Lead Consultant Appointment for the AMIDS South Project
Renfrewshire Council · 5 February 2026
Back to Finance, Resources and Customer Services Policy Board — 5 February 2026 and its agenda
Text extracted from the council's PDF. Layout and reading order may differ from the original.
Page 1
PUBLIC _______________________________________________________________________ To: Finance, Resources and Customer Services Policy Board On: 05 February 2026 _______________________________________________________________________ Report by: The Chief Executive and the Director of Finance and Resources _______________________________________________________________________ Heading: Notification of Cost Increases –Lead Consultant Appointment for the AMIDS South Project (formerly GAIA South Project) (RC-CPU-19-081) _______________________________________________________________________ 1. Summary 1.1 The purpose of this report is to notify the Finance, Resources and Customer Services Policy Board of an increase in cost to the Lead Consultant for the Advanced Manufacturing Innovation District (AMIDS) South (formerly GAIA South) Project appointment. _________________________________________________________________ 2. Recommendations 2.1 It is recommended that the Finance, Resources and Customer Services Policy Board: 2.1.1 Note the increase in the approved contract value for the Lead Consultant for AMIDS South Project (RC-CPU-19-081) contract awarded to Amey OW Limited from £3,000,000.00 excluding VAT to a forecast fee of £8,000,000.00 excluding VAT. 2.1.2 Note the completion of the Lead Consultant for AMIDS South Project (RC- CPU-19-081) contract is anticipated to be the end of March 2028 upon completion of the AMIDS South construction works. 2.1.3 Note that variations to this contract have been negotiated and agreed with the Lead Consultant in accordance with Standing Orders Relating to Contracts 34.4 and 34.5 and follow assessment of best value including Regulation 72 of the Public Contract (Scotland) Regulations 2015.
Page 2
PUBLIC 3. Background 3.1 The AMIDS South project (the Project) will provide a 1.7km ‘gateway route’ along the White Cart river with a network of road, cycling and walking links from the town centre train station and bus interchange to Glasgow Airport, AMIDS and onwards to Inchinnan. The project includes landscaping as well as a new bridge crossing around Paisley Harbour for pedestrians, cyclists and road traffic. AMIDS South is a high-impact local transport scheme which will reduce carbon emissions, improve air quality, cut congestion, support economic growth and improve the experience of transport users. 3.2 As part of the Project, the works include a new east-west road linking Renfrew Road to the new Gateway route which will increase connectivity to and from the new manufacturing district and improve accessibility to the new Paisley Grammar community campus (PGSCC), West College Scotland and the Gallowhill area. A contract for these elements of the AMIDS South works was awarded in August 2025 and the Lead Consultant will provide the project management and site supervision services. 3.3 On 04 September 2019 the Finance, Resource and Customer Services Policy Board approved a recommendation to award the Contract for the Lead Consultant for the AMIDS South (formerly Glasgow Airport Investment Area (South)) Project to Amey OW Limited for a contract value up to £3,000,000.00 exclusive of VAT. 3.4 The reasons for the increase in the Lead Consultant fee forecast from 2019 include changes and enhancements to the scope of the Project, and extensions to the programme requiring extension to the quantity of services required from the Lead Consultant. These modifications and enhancements have been instructed incrementally and are summarised below: i. Additional services relating to the Levelling Up Fund (LUF) including the requirement to work with both the Department for Transport (DfT) and subsequently Active Travel England (ATE) to develop and produce the outline business case to meet LUF governance requirements. As this was a new initiative, DfT and ATE were still in the process of establishing their business case requirements and assembling their teams during the first two years of LUF. This led to the Council’s team having to repeat work to align with newly introduced personnel and evolving business case criteria; ii. Additional surveys and sub-commissions (e.g. ground investigation surveys and site clearance) required to progress the Gallowhill cycle link due to the unexpected discovery of significant drainage and ground condition issues on the old train cutting;
Page 3
PUBLIC iii. Additional services carried out at the direction of the Council’s EH&I service for the development of the plans and drawings for the Paisley Gateway Junctions, a separate project being considered by EH&I; iv. Redesign of proposed elements of the works required for planning and land assembly, including successive revisions of Compulsory Purchase Order (CPO) documentation; v. Additional services due to the requirement for Public Local Inquiry (PLI) relating to the CPO despite the scheme only receiving one objection which necessitated additional documentation, technical support and attendance at the PLI and extended the CPO work requirements by approximately 6 months; vi. LUF granted the Outline Business Case (OBC) approval in February 2023 with conditions that required additional consultant services due to the significant number of additional reviews and requests for information including re-runs of the economic model and traffic model necessary to obtain full approval at Full Business Case (FBC) stage. This was in part due to the changing requirements of LUF outlined above; vii. Additional services to respond to a design audit carried out by Active Travel England (ATE), part of the LUF review team. Consultant required to review the comments issued by ATE and close them out for FBC stage. Again, this was a consequence of the changing LUF requirements; viii. Additional design work required as a result of independent structures and geotechnical checks; ix. Additional design development required on the Harbour Road Retaining Wall as a result of ground investigations indicating that the existing wall condition was poorer than originally anticipated; x. Surveys identified the location of a Scottish Water Sewer on Harbour Road. Design of the protection structure required for crossing the sewer was more complex than initially foreseen by the design team, leading to additional time and resources to resolve with Scottish Water. The main factors impacting the design are: a. Accommodating the highways drainage design, which is affected by Renfrew Road and the school requirements, within the bridge. b. Scottish Water engagement and ensuring their requirements are accommodated within the design, acquiring Scottish Water’s approval and conditions letter. c. design changes to deal with the comments from Scottish Water.
Page 4
PUBLIC xi. Additional services relating to the interface between AMIDS South project and Paisley Grammar School community campus (PGSCC) project, which extended the overall detailed design stage and necessitated rework of the initial AMIDS South design and construction contract documents to accommodate the following: a. A new junction design on Renfrew Road including tie-ins for the PGSCC vehicular and pedestrian accesses. b. Facilitating access for PGSCC Principal Contractor within the site boundary for AMIDS South construction contract during construction phase. c. Redesign of drainage on the east- west link road. d. Redesign where the PGSCC construction works extended into the AMIDS South site boundary e. Constraints added to the AMIDS South construction works contract to require access to the PGSCC via the east-west link road by a specified key date of 30 June 2026; xii. the bridge design required updates to align with the agreed procurement strategy and construction method required for the works contract; xiii. Further geotechnical analysis required to show that the existing quay wall is adequate to carry the additional loads from plant and equipment required during the construction of the improved Harbour Road retaining wall referenced at ix; xiv. The anticipated duration of the works contract has increased from 18 months as assumed at tender stage to 30 months, which necessitates additional costs for extended site supervision and project management support. The overall contract is more complex due to the new junction design on Renfrew Road and the additional complexity of the east west link road with the PGSCC tie-ins and the requirement to deliver this element of the project by 30 June 2026. Along with lessons learned on previous projects as to Contractor delivery times, this necessitated an extension of the overall Construction programme; xv. Anticipated value includes contingency for delay to the construction works contract and contingency for additional design services required in case of compensation events under the construction works contract necessitating re-design work; and xvi. Inflationary increase in key staff rates, in line with the Consumer Price Index and in accordance with the Conditions of Contract over and above initial fee forecasts to cover extended site supervision and project management services required to manage the construction works phase.
Page 5
PUBLIC 3.5 The construction works for the AMIDS South project was awarded on 14 August 2025 for a period of 30 months with completion anticipated in March 2028. As the project is ongoing, there are a number of live risks detailed in the project’s quantified risk assessment including public utility diversions, ground conditions, contamination and non-native invasive species (NNIS) and completion of works to allow access for the PGSCC from Summer 2026 which may impact the services required from the Lead Consultant during the site supervision and contract management phase of the project. It is anticipated the revised contract value for AMIDS South Lead Consultant is sufficient for these risks. _________________________________________________________________ 4. Project Governance 4.1 The modifications and additional instructions for the Lead Consultant have been fully documented and approved in accordance with the Change Control process and project governance, which requires the approval of the City Deal and Infrastructure Programme Board prior to agreeing the final modifications / changes to external consultant appointments. 4.2 The increases in consultant fees will be met from project resources earmarked for site supervision services and contingencies within the agreed budget for AMIDS South. 4.3 This report is submitted in accordance with Standing Order 20.3, which requires that where it becomes apparent that the total value of a contract as previously reported to the Finance, Resources and Customer Services Policy Board is likely to be exceeded by more than the greater of £100,000 or 25% of the approved contract value, that a report on the matter be submitted to the Finance, Resources and Customer Services Policy Board. 4.4 As outlined above, the increase in cost has arisen from a number of factors, which are being monitored closely by the project team. While the cumulative total of the modifications to the external consultant appointment is high, each modification has been made in accordance with the Council’s Standing Orders relating to Contracts and with consideration to Regulation 72 (1) (a) or 72 (1) (e) of the Public Contract Scotland Regulations 2015 where appropriate for each modification over the course of the contract. Implications of the Report 1. Financial - The increase of £5m in consultant fees will be met from capital project resources earmarked for site supervision services and contingencies within the agreed budget for AMIDS South. 2. HR & Organisational Development – None directly arising from this report.
Page 6
PUBLIC 3. Community/Council Planning - Reshaping our place, our economy and our future - The contract will assist the project team in delivering the strategic aims and outcomes of the Council’s AMIDS South project and objectives of the Levelling Up Fund (LUF). 4. Legal – While the cumulative total of the modifications to the external consultant appointment is high, each modification has been made in accordance with the Council’s Standing Orders relating to Contracts and with consideration to Regulation 72 (1) (a) or 72 (1) (e) of the Public Contract Scotland Regulations 2015 where appropriate for each modification over the course of the contract. As noted in item 4.1, each modification and additional instruction for the Lead Consultant contract as summarised in item 3.4 have been approved in accordance with the Change Control process and project governance for the City Deal & Infrastructure (CD&I) Programme Board. 5. Property/Assets - None directly arising from this report 6. Information Technology - None directly arising from this report. 7. Equality & Human Rights – The recommendations contained within this report have been assessed in relation to their impact on equalities and human rights. No negative impacts on equality groups or potential for infringement of individuals’ human rights have been identified arising from the recommendations contained in the report. 8. Health & Safety- None directly arising from this report. 9. Procurement - The modifications were considered in accordance with the Council’s Standing Orders relating to Contracts and officers do not consider any of these to be substantial modifications to the existing contract and therefore permissible under Regulation 72 (1) (e) of the Public Contracts (Scotland) Regulations 2015. 10. Risk – As noted in item 3.7, the AMIDS South project is ongoing and there are live risks that may further impact the progress of the project, and the constructions works. It is anticipated the revised contract value noted in item 2.1.1 is sufficient for risks. However, the project team will continue to monitor the services required from the Lead Consultant and report any further modifications or additional instructions required through the CD&I programme board for approval in accordance with the Change Control process and project governance. 11. Privacy Impact - None directly arising from this report. 12. Climate Risk - None directly arising from this report.
Page 7
PUBLIC 13. Children’s Rights – None directly arising from this report. 14. Cosla Policy Position - None directly arising from this report. _________________________________________________________ List of Background Papers a) Contract Authorisation Report for the Contract for the Lead Consultant for the AMIDS South (formerly Glasgow Airport Investment Area (South)) Project approved by the Finance Resources and Customer Services Policy Board on 04 September 2019. b) Unaudited Annual Accounts 2024/25 and Interim Financial Update approved by the Council at its meeting on 26 June 2025. _________________________________________________ Author: Rebecca Park, Strategic Category Manager – City Deal and Infrastructure, rebecca.park@renfrewshire.gov.uk