Renfrewshire Council · 31 October 2024
Back to Education and Children's Services Policy Board — 31 October 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

To:  Education and Children’s Services Policy Board
On: 31 October 2024
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________
1. Summary
1.1  Renfrewshire Council is delivering a large-scale investment into the learning
estate. This programme of works that are underway includes four major
projects to enhance and expand the current estate. 
1.2 This report provides an update on the delivery of these projects and insight
into the next steps. An update is also provided on three other projects that
have been ongoing to enhance current establishments. Projects continue to
progress in line with agreed timescales and scope of delivery. The projects
covered in this report are as follows:
• Paisley Grammar School Community Campus
• Park Mains High School extension and alterations
• New Dargavel Primary School
• Thorn Primary School new build
• Dargavel Primary School internal alterations
• Bishopton Primary School classroom block
• Castlehead High School roof strengthening works
__________________________________________________________________
2. Recommendations
2.1. The Board is asked to note the contents of this report.  
2.2. The Board is asked to note the plans to upgrade the sports pitch at Dargavel
Primary School to 3G astro turf to support school and community use.

Page 2

3. Paisley Grammar School Community Campus 
3.1. The project to deliver a new Paisley Grammar School continues with
construction progressing on track. A visible structure of what will become the
new three storey school and community campus can now be seen from
across Paisley. 
3.2. The project is due to complete construction in the summer of 2026. From a
construction perspective, all work is planned, and regular updates will be
provided to this board at significant milestones during the work. 
3.3. Whilst construction is the material concept, in order to deliver a new building,
an equally important aspect is ensuring that the wider school fit out; operation
and transition is planned in parallel with the delivery of the building. Work
continues in the planning of all aspects which will contribute to the school
operating and delivering in line with the vision. This work is being planned
significantly well in advance of the school opening due to the complexity of all
work associated with planning, procurement, and execution of aspects,
including digital, building and school operations, transition planning of
resources and people, amongst other complex workstreams. All of the above
support not only the planning of an exceptional building, but the delivery of
high quality teaching and learning within.
3.4. Whilst this is ongoing, we are engaging fully with the school community. Work
is ongoing with the school parent council as well as all parent councils of
associated primary schools. A communications plan is in place that identifies
key activities and collaboration opportunities. Our contractor and partner
consultants are also planning and already undertaking a programme of
valuable community benefits and engagement. 
3.5. Representation was made at the recent ‘Renfrewshire Employability Week’
from our contractor and key consultants, and activity is underway to support
Paisley Grammar School pupils with site visits to view the construction first
hand. 
4. Park Mains High School Extension & Internal Alterations 
4.1. The project to extend and enhance Park Mains High School is progressing
through design stages with an initial concept design being created. The
procurement process to appoint a main contractor for the final design and
construction is also underway. This complex process is expected to complete
in early 2025, where the successful contractor will be appointed. 
4.2. Following the appointment of a contractor, a period of roughly one year will be
required to finalise all design, planning permission and market testing to arrive
at a final construction contract sum. This will then allow the planned
construction and handover period to commence to deliver by the summer of
2027. This process will comprise extending the current school as well as
significant internal interventions to enhance the current school footprint by
maintaining subject adjacencies and implement sufficient building provisions.

Page 3

4.3. The project has now progressed to the next required stage of statutory
consent, where a proposal of application notice (PAN) has been submitted to
the planning authority. This process triggers a statutory period of consultation
where two public information events will be held to inform the school and local
community of the intention to submit a planning application. Communication
has been issued to local community groups and parents and carers at Park
Mains and its associated primary schools to inform of the process and the
events.
4.4. The events will be held as follows:
• Event 1 – Wednesday 7th November 2024, 5-8pm, Park Mains High
School 
• Event 2 – Wednesday 4th December 2024, 5-8pm, Park Mains High
School 
4.5. The events are open to all, and the project team will be in attendance with
relevant council officers to discuss the project with the public and school
community. This process will inform the ongoing design of the project and will
support the planning application process. 
5. New Dargavel Primary School 
5.1. Communication and engagement on the delivery of the new primary school in
Dargavel Village has been a key focus in recent months. This has been used
to continuously inform the design of the new school, whilst understanding
what is important to the school community, local residents and wider
stakeholders. 
5.2. To inform the above, a series of focus groups have taken place to inform the
design and operation of the new school. The following focus groups have
been established:
• New school design 
• Traffic and transport 
• Additional support needs 
• Staff 
• Pupil voice 
5.3. These focus groups have been supported by two public events as part of the
PAN process for the planning application for the new school. Two events were
held in Dargavel Primary School across August and September where circa
80 people attended to discuss the development. These events were open to
all, and were publicised via all usual council communication channels as well
as direct text message to all signed up to the Dargavel newsletter, parents
and carers of pupils in the current Dargavel Primary School, email to the
parent council, a dedicated website update, posters in the local area, and
direct communication to all local community groups and stakeholders. 
5.4. The project team and senior council officers were in attendance, and were
supported by the architect, construction contractor, and the Council’s delivery

Page 4

partner Hub West Scotland. These events allowed the public to attend and
give their views on the development whilst engaging in communication to
answer queries, concerns, or inform their knowledge of what the development
would deliver. 
5.5. All views have been noted and taken on board to assist in shaping the new
primary school. The overall feedback was extremely positive about the design
and concept of the new school, particularly regarding community facilities and
what it would offer to the local area. However, concerns remain about the
impact of traffic and the transport network which is, and will continue to be, a
key consideration of the project. 
5.6. One of the main topics of discussion was the drop-off and pick-up facilities at
the new school. It should be recognised the project is being designed to
standards in excess of those stipulated by planning and national guidance.
This means more parking and drop-off facilities than are required will be
implemented, in recognition of the individual circumstances within this
development. 
5.7. To assist in identifying the true position to establish an independent view of
how the local area will perform from a traffic and transport perspective, the
Council is in the process of commissioning a detailed traffic assessment of the
area. This assessment will progress on the findings of any previous reports
undertaken and will model the transport flow of the area when there are two
schools in operation, as well as an increase in traffic for secondary schools
leaving the local area at peak times. This is a mandatory process of the
planning application, and we have brought the timing of this forward to help us
develop a deeper understanding of how traffic will operate, as well as plan
any appropriate mitigations. 
5.8. It is important to recognise Renfrewshire Council are not the landowner of the
wider Dargavel area and are not responsible for designing or implementing
the road network of the local masterplan. Council officers are in regular
dialogue with BAE Systems who own and are responsible for the design and
installation of the road network, to ensure that any influence on improvements
can be given. Full findings of the traffic assessment will also be used to inform
these discussions. 
5.9. From a school design perspective, work is ongoing as planned, and the formal
planning application is scheduled to be submitted by the end of October 2024.
This will allow the project to continue to progress through the next stage of
detailed design, and with the main contractor who will construct the building
already on board, this process will be at an advantage to allow works to begin
efficiently in late summer 2025.
6. Thorn Primary School New Build 
6.1. The project to deliver a new Thorn Primary School remains at the early design
stage with work ongoing to focus on key outputs of the project including client
requirements, sustainability objectives, and general layout concepts of the
school grounds. 
6.2. Engagement and input has been received from the school community and key
stakeholder groups and this process will continue through more detailed
design stages.

Page 5

6.3. A recent exercise has been undertaken with school pupils to understand their
views on what is important about the school design and what they would like
to see in the new building. This is an important step to gaining feedback from
our children who will receive learning and life experiences from these projects. 
6.4. An engagement session with elected members will also be planned to provide
information on the project timeline, key stages, and show current concepts.
The plan remains to deliver this school in 2028. Whilst the overall output is a
relatively small school in comparison to other projects, this is a complex
project with factors such as scheduling demolition of current building and
transitioning the school to the new building in a safe and efficient manner
around school calendars.  
7. Dargavel Primary School Internal Interventions 
7.1. Work to deliver internal interventions to improve acoustics at Dargavel
Primary School was undertaken during the summer break.
7.2. This work was successfully completed, and feedback has been very positive
about the improvements delivered.
7.3. Following representations from the community through various engagement
forums, there has also been clear demand for the sports pitch at the current
Dargavel Primary School to be upgraded to provide much needed facilities
suitable for the community and local sports clubs. Following this feedback, the
Council has undertaken assessment and is now able to proceed with
upgrading the sports pitch at the school. Work is being planned to upgrade
the facility in spring 2025, to create a 3G playing surface that will be suitable
for lets out of school hours and weekends. 
8. Bishopton Primary School Classroom Block 
8.1. This project has delivered a new permanent building at Bishopton Primary
School which comprises of two modern classrooms. These classrooms
replace an old modular unit that had been at the school for a number of years. 
8.2. These classrooms are in use and are proving to be an excellent asset to the
school. Throughout the summer break, works have also been undertaken to
significantly improve the aesthetics of the main school building. 
9. Castlehead Roof Strengthening Works
9.1. Work to provide strengthening to the roof of the PE block of Castlehead High
School has been ongoing throughout the summer break and has completed in
early October. 
9.2. This vital work has ensured the safety of all building users and also delivered
improvements in the form of new lighting to all areas. Communications have
been issued to parents at the school to make them aware. 
___________________________________________________________________ 
Implications of this report

Page 6

1.  Financial 
All projects are costed and included in Council financial planning. Projects
are bound by rigorous governance including budget management and
reporting. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights   
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement

Page 7

Any procurement work required will be conducted in collaboration with the
Council’s Procurement team, and adhere to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place. 
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the
direct needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14. Cosla Policy Position 
None.     
Children’s Services
JL/JO
Oct 2024 
Author: Jack Lochans – jacklochans@renfrewshire.gov.uk