Renfrewshire Council · 23 May 2024
Back to Education and Children's Services Policy Board — 23 May 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

Page 1 of 6 
To:  Education and Children’s Services Policy Board
On: 23 May 2024
__________________________________________________________________ 
Report by:  Interim Head of Education 
__________________________________________________________________ 
Heading:  Learning Estate Update 
__________________________________________________________________
1. Summary
1.1 The purpose of this report is to provide members with a further update on
current capital projects to develop and improve the learning estate, as well as
providing a brief overview of the next steps of the Learning Estates Strategy
under development. 
1.2 A number of significant projects are underway to enhance the school estate,
and this report will cover:
• Paisley Grammar School Community Campus 
• Park Mains High School extension and alterations 
• New Dargavel Primary School 
• Dargavel Primary School internal alterations
• Bishopton Primary School classroom block
• Thorn Primary School new build
• Castlehead roof strengthening works 
1.3 The programme of work continues at pace and remains on track as per
agreed timescales. Further detail of each project is provided within this report. 
2. Recommendations
2.1. It is recommended that members note the content of this report.

Page 2

Page 2 of 6 
2.2. Members are asked to note the intent to construct a new Thorn Primary
School on the grounds of the current school, following final assessment of the
business case. 
3. Paisley Grammar School Community Campus
3.1. This project will deliver a new state of the art education and community facility
for Paisley Grammar School. The project to deliver a new Paisley Grammar
school has made significant progress in recent months with the enabling
works beginning on site in March 2024. This work will ensure all land is
prepared and in a ‘construction ready’ state, ahead of the main works contract
beginning on 17 June 2024. 
3.2. The contract for the main works is going through final governance approvals
currently, and will be announced imminently, to ensure the contractor can
begin work on 17 June. 
3.3. Whilst a series of public engagement has already taken place, officers will
ensure that the school community, local community and elected members
remain updated on progress through a communications plan. 
4. Park Mains High School Extension and Adaptations 
4.1. As reported to the last Policy Board, a series of space planning sessions have
been undertaken to determine how the school could be increased to a 2,000
capacity school. This exercise has produced a model that is deliverable from
a construction and education perspective. 
4.2. The next steps of this exercise is to complete detailed cost planning on the
proposed model to determine exact cost outturn, which is the standard
process for all construction projects. 
4.3. To ensure the model will deliver an excellent education experience, significant
work has taken place with professional school space planners, the Head
Teacher and senior management, as well as multiple information gathering
and sharing exercises with staff. This has been supported by engagement
sessions with parent council groups of both the secondary school, and all
feeder primary schools. 
4.4. The extended Park Mains High School is planned to deliver for summer 2027
in line with projections of increased demand. The project is currently finalising
Stage 1 of the design and once agreed by the Learning Estates Programme
Board, progress will be made with planning the procurement of a contractor
and the remaining design stages. 
4.5. A full engagement plan is being developed, and all stakeholders will remain
fully updated with proposed plans and progress and will have opportunity to
engage with plans.
4.6. Whilst this project is being delivered, the installation of temporary modular unit
has been taking place at the school to deliver flexibility and an increase in
space. This modular unit has delivered five additional classrooms, and is on

Page 3

Page 3 of 6 
track to be handed over for use in June 2024. The final fit out of these
classrooms is currently taking place. 
5. New Dargavel Primary School 
5.1. Under the Schools (Consultation) (Scotland) Act 2010 the Council has
completed a formal consultation on a proposal to establish a new primary
school in Dargavel. A separate paper on this consultation has been provided
to this Policy Board and therefore this paper will not address the detail of that
consultation. 
5.2. If a decision is made to proceed with delivering a new primary school in
Dargavel, the Council has taken pro active steps to ensure a tight timescale
for delivery can be achieved. This has included engaging with Hub West
Scotland for an accelerated route to market for construction contractors and
consultants to deliver a new school. Whilst no detailed work has been
possible until the decision of the consultation is known, this approach will
ensure that the project can hit the ground running.
5.3. Coupled with engagement of Hub West Scotland, the project team has also
continued detailed information gathering with key stakeholders to ensure the
brief and requirements of the new school are known. This will also include all
feedback from public engagement throughout the course of the public
consultation process. 
5.4. It should also be noted that this project will continue to engage with the public
and key stakeholders through the design stages of the project if agreement is
made to proceed with the delivery of a new primary school in Dargavel. 
5.5. Plans are in place to ensure that this school can be delivered for summer
2027 which matches the requirement for demand with roll projections. 
6. Dargavel Primary School Internal Alterations 
6.1. Following the opening of Dargavel Primary School, allowing time for staff and
pupils to embed and get to know their school, a number of feedback points
have been received. These matters have been addressed and has resulted in
some internal alterations being planned for summer 2024. 
6.2. This work will address noise disruption in some areas of the school, caused
through the open plan nature of the design. The building warrant associated
with these works has been approved and the contractor has completed some
early work over the Easter holidays. The contractor is ready to commence the
remainder of the work in the summer holidays this year. 
6.3. These works seek to achieve better use of space in the school as well as
improved educational experience for pupils through a reduction in noise.

Page 4

Page 4 of 6 
7. Bishopton Primary School Classroom Block
7.1. Work to deliver an improved classroom block at Bishopton Primary School
has been ongoing. This facility will provide a modern teaching environment
and increased flexibility to the school. 
7.2. Work remains on track for a handover of this facility during summer 2024
which will allow use from the new school year. 
8. Thorn Primary School 
8.1. The Council agreed under the previous School Estates Management Plan to
invest £10million to deliver a new Thorn Primary School, with the intention for
the balance of the funding required to be funded through the Learning Estate
Investment Programme managed by the Scottish Futures Trust.
8.2. Following an unsuccessful funding bid, the Council agreed to apply additional
funds to meet the budget gap to enable the delivery of this new school. This
was provided with support from a business case which showed that the
expected cost to deliver a refurbishment and extension to increase the
condition and suitability of the school would cost circa. £10.8million compared
to the indicative costs for a new build which would cost circa £14million. 
8.3. On the balance of economic advantage and a much improved suitability of
school through the delivery of a new build, the council agreed to fund this
additonal budget requirement. 
8.4. Members are asked to note the intention that upon initial site ivestigation to
determine the viability of delvering a new school on the grounds of the current
school, and on review of the business case, it is the intention to proceed with
the delivery of a new build school for Thorn Primary. 
8.5. The project remains at very early stages, and intial stakeholder engagement
is being planned to ensure that all views are heard and can be appropriately
implemented into the design of the new school where possible. 
8.6. Current estimates project that a new school can be delivered by 2028.
However, a full programme will be developed shortly, and will be shared with
Elected Members and the community. 
9. Castlehead Roof Strengthening Work 
9.1. Following the discovery of reinforced autoclaved aerated concrete (RAAC) in
the gym areas of Castlehead High School, a procurement exercise has been
completed to appoint a contractor to undertake remedial strengthening works
in these areas. 
9.2. A contractor has been appointed and will commence work in early June 2024,
with an expected contract period of 17 weeks. Throughout this process, the
school and education management will continue to manage any disruption to
staff and pupils.

Page 5

Page 5 of 6 
9.3. This work will provide essential safety improvements and improve the
condition of all gym areas in the school which will ensure that the space can
be used safely with an improved experience for all. 
10. School Estates Management Plan / Learning Estates Strategy
10.1. As previously agreed with this Board, a School Estates Management Plan will
be provided to the August Policy Board. This plan is currently being worked
on and will encompass the proposal for a new strategic model for how the
school estate will be managed and improved going forward. 
10.2. This strategy aims to produce a comprehensive model for future years to
ensure that Renfrewshire can provide a high class education experience for
all, and draws on many lessons learned from recent years. 
10.3. Further communication will be shared with Members on this strategy prior to
publication. 
Implications of this report 
1.  Financial 
This report is for noting and as such there no implications which arise
directly from this report. 
2.  HR and Organisational Development 
None 
3. Community/Council Planning 
Our Renfrewshire is thriving -  The new learning environment will
support learning and achievement
for all.
Our Renfrewshire is well -  The new learning environment will
support the Health and Wellbeing of
all.
Our Renfrewshire is safe  -  The new learning environment will
provide safe and secure spaces for
all users.
Reshaping our place, our
economy and our future 
-  The new learning environment will
provided spaces which support local
enterprise.
Building strong, safe and
resilient communities 
-  The new learning environment will
provide spaces to support
community activities. 
4.  Legal 
Renfrewshire Council adheres to all relevant legislation.

Page 6

Page 6 of 6 
5.  Property/Assets 
Through its school estate management plan the Council aims to have an
efficient and well maintained property portfolio which provides learning
environments which support the delivery of the curriculum. 
6.  Information Technology 
The new campus will have IT provision which supports digitally enabled
learning. 
7.  Equality and Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. There has been a
full Equalities and Human Rights Assessment carried out for the
consultation process to ensure it is fully inclusive. No negative impacts on
equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report.   If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.   
8. Health and Safety
None. 
9. Procurement 
Renfrewshire Council adheres to all procurement regulations. 
10. Risk 
A full risk register will be compiled for the project in accordance with the
Council’s established risk management protocols. 
11. Privacy Impact
None. 
12.  Cosla Policy Position 
None. 
13. Climate Risk
The project aims to comply with the requirements for ambitious energy
efficiency targets over the long term and to contribute to the Council’s net-zero
commitments. 
Children’s Services
JL/GL
10 May 2024 
Author:   Gerry Lyons, Interim Head of Education gerry.lyons@renfrewshire.gov.uk