To:  Education and Children’s Services Policy Board
On: 2 November 2023
___________________________________________________________________ 
Report by:  Director of Children’s Services
___________________________________________________________________ 
Heading:  PGSCC Update 
___________________________________________________________________
1. Summary
1.1 Paisley Grammar School Community Campus is on track for completion in
Summer 2026.
1.2 The Council previously approved a new Paisley Grammar School and
Community Campus on Renfrew Road to replace the existing Paisley
Grammar School on Glasgow Road. 
1.3 The cost of the new school is estimated at £74.8million, which is part funded
through the Scottish Government’s Learning Estate Investment Programme.
There is a risk to this budget given the inflationary pressures being seen
across the construction sector. Other similar projects in receipt of government
funding which reach financial close before December this year will receive an
11% funding increase to the base funding provision. A decision on any
funding uplift for this project from the Scottish Government is expected in the
final quarter of this year. 
1.4 The school is estimated to be complete in the Summer of 2026. An earlier
programme had a completion date of December 2025, but this was
recognised by the Council and the Scottish Government as a risk, with the
result that the Summer date was subsequently agreed. 
1.5 There has been engagement with key stakeholders throughout the design
process, which is vital in informing the plans not only for how the school will
look but also how it will operate. 
1.6 Various key strategies like the access and facility management strategies are
currently being developed, with our pre-construction advisors and the design
team developing sub-contract work packages to build up the overall project
cost. Once that process is complete we will contract Morrison Construction as
the Principal Contractor ahead of construction beginning in March 2024.

Page 2

Page 2 of 7 
___________________________________________________________________
2. Recommendations
2.1 The Education and Children’s Services Policy Board are asked to note the
content of this report.
___________________________________________________________________
3. Background
3.1 In May 2019, the Education and Children Services Policy Board approved the
proposal to  build a Paisley Grammar School Community Campus on Renfrew
Road in Paisley, replacing the current Paisley Grammar School on Glasgow
Road.
3.2 The anticipated cost of delivering the project is £74.8m with a completion date
of Summer 2026 
3.3 A funding contribution, to support the school element of the project, was
secured through Phase 2 of the Scottish Government’s Learning Estate
Investment Programme (LEIP) in January 2021, with the community provision
funded from Council resources.  
3.4 The LEIP funding award is subject to compliance with funding criteria which
require that the building’s condition is maintained at category A/B for 25 years;
that the building must be energy efficient and digitally enabled; and that the
project must support economic growth. 
3.5 An internal project team is in place and a Multi-Disciplinary Design Team and
Principal Contractor (providing pre-construction services only at this stage)
have been appointed to support the design and delivery of the new campus.
3.6 Engaging with a wide range of stakeholders was central to the development of
the project’s strategic brief and feedback from pupils, staff and parents/carers;
the wider community; and partner organisations has informed the
development of an overarching project vision. 
3.7 Renfrewshire Council’s ambition for the young people of Paisley Grammar
School and its wider community is to provide a campus which enables new
learning in flexible, innovative spaces; a campus which is an exemplar for
sustainability in learning, design, and the future Renfrewshire Council learning
estate. The campus will create opportunities for, and connections with, the
wider community, and it will deliver an environment which is inclusive, safe
and engenders a culture of respect, building on the tradition and values of
Paisley Grammar School.
___________________________________________________________________
4. Governance
4.1 An outline business case has been developed and industry recognised
frameworks and methodologies have been employed to ensure a robust
governance structure is in place.

Page 3

Page 3 of 7 
4.2 This structure involves regular engagement with key stakeholders.. 
Governance arrangements are in place with Scottish Futures Trust (SFT);
Learning Estate Programme Board (Replacing PGSCC Governance Board);
PGSCC Project Team; and the MDDT and Principal Contractor. 
___________________________________________________________________
5. Review of Programme 
5.1 At an early point in project development, it was identified that the original
delivery date of December 2025 was extremely tight and that this created an
unacceptable risk to project quality, funding outcomes and staff and pupil
transition to the new building.  
5.2 A meeting with SFT was convened to discuss this challenge in November
2022 and it was accepted in principle that the delivery date should be
rescheduled to August 2026.
5.3 A report explaining the rationale and mitigation behind the reprogramming
was submitted to the Education and Children Services Policy Board in
January 2023.
5.4 In April 2023 the Scottish Government agreed the reprogramming of the
project and approved the revised completion date of August 2026.
___________________________________________________________________ 
6. Consultative Approach and Design Development
6.1 A wide variety of internal and external stakeholders are involved in continued
engagement with the design process, in addition to the core group of pupils
and parents/carers.  These stakeholders include:
School Facilities Community Facilities
• Paisley Grammar School
Community
• Facilities Management 
• Street Scene
• Passivhaus Delivery Forum 
• West College Scotland
• Energy Management Unit
• OneRen
• Social Work
• HSCP
• Adult and Youth Services
• Police Scotland
• AMIDS 
• Community Council 
6.2  Informed by these groups, the Project Team and MDDT is now developing
detailed plans to reflect requirements in respect of floor plan and room
layouts, adjacencies, FF&E requirements; toilet provision; ensuring we offer
flexibility and choice for pupils; lifecycle maintenance; digital and wider access
strategies; and external grounds materiality. 
6.3 A major planning application was submitted in May 2023 after fulfilling the
statutory pre-submission activities required for the development. This has
included two public consultations, briefings to elected members and
community councils and briefings to Paisley Grammar School staff and pupils
and the parent councils of Paisley Grammar School and its five feeder
Primary Schools.

Page 4

Page 4 of 7 
6.4 The submission of the planning application marked a major milestone for
public awareness of the project.  This allowed articulation of the full scale and
ambition of the PGSCC project for the first time. The application included
some architectural images showing the outside of the building and was
released to the council’s social media channels, billed as ‘the first public
reveal of how Paisley’s new super-school will look’. The content showcased
the quality of the work that has gone into the planning and design of the new
campus and expressed how our vision will be realised. 
6.5 The PGSCC Programme is adhering to the RIBA (Royal Institute of British
Architects) Plan of Work and is currently within its Stage 4 Technical Design
element of the framework, which is planned to complete within the first quarter
of 2024.  Stage 5 commences in the second quarter of 2024 which marks the
commencement of construction works.
___________________________________________________________________ 
7. Funding
7.1 At present the approved capital budget of £75M is at risk with running
forecasts in the range of circa £75M to £80M inclusive of Value Engineering
(VE) options instructed. At the PGSCC Governance Board in August, the
project team advised that if the contractor's original inflation cost were still to
be utilised then the overall upper cost range would extend to circa £83M (
£75M ‐ £83M overall range) due to cost volatility in the construction industry at
present. 
7.2 Furthermore, budget pressures for Schools construction are occurring on a
national scale which directly impacts PGSCC. Officers recommended to the
PGSCC Governance Board that budgetary issues be considered with
reference to a report issued by COSLA advising that selected SFT funded
projects (those that reach financial close by December 2023) would be
receiving an 11% uplift to the base m2 funding provision; at present PGSCC
has not been awarded such an uplift. SFT have confirmed that Renfrewshire
Council will receive a formal statement regarding any uplift after the Scottish
Government Board meeting in the final quarter of 2023. However, members
should be aware that in the absence of additional government funding the
Council may require to allocate increased capital resource to the project,
which may also increase ongoing revenue costs should any Council
contribution be funded through prudential borrowing. 
___________________________________________________________________ 
8. Next Steps
8.1  Development of a Wider Access Strategy for the new campus will involve a
variety of council services, community partners and West College Scotland.
This piece of work will evolve over the span of the project and will be finalised
in advance of occupation of the building in 2026.
8.2  Development of a Facilities Management Strategy for the new campus
involves a variety of council services within EH&I and includes a soft-landings
approach to ensure all decisions made during the project are based on
improving operational performance whilst meeting the SFT funding conditions.
Input at this stage of the project allows the FM teams to assist in the shaping
of and planning for the building they will receive to develop maintenance

Page 5

Page 5 of 7 
strategies ahead of time ie a soft landing of the asset into FM control.  The
strategy continues to progress and will be finalised in advance of the
building’s operational hand over. 
8.3  At this point, Morrison Construction has been appointed by Renfrewshire
Council to provide pre-construction advice to the design team on buildability,
commercial viability of emerging design concepts and to competitively tender
Sub-Contract work packages to build up the overall project cost.  Upon
successful completion of this process, Morrison Construction will be
contracted to act as Principal Contractor for the construction phase due to
begin March 2024.
8.4  The FF&E (Furniture, Fixtures, and Equipment) design and the interior
strategy has been under development for the past year. Engagement with the
school staff has been undertaken throughout this process. Utilising
appropriate FF&E we aim to create spaces that are dynamic, engaging, and
innovative and that cater to the evolving needs of both teachers, pupils, and
the wider community, ensuring a productive and inspiring learning experience
for all. 
8.5 The project has been split into 57 sub-contract work packages which is being
tendered through Morrison Construction’s supply chain.  Review of the design
information developed for these packages is underway to check for accuracy
of interpretation of the client’s brief and completeness of information to allow a
meaningful tendering exercise to be undertaken to achieve fixed prices for the
works. This exercise is due to complete in November 2023.
___________________________________________________________________ 
Implications of this report 
1.  Financial 
This report is for noting and as such there no implications which arise
directly from this report, however the risk to the current capital budget is
outlined. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  The additional learning environment
will support learning and
achievement for all. 
Our Renfrewshire is well -  The additional learning environment
will support the Health and
Wellbeing of all. 
Our Renfrewshire is safe  -  The additional learning environment
will provide safe and secure spaces
for all users.

Page 6

Page 6 of 7 
Reshaping our place, our
economy and our future 
-  The additional learning environment
will provide an opportunity in
supporting local population growth. 
Building strong, safe and
resilient communities 
-  The additional learning environment
will provide spaces to support
community activities. 
4.  Legal 
Renfrewshire Council adheres to all relevant legislation. 
5.  Property/Assets 
Through its school estate management plan the Council aims to have an
efficient and well-maintained property portfolio which provides learning
environments which support the delivery of the curriculum. 
6.  Information Technology 
The school expansion will have IT provision which supports digitally enabled
learning 
7.  Equality and Human Rights 
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.   
8. Health and Safety
None. 
9. Procurement 
Renfrewshire Council adheres to all procurement regulations. 
10. Risk 
A full risk register is currently active for the PGSCC project in accordance
with the Council’s established risk management protocols. 
11. Privacy Impact
None. 
12.  Cosla Policy Position 
None. 
13. Climate Risk 
The project aims to comply with the requirements for ambitious energy
efficiency targets over the long term and to comply with metrics set by funding
partners Scottish Futures Trust and contribute to the Council’s net-zero
commitments where possible.

Page 7

Page 7 of 7 
List of Background Papers 
(a) Background Paper 1:  SG response to PGSCC opening date- 18/04/2023 
(b) Background Paper 2:  Notice of Meeting and Agenda: Education and 
Children Services Policy Board - 19/01/2023 
The foregoing background papers will be retained within children’s services for
inspection by the public for the prescribed period of four years from the date of the
meeting.  
___________________________________________________________ 
Children’s Services
JC/RP
23/10/2023