To: Finance, Resources and Customer Services Policy Board
On: 23 April 2026 
Report by: Director of Environment, Housing & Infrastructure 
Heading: Facilities and Property Services - Service Update Report 
1 Summary 
1.1 Environment, Housing & Infrastructure brings together a range of Council
services and activities, with both strategic and operational responsibilities. This
report provides an operational performance update on Facilities Management
(Hard and Soft Services), Building Services and Technical Services delivered by
Environment, Housing & Infrastructure since the last Policy Board in February
2026. 
2 Recommendations
It is recommended that members of the Finance, Resources and Customer
Services Policy Board: 
2.1 Note the content of this report. 
3 Operational Update 
Hard Facilities Management (Hard FM) 
3.1 Public Buildings – Capital Projects 
3.1.1 As part of on-going improvements for sports/activities across the learning estate,
Officers are currently exploring the provision for additional Multi Use Games
Arenas (MUGAs) and upgrades to red blaes pitches, within a number of primary
schools. This work will be discussed with Children’s Services and undertaken on
a priority basis as the budget allows. A commission has been raised for feasibility
studies to 5 schools:
• Barsail PS
• St Anne’s PS

Page 2

PUBLIC
• Gallowhill PS
• East Fulton PS 
• Kilbarchan PS 
3.1.2 Feasibilities studies are now complete, and the reports are currently being
reviewed. Officers have also shared with colleagues within Children’s Services,
and a meeting will be arranged to discuss best way forward. The current estimated
cost plan indicates a budget of more than £1m may be required for the works,
therefore, certain schools will require to be prioritised as the current capital budget
remaining (circa £0.5m) is not sufficient. 
3.1.3 Following the commitment at the Council budget in February 2026 to provide
£1.4 investment in school football pitches, preparation has started on the
provision of 2 new artificial pitches for St Benedict’s HS and Linwood HS. This
would ensure a 3G provision at all secondary schools in Renfrewshire. Due to
the PPP contract, discussions have started with AMEY and Renfrewshire
Schools Partnership to assess ground conditions and look to move forward.  
3.1.4 The tender for decarbonisation surveys to 5 schools went out to the market and
was reviewed in late January 2026. The contract has been awarded to ECD
Architects and surveys have concluded. The current programme indicates that
reports will be ready for submission/review by mid-May 2025. A further update
will be brought to this policy board in due course. 
3.1.5 A contract has been awarded for part renewal of Heriot Primary School roof and
works will commence during the summer break. 
3.1.6 A project is currently being set up for future investment in the OneRen estate
following the allocation of funding as part of the budget setting meeting in
February 2026. 
3.2 Public Buildings - Lifecycle Replacement works 
3.2.1 Works have progressed well this fiscal year and officers continue to explore
areas of investment across the estate. 
3.2.2 The 26/27 Lifecycle Proposals for the PPP Schools estate has been received
from Renfrewshire Schools Partnership and is currently under review by the
Authority. 
2025/26 (New Works) 
Site Work Required
Park Mains H.S. Replace door swing operators and sensors
Johnstone Town Hall
Replace automatic door operator (inner disabled
access door)
Renfrewshire House South roof pipework/insulation replacement

Page 3

PUBLIC
Beechwood Community Centre
Restoration of Mahogany basket weave mosaic
parquet staves (complete)
Johnstone Castle Community Centre Replace Network Video Recorder
Castle Semple Condition survey 
Underwood Road Improve barriers
St Margarets P.S. Remove bossed render
Mary Russell Various roof repairs and gym wall
Weavers Linn Replace fire alarm panel
Renfrew High School Repairs to windows
Houston Park Repair fence
Riverbrae school
Fit access ladder at Sprinkler tank for H&S
purposes
Glenburn Resource Centre Signage and lighting upgrades 
3.3 Public Buildings – Reactive/General Improvement works: 
3.3.1 The Hard FM team are currently working on the following commissions: 
• HQ Building Management System upgrade - options appraisal includes
the installation of new routers and is currently being finalised with ICT.  
• HQ lining of car park, general clean up and drainage works. Works are
on-going. 
• Renfrew Victory Baths – Roofing works to be added to the contract
planned for late 2026/27. Minor improvements or upgrades will be carried
out post contract award.
• Officers continue to explore potential upgrade works within community
buildings and to help promote potential CAT transfers.
• Lochfield Primary School party wall – 3 design packages have been
issued to the neighbours affected. The plan is to knock down the wall and
rebuild during the summer break.
• Over 40 defibrillators across the school estate have been being renewed. 
3.4 Public Buildings compliance – Key Performance Indicators (KPIs) 
3.4.1 Compliance stats for this quarter are on target, returning 90% across all tasks.
Officers will continue to monitor to ensure high levels are maintained. 
3.4.2 Compliance performance within the PPP Schools has returned to 100% for
October, November & December. 
3.5 Public Buildings - Repairs data 
3.5.1 The repairs profile remains as expected, as detailed below:

Page 4

PUBLIC
2025/26
Repairs
Education Core Prestige OneRen Total
7542 1962 958 267 10729 
The pressure on the repairs budget remained a challenge at the end of the
financial year which led to emergency-only jobs. Any deferred jobs will be
actioned early in the 2026/27 financial year. 
3.6 Responsive Repairs 
3.6.1 The numbers shown below are only the repairs carried out by Building Services
on behalf of Housing Services from April 2025 to February 2026. These numbers
are very similar to the total numbers at the same point in 2024/25. 
3.6.2 Repairs to Public Buildings
Building Services carry out responsive repairs across public buildings and OneRen
properties across Renfrewshire. Officers are working with our colleagues within Hard FM
to identify and improve aspects of categorisation to ensure the works are being deployed
with the correct timescale for completion.

Page 5

PUBLIC 
3.6.3 Compliance - Public Buildings
Building Services carry out compliance works across a number of areas. Officers from
both teams work together to continue to track and monitor data to maximise and increase
the compliance of the Renfrewshire Council estate. 
3.7 Voids 
3.7.1 From January through February 2026, Building Services void team received
278 job orders, 79 of which have been full Void packages with an average
estimation of 133 operative hours per property, the team are continuing to
perform well and turn around void properties quickly. 
3.7.2 The increased remedial workload in void properties shows no sign of falling and
continues keeping within KPI targets challenging. Building Services continue to
use every available resource to ensure the timescales are being met, with
reports showing the average void days for Building Services, minus exemptions
in January was 10.7 days and February coming in at 12.2 days, this puts
Building Services in a great position for finishing year end below the 14-day KPI
target. 
4     Soft Facilities Management (Soft FM) 
4.1 School Meals 
4.1.1 The annual School meal survey has been issued for completion by Soft FM staff,
Children's Services staff, pupils and parents to gain wider feedback on the current
menu cycle. Open for 4 weeks this will provide a narrative to develop the next menu
cycle for Aug 2026. This has been shared on learning platforms, and the cashless
catering system Parent Pay. 
4.1.2 New tills are being installed in Renfrewshire Secondary Schools to help assist in the
rollout of the pre-order app across the remaining Secondary School sites. Due to
connectivity issues due to the age of the on-site equipment, this was identified as a
requirement to enable a smoother service delivery without wi-fi connectivity impacting
service. 
4.1.3 All planned kitchen works to upgrade school sites to cooking establishments have been
implemented. A further 2 sites, St John Ogilvie Primary in Paisley and St Fillan's
Primary in Houston, are planned to return to fully operational cooking kitchens by April
2026 utilising remaining capital budget. These will see minor kitchen improvements
carried out with the purchase of new equipment along with the creation of new Senior

Page 6

PUBLIC
Facilities Operative - Production Cook positions. 
4.2 Scottish Child Payment 
4.2.1 Work continues to focus on increasing the number of pupils accessing universal free
school meals (P1–P5), free school meals, and paid meals across both primary and
secondary schools. While uptake remains strong in the early years of primary
education, data indicates a gradual decline in participation among older primary year
groups.   
4.3 Food Waste Management in Renfrewshire Primary Schools 
4.3.1 In response to heightened focus on sustainability and compliance with HMIE
inspections and Food for Life award criteria, Renfrewshire Primary Schools have fully
implemented a comprehensive food waste management strategy. Beginning in August
2025, a structured process was introduced to track and measure food production,
service, and dining hall waste across all schools. This initiative included the installation
of new waste segregation units in dining halls and close collaboration with Children’s
Services to actively engage pupils in reducing food waste through awareness and
participation. 
4.3.2 Branding has now been introduced within school dining environments. New signage,
badges, and associated materials have been implemented and introduced to schools
to promote positive messaging around school meals and sustainability, reinforcing the
importance of reducing waste. 
4.3.3 Food waste at production and service stages has been significantly minimised through
the pre-order system integrated with cashless catering. However, despite these
measures, waste levels within dining halls remain a challenge, primarily due to uneaten
meals and plate waste. A PowerPoint education resource has been developed and
shared with Children's Service’s staff to further share the collaborative approach to
reducing food waste within dining halls continued engagement with pupils, staff, and
stakeholders will be essential to address this issue and drive further improvements. 
4.4    Breakfast Provision 
4.4.1   In response to the Scottish Governments announcement in relation to a free breakfast 
provision for all primary age pupils, discussions have begun with other Local Authorities         
to understand models currently in place and the logistical challenges around the 
supervision of pupils at breakfast services. Due to the announcement of 1 hour per day 
supervision.  
5     Technical Services 
5.1 Current Commissions 
5.1.1 Officers within Technical Services continue to work across the Renfrewshire
Council’s property portfolio and given the workload, major projects are reported
to the respective Board e.g. Education and Children’s Services Board.

Page 7

PUBLIC 
Implications of the Report 
1. Financial – Any financial elements referenced in this report will be progressed
through the Council’s financial & budget planning process. 
2. HR & Organisational Development – Apprentice recruitment detailed in the
report will be undertaken as per standard Renfrewshire Council recruitment
processes. 
3. Community/Council Planning – the report details a range of activities which
reflect local community and council planning themes. 
4. Legal – As detailed within the report. 
5. Property/Assets – As detailed within the report in relation to work on the
Council property portfolio. 
6. Information Technology - None 
7. Equality & Human Rights – The recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following implementation,
the actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8. Health & Safety – Advice and guidance is being given to protect the health and
safety of employees and service users when carrying out priority services for
the
Council in line with government and health guidance. 
9. Procurement – As noted within the report. 
10. Risk – None 
11. Privacy Impact – The Scottish Government have introduced legislation to
allow the data sharing with local authorities in relation to parents/carers who
receive the Scottish Child Payment. 
12. COSLA Policy Position – None 
13. Children’s Rights – Facilities and Property Services are essential in trying to
assist and deliver in support of Children’s Rights. In particular, the report
demonstrates compliance by ensuring buildings are suitable provides good
educational establishments (Article 28 - Access to Education) and by delivering
schools meals and nutritious food (Article 27 – Food, Clothing, and a safe
home).

Page 8

PUBLIC 
14. Climate Change – Parts of the work undertaken in this report will reduce
carbon emissions and assist in trying the reach Net Zero targets by improving
efficiency of current buildings and new buildings across the portfolio. 
List of Background Papers 
None 
Author: Gordon McNeil, Director of Environment, Housing & Infrastructure