre-determined set of criteria

Page 4

PUBLIC
in the SPD. All 8 Tenderers satisfied the Council’s requirements in
respect of their responses to the SPD.
3.7 The technical and commercial responses in each Tender Submission
were then scored against the award criteria of 40% technical (Quality)
and 60% commercial (Price) in accordance with the Invitation to Tender
(ITT). The Council stated in the ITT that Tenderers must bid for both
Phases 4 and 5, and Phase 6 and that Tenderers who failed to submit
a bid for both Contracts would have their bid rejected.  The ITT also
stated that the Council intended to award both Contracts to one
Contractor. 
3.8 Tenderers were required to provide one Technical response and one
Commercial response within their submission.  As part of the
Commercial response, Tenders had to submit tendered sums for both
Contracts, which were aggregated and evaluated.  One Tenderer failed
to provide a Commercial response and their Tender was rejected as a
result. 
3.9 The scores relative to the award criteria of the Tenderers are noted
below: 
Price
(60.00%)
Quality
(40.00%)
Total
(100.00%)
1 John McGeady Limited
(SC080553) 58.15% 31.25% 89.40%
2 Bottom Groundworks & Plant
Hire Limited (SC578729) 60.00% 21.75% 81.75%
3 Covanburn Contracts Limited
(SC263761) 48.17% 31.00% 79.17%
4 Advance Construction
(Scotland) Limited (SC202570) 53.35% 24.25% 77.60%
5 Hillhouse Quarry Group Limited
(SC135103) 49.87% 21.25% 71.12%
6 M Squared (Scotland) Ltd
(SC479137) 39.67% 30.00% 69.67%
7 Ground Control Limited
(01795094) 20.47% 21.25% 41.72% 
3.10 The evaluation of tender submissions received identified that the
submission by John McGeady Limited (SC080553) was the most
economically advantageous Tender for both Contracts.
3.11 Community Benefits were requested as part of the procurement
process and John McGeady Limited has committed to the following
Community Benefits across these two Contracts: 
Community Benefit Description No of People
/ Activity

Page 5

PUBLIC
S/NVQ (or equivalent) for  
• New Employee
• Existing Employee  
• Supply Chain Employee
2
Business advice/support to a local SME /Social Enterprise/
Voluntary organisation 1
Commitment to ensure that supply chain opportunities are
prioritised for Renfrewshire based businesses 2
___________________________________________________________________
Implications of the Report
1. Financial – the maximum approved Contract value for:
• Construction of Red Smiddy to Erskine Active Travel Route
Phases 4 and 5, reference RC-CPU-25-158 is £811,095 which
includes the Total Tendered Contract Sum plus 10%
contingency.  
• Construction of Red Smiddy to Erskine Active Travel Route
Phase 6, reference RC-CPU-25-159, is £351,358 (excluding
VAT) which includes the Total Tendered Contract Sum plus 10%
contingency.  
The costs for these Contracts will be wholly met through the Transport
Scotland’s Tier 2 Active Travel Infrastructure Fund for Construction. 
2. HR & Organisational Development – None arising directly from this
report. 
3. Community/Council Planning – Place – Working with partners to
enhance wellbeing across communities. The Contracts will support the
delivery of this outcome. 
4. Legal – the exemption under Standing Orders relating to Contract 9.1k
was used for the award of these two Contracts. The Contracts were
awarded by CPU and Environment, Housing and Infrastructure. 
5. Property/Assets – these Contracts will build a segregated two-way
cycle/pedestrian track located between the Red Smiddy roundabout
and Erskine. 
6. Information Technology – none arising directly from this report. 
7. Equality & Human Rights – none arising directly from this report.

Page 6

PUBLIC
8. Health & Safety – John McGeady Limited’s health and safety
credentials were evaluated by Corporate Health and Safety and met
the Council’s requirements regarding health and safety. 
9. Procurement – The procurement procedures outlined within this report
shall ensure that the Council meets its statutory requirements in
respect of procurement procedures, efficiency and modern
government.
10. Risk – John McGeady Limited’s insurances were assessed to confirm
that they have met the minimum requirements regarding insurable risk.
11. Privacy Impact – None arising directly from this report. 
12. Climate Risk – The level of impact associated with works connected
with the Contracts has been assessed using the Scottish Government
Sustainability Test and is high risk. John McGeady Limited have been
required to organise their activities in such a way that the impact they
have on the environment is minimised.
13. Children’s Rights – None arising directly from this report.
14. Cosla Policy Position – None arising directly from this report.
_________________________________________________________
List of Background Papers 
None. 
___________________________________________________________________ 
Author:           Brian Bradley, Assistant Category Manager, 0141 487 1522,
brian.bradley@renfrewshire.gov.uk