Democracy Spraffa

Paisley Grammar School Community Campus Update Report

Renfrewshire Council · 19 January 2023
Back to Education and Children's Services Policy Board — 19 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Page 1 of 6 
To:  Education and Children’s Services Policy Board
On: 19 January 2023
__________________________________________________________________ 
Report by:  Joint Report
Director of Children’s Services &
Director of Finance and Resources
__________________________________________________________________ 
Heading:  Paisley Grammar School Community Campus:  Update
Report
__________________________________________________________________
1. Summary
1.1 A formal consultation on the proposal to relocate Paisley Grammar School to
a new community campus building at Renfrew Road in Paisley commenced
on 31 August 2020 and closed on 20 October 2020.
1.2 The proposal gained support from the school, wider community and Education
Scotland and the recommendation to progress the new build community
campus was approved by the Education and Children’s Services Policy Board
in January 2021.
1.3 The new community campus will provide facilities for the full breadth of the
curriculum. It will incorporate a flexible learning resource for young people
with additional support needs and a variety of facilities to support community
learning and enterprise activity for the wider community.
1.4 To supplement its investment the Council secured Scottish Government -
Scottish Futures Trust (SFT) - Learning Estate Investment Programme (LEIP)
funding of £1.45m per annum over a 25 year period. Conditions of funding
targetted completion of the project by December 2025.  Detail of LEIP funding
conditions were detailed in a previous report to Board (Paisley Grammar
School Community Campus: Update Report 18 August 2022).
1.5 This report seeks to provide elected members with an update on progress
including the target completion date following project development with the
Muti Diciplinary Design Team, the pre construction services Contractor and
crucially, the Scottish Futures Trust.
__________________________________________________________________

Page 2

Page 2 of 6 
2. Recommendations
2.1. The Education and Children’s Services Policy Board is asked to:
 Note the progress made to date including the updated target
completion date.
__________________________________________________________________
3. Background
3.1. A formal consultation on the proposal to relocate Paisley Grammar School to
a new community campus building at Renfrew Road in Paisley commenced
on 31 August 2020 and closed at 12 noon on 20 October 2020.
3.2. The proposal gained support from the school, wider community and Education
Scotland and the recommendation to progress the new build community
campus was approved by the Education and Children’s Services Policy Board
in January 2021.
3.3. The new community campus will provide facilities for the full breadth of the
curriculum. It will incorporate a flexible learning resource for young people
with additional support needs and a variety of facilities to support community
learning and enterprise activity for the wider community.
3.4. The Council’s vision for the new Campus is ambitious and forward thinking.  It
is expected that our Project Team will deliver an innovative and creative
learning environment which is welcoming to all; learner focused; supportive
and inclusive; sustainable; and agile enough to support the needs and
aspirations of all users.
3.5. The project has been developed through a stand-alone Multi-Disciplinary
Design Team (MDDT) appointment (as well as QS, BIM manager; Principal
Designer; and Passivhaus certifier appointments) and a stand-alone Design
and Build Contractor.  Information regarding appointments were detailed in a
previous report to Board (Paisley Grammar School Community Campus:
Update Report 18 August 2022).
3.6. A communications plan has also been developed to ensure pupils, parents
and staff are kept up to date. It supports community engagement and it will
raise wider local awareness. The plan also aligns with communication relevant
to wider regeneration of the area.

Page 3

Page 3 of 6 
4. Progress Update:  Multi-Disciplinary Design Team and Principal
Contractor
4.1. A Multi Disciplinary Design Team was appointed on 20 May 2022.  The design
team is being led by Ryder Architecture Limited which has a wealth of
experience of schools’ construction and Passivhaus building structures. 
4.2. Galliford Try, trading as Morrison Construction, have been appointed as the
Principal Contractor for delivery of the project. At this stage the appointment is
in respect of Pre-Construction Services only.  A further report will be taken to
FRCS board to enter into the Design and Build Contract with Morrison
Construction when the design is sufficiently advanced. 
4.3. The design development has progressed well including staff, pupil and wider
access workshops being undertaken to consider space typologies and new
learning spaces and a presentation on the new learning landcape has been
develivered to the parent council.
4.4. The first 'Design Sprint' has taken place which was a 2 day event facilitated by
Ryder Architecture involving the full design team and RC internal
stakeholders. This allowed intense design workshops to be undertaken to help
drive the direction of the technical development of the building.
4.5. The MDDT are currently reviewing the standard ‘Royal Institute of British
Architects (RIBA) Plan of Works Stage 2 Report with positive feedback. The
outcome of RIBA Stage 2 should be the Architectural Concept being approved
by the client which aligns to the Project Brief. 
__________________________________________________________________
5. Programme Update
5.1. It should be noted that a condition of LEIP funding was that the new Paisley
Grammar School Community Campus targeted operation by December 2025.
Given the global market conditions affecting the availability of materials and
labour in the construction industry, this was recognised as an extremely
challenging delivery programme.
5.2. Property Services have undertaken a thorough review of the delivery
programme in conjunction with the MDDT and pre-construction services
Contractor.  The result is that it has become clear that it will not be optimal to
meet the target operational date of December 2025.  In developing the
optimum delivery strategy it would be beneficial to attain 100% design,
excepting some Contractor Designed Portions, prior to agreement of the
contract for the main works.  The MDDT also wish to ensure that the golden
thread from design to construction to operation is given due consideration to
provide an excellent facility that performs well throughout its life cycle.  The
Project Team are minded that a delivery programme of December 2025 would
not meet this objective and is likely to create substantial financial and
programme risks to any contractual agreement we would enter on this
basis.  Furthermore, this programme could not deliver a building of the form
and function that would best suit pedagogy for this School in the
aforementioned target timescale.

Page 4

Page 4 of 6 
5.3. To deliver the proposed Paisley Grammar School Community Campus
(PGSCC) in the optimal way the team would like to implement an improved
approach to quality which has been developed in partnership with the MDDT
and pre-construction services Contractor.  It is intended to meaningfully
engage with the Sub-Contractor market in a competitive manner as soon as
possible during RIBA Stage 3 to develop ‘not to exceed’ work package costs
with the intention to align design with key Sub-Contractor partners who may
then be appointed for the main works.  This will continue during RIBA Stages
3 and 4 with all Sub-Contractors where design engagement will be carried out
to varying degrees, based on the particular work package, to achieve as close
as possible to 100% design and 100% cost certainty.  This strategy flips some
traditionally post contract design work into the pre-contract stage and this can
substantially decrease risk and improves quality, however, this process
inevitably extends the programme during the pre-contract phase of
development.  The Project Team have worked closely with the MDDT and
pre-construction services Contractor as well as the Scottish Futures Trust to
develop a robust delivery programme that responds to the reality of the
current circumstances of the construction industry and the quality aspirations
of the Team.  This process led to the identification of an operational ready
date during Summer 2026 that best suits the needs of pupils and staff
alike. This programme would also avoid a school relocation over the Spring
Break which could be disadvantageous to the senior school pupils’ exam diet.
5.4. SFT have advised that a number of LEIP funded projects across Scotland are
similarly considering revised target operation dates. SFT also noted that our
approach was realistic in terms of the factors affecting the industry, it was
quality focussed and prudent.   
Implications 
1.  Financial 
As previously reported (Paisley Grammar School Community Campus:
Update Report 18 August 2022)
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  The new learning environment will
support learning and achievement
for all. 
Our Renfrewshire is well -  The new learning environment will
support the Health and Wellbeing of
all. 
Our Renfrewshire is safe  -  The new learning environment will
provide safe and secure spaces for
all users.

Page 5

Page 5 of 6 
Reshaping our place, our
economy and our future 
-  The new learning environment will
provided spaces which support local
enterprise.
Building strong, safe and
resilient communities 
-  The new learning environment will
provide spaces to support
community activities. 
4.  Legal 
Renfrewshire Council adheres to all relevant legislation. 
5.  Property/Assets 
Through its school estate management plan the Council aims to have an
efficient and well maintained property portfolio which provides learning
environments which support the delivery of the curriculum. 
6.  Information Technology 
The new campus will have IT provision which supports digitally enabled
learning. 
7.  Equality and Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report.   If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.   
8. Health and Safety
None. 
9. Procurement 
Renfrewshire Council adheres to all procurement regulations. 
10. Risk 
A full risk register will be compiled for the project in accordance with the
Council’s established risk management protocols. 
11. Privacy Impact
None. 
12. 
13.
Cosla Policy Position 
None. 
Climate Risk
The project aims to comply with the requirements for ambitious energy
efficiency targets over the long term and to contribute to the Council’s net-
zero commitments.

Page 6

Page 6 of 6 
List of Background Papers 
(a) Background Paper 1:  Paisley Grammar School Community Campus:
Update Report 18 August 2022 
The foregoing background paper(s) will be retained within children’s services for
inspection by the public for the prescribed period of four years from the date of the
meeting.  The contact officer within the service is Ian Thomson, education
manager.
___________________________________________________________ 
Author:  Joe Lynch – Head of Property Services