To:  Education and Children’s Services Policy Board
On: 13 March 2025
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________
1. Summary
1.1. Renfrewshire Council is delivering a large-scale investment into the learning
estate. This programme of works which is underway includes four major
projects to enhance and expand the current estate. 
1.2. This report provides an update on the delivery of these projects and highlights  
next steps. The projects covered in this report are as follows:
• Paisley Grammar School Community Campus
• Park Mains High School extension and alterations
• New primary school in Dargavel 
• Thorn Primary School new build
__________________________________________________________________
2. Recommendations
2.1. The Board is asked to note the contents of this report.   
3. Paisley Grammar School Community Campus 
3.1. The project to deliver a new Paisley Grammar School remains on track for a
2026 completion and handover. Construction has progressed to a point where
the majority of structural assembly is complete, and a transition has begun to
shape the internal of the building.

Page 2

3.2. Members have had the opportunity to visit the site to take in the scale of the
project being delivered, and further opportunities will be made available as the
development progresses.
3.3. Further relevant updates will be provided on the project at future meetings
where appropriate.  
4. Park Mains High School Extension & Internal Alterations 
4.1. The project to extend and enhance Park Mains High School is progressing
with the procurement process to appoint a contractor to develop the design
now almost complete with a recommendation being made to the Council’s
Finance, Resources & Customer Services Policy Board. This is now
completing the final contractual agreement and standstill process. 
4.2. The proposed design of the extended Park Mains High School has been
available on the Council website to view since November 2024, and further
engagement sessions with Ward Members has now also taken place. 
4.3. The next phase of the project will develop the design further and will now be
led by the successful contractor and their design team, in collaboration with
the Council officer project team that has developed the project to this point.
The next significant milestone will be summer 2025 when it is expected that
planning permission will be submitted. 
4.4. Ongoing engagement on the development of the design will continue, and
further updates will be provided on this at future meetings. 
5. New Primary School in Dargavel  
5.1. The project to deliver a new primary school in Dargavel remains on track for a
2027 construction completion and handover. A recent report to the Finance,
Resources & Customer Services Policy Board approved the recommendation
to award an enabling works package to Hub West Scotland. These enabling
works will allow important drainage, and earth works to take place well in
advance of full construction of the school building and associated provisions.
Planning permission has now been granted for these earth works which will
allow the first site activity to begin. 
5.2. This enabling works package contributes to the plan of meeting a demanding
timescale for delivery and will allow a smooth transition to the wider
construction process, pending planning permission approval, of which a
decision is expected in May 2025, at the Planning and Climate Change Policy
Board. 
5.3. Officers have been conducting engagement with children in Dargavel and
Bishopton Primary Schools to begin the planning process for naming this new
school. This process has allowed the young people to have their views heard,
as well as learn more about the history of the area and what may constitute a
meaningful name. The Board should note that in line with the Naming of
Schools Policy, the Director of Children’s Services, in collaboration with the
Convener, will determine a short list of school names produced by the local
young people. This will then be followed by a poll to all local residents and
community groups to vote for their preferred name. The outcome of this poll
will then be put forward to the May 2025 Education and Children’s Services
Policy Board for Members to agree.

Page 3

6. Thorn Primary School New Build 
6.1. Members are asked to note the contents of a separate report provided to this
board regarding the next phase of Learning Estate Strategy. This separate
report provides context around various data sets and the wider strategy and
seeks a decision in relation to the route forward for delivery of a new Thorn
Primary School. 
___________________________________________________________________ 
Implications of this report 
1.  Financial 
All projects are costed and included in Council financial planning. Projects
are bound by rigorous governance including budget management and
reporting. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights   
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts

Page 4

on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement 
Any procurement work required will be conducted in collaboration with the
Council’s Procurement team and adhere to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place. 
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the
direct needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14. Cosla Policy Position 
None.     
Children’s Services
JL/GM Feb 2025 
Author: Jack Lochans jack.lochans@renfrewshire.gov.uk