Page 1

PUBLIC 
To: Finance, Resources and Customer Services Policy Board
On: 05 February 2026 
Report by: Director of Environment, Housing & Infrastructure 
Heading: Facilities and Property Services - Service Update Report 
1 Summary 
1.1 Environment, Housing & Infrastructure brings together a range of Council
services and activities, with both strategic and operational responsibilities. This
report provides an operational performance update on Facilities Management
(Hard and Soft Services), Building Services and Technical Services delivered by
Environment, Housing & Infrastructure since the last Policy Board in November
2025. 
2 Recommendations
It is recommended that members of the Finance, Resources and Customer
Services Policy Board: 
2.1 Note the content of this report. 
3 Operational Update 
Hard Facilities Management (Hard FM) 
3.1 Public Buildings – Capital Projects 
3.1.1 As part of on-going improvements for sports/activities across the learning estate,
Officers are currently exploring the provision for additional Multi Use Games
Arenas (MUGAs) and upgrades to red blaes pitches, within a number of primary
schools. These works will be discussed with Children’s Services and undertaken
on a priority basis as the budget allows. A commission has been raised for
feasibility studies to 5 schools:
• Barsail PS
• St Anne’s PS

Page 2

PUBLIC
• Gallowhill PS
• East Fulton PS 
• Kilbarchan PS 
Once the feasibility study is complete, a further update will be brought back to this
policy board. 
3.1.2 Waterproofing/ramp works at Renfrewshire House have now been completed. 
3.1.3 The tender for decarbonisation surveys to 5 schools went out to the market and
was reviewed in late January 2026. 
3.2 Public Buildings - Lifecycle Replacement works 
Works have progressed well this fiscal year and officers continue to explore
areas of investment across the estate. 
2025/26 (New Works) 
Site Work Required
McKillop Institute Lining Disabled car park spaces
Castle Semple Country
Park Replace shutter
Parkmains HS Replace PC lighting control
Castlehead HS Replace carpet 
Ralston PS Electric works (re-cabling)
Trinity HS Renew Single door set 
3.3 Public Buildings – Reactive/General Improvement works: 
3.3.1 The Hard FM team are currently working on the following commissions:
• Condition surveys for various community buildings (19 buildings in
total). Surveys have concluded and reports are being reviewed.
• HQ Building Management System upgrade - options appraisal includes
the installation of new routers and is currently being finalised with ICT.  
• HQ lining of car park, general clean up and drainage works. Works due
to commence in early 2026. 
• Underwood Road Depot – improvements to depot systems and security
on going. Progress to date includes interlinking of all fire alarms
systems. 
• Back Sneddon Street refurbishment – cost plans currently being finalised.
Some priority works planned for early 2026.
• Renfrew Victory Baths – roofing works prior to further capital investment.
• Children Services upgrade works within various schools following Care
Inspectorate inspection and recommendations. 
• Howwood Village Hall (minor internal upgrade works) is currently with

Page 3

PUBLIC
contractor for pricing.
• Officers continue to explore potential upgrade works within community
buildings and to help promote potential CAT transfers. 
3.4 Public Buildings compliance – Key Performance Indicators (KPIs) 
3.4.1 Compliance stats for this quarter are slightly below target returning 88% across
all tasks. Officers will continue to monitor to ensure high levels are maintained. 
3.4.2 Compliance performance within the PPP Schools estate dropped to 92.5% for
September 2025 due to 5 tasks being completed late. 
3.5 Public Buildings - Repairs data 
3.5.1 The repairs profile remains as expected, as detailed below: 
2025/26
Repairs
Education Core Prestige OneRen Total
6096 1544 779 211 8630 
The pressure on the repairs budget remains a challenge as such, all non-
essential works are currently being deferred for the remainder of the financial
year. 
3.5.2 The new Multi-Trade Framework is up and running and is currently progressing
as expected. Officers have met with all the new suppliers and work orders are
now being issued. Moving forward, regular meetings will be set up to ensure
performance targets are met. 
3.6 Responsive Repairs 
3.6.1 The numbers shown below are only the repairs carried out by Building Services
on behalf of Housing Services from April 2025 to December 2025. These
numbers are very similar the total numbers at the same point in 2024/25.

Page 4

PUBLIC 
3.6.2 Repairs to Public Buildings 
Building Services carry out responsive repairs across public buildings and OneRen
properties across Renfrewshire. Officers are working with our colleagues within Hard FM
to ensure the categorisation of the urgent repairs is correct. 
3.6.3 Compliance - Public Buildings 
Building Services carry out compliance works across a number of areas. Officers continue
to track and monitor data to maximise and increase the compliance of the Renfrewshire
Council estate. There are a large number of electrical certificates requiring to be validated
by the Qualified Supervisor and as a result, another Officer is due to be recruited. 
3.7 Voids 
3.7.1 From October 2025 through December 2025, Building Services void team have
received 469 job orders, and continue to perform well and turn around void
properties quickly. 
3.7.2 The increased remedial workload in void properties makes keeping within KPI
targets challenging, this is further heightened by the increase in GCH installs
which require completion before the majority of other Trades can begin work
within void properties. Building Services continue to use every available
resource to ensure the timescales are being met, with reports showing the
average void days for Building Services minus exemptions in Q3 was 13.3
days. The current average is below the 14 day KPI for the first time since post
Covid (Q2 2019-2020, 13.8 days). 
3.7.3 Building Services have continued the implementation of the 360° Viewing
Technology with a mix of 291 post and pre-tenancy tours carried out over Q3,
this brings the total number of tours carried out since the technology was

Page 5

PUBLIC
introduced last year to 1,685. 
3.8 Electrical Testing programme 
3.8.1 There is currently a programme for carrying out the Electrical Installation
Condition Report (EICR) testing across both Housing properties and Public
Buildings. Building Services are working hard to ensure that the electrical
compliance across both domestic and public buildings is maintained. 
3.8.2 For every electrical job carried out across Renfrewshire, even minor works,
there requires to be an electrical certificate issued by the electrician and then
fully checked by the Electrical QS (Qualified Supervisor) before it is issued. The
chart below demonstrates the volume of electrical work and certificates that are
being managed by Building Services. 
• 21% increase from quarter 1 to quarter 2.
• 24% increase from quarter 2 to quarter 3.

Page 6

PUBLIC 
3.9 Gas servicing 
3.9.1 From October 2025 to the end of December 2025, the domestic gas servicing
and repairs team carried out 3,600 gas services. This is 30% higher than the
gas services carried in the previous 2 years due to the change in procedures
to service a boiler at a forced entry if there is sufficient funds in the meter. 
3.10 Kitchen and Boiler Replacement Programme 
3.10.1  Building Services have commenced work to put a programme in place to replace a
substantial number of kitchens and gas boilers throughout the estate. Surveys and pre-
measures have commenced, and boiler installations began on the 23 July 2025 and
Kitchen installations started in August 2025.

Page 7

PUBLIC 
3.10.2  Boilers 
Building Services are now fitting 16 Boilers per week. There were 242 fitted and installed
by 31 December 2025. 100% inspection checks from Building Services have been
undertaken and agreed following  inspections by Housing Services Quality Officers. All
categories are achieving positive feedback following the checks with Housing Services
and tenant. 
3.10.3 Kitchens 
Building Services are fitting 8 kitchens per week. Since the 11 August 2025, there have
been 72 fully completed kitchens by 31 December 2025. 100% inspection from Building
Services with routine inspections by Housing Services. All categories are achieving
positive feedback following the checks with Housing Services and tenant. 
Building Services were made aware on 19 January 2026 that the kitchen supplier that had
been awarded the contract via the procurement framework had gone into administration.
Officers are working with colleagues in Corporate Procurement to assess options to
appoint a new supplier and an update will be provided to this Policy Board in due course.  
3.11 Capital / Planned Works 
3.11.1 School Toilet Refurbishments
Works are currently ongoing to refurbish school toilets. This has been an
ongoing program working through the education estate to improve the toilets
within schools. Works include Wetwall, vinyl flooring, ceilings, new sanitary
ware and plumbing, all electrics including hand dryers, new radiators, new
cubicles vanity units and decoration. 
3.11.2 Building Services have recently completed Barsail PS. St Charles PS toilet
refurbishment started in January 2026. 
3.12 Apprentices/Training 
3.12.1 Building Services submitted 13 comprehensive apprentice applications for
APSE - UK apprentice of the year 2026. 4 Apprentices have made it through
to the finals (Joiner/Painter/Electrical and Non-Trade specific) with the event
being held on 5/6 March 2026. 
4     Soft Facilities Management (Soft FM) 
4.1 School Meals 
Kitchens & Boilers KPI Target Jul-25 Aug-25 Sep-25 Oct-25 Nov-25 Cumulative Status
1.0  Satisfaction 1.1 Customer Satisfaction 85% n/a n/a 96% 100% 93% 96% ✓ On Track
2.0  Quality 2.1 Zero Defects 90% 100% 95% 100% 90% 94% 96% ✓ On Track
3.0 Timescales 3.1 Units 80% 100% 100% 100% 90% 100% 98% ✓ On Track
4.0 Programme 4.1 Programme Updates 90% 100% 100% 100% 100% 100% 100% ✓ On Track
5.0 Health & Safety 5.1 RIDDOR Notifications 100% 100% 100% 100% 100% 100% 100% ✓ On Track
5.2 Risk Management 100% 100% 100% 100% 100% 100% 100% ✓ On Track

Page 8

PUBLIC
4.1.1 The rollout of the pre-order app continues across the remaining secondary school sites,
supporting Renfrewshire Council’s commitment to improving the school dining
experience and reducing food waste. Registration data shows steady growth, with Park
Mains High School reporting 440 pupils registered and Castlehead High School at 298
registrations. 
Feedback from pupils has been overwhelmingly positive, highlighting key benefits such
as reduced queuing times and the ability to secure their preferred lunch choices, which
enhances satisfaction and minimizes waste from unserved meals. 
Work will continue to promote the functionality of the system within the remaining
schools ahead of their go-live dates. Engagement activities will focus on demonstrating
the convenience and efficiency of the app to pupils, ensuring a smooth transition and
maximizing uptake. 
4.1.2 The pre-order app has now been successfully implemented for senior pupils at St
Benedict’s High School within the PPP school estate. 
PPP Management has adopted a targeted approach to increase uptake, resulting in      
372 active users at St Benedict’s High School. Plans are in place to extend the rollout
to other PPP school sites, with promotional activities aimed at demonstrating the
benefits of the system to pupils prior to go-live. Early feedback indicates that pupils
value the convenience of securing their preferred meal choices and the efficiency of the
lunch service. 
4.1.3 The introduction of a new menu for mid-year has contributed to an increase in school
meal uptake. A review of preferred choices will be undertaken, with adjustments made
to the current menu to further reduce dining hall waste.  The annual pupil and parent
survey, undertaken in January 2026, will inform the next menu cycle due for
implementation August 2026. 
4.1.4 In addition to these initiatives, significant kitchen upgrades were completed in early
November 2025 at Heriot PS, Kilbarchan PS, Our Lady of Peace PS, and St
Margaret’s PS. These schools have now returned to fully operational production
kitchens, supporting improved service delivery and compliance with food safety
standards. 
4.1.5 HMIE Health & Nutrition inspection was undertaken at Castlehead High School in
November 2025 with recommendations for further promotion of fruit & vegetables to
actively encourage increased consumption. Actions have been implemented. 
4.2 Scottish Child Payment 
4.2.1 Work continues to focus on increasing the number of pupils accessing Universal Free
School Meals (P1–P5), Free School Meals, and paid meals across both primary and
secondary schools. While uptake remains strong in the early years of primary
education, data indicates a gradual decline in participation among older primary year
groups.   
As part of the 2026 strategy, targeted efforts will be made to increase uptake in P4-P7

Page 9

PUBLIC
ensuring pupils continue to benefit from healthy, balanced meals and supporting the
wider objectives of reducing food waste and improving nutritional outcomes.
Engagement will include collaboration with schools, parents, and pupils to understand
barriers to participation and implement initiatives that encourage consistent meal
uptake 
4.2.2 A process was implemented on 4 April 2025 where Parents/Carers of pupils in P6/7
that are eligible for Scottish Child Payment can apply for Free School Meals.
Renfrewshire Council continues to share with families as part of the general contact
relating to School meals, Clothing grants and changes to eligibility criteria. 
4.3 Food Waste Management in Renfrewshire Primary Schools 
4.3.1 In response to heightened focus on sustainability and compliance with HNIE
inspections and Food for Life award criteria, Renfrewshire primary schools have
implemented a comprehensive food waste management strategy. Beginning in August
2025, a structured process was introduced to track and measure food production,
service and dining hall waste across all schools. This initiative included the installation
of new waste segregation units in dining halls and close collaboration with Children’s
Services to actively engage pupils in reducing food waste through awareness and
participation. 
4.3.2 To further support this strategy, branding enhancements have been introduced within
school dining environments. New signage, badges, and associated materials have
been developed to promote positive messaging around school meals and
sustainability, reinforcing the importance of reducing waste. 
4.3.3 Food waste at production and service stages has been significantly minimized through
the pre-order system integrated with cashless catering. However, despite these
measures, waste levels within dining halls remains a challenge, primarily due to
uneaten meals and plate waste. Continued engagement with pupils, staff, and
stakeholders will be essential to address this issue and drive further improvements. 
5     Technical Services 
5.1 Current Commissions 
5.1.1 Officers within Technical Services continue to work across the Renfrewshire
Council’s property portfolio and given the workload, major projects are reported
to the respective Board e.g. Education and Children’s Services Board. 
5.2 Infrastructure Programme 
5.2.1 Renfrewshire House Archive Store Waterproofing/Ramp Upgrade
o The commencement date was 12 July 2025, the existing condition
of the ramp was in much worse condition that anticipated from the
trial pits that were dug as per the site investigation works. Works
were delayed and are now complete. The main source of delay has
been primarily the wet weather inhibiting the contractor from
installing the waterproofing and concrete.

Page 10

PUBLIC
5.2.2 Heriot PS Boiler House Heating Pipe Replacement
o Tender documents have been revised and updated to capture some
of the issues identified as part of the initial tender process. The
works are programmed for site commencement in summer 2026.
Major repairs have been completed to allow the building to operate
as normal. 
5.3 Life Cycle Maintenance: Schools Retrofit Programme 
5.3.1 External consultants are currently being engaged to carry out feasibility studies
on potential energy efficiency upgrades across five initial school and ELCC
sites. A procurement exercise/approach has been agreed and will be taken
forward. Hard FM has directed Technical Services to initiate a pilot project at
Douglas Street ELCC. 
5.4 Life Cycle Maintenance: General Programme 
5.4.1 Technical Services, in collaboration with Hard FM, is currently reviewing the
short-term component renewal programme. The aim is to identify priority works
over the next 1–3 years, focusing on boilers, MUGAs, and other key
components. Proposed projects are being cross-referenced with upcoming
Children’s Services estate plans to avoid duplication and reduce costs. 
Implications of the Report 
1. Financial – Any financial elements referenced in this report will be progressed
through the Council’s financial & budget planning process. 
2. HR & Organisational Development – Apprentice recruitment detailed in the
report will be undertaken as per standard Renfrewshire Council recruitment
processes. 
3. Community/Council Planning – the report details a range of activities which
reflect local community and council planning themes. 
4. Legal – As detailed within the report. 
5. Property/Assets – As detailed within the report in relation to work on the
Council property portfolio. 
6. Information Technology - None 
7. Equality & Human Rights – The recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following implementation,
the actual impact of the recommendations and the mitigating actions will be

Page 11

PUBLIC
reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8. Health & Safety – Advice and guidance is being given to protect the health and
safety of employees and service users when carrying out priority services for
the
Council in line with government and health guidance. 
9. Procurement – As noted within the report. 
10. Risk – None 
11. Privacy Impact – The Scottish Government have introduced legislation to
allow the data sharing with local authorities in relation to parents/carers who
receive the Scottish Child Payment. 
12. COSLA Policy Position – None 
13. Children’s Rights – Facilities and Property Services are essential in trying to
assist and deliver in support of Children’s Rights. In particular, the report
demonstrates compliance by ensuring buildings are suitable provides good
educational establishments (Article 28 - Access to Education) and by delivering
schools meals and nutritious food (Article 27 – Food, Clothing, and a safe
home). 
14. Climate Change – Parts of the work undertaken in this report will reduce
carbon emissions and assist in trying the reach Net Zero targets by improving
efficiency of current buildings and new buildings across the portfolio. 
List of Background Papers 
None 
Author: Gordon McNeil, Director of Environment, Housing & Infrastructure