Park Mains High School Extension – Design and Build – Advance Works Contract

Renfrewshire Council · 5 February 2026
Back to Finance, Resources and Customer Services Policy Board — 5 February 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

PUBLIC 
___________________________________________________________________
To: Finance, Resources and Customer Services Policy Board
On: 5 February 2026
___________________________________________________________________
Report by: Report by the Director of Environment, Housing and Infrastructure and
the Director of Finance and Resources
___________________________________________________________________
Heading: Contract Authorisation Report for Park Mains High School Extension –
Design and Build – Advance Works Contract (RC-CPU-24-053)
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to seek the approval of the Finance, Resources
and Customer Services Policy Board to award an Advance Works Contract for
Park Mains High School Extension – Design and Build (RC-CPU-24-053) to
Galliford Try Construction Limited, T/A Morrison Construction Scotland (co.no.
02472080). 
1.2 The Pre-Construction Services Agreement, approved at the Finance,
Resources and Customer Services Policy Board meeting on 13 February
2025, is due for completion in May 2026. RIBA stage 3 is complete, and it is
currently in RIBA stage 4. At the Finance, Resources and Customer Services
Policy Board meeting on 13 February 2025, it was advised that a further
report would be brought to a future Finance, Resources and Customer
Services Policy Board to seek approval of the award of an Enabling Works
Contract. For clarity, the Enabling Works Contract is now renamed the
Advance Works Contract. 
1.3 Formal approvals are now required to progress the Project to ensure it
remains on track with the agreed timescales; therefore the Finance,
Resources and Customer Services Policy Board approval is requested to
award the Advance Works Contract Park Mains High School Extension –
Design and Build to Galliford Try Construction Limited, T/A Morrison
Construction Scotland.

Page 2

PUBLIC
___________________________________________________________________ 
2. Recommendations
It is recommended that the Finance, Resources and Customer Services Policy
Board: 
(a) Authorises the Head of Corporate Governance to award an Advance
Works Contract for the Park Mains High School Extension – Design and
Build (RC-CPU-24-053) to Galliford Try Construction Limited, T/A
Morrison Construction Scotland (co.no. 02472080). 
(b) Authorises the amount for the Advance Works Contract of £1,876,270.82
exclusive of VAT. 
(c) Authorise a contingency spend of £187,627.08 which equates to 10% of
the Advance Works Contract. 
(d) Authorise a total Approved Contract Value of £2,063,897.90 (which is
the total of the Advance Works Contract plus the contingency spend)   
(e) Authorises that the Contractor’s total liability for matters which would be
covered by Professional Indemnity is limited to £10m in the aggregate
with an annual automatic reinstatement. 
(f) Note the anticipated Date of Commencement of the Works is 23 March
2026 and the Date for Completion is 12 weeks from the Date for
Commencement of the Works. The actual dates will be confirmed in the
Council’s Letter of Acceptance to Galliford Try Construction Limited, T/A
Morrison Construction Scotland. 
(g) Note that a further report will be brought to a future Finance, Resources
and Customer Services Policy Board seeking formal approval to enter
into the Design and Build Contract (the Main Works) with Galliford Try
Construction Limited, T/A Morrison Construction Scotland.
_________________________________________________________
3. Background
3.1 This procurement exercise is for the appointment of a Contractor for the
creation of an extension at Park Mains High School. The requirement
was tendered for a single Contractor to provide both pre-construction
services and construction.
Park Mains High School is located in Erskine within the Renfrewshire
Council area. Learning estate planning is central to the Council’s asset
management strategy. Planned housing developments within the
school catchment area will  result in significant school roll growth.

Page 3

PUBLIC
As a result of these planned housing developments there is a need to
increase the current pupil capacity within Park Mains High School by
extending the current building infrastructure to accommodate the
increasing pupil roll. 
3.2 The procurement exercise is for a single contractor to deliver all
Contracts related to the Park Mains High School Extension. This
procurement was tendered as an above Threshold procurement in
accordance with Public Contracts (Scotland) Regulations 2015
Regulation 29 – Restricted Procedure. The Restricted Procedure is
conducted in two stages, Selection (Stage 1) and Invitation to Tender
(Stage 2). 
3.3  The Pre-Construction Services are due to conclude May 2026, RIBA
stage 3 is complete, RIBA Stage 4 is currently underway. The
requirement for final design services will be instructed under the Pre-
Construction Services Agreement under the existing Terms and
Conditions and the already approved budget. 
3.4 It has been identified that an Advance Works Contract is required to
ensure the project is delivered on time. The Advance Works will consist
of site set-up, soil strip & formation of pilling mat, localised drainage
and fire hydrant diversions, installation of underground drainage
attenuation tanks and formation of the new carpark to base course
level. The Advance Works Contract will also allow the Contractor to
place orders for materials with long lead times that will be required by
the Contractor to complete Phase 1 of the internal re-purposing work
within the existing school building. This work is planned during over the
2026 summer school holiday period. 
3.5 The form of Contract to be utilised for the Advance Works Contract is
the SBCC Minor Works Building Contract with Contractor’s Design for
use in Scotland 2016 edition accompanied with bespoke Employer’s
Amendments. 
3.6 Subject to further approval from a future Finance, Resources and
Customer Services Policy Board, the intention would be to enter into a
Design and Build Contract with Galliford Try Construction Limited, T/A
Morrison Construction Scotland at the end of RIBA stage 4 to complete
the Main Works construction contract. As tendered, the form of Design
and Build Contract required will be SBCC Design and Build Contact for
use in Scotland 2016 edition accompanied with bespoke Employer’s
Amendments and Preliminaries.

Page 4

PUBLIC
3.7 Mandatory Community Benefits were included as a condition of
contract award. Galliford Try Construction Limited T/A Morrison
Construction Scotland confirmed they would provide community
benefits as disclosed with their Tender Submission. The commitment
as tendered was to deliver 10 employment opportunities. 
In addition to the mandatory Community Benefits Galliford Try
Construction Limited T/A Morrison Construction Scotland committed to
delivering 180 community benefit points. The community benefits to be
delivered across, Pre Constructions Services, Advance Works and the
Main Contract will be agreed and will include discussion with the
Council’s Community Benefit Forum.
3.8 The costs for all Contracts forming the Park Mains High School
Extension – Design and Build (RC-CPU-24-053) will be met through the
Capital – General Services budget. 
___________________________________________________________________
Implications of the Report
1. Financial - The cost for this Advance Works Contract of £2,063,897.90
(which is the total of the Advance Works plus the contingency spend)
excluding VAT, will be met through the Capital – General Services
budget. 
2. HR & Organisational Development - None directly arising from this
report. 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – maximising economic growth,
which is inclusive and sustainable.
• Our Renfrewshire is well - supporting the wellness and resilience
of our citizens and communities.
• Our Renfrewshire is fair - addressing the inequalities which limit
life chances.
• Our Renfrewshire is safe - protecting vulnerable people and
working together to manage the risk of harm.   
Place:
- Demonstrating that Renfrewshire is a great place to grow up, it's a
place of opportunity for those that live and work here,

Page 5

PUBLIC 
Economy:
- Improving lives and securing wellbeing through a stronger, inclusive
and sustainable economy, being creative, imaginative and linking
opportunities to enhance the benefits for Renfrewshire. 
- Matching the skills developed in Renfrewshire with the opportunities
available in Renfrewshire and equipping all children and young
people to achieve success in life. 
Fair: 
- Reducing inequalities in Renfrewshire, focusing on supporting our
communities through the cost-of-living crisis with dignity and
empowering people to live fulfilled lives. 
Green: 
- Working across partners and communities to deliver the priority
areas highlighted in our Plan for Net Zero, working towards a net
zero Renfrewshire by 2030.
- Ensuring our journey to net zero is a just transition with climate
justice and fairness at the heart, finding opportunities to challenge
inequalities in new green ways as we tackle the climate crisis.
- Integrating climate considerations into our long term strategic and
financial planning as an organisation 
- Planning for future climate adaptations when designing our services
and our developing our place, particularly considering the impacts
for our most vulnerable citizens.
- Boosting our green economy, creating good green jobs that are
sustainable for the future. 
Living Our Values:
- Leading positively through transition and change. 
- Delivering best value for our citizens and customers. 
4. Legal - The procurement of this and related Contracts for the Park
Mains High School Extension have been conducted in accordance with
the Restrictive Procedure under the Public Contracts (Scotland)
Regulations 2015, as amended and the Renfrewshire Council’s
Standing Orders Relating to Contracts for an above GPA works
Contract.

Page 6

PUBLIC
5. Property/Assets - The Council’s investment in its learning estate offers
the opportunity for a place-based approach to local outcomes:
integrating local services to support communities. Extending the current
building infrastructure at Park Mains High School to accommodate the
increasing pupil roll. 
6. Information Technology – None directly arising from this report 
7. Equality & Human Rights - None directly arising from this report.
8. Health & Safety - Galliford Try Construction Limited, T/A Morrison
Construction Scotland health and safety credentials were evaluated by
Corporate Health and Safety and met the Council’s requirements
regarding health and safety for this procurement exercise 
9. Procurement – The procurement procedures outlined within this report
shall ensure the Council meets its statutory obligations in respect of the
Public Contracts Scotland Regulations 2015, the Renfrewshire
Council's Standing orders Relating to Contracts and the Renfrewshire -
Council's Financial Regulations.   
10. Risk - The Contractor’s total liability for matters which would be
covered by Professional Indemnity is limited to £10m in the aggregate
with an annual automatic reinstatement. 
Project specific risk registers have been established. These internal risk
registers will be kept under regular review and reported to the Council’s
internal Learning Estate Project Board. 
11. Privacy Impact - None directly arising from this report.
12. Climate Risk – The level of impact associated with the provision of
these works have been assessed using the Scottish Government
Sustainability Test and is considered to be overall high risk. 
Mitigations the Council has taken in regard to sustainability within this
Contract is to include contractual elements within the Scope such as:
- The Contractor should aim to ensure that any deliveries to site are
consolidated to reduce emissions.  
- The Contractor is required to provide a Site Specific Waste
Management Plan detailing where all the waste produced will be
recycled or if it cannot be recycled where the waste will go.

Page 7

PUBLIC
13. Children’s Rights – This report does not cover a new policy, function
or strategy nor a substantive change to an existing policy, function or
strategy which will have an impact on children’s rights. 
14. Cosla Policy Position – None directly arising from this report.
_______________________________________________________
List of Background Papers 
(a) Contract Authorisation Report: Park Mains High School Extension –
Design and Build (RC-CPU-24-053) on 13 February 2025 to Finance,
Resources and Customer Services Policy Board
___________________________________________________________________ 
Author:           Joanna Tannock, Interim Strategic Category Manager, Corporate
Procurement Unit, Joanna.tannock@renfrewshire.gov.uk