Education and Children's Services Policy Board Report - 2022-23 Period 8 (final)

Renfrewshire Council · 19 January 2023
Back to Education and Children's Services Policy Board — 19 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Page 1 of 4 
To: Education and Children’s Services Policy Board
On: 19 January 2023
Report by:  Director of Finance and Resources and Director of Children’s
Services
Heading:  Revenue and Capital Budget Monitoring as at 11 November 2022 
1. Summary of Financial Position
1.1. The projected Revenue outturn at 31 March 2023 for Children’s Services is an
overspend of £5.269m (2.3%) against the revised budget for the year.
1.2. The projected Capital outturn at 31 March 2023 for Children’s Services is an
underspend of £0.100m (0.6%). 
1.3. This is summarised over the relevant service in the table below and further
analysis is provided in the Appendices. 
Table 1: Revenue
Division
Revised
Annual Budget
£m
Projected
Outturn 
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services £225.765 £231.034 (£5.269m) (2.3%) 
Table 2: Capital
Division
Revised Annual
Budget
£m
Projected
Outturn 
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services £5.753 £5.653 £0.100 1.7% 
2. Recommendations
Members are requested to:
2.1. Note the projected Revenue outturn position for Children’s Services detailed
in Table 1 above, and further note that the forecast position is based on best

Page 2

Page 2 of 4 
estimates and confirmed government support at this point in time; forecasts
are likely to be subject to fluctuation as the year progresses;
2.2. Note projected Capital outturn position for Children’s Services detailed in
Table 2 above; and
2.3. Note the budget adjustments detailed in sections 4 and 6. 
3. Children’s Services Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £5.269m (2.3% of total budget). Detailed service division
reports can be found in Appendix 2, along with an explanation of each
significant projected variance.
3.2. The projected outturn is based on available information and assumptions
made by service budget holders in November 2022. These assumptions will
be refined during the year as more information becomes available.
3.3. The main reasons for the projected outturn position are indicated below the
table showing the objective analysis (which division is spending the budget). 
3.4. A £4.158m overspend is anticipated within Children & Families related mainly
to external residential accommodation placements. During the second year of
the pandemic the service required to place a number of children and young
people in external residential accommodation. These placements have
resulted in overspend due to the cost of the specialised services required to
meet the complex needs of the children and young people who have been
accommodated.
3.5. All external placements are held under continual review by the service to
ensure they continue to meet the needs of the individual children and young
people. Options to mitigate cost pressure are examined on an ongoing basis.
3.6. The impact of rising energy costs across the various divisions of service is
contributing a further £1.502m to the full-year projected overspend. This
service is responsible for around 75% of the Council’s annual electricity and
gas costs. 
4. Revenue Budget Adjustments
4.1. Members are requested to note from Appendix 1 that budget adjustments
totalling £0.202m have been processed since the last report. These relate
mainly to an adjustment to remove rates budgets from Early Learning &
Childcare Centres (£0.177m) and transfers to other services for property
adaptations (£0.025m)
5. Children’s Services Capital
5.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022.
5.2.  The Capital Monitoring report at Appendix 3 indicates changes totalling
£9.735m in the approved capital programme for Education and Children’s

Page 3

Page 3 of 4 
Services since the previous Policy Board, bringing the total changes to date to
a net of £7.606m. This relates to budget carried forward into 2023/24 from
2022/23 in relation to the new Paisley Grammar Campus.
5.3. Further detail, including reasons for significant variances, can be found at
Appendix 3. 
6. Capital Budget Adjustments
6.1. Since the last report, budget changes totalling £9.735m have arisen which
reflect the following:
Budget carried forward to 2023/24 from 2022/23 (9.735m)
• Paisley Grammar New Campus (£9.735m) to reflect the expected
project timescales. 
___________________________________________________________________ 
Implications of this report 
1.  Financial 
The projected budget outturn position for Children’s Services’ Revenue
budget is an overspend of £5.269m. Income and expenditure will continue
to be monitored closely for the rest of the financial year and, where
necessary, steps will be taken to mitigate any overspend including applying
flexibility within specific grant funding as permitted by the Scottish
Government. 
The projected outturn position for Children’s Services’ Capital budget is an
underspend of £0.100m. The Capital programme will continue to be
monitored closely for the rest of the financial year.   
Any changes to current projections in either Revenue or Capital budgets
will be reported to the board as early as possible, along with an explanation
for the movement. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
None directly arising from this report. 
4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
None directly arising from this report.

Page 4

Page 4 of 4 
6.  Information Technology 
None directly arising from this report. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website.   
8. Health and Safety
None directly arising from this report. 
9. Procurement 
None directly arising from this report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
None directly arising from this report. 
12. 
13.
CoSLA Policy Position 
n/a 
Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers: None
__________________________________________________________________ 
Authors:   Richard Conway, Extension 0879
Kevin Festorazzi, Extension 4885

Page 5

Appendix 1 
Subjective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 155,932 5,696 161,628 159,459 2,169 1.3% 735 1,434
Premises Related 9,221 (201) 9,020 10,832 (1,812) (20.1%) (1,642) (170)
Transport Related 4,598 1 4,599 5,780 (1,181) (25.7%) (898) (283)
Supplies and Services 35,031 (4,906) 30,125 29,420 705 2.3% 779 (74)
Third Party Payments 13,199 5 13,204 17,785 (4,581) (34.7%) (4,676) 95
Transfer Payments 14,394 (6) 14,388 15,591 (1,203) (8.4%) (256) (947)
Support Services 46 22 68 61 7 10.3% 7 (0)
Depreciation and Impairment Losses 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 232,421 611 233,032 238,928 (5,896) (2.5%) (5,951) 55
Income (6,454) (813) (7,267) (7,894) 627 8.6% 517 110
NET EXPENDITURE 225,967 (202) 225,765 231,034 (5,269) (2.3%) (5,434) 165
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 11 November 2022
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES

Page 6

Appendix 2 
Objective Summary
Approved
Annual Budget
at Period 6
Budget
Adjustments
Revised Annual
Budget at
Period 8
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Directorate 486 (14) 472 442 30 6.4% 0 30
Early learning and childcare 34,056 (194) 33,862 32,476 1,386 4.1% 1,682 (296)
Primary 56,779 985 57,764 58,476 (712) (1.2%) (1,113) 401
Secondary 78,501 611 79,112 80,072 (960) (1.2%) (735) (225)
ASN (Special) Schools 6,397 31 6,428 6,512 (84) (1.3%) (87) 3
Additional support for learning (ASL) 15,441 146 15,587 16,319 (732) (4.7%) (688) (44)
Psychological services 744 0 744 764 (20) (2.7%) (39) 19
Education development 1,790 (20) 1,770 1,770 0 0.0% 0 0
Attainment Challenge 635 (1,366) (731) (731) 0 0.0% 0 0
Facilities management 598 (21) 577 596 (19) (3.3%) 0 (19)
Children & Families 30,540 (360) 30,180 34,338 (4,158) (13.8%) (4,454) 296
NET EXPENDITURE 225,967 (202) 225,765 231,034 (5,269) (2.3%) (5,434) 165
Objective Heading
Directorate
Early Learning and Childcare
Primary Schools
Secondary Schools
ASN Schools
Additional Support for Learning
Psychological Services
Education Development
Facilities Management
Children & Families
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 11 November 2022
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES
Key Reasons for Projected Variance
An underspend in Employee Costs is projected, mainly in relation to indirect employee costs.
An underspend in Employee Costs is projected due to vacancies within the authority’s Early Learning & Childcare Centres. This
underspend is offset by a projected overspend in Transfer Payments in relation to an increase in the rate paid to funded providers
(private and voluntary sector nurseries and childminders), and a projected overspend in Premises Costs resulting from the
increase in energy costs.
Overspends in Premises Costs and Transport Costs are projected. The overspend in Premises Costs is due an expected increase in
energy and refuse collection costs. The overspend in Transport is due to an expected increase in the cost of the mainstream
school transport contract.
Overspends in Premises Costs and Transport Costs are projected. The overspend in Premises Costs is due an expected increase in
energy and refuse collection costs. The overspend in Transport is due to an expected increase in the cost of the mainstream
school transport contract.
An overspend in Premises Costs is projected. This is due to the increase in energy costs.
An overspend in Transport Costs is projected. This is due to increases in the cost of transport contracts for pupils with additional
support needs.
An overspend in Employee Costs is projected.
No significant projected year end variances to report.
An overspend in employee Costs is projected, arising the service’s share of the council-wide occupational health contract.
An overspend in Transfer Payments is projected, mainly in relation to external residential accommodation placements, where the
number of complex, expensive packages has increased significantly. All external placements are held under continual review by
the service, with options to mitigate cost pressure being examined on an ongoing basis. The full-year projected (adverse) variance
has improved since the previous position due mainly to staff vacancies within Children's Residential Accommodation and to an
increase in the number of placements for unaccompanied asylum-seeking children (for which Home Office funding is provided).

Page 7

Appendix 3 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2022 2022-23 in 2022-23 2022-23 2022-23 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
EDUCATION & CHILDREN SERVICES
Primary Schools Estate Programme(SEMP) 42,665 0 233 233 133 100 43% 42,898 42,798 100 0%
Paisley Grammar New Campus 1,110 10,950 (9,950) 1,000 1,000 0 0% 51,250 51,250 0 0%
Primary Schools Estate Programme(SEMP 2020) 0 0 0 0 0 0 0% 10,000 10,000 0 0%
Other Schools Investment Programmes 22,057 2,009 2,111 4,120 4,120 0 0% 26,231 26,231 0 0%
Technology Replacement Strategy ICT 0 400 0 400 400 0 0% 2,000 2,000 0 0%
TOTAL EDUCATION & CHILDREN'S SERVICES
BOARD 81,011 13,359 (7,606) 5,753 5,653 100 2% 147,558 147,458 100 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Objective Heading
Primary Schools Estate Programme(SEMP)
Paisley Grammar New Campus
Primary Schools Estate Programme(SEMP 2020)
Other Schools Investment Programmes
Technology Replacement Strategy ICT
RENFREWSHIRE COUNCIL
1st April to 11th November 2022
POLICY BOARD: EDUCATION & CHILDEN'S SERVICES
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
Key Reasons for Projected Variance
Minor underspends relate to St Fergus new build and St Anthony refurbishment.
Budget Variance (Adverse) or
Favourable
Current Year 2022-23
Budget Variance (Adverse) or
Favourable
Full Programme - All years