Renfrewshire Council · 22 August 2024
Back to Education and Children's Services Policy Board — 22 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Page 1 of 16 
To:  Education and Children’s Services Policy Board
On: 22 August 2024
__________________________________________________________________ 
Report by:  Director of Children’s Services 
__________________________________________________________________ 
Heading:  Strategic Learning Estate Strategy 
__________________________________________________________________
1. Summary
1.1 The new Childrens Services Service Improvement Plan 2024 to 2029 includes
a clearly stated priority to “Create the best possible learning estate to
allow children and young people to thrive”.
1.2 To deliver on this vision, it is intended that the learning estate be assessed in
its entirety, utilising data already available within the Council, and by
establishing a programme to revitalise our learning estate to meet the
strategic vision and objectives outlined in this report and provide learning
environments suitable for the 21st century.
1.3 The Council has adopted an improved placed based approach to developing
our communities. In addition, a new approach to strategic property
management is ongoing under the banner of ‘Strategic Property Review’.
Education establishments are a significant element of the overall property
portfolio, and a modern inclusive learning environment is imperative for the
prosperity, safety, and education of our young people. A highly suitable and
good condition establishment has a direct correlation to engagement and
raising attainment. Growing evidence also shows the benefits to the wider
community by making the learning estate an asset for all. For these reasons,
the development and delivery of the learning estate strategy has been
identified as a top priority.
1.4 A strategic methodology has been developed that will allow a structured
assessment of our existing learning estate and the establishment of a
prioritisation framework that will help secure an understanding of how to
approach delivering on our strategic vision and provide a comprehensive and
transparent process to develop prioritised investment proposals to reshape,
refurbish or rebuild our learning estate over the long term. This involves an
analysis of every establishment in the learning estate and includes improved
asset management and investment in existing schools to improve standards
for every learning environment.

Page 2

Page 2 of 16 
1.5 If approved, this approach will initiate the development of the most ambitious
strategic programme of investment planning ever in our learning estate,
underpinning an ambition to provide the very best environments and facilities
for our young people and communities, with every single establishment being
considered as part of what is envisaged will be a programme which will span
over 20 years.
1.6 The strategic methodology outlined in this report will enable the development
of an objective investment programme spanning multiple years. This will
enable the council to drive the pace of delivery through a thoughtful and
overarching consideration of cost, need, and ambition.
1.7 It is clear that the establishment of a dedicated multi-disciplinary team will be
required to deliver an ambitious programme such as is proposed, and
approval of the strategy will enable the investment programme detail to be
developed and provided to members for consideration as part of the Council’s
financial planning arrangements and annual budget setting process.
Development of a long term strategic approach in this manner will ensure the
programme has flexibility, with the pace of delivery able to be adjusted as
required in response to any anticipated financial or affordability adjustments
over the long term, without reducing the overall strategic ambition.  
__________________________________________________________________
2. Recommendations
2.1 The Education and Children’s Services Policy Board is asked to:
2.1.1 Agree the strategic vision and objectives.
2.1.2 Adopt the objective assessment and prioritisation criteria and
methodology.
2.1.3 Agree governance proposals as detailed in Appendix 1.
2.1.4 Agree to proceed to the identification of priority projects for further
consideration based on approved methodology and objectives.
2.1.5 Agree to the development of a long-term funding model to set out the
financial deliverability requirements of the vision. 
3. Background 
3.1 Renfrewshire Council has historically approved an ambitious rolling medium
term capital investment programme updated on an annual basis to deliver
new and improved strategic assets for communities and to maintain and
ensure continuing service delivery across all services.
3.2 Whilst this has allowed the delivery of major projects and, specifically,
improvements and new build projects in the learning estate, the focus in the
recent past has been on town centre and city region investment. Learning
estate initiatives have been limited to those agreed through the School Estate
Management Plan (SEMP) which has had a narrower focus based around
ongoing maintenance and short-term necessity, rather than a long-term area
wide approach to investment.

Page 3

Page 3 of 16 
3.3 A strategic review of the learning estate has commenced, and this has
supported the development of an ambitious long term strategic approach to
improving the learning estate within Renfrewshire. Such an approach is
essential to ensure that the significant scale of required improvements in
Renfrewshire’s learning estate can be appropriately planned for and
implemented to create a high standard of school accommodation over the
medium to long term.
3.4 It is intended that the learning estate be assessed in its entirety, utilising data
already available within the council, with a proposed strategic programme
established to revitalise all learning establishments to meet the strategic
vision and objectives outlined in this report. A strategic methodology has been
developed that will allow a structured assessment of our existing learning
estate and the establishment of a prioritisation framework that will help secure
an understanding of how to approach delivering on our strategic vision and
provide a comprehensive and transparent process to develop prioritised
investment proposals to reshape, refurbish or rebuild our learning estate over
the long term. This proposed long term strategic investment approach will
represent the most ambitious programme of investment ever in our learning
estate and provide the opportunity to provide the very best environments and
facilities for our young people and communities, with every single learning
establishment being considered in a programme which is anticipated will span
over 20 years.
3.5 A strategic vision and set of objectives defining the vision have been
developed, and if this strategic approach is approved by the Policy Board the
first phase of priority projects will be developed for consideration, approval
and subsequent inclusion in medium term financial planning arrangements.
3.6 At present, the existing learning estate new build programme in delivery over
the next four years, is currently estimated at approximately £175 million,
covering a new build secondary, two primary schools and a secondary school
extension. The scale of investment need in the whole learning estate that is
anticipated to be established through this much longer-term period will be
significantly greater by comparison, likely running into billions as opposed to
hundreds of millions of pounds. In this context, a commensurately long term
20 – 25 year strategic funding model will require to be developed to set out
financially, how the most significant investment programme undertaken by the
Council can be financially deliverable over the very long term. This long term
strategic funding model will be required to set out: - 
i. the proposed funding approach – that would be designed to secure
funding confidence in advance of projects progressing to provide
assurance around the financial capacity to develop, design and deliver
major phases of a long-term investment programme of this nature,
ii. affordability considerations – setting out the scale of financial
commitment that would be required from the Council over the long
term, how delivering the funding model can be effectively integrated
into the Council’s long term financial planning arrangements and short
term budget setting as well as the range of interchangeable strategies
available to meet this requirement over the longer term,

Page 4

Page 4 of 16 
iii. financial sustainability – setting out how the cumulative impact of the
funding model on the Council’s finances will remain within financially
sustainable levels over the very long term,
iv. the scale and timing of the financial investment capacity the Council is
prepared and able to commit to over the long term which will be a key
factor in determining the potential pace of delivery and scale of each
major phase of investment. 
3.7 To deliver this unprecedented strategic ambition, the following are key
elements of the new strategic approach:
i. A strategic vision which clearly states our long term aspirations,
ii. A defined set of strategic objectives which articulate the specific
requirements to be delivered to meet our vision,
iii. A transparent and objective methodology to identify and prioritise
projects to enable a delivery programme to be established,
iv. A financial model which will enable the Council to establish a fund of
sufficient scale to meet our ambition,
v. An internal governance structure, incorporating our already robust and
established formal approval and oversight requirements, but with a
programme board dedicated to oversight and delivery of the strategic
programme. 
vi. A standardised business case process which will be applied to each
proposed project prior to formal project approval. 
4 Strategic Vision and Objectives
4.1 The new Childrens Services Service Improvement Plan 2024 to 2029 was
approved by the Policy Board in May 2024 and includes a clearly stated
priority to “Create the best possible learning estate to allow children and
young people to thrive”. This is a key priority specifically for the learning
estate and it is proposed that this is adopted as our strategic vision.
4.2 To define what is considered necessary to deliver the “best possible learning
estate” a set of strategic objectives has been established, which will inform
and drive the programme and which clearly articulate the pragmatic and
deliverable requirements for the key elements of any learning establishment.
These objectives have been derived from a series of engagement and
discovery sessions with officers across many council services, as well as
consideration of national strategies, objectives, and community
engagement/feedback. 
4.3 Strategic Objective 1 – Condition
All blocks in all schools, and all schools overall shall be rated A or B as
defined in Scottish Government Guidance for local authorities reporting on the
condition of learning estates.

Page 5

Page 5 of 16 
4.4 Strategic Objective 2 – Suitability
All blocks in all schools, and all schools overall shall be rated A or B as
defined in Scottish Government Guidance for local authorities reporting on the
suitability of learning estates.
4.5 Strategic Objective 3 – Sufficiency (Capacity)
To ensure fair and equitable provision, schools should be operating within an
optimal occupancy efficiency range of 80-95%.
4.6 Strategic Objective 4 – Inclusivity
All users are safe, achieving, nurtured, responsible and included. The school
is fully accessible inside and outside for all learners, staff and community
users and facilities are designed and provided to enable diverse needs of
users to be accommodated in relation to medical, religious and specific
personal needs.
4.7 Strategic Objective 5 – Digital 
Within Renfrewshire we shall provide the following digital connectivity to allow
all children access to digital tools and grow their skills as part of the
curriculum:
• Network with a minimum 1GBps download speed and a minimum of
1GBps upload speed for all schools. 
• A backup connection to prevent a single point of failure leading to a total
loss of connection. 
• Wi-Fi capacity for all users to experience the minimum performance
standards in each school and offer flexibility throughout. 
4.8 Strategic Objective 6 – Sustainability and Net Zero
We shall apply net zero and low carbon principles to all new build and
refurbished schools to meet and exceed where possible the standards set by
Government and the Council for such establishments. It is recognised that the
learning estate plays a major part in the total combined carbon footprint, and
all considerations moving forward must effectively contribute to
Renfrewshire’s net zero ambitions. 
4.9 Strategic Objective 7 – Community Facilities and Placeshaping
Learning establishments shall serve the wider community and at every stage
from design to construction, consideration shall be given to the provision of
work, community and partner accommodation, and ongoing use. This will
ensure efficiency and modern standards across the wider council estate, by
maximising the learning estate, and will work collaboratively with wider
placeshaping initiatives.

Page 6

Page 6 of 16 
4.10 Strategic Objective 8 – Active Travel 
All schools will be provided with safe and accessible walking, cycling and
wheeling routes to promote healthy and environmentally friendly alternatives
to car use. 
5 Current Learning Estate
5.1 Renfrewshire Council currently has 63 schools comprising of 50 primary, 11
secondary, and 2 ASN schools. Appendix 2 details all primary, secondary
and ASN establishments with the core condition, suitability and capacity data
currently held within the Council.
5.2 The current condition and suitability assessments of all schools, as defined in
the Scottish Government’s ‘Core Facts’ guidance is outlined in the tables
below and shows that 16 of the 63 schools are categorised as ‘A – Good’. The
majority of schools fall into the category of ‘B – Satisfactory’ for both condition
and suitability, but there has been a gradual deterioration when compared to
2019 when the last School Estate Management Plan was approved by the
Board. A full overview of the Core Facts data for all schools can be found in
appendix 2 of this report, as well as descriptions of what is meant by the main
core fact headings. A more detailed description of this process as well as full
supporting data can also be found in the School Estate Management Plan
report, which has been provided to this board.
5.3 Implementation of the proposed new strategic approach to learning estate
revitalisation will enable the Council to improve the whole estate over the long
term to ensure it is able to meet the demands of our communities as we move
to the middle of the 21st Century. 
6 Condition   8 Suitability   
2019  2024  Change      2019  2024  Change 
A  18  16  -2    A  14  13  -1 
B  43  42  -1    B  46  46  0 
C  1  5  4    C  2  4  2 
D  0  0  0    D  0  0  0   
62  63        62  63   
5.4 These core facts, along with other data analysis and intelligence including
future roll projections and sufficiency data, clearly indicate that we must take
action to address key challenges across the learning estate with the guiding
benefit that doing so will directly improve the lives and experiences of our
young people.

Page 7

Page 7 of 16 
6. Strategic Alignment 
6.1 Renfrewshire Council Plan 2024 - 2027 states a vision of "Creating a fairer
Renfrewshire built on innovation, wellbeing and opportunity”. It is therefore
important that this vision is engrained throughout all aspects of council
business and service provision. 
6.2 Drawing on the overarching council vision, the learning estate strategy must
seek to address the key components of this vision, namely, innovation,
wellbeing, and opportunity, to set a vision for how the estate can be improved
and maintained to positively impact our young people, employees, and
communities. 
6.3 The learning estate strategy has also been devised by drawing on core
concepts of wider council strategies. This includes a link to the strategic
property review strategy which has an objective “to assess the size of and
shape of the Council’s property estate, to provide a modern property estate
that meets the current and future requirements to:
• Support learning
• Support Service delivery outcomes
• Support community needs
• Reduce its carbon footprint (including energy consumption)
• Have a financially sustainable property portfolio”
6.4 The learning estate strategy also follows the guiding principles set by the
Scottish Government in its own national learning estate strategy, which can be
found in Appendix 3 of this report. 
7. Governance and Delivery
7.1 Work has been undertaken to ensure that best practice methods and
processes are implemented from a management and delivery perspective.
This has informed a proposed refresh to the establishment and terms of
reference for the officer level governance and programme arrangements
established to oversee the development and delivery of the overall
programme. 
This has included, within the context of the Council’s formal governance
arrangement, what and how the programme board proposes to exercise
delegated authority within the overall officer level governance, to allow
appropriate flexibility to dynamically manage the demands of a major long-
term programme of this nature. 
7.2 There will continue to be appropriate and effective governance in place at
Council and Policy Board level for the learning estate programme to be

Page 8

Page 8 of 16 
delivered and controlled and all formal governance requirements within the
Council will be fully observed and followed as part of the overall programme
governance arrangements. 
7.3 The terms of reference for the revised officer level programme delivery board
and associated authority thresholds are included in Appendix 1 – Learning
Estate Strategy and Delivery Board Terms of Reference & Governance
Framework. These terms of reference will be used to manage and control the
delivery of the learning estate programme effectively and reflect the
governance authorities already in place. 
7.4 Beyond governance and authority levels, it is recognised that the scale of the
learning estate programme will require a core multi-disciplinary team to
support its development and deliver over the long term. The Council has
adopted similar approaches with other major investment programmes in
recent years, most notably City Deal and Cultural Regeneration Programme. It
is recognised that this programme as envisaged will be much broader than
construction and infrastructure, and a competent professional team must be
established to strategically plan the development of the learning estate by
looking forward, considering all relevant data, legislation, and requirements to
achieve a learning estate that is fit for purpose and integrates effectively with
wider Council strategic objectives in relation to place shaping, community and
strategic use of our property portfolio.
7.5 It is intended to implement a team structure that broadly mirrors that which
has effectively delivered and continues to deliver major investment projects as
part of the City Deal and Cultural Infrastructure programmes. Following
approval of this strategy, steps will be taken to begin assembling over time the
required multi-disciplinary team and where required external engagements to
ensure access to highly specialist skills to be drawn into the team as and
when they are required. 
7.6 A core team of this nature will provide highly focused support to the
programme which will also help drive longer term benefits such as ensuring
high levels of consistency and quality of support and approach to be applied
to individual projects over the long term, including but not limited to project
management approach adopted across all learning estate projects,
consistency in the scale and nature of business case development,
maximising procurement opportunities and community benefits, providing a
consistent and structured approach to delivery of all capital projects,
irrespective of the school or scale of the project etc. 
8. Financial Modelling 
8.1 At present, the existing learning estate new build programme in delivery over
the next four years, is currently estimated at approximately £175 million,
covering a new build secondary, two primary schools and a secondary school
extension. The scale of investment need across the whole learning estate that
is anticipated to be established through this much longer-term planning period
will be significantly greater by comparison, likely running into billions as
opposed to hundreds of millions of pounds.

Page 9

Page 9 of 16 
8.2 In this context, a similarly long term 20 – 25 year strategic funding model will
require to be developed to support the Learning Estate strategy that will set
out financially how the most significant investment programme undertaken by
the Council can be financially deliverable over the very long term. This long
term strategic funding model will be required to set out: - 
i. the proposed funding approach - that will be designed to secure funding
confidence several years in advance of projects progressing, providing
confirmed deliverability of the financial capacity to move forward with
plans to develop, design and deliver major phases of a long-term
investment programme of this nature,
ii. affordability considerations – setting out the scale of financial commitment
that will be required from the Council over the long term to underwrite the
funding model, how delivering the funding model can be effectively
integrated into the Council’s long term financial planning arrangements
and short term budget setting as well as the range of interchangeable
strategies available to the Council to meet this requirement over the
longer term,
iii. financial sustainability – setting out how the cumulative impact of the
funding model can remain within financially sustainable levels in the
context of the Council’s overall resources over the very long term,
iv. the scale and timing of the financial investment capacity the Council is
prepared and able to commit to over the long term which will be a key
factor in determining the potential pace of delivery and scale of each
major phase of investment,
v. how both the funding model and indeed the investment programme itself
can be flexibly adapted to respond to shorter term affordability pressures
that may emerge for the Council recognising that over such a long-term
period the Council is likely to face a range of financial pressures, shifting
demands and priorities that will have been unexpected and it will be
required to manage. 
8.3 In broad terms the funding model requires to support three key elements
within the overall programme:
i. The funding of the core team through appropriate capitalisation of costs
across the lifespan of live projects to minimise any ongoing revenue
burden in a challenging financial climate. 
ii. Capital project funding for the delivery of all major investment projects –
which will encompass new build projects and significant refurbishment
projects where deemed appropriate. 
iii. Strategic lifecycle maintenance – working collaboratively with colleagues
in facilities management, the Council also needs to develop and deliver
major long term planned lifecycle maintenance programmes underpinning
an objective to pro-actively and appropriately protect the fabric of the
learning estate assets to retain all schools in a category A or B for
condition. 
8.4 At present, delivery of the existing SEMP projects, totalling approximately
£175 million of investment is already planned for and accommodated within

Page 10

Page 10 of 16 
the Council’s existing medium term financial planning with delivery of these
projects currently planned over the period 2026 – early 2028. It is envisaged
that subject to appropriate approvals and project development future phases
of investment at scale emerging from this strategic programme and the
associated financial implications will not begin to impact until post 2027/28
financial year. Detailed and appropriate consideration of the financial
implications of planned commitments made by the Council will however be
incorporated as appropriate into existing medium and longer term financial
planning as the initial phase of this strategic programme is considered,
developed and approved ultimately by Council as part of the overall financial
and capital planning processes.
8.5 Whilst the Council has previously secured funding through national school
investment initiatives such as the Learning Estate Investment Programme
provided by the Scottish Government, progressing a strategic programme with
significant reliance on any future national funding schemes would be
inappropriate to deliver the scale of the stated ambitions – albeit depending
upon future national government decisions such funding schemes will
undoubtedly continue to play an important role as part of the overall funding
mix. This strategic approach to the planning of investment priorities and a
longer term pipeline of projects will ensure the Council is will be well placed,
with well developed project options to react quickly as such opportunities arise
and maximise the opportunity to secure funding support. In this context it is
therefore important that the Council develops and implements its own capital
funding model that can be supplemented should any external national funding
routes become available throughout the long term period. 
8.6 At present the Council currently manages capital financing through a rolling
five year investment programme, and it is anticipated the future learning
estate investment phases will continue to be framed in the context of rolling 5
year programmes. 
8.7 The rolling nature of this approach ensures a five year forward projection is
annually re-evaluated, utilising the prioritisation matrix (set out in section 11 of
this report) as the underlying catalyst for priority project identification and to
maintain an evolving list of investment projects for development on an
ongoing basis through the Learning Estate Strategy and Delivery Board and
ultimately for approval through the Education and Children’s Services Policy
Board and Council. This rolling 5 year time horizon is well aligned with the
length of time taken for community engagement, design, development and
delivery of a large scale project such as a school. 
9. Design Development & Procurement
9.1 In line with implementing a core team for consistent practice, this strategy will
also seek to develop a consistent approach to school design and
requirements. The strategy will allow the core team to have clear
understanding of baseline requirements for school design to remain up to date
with current standards, best practice, and consistently implement lessons
learned from ongoing projects to ensure these requirements remain relevant. 
9.2 It is the intention that the core team will develop clear design intent
requirements which align with the 8 strategic objectives outlined as part of this
paper. This approach will ensure that equality is provided in all new school

Page 11

Page 11 of 16 
design moving forward, and to assist with efficiency of delivery, a baseline set
of requirements will be created as part of the strategy that will allow project
teams to have clear understanding of what should be delivered to make an
excellent learning environment.   
9.3 By drawing on lessons learned from previous school delivery projects, as well
as learning from other organisations, it also provides assurance that school
design will be optimal for learning and teaching which should be at the heart
of all decision making. 
9.4 Coinciding with both design development and financial modelling, a further
key component to strategy delivery is the implementation of a clear
procurement strategy. Following approval of the learning estate strategy,
further work will take place with procurement colleagues to create a sub
strategy of the learning estate. 
9.5 Committing to a long term pipeline of planned learning estate projects opens
up the opportunity for the Council to carefully consider optimal routes to
market and maximise best value that can be secured. It is intended that the
procurement strategy will offer options to achieve best value route to market,
per type of project, that creates efficiency in project delivery and establishes
significantly more attractive package of projects to be taken to the market to
maximise interest from the very best contractors. 
9.6 In addition, the scale and nature of package likely to be taken to market by the
Council over a long-term period also provides the opportunity to maximise
community benefits that are derived as part of the procurement process and
this will be a key objective as part of the overall procurement strategy. 
10. Engagement
10.1 Strong community engagement throughout project delivery is an essential
component and is recognised by the Scottish Government as a key process
as part of any learning estate programme. Designing with communities and
stakeholders should be adopted as best practice. Current processes
surrounding Dargavel Village and its associated primary schools, show that
the feedback and input through engagement proves invaluable to overall
design and direction. 
10.2 It is intended that an overall corporate engagement policy that is under
development will guide development of engagement strategy for the learning
estate. The policy will provide guidance on best practice engagement to
ensure early planning, integration with equality impact assessment, robust
pre-engagement and identification of options, identification of all relevant
stakeholders, clarity on engagement objectives and data management and
analysis, and that risks are understood. It will also provide a range of tools to
support engagement with different audiences and groups. 
10.3 A strong engagement strategy as part of the overall design of the learning
estate strategy will ensure that communities and stakeholder are truly
engaged in the process of why a change to a school provision is required and
allow them to become a part of the process of development for an asset that
will serve them and their wider communities for the better.

Page 12

Page 12 of 16 
11. Identification of Priority Projects for Investment 
11.1 To deliver the strategic vision, an improved methodology is proposed to
identify and prioritise future investment projects that would be subject to
detailed business case development. When developing the methodology, an
objective approach was taken to assess the whole estate against the
recommended strategic objectives and highlight the schools which should
form the focus of the investment programme. 
11.2 Based on a weighted evaluation for each school establishment, a prioritised
list of all schools can be produced. The weighted criteria will contain data on
the three core fact topics which are condition, suitability, and sufficiency
(capacity). A further suite of data will also be considered which is quartile data
held by Renfrewshire Council. Quartile data is a range of socio-economic data
used in a formula to rank schools in relation to deprivation. Schools are
organised into 4 quartiles with quartile 1 having higher deprivation measures
than 4. In many circumstances, this data is used to target support and
resources, particularly in relation to raising attainment. It is therefore proposed
that the four categories of condition, suitability, sufficiency, and quartiles are
used to contribute to an overall weighted score per establishment. By
compiling the four score categories described above along with their weighted
score, a final total rating per establishment can be produced. This will allow an
overall priority list of establishments to be created.  
11.3 The proposed weighted criteria to each of the four elements of decision
making can be seen below.
Condition
30%
Suitability
40%
Capacity
10%
Quartile
20% 
11.4 This approach ensures that identification of which school requires investment
as a priority is underpinned by a data driven approach that can be
implemented to create the proposed programme of investment, maximising
the opportunity for transparency and mitigating the risk of subjectivity.
11.5 Chief Officers directly involved in school estate investment, maintenance, and
planning participated in a workshop where alternative weighting scenarios
were explored and evaluated and the weightings proposed above were
identified as most appropriate for our learning estate. Suitability was identified
as the key factor as this is: “the measure of whether a school building and its
grounds are fit for the purpose of delivering the education curriculum” (The
Scottish Government, School Estates: Core Facts Overview , 2017) 
11.6 It is important to note that a caveat to the above exists where there is a clearly
identified need to address developing and projected capacity pressures within
a school, which will by necessity require to be dealt with as a priority project.
The general weighted score of capacity has been included in the overall
decision making of combined scoring to assess schools that are operating
under capacity and should be assessed strategically as part of future
planning.

Page 13

Page 13 of 16 
12. Business Case and Option Appraisal - including New Build vs
Refurbishment
12.1 It is proposed that as projects are identified through the strategic prioritisation
process, those identified as priority projects for the next phase of investment
will be subject to the development of a detailed business case. All individual
business cases will require to be considered and approved by the Board and
Council as part of the Council’s overall financial planning arrangements before
moving forward to detailed project development.
12.2 A standardised business case process will be developed, compliant with HM
Treasury Green Book guidance, to support the overall assessment of the
project proposal. This process will include assessing the overall scope of the
proposed project, taking into account wider community, placeshaping and
strategic property considerations as well as consideration of potential
opportunities that may arise in relation to wider estate configuration in the
context of existing and longer term roll projections. 
12.3 The business case development process will also consider the role of new
build vs the role of significant refurbishment. Such an option appraisal will
require to take a holistic view of the merits of each and as a minimum it is
proposed to consider the following key criteria as an initial triage assessment
of whether a major refurbishment is likely to represent a viable option for
detailed consideration. , to determine if “following a refurbishment, will the
answer be yes to all of the below criteria?”:
Refurbishment Triage Assessment  
Can long term sustained condition A or B be
achieved?
Can Suitability A or B be achieved?
Can sufficiency at 80% to 95% be achieved?
Can the Educational Requirements be met?
Will a refurbishment provide whole life value for
money benefits?
12.4 Should the triage assessment of all questions produce the answer ‘yes’, the
decision should be to proceed with a full option appraisal that consider a
major refurbishment as a viable option. If any of the answers to the above
results in a ‘no’, then the decision should be to proceed with developing
option(s) for a new build facility. 
12.5 A further key consideration for any new development is based on land
availability. Some areas of Renfrewshire currently have limited land available
for construction and development which may present specific challenges. This
must be factored into detailed business case planning and will be a further
stage of decision making when it comes to options appraisal assessment
once a decision is made on new build vs refurbishment. To ensure progress

Page 14

Page 14 of 16 
can be made on any development where land is a constraint, close working
relationships will continue between the learning estate team and the Economy
& Development service. 
12.6 Should land availability be identified as a constraining factor for any required
project within the learning estate strategy, this will require innovation including
the potential for land and property acquisition and sales to facilitate the
assembly of a suitable site. The Council has had recent experience of
adopting such an approach by securing the current site for the new Paisley
Grammar School currently under construction. Such challenges will require
the council to be proactive and determined to deliver on this major ambition to
significantly enhance the learning estate. This also reinforces the need for a
core team to be working on the delivery of the learning estate strategy to
ensure key professional resources are available to work collaboratively on this
strategy and contribute on a council wide level to our place making ambitions.  
12.7 Whilst much of Renfrewshire’s learning estate has remained static for a
number of decades, we are committed to delivering on the vision to “Create
the best possible learning estate to allow children and young people to thrive”
and consideration must be given to all options when assessing the most
appropriate solution for the development of a new learning environment. This
could include matters such as catchment reviews, however, should this be
required it would be subject to statutory consultation with the community
affected. 
13. Conclusion
13.1 To deliver the most ambitious programme of investment for our learning
estate, the Council must be innovative and forward thinking to collectively
drive the delivery of the vision of this strategy, within the overarching strategic
priorities of the council. 
13.2 Learning estate establishments are imperative for the prosperity, safety, and
education of our young people, but growing evidence shows the benefits to
the wider community to make the learning estate an asset for all. It is noted
that the condition as well as how fit for purpose the establishment is, has a
direct correlation to engagement and raising attainment.  For these reasons,
Children’s Services considers the delivery of the learning estate strategy to be
a key priority. 
13.3 The strategic approach set out in this paper, supported by the business
requirements and resources outlined, will allow an objectively assessed long
term prioritised programme of investment to be developed to allow the Council
to be best placed to understand what requires to be delivered over the next 20
years in the learning estate to meet the Council’s ambitions for our young
people and communities and demonstrate how such a programme can be
achieved in a financially responsible and sustainable manner. 
Implications of the Report
1. Financial

Page 15

Page 15 of 16 
This report outlines what will be a substantial financial investment for the
Council. Should recommendations in this report be approved, detailed work
will take place to develop financial models and funding mechanisms for the
learning estate strategy which will directly inform long term financial planning
and future annual budget considerations, always ensuring that the Council’s
financial sustainability is maintained. 
2. HR and Organisational Development 
A dedicated staffing establishment will be required to manage the ambitions
set out in this strategy. Work will take place with HR to determine roles, and
recruit in line with council policy. 
3. Community/Council Planning 
Our Renfrewshire is thriving - Learning environments will support learning
and achievement for all. 
Our Renfrewshire is well - Learning environments will support the Health
and Wellbeing of all. 
Our Renfrewshire is safe - Learning environments will provide safe and
secure spaces for all users. 
Reshaping our place, our economy and our future - Learning
environments will provide spaces which support local enterprise. 
Building strong, safe and resilient communities - Learning environments
will provide spaces to support community activities. 
4. Legal 
Renfrewshire Council adheres to all relevant legislation. 
5. Property/Assets 
The learning estate strategy will offer significant investment to council assets
and specifically address constraints on building maintenance. This will offer
an improved estate which will bring ongoing financial benefits by having an
estate in a positive state of condition. This strategy aligns with the ongoing
Strategic Property Review to ensure consistency in decision making. 
6. Information Technology 
Learning environments will have IT provision which supports digitally enabled
learning. 
7. Equality and Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. There has been a full
Equalities and Human Rights Assessment carried out for the consultation
process to ensure it is fully inclusive. No negative impacts on equality groups
or potential for infringement of individuals’ human rights have been identified

Page 16

Page 16 of 16 
arising from the recommendations contained in the report. If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment will
be published on the Council’s website. 
8. Health and Safety 
None. 
9. Procurement 
A procurement strategy which supports the aims and objectives of the
learning estate strategy will be developed, including principles to deliver
efficient routes to market. 
10. Risk 
A full risk register is compiled for all projects in accordance with the Council’s
established risk management protocols. All projects will continue to be
managed under industry standard best practice methodologies and assess
risk on an ongoing basis.   
11. Privacy Impact 
None. 
12. Climate Risk 
All assets aim to comply with the requirements for ambitious energy efficiency
targets over the long term and to contribute to the Council’s net-zero
commitments. 
13. Children’s Rights
The rights and wellbeing of children and young people is at the heart of our
Children’s Services Health and Safety Plan. As a council we will continue to
work together to promote equality and raise awareness of the United Nations
Convention on the Rights of the Child (UNCRC) to make sure children and
young people’s rights are promoted and reflected in all that we do. This will
ensure that we are meeting the requirements of the new duties under
the United Nations Convention on the Rights of the Child (Incorporation)
(Scotland) Act 2024. 
14. Cosla Policy Position 
None. 
__________________________________________________________________ 
Children’s Services
JO/JL/AR
2 August 2024 
Author:  Jack Lochans, Education Manager, Learning Estate (jack.lochans@renfrewshire.gov.uk

Page 17

Page 1 of 9 
Appendix 1 – Learning Estate Strategy and Delivery Board Terms of Reference
& Governance Framework 
1. ROLE     
The Learning Estate Strategy and Delivery Board is a working strategic Board
convened of senior officers. The Learning Estate Strategy and Delivery Board
advises elected members in terms of capital allocation and project approval
and has responsibility for the day-to-day management of the Learning Estate
capital programmes, including the realignment of resources to facilitate the
effective delivery of the Learning Estate Strategic Capital Investment
Programme, including:    
• Learning Estate New Build   
• Learning Estate capital improvements and refurbishment/retrofit 
• Learning Estate extension and modification 
The Learning Estate Strategy and Delivery Board makes recommendations on
any amendments to the approved capital programmes, as required, with any
amendments approved by Council and Policy Boards in line with the financial
regulations and Scheme of Delegation.    
1.1 Chair     
The Director of Childrens Services will act as Chair of the Learning Estate
Strategy and Delivery Board, with the Director of Finance and Resources as
Depute.    
1.2 Learning Estate Strategy and Delivery Board objectives     
These strategic objectives are to align with the following national and local
priorities and guidance: 
• Scotland’s Learning Estate Strategy: Connecting People Place and
learning  
• Council Plan 2022-27 
• Renfrewshire’s Plan for Net Zero 
• Renfrewshire Council’s Strategic Property Review 
The Learning Estate Strategy and Delivery Board shall also 
i. Develop a Learning Estate Renewal and Improvement Strategy and
Finance Model; 
ii. Implement a Learning Estate Strategic Capital Investment Programme(s)
to deliver the Learning Estate Renewal and Improvement Strategy; 
iii. Monitor the Learning Estate Strategic Capital Investment Programme(s),
including performance against delivery aims and objectives;  
iv. Advise Elected Members on capital allocations and project approval,
making recommendations on any amendments to the approved capital
programme;  
v. Ensure the proper alignment of capital resources to allow for effective
delivery of the programme(s);

Page 18

Page 2 of 9 
vi. Monitor expenditure projections against budgets and available resources,
revising these where necessary, subject to the limits set out in Section 4 –
Authority;  
vii. Ensure robust governance arrangements around the delivery, monitoring
and reporting of capital programmes;  
viii. Consider the capital monitoring reports to Policy Boards to ensure
appropriate actions are agreed for review by Elected Members;  
ix. Ensure Budgeting principles are embedded in key capital investment
decisions of the Council;  
x. Arrange and undertake training/awareness sessions as required to
reinforce skills/knowledge across the Council in respect of capital
monitoring and capital financing;  
xi. Ensure all decisions made by the Learning Estate Strategy and Delivery
Board are Intra Vires and in line with the policies and vision of the
Council.     
As a minimum, updates on the Learning Estate Renewal and Improvement
Strategy and Finance Model should be provided to both the Children’s
Services Directorate and the Council’s Corporate Management Team bi-
annually and as required. An annual report on the status of the overall
Learning Estate Renewal and Improvement Strategy and Finance Model
should be provided to the Education and Children’s Services Policy Board. 
2. MEMBERSHIP    
2.1 Membership 
Membership to include: 
Director of Childrens Services 
Director of Finance and Resources 
Director of Environment, Housing and Infrastructure 
Head of Facilities and Property Services 
Head of Climate, Public Protection and Roads 
Head of Economy and Development Services 
Head of Policy and Partnerships 
Head(s) of Education
Head of Marketing and Communications 
Corporate Procurement Manager 
Managing Solicitor (Projects) 
Finance Business Partner (Children’s Services) 
Education Manager (Learning Estate & Resources) 
Learning Estate Programme Manager 
Service Improvement Manager 
Membership of the Learning Estate Strategy and Delivery Board reflects the
composition of the capital programmes and ensures the fair representation of
Council services responsible for investment in all Council assets. 
The Learning Estate Strategy and Delivery Board must make decisions on a
corporate basis, in line with the policies and strategies of the Council,
Financial Strategy, Financial Regulations, Scheme of Delegation and other

Page 19

Page 3 of 9 
relevant plans and policies. If the Council structure changes the membership
will be aligned to the new structure. 
2.2 Attendance    
Where Learning Estate Strategy and Delivery Board members are unable to
attend meetings, nominated deputies should attend. Learning Estate Strategy
and Delivery Board membership should be representative of Council services
involved in delivering capital projects within the Learning Estate, with
members acting in an independent manner. Quorum is achieved with 70%
attendance (including substitutes). If a meeting is not quorate, the Learning
Estate Strategy and Delivery Board is required to reconvene. Officers and
external parties may be invited to attend meetings of the Learning Estate
Strategy and Delivery Board to provide information/ support and to answer
questions in respect of the Council’s capital programmes.    
3. PROCEDURES 
3.1 Meeting Frequency 
The Learning Estate Strategy and Delivery Board will meet monthly and as a
minimum prior to each cycle of the Education and Childrens Services Board
and the Finance, Resources and Customer Services Board.    
3.2 Administration 
Administrative support will be arranged by the Chair with the Programme
Manager to coordinate and distribute agendas, minutes and meeting papers.
Records of all minutes, decisions and actions will be maintained.    
3.3 Submissions and Reports 
Learning Estate Strategy and Delivery Board members may make
submissions to the Learning Estate Strategy and Delivery Board. Submissions
and progress reports should reach the nominated administrative support no
later than five working days before each meeting. Urgent matters may be
submitted later than this deadline, but only with the approval of the Chair. 
3.4 Agendas and Papers 
Agendas will be prepared and distributed to Learning Estate Strategy and
Delivery Board members with supporting papers at least three working days
before each meeting.    
3.5 Actions from Meetings 
Actions will be taken of meetings and will be distributed in draft via email
within five working days of the Learning Estate Strategy and Delivery Board
meeting. Minutes will be approved by the Learning Estate Strategy and
Delivery Board at the following meeting.    
3.6 Actions and Communication

Page 20

Page 4 of 9 
Learning Estate Strategy and Delivery Board members shall ensure that any
decisions relevant to their Service are actioned by relevant officers.
Responsibility for actions arising from meetings will be recorded in an action
log or updated work plan as per the outcome of the meeting. The members of
the Learning Estate Strategy and Delivery Board shall refer decisions to
individual Policy Boards for approval or noting as appropriate and required, in
accordance with agreed limits outlined in Section 4 – Approvals below and will
advise the Learning Estate Strategy and Delivery Board of outcomes and
decisions made by Policy Boards. The Chair will refer Learning Estate
Strategy and Delivery Board minutes to Corporate Management Team as
appropriate and required. 
3.7 Special Meetings 
Special meetings of the Learning Estate Strategy and Delivery Board may be
called at the discretion of the Chair. As far as possible, normal procedures will
be followed.    
4. AUTHORITY 
4.1 Resources     
The Capital Programmes are based on estimates of future investment targets
funded by a combination of Scottish Government Grants, capital receipts,
CFCR and prudential borrowing. When confirmation of investment targets is
reviewed or amendments to resources are known, the Learning Estate
Strategy and Delivery Board will consider adjusting the Programme
accordingly. Recommendations for a revised programme, based on the actual
level of resources will subsequently be referred to the Education and
Childrens Services Board and/or the Finance, Resources and Customer
Services Board for approval, with Council agreeing the overarching annual
capital plan.    
4.2  Virement & Re-profiling 
General Fund Capital Programme 
The Learning Estate Strategy and Delivery Board has the authority to redirect
resources across thematic or project categories within the Learning Estate
Capital Programme(s). In the event the Learning Estate Strategy and Delivery
Board agrees a virement between approved Project / Thematic Categories,
this will be up to a maximum of £100,000. Virements above this value require
the approval of the Education and Childrens Services Board and the Finance,
Resources and Customer Services Board if the virement is across Services.

Page 21

Page 5 of 9 
4.3 Re-profiling of Capital Allocations 
The Learning Estate Strategy and Delivery Board has authority to re-profile
capital allocations within Project / Thematic Categories up to a maximum of
£10,000,000 to and from future years of the Programme to ensure effective
delivery over the 3 year rolling programme timeframe, provided this can be
managed within the overall annual budgeted resources (i.e. does not create
additional unbudgeted borrowing costs). Any reprofiling will be reported to
Education and Childrens Services Board and the Finance, Resources and
Customer Services Board for noting.    
4.4  Over - programming Allowance 
An over programming allowance may be incorporated into the Learning Estate
Capital Programme if the Learning Estate Strategy and Delivery Board
consider it appropriate and necessary. This will enable the inclusion of
additional capital projects within the programme which take the cost estimates
beyond available allocated and approved project budgets to enable utilisation
of underspends or funds from aborted or delayed projects within an approved
programme allowance. The Learning Estate Strategy and Delivery Board is
required to review and monitor any over-programming allowance to ensure
levels of funding remain sufficient to meet programme commitments.    
4.5 Additional Project Approval 
Approval must be sought from the Learning Estate Strategy and Delivery
Board for new projects/ additional investment which cannot be contained
within the currently approved Council Programmes. If approval is granted, the
programme must be amended to maintain projected spend within the
approved capital budget and approval sought from the Education and
Childrens Services Board and/or the Finance, Resources and Customer
Services Board as appropriate. Emergency works outwith the approved
Programme should be referred to the Chair who will consult as appropriate
with the Director of Finance and Resources, the Chief Executive and/or the
Council Leader.    
4.6  Monitoring 
Individual Service Policy Board reports will provide monitoring information
showing the appropriate level of detail, in line with the project theme
groupings as laid out within the Learning Estate Strategic Capital Investment
Programme or alternatively in accordance with the appropriate Strategic
Delivery Groupings within the individual service programmes. Whilst individual
budget holders have responsibility for reporting variances and ensuring
compliance with Financial Regulations and General Contract Standing Orders,
overall responsibility for financial management lies with the Director of
Finance and Resources. Therefore, finance staff must be provided with
information for individual projects to allow for effective financial monitoring.

Page 22

Page 6 of 9 
4.7 Sub Learning Estate Strategy and Delivery Boards 
To ensure specific management of resources to advance the Councils
programme and objectives, the Learning Estate Strategy and Delivery Board
may establish and delegate authority to either sub-Learning Estate Project
Boards or other Project Boards as considered necessary to progress the
Strategic Programme(s). The sub-Learning Estate Project Boards will have
Terms of Reference and Governance Frameworks established which shall
include the requirement to report back to the Learning Estate Strategy and
Delivery Board. 
5. POST PROJECT AND POST OCCUPANCY REVIEWS 
To ensure specific management of resources to advance the Councils
programme(s) and objectives, the Learning Estate Strategy and Delivery
Board will establish and commission post project reviews for all investments
exceeding £2M and a post project review report will be presented to the
Learning Estate Strategy and Delivery Board within 6 months of completion of
each project. The Board shall also commission a Post Occupancy Evaluation
to be completed after one full year of occupation and use and presented to the
Board within 15 months of occupation. 
6. RISK MANAGEMENT 
All risks relating to the Programme and to individual projects will be managed
in line with the Council’s Risk Management Strategy and in accordance with
Project Management guidelines.

Page 23

Page 7 of 9 
Appendix 2 – Core Facts Summary by Establishment 
Condition - is described as the current state of the fabric of a school and the safety
and security. The condition core fact is based on the latest condition survey, updated
with any maintenance or repair work carried out in the intervening periods. The
condition rating assesses the physical elements of the school structure and extends
to playgrounds; external structures and services; security facilities; and playing
fields.   
Suitability - is a measure of whether a school building and its grounds are fit for the
purpose of delivering the education curriculum. The suitability of a school is
determined by an assessment of internal and external facilities.  This assessment is
carried out by the school community and moderated by children’s services. 
Sufficiency - is concerned with the occupancy levels of schools and assesses which
schools are over, or under capacity to determine pupil places available 
Establishment Name
Overall
Condition
Suitability
Of Estate
Pupil Roll
At last
Census
School
Capacity
Roll
Sufficiency
Primary Estate
Arkleston Primary School B B 295 352 83.8%
Auchenlodment Primary School C B 195 302 64.6%
Bargarran Primary School A B 216 272 79.4%
Barsail Primary School B B 308 401 76.8%
Bishopton Primary School B B 367 519 70.7%
Brediland Primary School B B 196 377 52.0%
Bridge Of Weir Primary School C C 442 489 90.4%
Bushes Primary School B B 330 489 67.5%
Cochrane Castle Primary A A 126 242 52.1%
Dargavel Primary School A A 590 534 110.5%
East Fulton Primary School B B 224 377 59.4%
Fordbank Primary School A A 268 327 82.0%
Gallowhill Primary School B B 217 352 61.6%
Glencoats Primary School A A 181 352 51.4%
Heriot Primary School B B 232 434 53.5%
Houston Primary School B B 534 569 93.8%
Howwood Primary School B B 116 184 63.0%
Inchinnan Primary School B B 125 217 57.6%
Kilbarchan Primary School B B 214 352 60.8%
Kirklandneuk Primary School B B 446 619 72.1%
Langbank Primary School B B 75 100 75.0%
Langcraigs Primary School B B 286 434 65.9%
Lochfield Primary School B B 252 459 54.9%
Lochwinnoch Primary School B B 199 327 60.9%
Mossvale Primary School B A 207 272 76.1%
Newmains Primary School B B 403 459 87.8%
Our Lady Of Peace Primary School B B 230 352 65.3%
Ralston Primary School B B 382 459 83.2%
Rashielea Primary School B B 161 434 37.1%
St Anne's Primary School B B 137 242 56.6%
St Anthony's Primary School A B 245 302 81.1%
St Catherine's Primary School B B 218 272 80.1%
St Charles' Primary School B B 388 489 79.3%
St David's Primary School A A 91 184 49.5%
St Fergus Primary School A B 170 175 97.1%

Page 24

Page 8 of 9 
St Fillan's Primary School B B 90 184 48.9%
St James's Primary School (Paisley) B B 168 217 77.4%
St James's Primary School
(Renfrew) B B 558 676 82.5%
St John Bosco Primary School A A 257 272 94.5%
St John Ogilvie Primary School B B 244 272 89.7%
St Margaret's Primary School B B 170 272 62.5%
St Mary's Primary School B B 274 327 83.8%
St Paul's Primary School A A 180 217 82.9%
St Peter's Primary School C B 223 352 63.4%
Thorn Primary School B C 152 272 55.9%
Todholm Primary School A A 389 434 89.6%
Wallace Primary School B B 330 434 76.0%
West Primary School B B 403 761 53.0%
Williamsburgh Primary School B B 334 594 56.2%
Woodlands Primary School A B 249 459 54.2%
Secondary Estate
Castlehead High School B B 753 1230 61.2%
Gleniffer High School A B 1110 1425 77.9%
Gryffe High School B B 958 960 99.8%
Johnstone High School C B 869 1380 63.0%
Linwood High School A A 436 576 75.7%
Paisley Grammar School C C 1066 1329 80.2%
Park Mains High School B A 1467 1591 92.2%
Renfrew High School B B 829 1267 65.4%
St Andrew's Academy A B 1480 1250 118.4%
St Benedict's High School A A 725 850 85.3%
Trinity High School B C 953 1032 92.3%
ASN Estate
Mary Russell School B B 169 169 100.0%
Riverbrae School B A 219 219 100.0%

Page 25

Page 9 of 9 
Appendix 3 – Scottish Government Learning Estate Guiding Principles 
1. Learning environments should support and facilitate excellent joined up
learning and teaching to meet the needs of all learners;
2.  Learning environments should support the wellbeing of all learners, meet
varying needs to support inclusion and support transitions for all learners;
3.  The learning estate should be well-managed and maintained, making the best
of existing resources, maximising occupancy and representing and delivering
best value;
4.  The condition and suitability of learning environments should support and
enhance their function;
5.  Learning environments should serve the wider community and where
appropriate be integrated with the delivery of other public services in line with
the place principle;
6.  Learning environments should be greener, more sustainable, allow safe and
accessible routes for walking, cycling and wheeling and be digitally enabled;
7.  Outdoor learning and the use of outdoor learning environments should be
maximised;
8.  Good consultation about learning environments, direct engagement with
learners and communities about their needs and experiences, and an
involvement in decision making processes should lead to better outcomes for
all;
9.  Collaboration across the learning estate, and collaboration with partners in
localities, should support maximising its full potential; and finally,
10.  Investment in Scotland’s learning estate should contribute towards improving
learning outcomes and support sustainable and inclusive economic growth.