To:  Education and Children’s Services Policy Board
On: 14 March 2024
__________________________________________________________________ 
Report by:  Interim Head of Education 
__________________________________________________________________ 
Heading:  Learning Estate Update 
__________________________________________________________________
1. Summary
1.1 The purpose of this report is to provide members with a further update on
current capital projects to develop and improve the learning estate
1.2 The Council has engaged with Space Zero to develop a strategic planning
brief for the new primary school in Dargavel. This work has included
engagement with key stakeholders, visioning sessions, focus groups and
general data gathering around requirements and expectations for the new
school. This exercise was in advance of the required statutory consultation,
and concluded in December 23. This will inform the next key stage in the
design process which is the production of an accommodation schedule, which
will in turn enable clearer cost forecasting before producing the final brief
which will be handed over to the architects. 
1.3 The Education and Childrens Services Policy Board on 18 January 2024
agreed to move ahead with the formal consultation on the establishment of a
new school and associated catchment review.
1.4 Following discussion with the school management, designers have now
agreed a solution for the internal alterations to Dargavel Primary School that
satisfies the school requirements and meets statutory building requirements.
A Building Warrant has been applied for and is awaiting formal approval.
Suitable procurement routes are being considered with the aim being to
undertake the required works during the summer break in time for the new
school term.  
1.5 Works to repurpose the existing modular unit at Park Mains High School are
underway, with an expected completion date of April 2024. This will create five
additional classrooms which will provide flexibility for the school as the roll
increases.

Page 2

Page 2 of 6 
1.6 The Space Planning exercise for Park Mains High School is progressing. The
four planned Steering Group Sessions have been completed, feedback from
which will be used to finalise the Strategic Brief.
1.7 To provide an improved learning environment at Bishopton Primary School,
we are replacing the Classroom Block with a new, improved permanent
facility, in time for the new school year in August 2024. Our contractor began
work on site at the end of January 2024
1.8 The new Paisley Grammar School Community Campus remains on track.
Planning permission was granted at the end of January 2024. At the time of
writing (early Feb 2024) steady progress is being made towards being able to
hand over the site to the contractor to allow them to begin enabling works
towards the end of February 
1.9 Following the unsuccessful bid to the Scottish Futures Trust, there is further
planning required in relation to a new build Thorn Primary School. 
2. Recommendations
2.1. It is recommended that members note the content of this report. 
3. Next Steps for Primary Provision in Dargavel
3.1. Under the Schools (Consultation) (Scotland) Act 2010 the Council has started
a formal consultation on a proposal to establish a new school. The
consultation is on a proposal with 3 key aspects – the building of a school with
capacity for 800 children; the location of the proposed school, and a review of
the catchments for the new and existing Dargavel primaries. It launched on 29
January 2024 and will run until 26 March. A copy of the proposal paper with
full details has been shared with all statutory consultees and all relevant
groups. A series of information sessions, public meetings and informal drop-
ins designed to give as many members of the community the opportunity to
find out more about the proposal and discuss their views on the proposal and
possible alternatives with officers leading the consultation have been taking
place during February and March. 
3.2. Geotechnical Site Investigations have concluded at the proposed site to the
north of Craigton Drive. We are currently awaiting the final report. 
3.3. Discussions with HubWest Scotland have indicated their ability to provide an
accelerated route to market. HubWest Scotland have begun engaging with
consultants in order to present the Council with a stage one submission which
will provide Hubs Value for Money assessment and an outline design.
3.4. Identification of the preferred procurement and delivery route will take account
of anticipated programme, implications with the BAE associated remediation
and infrastructure programme, appropriate engagement timelines with the
local community, as well as wider resourcing demands within the Council.

Page 3

Page 3 of 6 
3.5. The estimate for delivery of the new school is currently no later than August
2027. As work progresses we will be able to refine the programme and
delivery timescales. 
3.6. Space planning consultants Space Zero have concluded all exercises
associated with preparation of a Strategic Brief. Following extensive
engagement with various stakeholders including, council technical officers,
existing cluster schools, education colleagues and the wider community
Space Zero have produced an outline briefing document demonstrating that
an 800 person school can be delivered within the target GIFA of 5200m2 and
provide quality spaces that are flexible, inclusive and sustainable for use by
Education and the wider community. 
3.7. Following approval of the Strategic Brief property services will arrange
handover from Space Zero to the design team thereby allowing core design
and technical strategies to be developed in accordance with the master
programme.
___________________________________________________________________
4. Park Mains High School
4.1. In May 2023, the Education and Children Services Policy Board approved a
400 pupil extension to the capacity of Park Mains High School, and to cap that
school’s total capacity at the extended 2000 figure.
4.2. To create additional flexibility for the school a modular unit has been moved to
Park Mains High School and will be repurposed into five additonal
classrooms, which will be able to accommodate a further 165 pupils. We are
expecting this to be in place and operational for April 2024
4.3. The high-level cost estimate for an extended building to the school is circa
£30m. Discussions are ongoing regarding the obligation of BAE Systems who,
under the existing Section 75 agreement, have an obligation to contribute
towards the expansion cost.
4.4. A model has been developed for 2000 learners to create a theoretical space
model required to support a school of this size. This model was overlaid on
the existing school to ascertain the extent of the additional accommodation
that would be required on a subject by subject and support services basis.
4.5. A scenario planning and validation exercise is currently ongoing which will
determine the schedule of accommodation required to be built within the new
extension areas and any changes needed within the existing school building
to ensure that the school operates as well as effectively and efficiently as
possible. 
4.6. A liaison group for Park Mains High School continues to meet regularly with
the last meeting held on 30 January 2024. Members of the PMHS Parent
Council and all its associated primaries attend to receive updates on roll
projections, share information on the programme and gather feedback which
will help inform the design of the building.

Page 4

Page 4 of 6 
5. Thorn Primary School
5.1. The Council agreed under the previous SEMP programme to invest £10million
to deliver a new Thorn Primary School, with the intention for the balance of
the funding required to be funded through the Learning Estate Investment
Programme managed by the Scottish Futures Trust. Following the funding bid
to the Scottish Futures Trust being unsuccessful, the Council agreed on 29th
February to fully fund the new Thorn Primary School.   
5.2. Further updates will be provided as the project develops. 
6. Next Steps
6.1. Officers are currently preparing the 5 year Learning Estate Management Plan
that will set out the short to medium term priorities for the estate. It is our
intention that this will be presented to the ECSPB in August 2024.
6.2. The review of the learning estate that will inform the long term strategy is in
the early stages; we are currently collecting all necessary data to inform next
steps.
6.3. Given the complexity of the exercise, the development of the strategy will
require significant time and attention.
___________________________________________________________________
Implications of this report 
1.  Financial 
This report is for noting and as such there no implications which arise
directly from this report. 
2.  HR and Organisational Development 
None 
3. Community/Council Planning 
Our Renfrewshire is thriving -  The new learning environment will
support learning and achievement
for all.
Our Renfrewshire is well -  The new learning environment will
support the Health and Wellbeing of
all.
Our Renfrewshire is safe  -  The new learning environment will
provide safe and secure spaces for
all users.
Reshaping our place, our
economy and our future 
-  The new learning environment will
provided spaces which support local
enterprise.

Page 5

Page 5 of 6 
Building strong, safe and
resilient communities 
-  The new learning environment will
provide spaces to support
community activities. 
4.  Legal 
Renfrewshire Council adheres to all relevant legislation. 
5.  Property/Assets 
Through its school estate management plan the Council aims to have an
efficient and well maintained property portfolio which provides learning
environments which support the delivery of the curriculum. 
6.  Information Technology 
The new campus will have IT provision which supports digitally enabled
learning. 
7.  Equality and Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. There has been a
full Equalities and Human Rights Assessment carried out for the
consultation process to ensure it is fully inclusive. No negative impacts on
equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report.   If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.   
8. Health and Safety
None. 
9. Procurement 
Renfrewshire Council adheres to all procurement regulations. 
10. Risk 
A full risk register will be compiled for the project in accordance with the
Council’s established risk management protocols. 
11. Privacy Impact
None. 
12.  Cosla Policy Position 
None. 
13. Climate Risk
The project aims to comply with the requirements for ambitious energy
efficiency targets over the long term and to contribute to the Council’s net-zero
commitments. 
List of Background Papers 
Background Paper 1: Proposal to Consult on:
 establishment of a new primary school to be built at Dargavel Village and

Page 6

Page 6 of 6 
 a Catchment Review Affecting Dargavel Primary School and a new primary
school to be built at Dargavel Village 
The foregoing background papers will be retained within children’s services for
inspection by the public for the prescribed period of four years from the date of the
meeting.  
___________________________________________________________
Children’s Services
JC/GL
14 February 2024 
Author:   Gerry Lyons, Interim Head of Education gerry.lyons@renfrewshire.gov.uk