To:  Education and Children’s Services Policy Board
On: 16 January 2025
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________
1. Summary
1.1. Renfrewshire Council is delivering a large-scale investment into the learning
estate. This programme of works which is underway includes four major
projects to enhance and expand the current estate. 
1.2. This report provides an update on the delivery of these projects and highlights  
next steps. The projects covered in this report are as follows:
• Paisley Grammar School Community Campus
• Park Mains High School extension and alterations
• New Dargavel Primary School
• Thorn Primary School new build 
__________________________________________________________________
2. Recommendations
2.1. The Board is asked to note the contents of this report.   
3. Paisley Grammar School Community Campus 
3.1. The project to deliver a new Paisley Grammar School continues at pace with
construction on track for completion in the summer of 2026. To demonstrate
the scale of the project and the progress being made, see attached images in
Appendix A of this report.

Page 2

3.2. Further updates will be provided on this project at points of major milestone
achievement.
3.3. The project team are in the process of designing information boards in
collaboration with Morrison Construction. These boards will be placed in a
prominent location in the current Paisley Grammar School to showcase to
pupils and staff what will be delivered as part of their new community-based
school. 
4. Park Mains High School Extension & Internal Alterations 
4.1. The project to extend and enhance Park Mains High School is progressing
with the procurement process to appoint a main contractor under way.
Tenders have been received and this will now progress through the relevant
process where a recommended contractor will be proposed to the Finance,
Resources and Customer Services (FRCS) Policy Board in February 2025.
4.2. Design work continues to develop with the project team now having a
proposed concept design. These designs have been informed through
significant engagement with the school community including the parent
council of Park Mains, parent councils of all associated primary schools,
pupils, and staff. This engagement began in late 2023 with design partners
from Space Zero who led in-depth engagement with the school community to
inform the provisional designs.
4.3. These concept designs have allowed the Council to progress to the point of
conducting the statutory Proposal of Application Notice (PAN) process. This
process was completed in December 2024 where the project team hosted two
information evenings at Park Mains High School on an open invite basis.
These events were supported by circa 15 large-scale printed boards that
showed the community all aspects of the proposed design of the extended
Park Mains High School. These boards were also emailed to all parents and
carers at Park Mains and its associated primary schools after the events. The
purpose of this process is to allow the community to comment on the proposal
to allow any reasonable and beneficial amendments to be made via the
feedback received, and for officers to discuss and document any concerns
raised. 
4.4. A full summary of the process has been compiled and will be submitted to the
Planning Authority for consideration when progressing to the full planning
application process in 2025.  
4.5. The next major steps of this project are to appoint a main contractor who will
then take on the final design stage and progress towards a 2026 construction
start, and completion in 2027. 
5. New Dargavel Primary School 
5.1. As part of the previous update to this Board on 31st October 2024, it was
noted that the project to deliver a new primary school in Dargavel had recently
completed the PAN process. This has allowed the project to progress where
the full planning application has now been submitted to construct the new 800
capacity primary school with community facilities. As this is a major planning
application, the decision will be made at the Council’s Planning and Climate
Change Policy Board in 2025.

Page 3

5.2. The project team continue to develop all detail supporting the delivery of the
project including design and programming. On this basis, the approach has
been agreed for the construction methodology and procurement strategy for
delivery. In collaboration with the Council’s delivery partner (Hub West
Scotland), main contractor (BAM Construction), and lead consultants, it has
been agreed that the most efficient route to constructing the school is to split
the project into defined stages. This will encompass the following:
• Enabling works to begin early ground works for aspects such as
drainage, will take place from early 2025. This will see the first activity
on site. 
• Main works to begin in autumn 2025. This will see the construction of
the building and all supporting components begin. 
5.3. From a contractual perspective, the project will be further broken down into
multiple subcomponents, as is normal in complex construction projects. These
matters will be dealt with through the appropriate governance route which is
the FRCS Policy Board. Members of the Education and Children’s Services
Policy Board will be kept fully up to date on progress of contractual
appointments, and should expect the first batch of contract recommendations
to be submitted to the February 2025 FRCS Policy Board which will include:
• Consultant appointments and payments 
• Enabling works package for ground works 
5.4. Beyond this, further reports will be submitted to the FRCS Policy Board later
in 2025 to make recommendations to award contracts for the main works
construction. The main works contract that will deliver all aspects of the
school will likely be broken down into two contract awards, the first being an
advanced works package, and the second being the remainder of the main
works. this will follow a similar route to previous projects including Paisley
Grammar, which provides an efficient procurement approach but importantly
the ability to maintain sustained momentum in delivering the project which is
particularly important for this project.
5.5. As noted, the FRCS Policy Board will be presented with these contract
recommendations throughout 2025. All of this is accounted for in the agreed
programme with Hub West Scotland.
6. Thorn Primary School New Build 
6.1. The project to deliver a new Thorn Primary School has been progressing with
early design work and has considered possible site layout as well as
indicative space requirements, based on engagement with school staff and
key stakeholders. This work is now being progressed in line with the principles
of the wider Learning Estate Strategy, approved by members of the board in
August, and considering the full-estate roll-projection data, which members
saw in October, to ensure we maximise the benefit the Thorn project brings to
the Johnstone community. A further update will be brought to the board in
March 2025 as part of the next stage of the Learning Estate Strategy. 
___________________________________________________________________

Page 4

Implications of this report 
1.  Financial 
All projects are costed and included in Council financial planning. Projects
are bound by rigorous governance including budget management and
reporting. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights   
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None.

Page 5

9. Procurement 
Any procurement work required will be conducted in collaboration with the
Council’s Procurement team and adhere to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place. 
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the
direct needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14. Cosla Policy Position 
None.     
Children’s Services
JL/JO/GMcL Dec 2024 
Author: Jack Lochans -  jack.lochans@renfrewshire.gov.uk

Page 6