To: Education and Children’s Services Policy Board
On: 13 March 2025
Report by: Director of Finance and Resources and Director of Children’s Services
Heading: Revenue and Capital Budget Monitoring as at 7 January 2025
1. Summary of Financial Position
1.1. The projected Revenue outturn at 31 March 2025 for Children’s Services is an
overspend of £1.059m (0.4%) against the revised budget for the year.
1.2. The projected Capital outturn at 31 March 2025 for Children’s Services is a
break-even position.
1.3. This is summarised in the table below and further analysis is provided in the
Appendices.
Table 1: Revenue
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 264.803 265.862 (1.059) (0.4%)
Table 2: Capital
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 30.286 30.286 0 0%
2. Recommendations
Members are requested to:
2.1. Note the projected Revenue outturn position for Children’s Services detailed
in Table 1 above;
2.2. Note the projected Capital outturn position for Children’s Services detailed in
Table 2 above; and
2.3. Note the budget adjustments detailed in sections 6 and 7.

Page 2

3. Children’s Services Revenue Budget Projection - overspend of £1.059m
by 31 March 2025
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £1.059m (0.4% of total budget).
3.2. It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle. Budget holders are obliged to seek mitigating action to
minimise significant budget variances.
4. Objective Analysis - Significant Variances
4.1. Early Learning & Childcare - £0.787m underspend
Employee costs are currently projected to underspend, mainly due to
vacancies. This is under review with management. 
4.2. Primary Schools - £0.038m overspend
Premises costs, Transport costs and Supplies and Services are projected to
overspend and are partly offset by a projected underspend in Employee costs,
which arises mainly within teachers’ salaries. 
The movement since last period’s forecast is due mainly to the in-year
realignment of underspent teachers’ salary budgets into Secondary and ASN
Schools. This is reflected in paragraph 6.3.
4.3. Secondary Schools - £0.149m overspend
Premises costs and Transport costs are currently projected to overspend and
are partly offset by a projected underspend in Employee costs, mainly within
teachers’ salaries. The overspend in Premises costs is mainly due to refuse
collection costs; the Transport costs overspend is partly due to the SPT
school transport contract being greater than available budget, and partly due
to the costs of transporting pupils from Castlehead High School to the Lagoon
Leisure Centre for PE earlier in the year whilst remedial works relating to
RAAC (reinforced autoclaved aerated concrete) were being carried out. 
The movement since last period’s forecast is due to the in-year realignment of
underspent teachers’ salary budgets from the Primary Schools division. This
is reflected in paragraph 6.3.
4.4. ASN Schools - £0.047m overspend
Premises costs are currently projected to overspend and are partly offset by
an underspend in Employee costs. The overspend in Premises costs is due to
requirement for janitorial costs and water charges being greater than available
budget, and the underspend in Employee Costs arises mainly within teachers’
salaries.
The movement since last period’s forecast is due to the in-year realignment of
underspent teachers’ salary budgets from the Primary Schools division. This
is reflected in paragraph 6.3.

Page 3

4.5. Additional Support for Learning - £0.526m overspend
Employee costs and Transport costs are currently projected to overspend.
The overspend in Employee costs mainly arises due to an increase in demand
for Additional Support Needs Assistants (ASNAs) within mainstream schools.
The Transport costs overspend is due to the cost of ASN transport contracts
being higher than available budget, predominantly caused by price inflation
and, to a lesser extent, by an increasing number of children requiring
transport.
4.6. Facilities Management - £0.058m underspend
Premises costs and Supplies and Services are projected to underspend and
are partly offset by a small projected overspend in Employee costs. The
Premises costs underspend may reduce during the year, as more of this
budget is committed to small property repairs across the school estate.
4.7. Children & Families - £1.109m overspend
Supplies and Services and Transfer payments are currently projected to
overspend, partly offset by an underspend in Employee costs due to staffing
turnover. The Supplies and Services projected overspend relates mainly to
demand for both Care at Home for children with additional support needs, and
payments to care leavers. The overspend in Transfer payments relates to
Section 22 payments across localities. 
5. Subjective Analysis - Significant Variances 
5.1. Employees - £0.874m underspend
Underspends are projected in both teaching and non-teaching staffing.
Projected underspends in non-teaching staffing in Children & Families and
Early Learning & Childcare, arising mainly from staff turnover, are partly offset
by an overspend in Additional Support for Learning due to the demand for
Additional Support Needs Assistants (ASNAs).
5.2. Premises Related - £0.295m overspend
The overspend in Premises costs is mainly due to increased janitorial costs
and refuse collection costs across the school estate.
5.3. Transport Related - £0.414m overspend
The overspend in Transport costs is due to SPT contracts for both
mainstream school transport and ASN transport being higher than available
budget, predominantly caused by price inflation and, to a lesser extent, by an
increasing number of children requiring transport.

Page 4

5.4. Supplies & Services - £0.593m overspend
The overspend in Supplies & Services relates mainly to payments to care
leavers and increased demand for Care at Home services for children with
additional support needs.
5.5. Third Party Payments - £0.252m overspend
The projected overspend in Third Party payments relates mainly to services
related to Children with Disabilities, particularly within placement costs.
5.6. Transfer Payments - £0.761m overspend
The projected overspend in Transfer payments relates mainly to Children &
Families, in particular Direct Payments and Section 22 payments.
5.7. Income - £0.370m over-recovery
A projected over-recovery of income is currently projected in Children &
Families in relation to charges to other divisions of the service not reported to
this Board. 
6. Revenue Budget Adjustments
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and Resources
for submission to the relevant policy board for approval. 
6.3. The Director now seeks homologation from the Board for the following
affected virements since the last report: 
Revenue Budget Adjustments
Objective Heading Subjective
Heading Amount
(£m) Reason 
Children’s Services Premises Related (0.040) Corporate Landlord
transfers to Environment,
Housing and Infrastructure
relating to small repair
projects 
Children’s Services
Primary division
Employee Costs –
teaching staff
(1.983) Realignment of teaching
staff budgets across three
service divisions in line
with need, as discussed at
previous Policy Board 
Children’s Services
Secondary division
Employee Costs –
teaching staff
1.480 
Children’s Services
ASN Schools 
Employee Costs –
teaching staff
0.503

Page 5

6.4. The following budget adjustments are in line with the earmarking of funds set
aside in budget motion and the allocation of centrally-held budgets, and are
therefore for noting only: 
Revenue Budget Adjustments
Objective Heading Subjective
Heading Amount
(£m) Reason 
Children’s Services Employee Costs 5.826
Agreed pay awards for
non-teaching employees
from 1 April 2024 and for 
teaching staff from
1 August 2024 
Children’s Services Premises Costs 0.597 Realignment of non-
domestic rates budgets 
Children’s Services Employee Costs 0.939
Realignment of Scottish
Government funding to
support newly qualified
teachers 
7. Capital Budget Projection - break even position by 31 March 2025
7.1. The Capital Investment Programme 2024/25 to 2028/29 was approved by the
Council on 29 February 2024. Education and Children’s Services revised
Capital spend for 2024/25 is £30.286m. 
7.2. The in-year Capital budget is forecast to break-even by 31 March 2025,
however, this will be monitored as the projects progress. Further details of the
programme can be found in the Capital Monitoring report at Appendix 3.
7.3. There have been no budget adjustments since the previous Policy Board.

Page 6

___________________________________________________________________ 
Implications of this report 
1.  Financial 
The projected budget outturn position for Children’s Services’ Revenue
budget is an overspend of £1.059m. Income and expenditure will continue
to be monitored closely for the rest of the financial year and steps will be
taken to mitigate any overspend, including virement, applying flexibility
within specific grant funding as permitted by the Scottish Government, and
potential use of earmarked reserves. 
The projected outturn position for Children’s Services’ Capital budget is a
break-even position. The Capital programme will continue to be monitored
closely for the rest of the financial year. 
2.  HR and Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations
in this report. 
3. Community/Council Planning 
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4.  Legal 
There are no direct implications arising from the recommendations in this
report.

Page 7

5.  Property/Assets 
The capital expenditure noted in this report will result in lifecycle
maintenance improvements to existing properties and replacement of ICT
assets and infrastructure. 
6.  Information Technology 
While ICT assets and revenue costs are included within these reported
budgets, there are no direct implications arising from the recommendations
in this report. 
7.  Equality and Human Rights 
While new areas of spend may impact on particular groups, any such
impact would be assessed prior to the spend being incurred, therefore
there are no direct implications arising from the recommendations in this
report. 
8. Health and Safety
The capital expenditure noted in this report will result in lifecycle
maintenance improvements to existing properties and replacement of ICT
assets, which may in some cases rectify health and safety issues. 
9. Procurement 
While Procurement is an important consideration prior to the Council
incurring any revenue or capital spend, there are no direct implications
arising from the recommendations in this report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
There are no direct implications arising from the recommendations in this
report. 
12. Children’s Rights
There are no direct implications arising from the recommendations in this
report. 
13. Climate Risk
The Council aims to reduce its carbon and other emissions to net zero by
2030, however there are no direct implications arising from the
recommendations in this report. 
14. CoSLA Policy Position 
n/a

Page 8

___________________________________________________________ 
List of Background Papers: 
•   Revenue Budget and Council Tax 2024/25, Council 29 February 2024
•   Capital Investment Programme 2023/24 to 2027/28, Council 29 February 2024 
Authors: Richard Conway, Finance Business Partner
Geoff Borland, Finance Manager

Page 9

Appendix 1 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 7 January 2025                  
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES                  
Subjective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 180,132 6,758 186,890 186,016 874 0.5% 1,197 (323)
Premises Related 9,100 605 9,705 10,000 (295) (3.0%) (289) (6)
Transport Related 6,499 0 6,499 6,913 (414) (6.4%) (291) (123)
Supplies and Services 31,554 355 31,909 32,502 (593) (1.9%) (762) 169
Third Party Payments 18,918 0 18,918 19,170 (252) (1.3%) (606) 354
Transfer Payments 16,432 737 17,169 17,930 (761) (4.4%) (803) 42
Support Services 941 1 942 930 12 1.3% 11 1
GROSS EXPENDITURE 263,576 8,456 272,032 273,461 (1,429) (0.5%) (1,543) 114
Income (5,991) (1,238) (7,229) (7,599) 370 5.1% 642 (272)
NET EXPENDITURE 257,585 7,218 264,803 265,862 (1,059) (0.4%) (901) (158)

Page 10

Appendix 2 
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 7 January 2025                  
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES                  
Objective Summary
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Budget
Variance 
(Adverse) or
Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Directorate 1,284 6 1,290 1,326 (36) (2.8%) (19) (17)
Early learning and childcare 33,659 919 34,578 33,791 787 2.3% 551 236
Primary 65,476 2,921 68,397 68,435 (38) (0.1%) 1,833 (1,871)
Secondary 90,442 1,860 92,302 92,451 (149) (0.2%) (734) 585
ASN Schools 7,302 180 7,482 7,529 (47) (0.6%) (490) 443
Additional support for learning (ASL) 17,964 812 18,776 19,302 (526) (2.8%) (623) 97
Psychological services 1,280 46 1,326 1,326 0 0.0% 0 0
Education development 2,457 (13) 2,444 2,444 0 0.0% 0 0
Attainment Challenge (800) (32) (832) (832) 0 0.0% 0 0
Facilities management 528 (5) 523 465 58 11.1% 82 (24)
Children & Families 37,993 523 38,516 39,625 (1,109) (2.9%) (1,501) 392
NET EXPENDITURE 257,585 7,218 264,803 265,862 (1,059) (0.4%) (901) (158)

Page 11

Appendix 3 
Prior Years Approved  Budget Revised Projected Total Approved Projected
Expenditure Budget Adjustments Budget Outturn Budget Outurn
to 31/03/2024 2024-25 since previous 2024-25 2024-25 to 31-Mar-29 to 31-Mar-29
Project Title Board report
£000 £000 £000 £000 £000 £000 £000
EDUCATION & CHILDREN SERVICES
Primary Schools Estate Programme(SEMP) 10,422 202 0 202 202 0 0% 10,623 10,623 0 0%
Paisley Grammar New Campus 6,707 27,138 0 27,138 27,138 0 0% 85,600 85,600 0 0%
Thorn PS New Build 79 150 0 150 150 0 0% 14,000 14,000 0 0%
Dargavel Extension (Modular Units) 2,133 117 0 117 117 0 0% 2,250 2,250 0 0%
DPS2 New Build 0 425 0 425 425 0 0% 45,000 45,000 0 0%
Other Schools Investment Programmes 0 213 0 213 213 0 0% 213 213 0 0%
Total Schools Estate(inc Early Years) Programme 1,553 302 0 302 302 0 0% 1,855 1,855 0 0%
PMHS Extension 0 1,000 0 1,000 1,000 0 0% 37,000 37,000 0 0%
ELCC Improvements 0 88 0 88 88 0 0% 88 88 0 0%
Technology Replacement Strategy ICT 0 651 0 651 651 0 0% 1,851 1,851 0 0%
TOTAL EDUCATION & CHILDREN'S SERVICES
BOARD 20,894 30,286 0 30,286 30,286 0 0% 198,480 198,480 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
1st April to 7th January 2025
POLICY BOARD: EDUCATION & CHILDEN'S SERVICES
Budget Variance
(Adverse) or
Favourable
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
Current Year 2024-25 Full Programme - All years
Budget Variance
(Adverse) or
Favourable