Page 1

To: Education and Children’s Services Policy Board
On: 2 November 2023
Report by:  Director of Finance and Resources,
Interim Chief Education Officer and Chief Social Work Officer
Heading:  Revenue and Capital Budget Monitoring as at 15 September 2023 
1. Summary of Financial Position
1.1. The projected Revenue outturn at 31 March 2024 for Children’s Services is an
overspend of £2.478m (1.0%) against the revised budget for the year.
1.2. The projected Capital outturn at 31 March 2024 for Children’s Services is an
underspend of £0.143m (1.9%).
1.3. This is summarised over the relevant service in the table below and further
analysis is provided in the Appendices. 
Table 1: Revenue
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 245.458 247.936 (2.478) (1.0%) 
Table 2: Capital
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 7.438 7.295 0.143 2% 
2. Recommendations
Members are requested to:
2.1. Note the projected Revenue outturn position for Children’s Services detailed
in Table 1 above, and further note that the forecast position is based on best
estimates and confirmed government support at this point in time;

Page 2

2.2. Note the projected Capital outturn position for Children’s Services detailed in
Table 2 above; and
2.3. Note the budget adjustments detailed in sections 4 and 6. 
3. Children’s Services Revenue
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £2.478m (1.0% of total budget). Detailed service division
reports can be found in Appendix 2, along with an explanation of each
significant projected variance.
3.2. The main reasons for the projected outturn position are indicated below the
table showing the objective analysis (which division is spending the budget). 
3.3. A £2.637m overspend is anticipated within Children & Families related mainly
to external specialised residential accommodation placements. An additional
£2m was provided for in the 2023/24 budget, with an “expectation that up to a
further £3m may be required to be funded from ringfenced balances in
2023/24”. This position will be closely monitored as the year progresses.  
3.4. All external placements are held under continual review by the service to
ensure they continue to meet the needs of the individual children and young
people. Options to mitigate cost pressures continue to be examined.
3.5. Further overspends are anticipated in relation to contracted mainstream and
additional support needs transport costs. 
4. Revenue Budget Adjustments
4.1. Members are requested to note from Appendix 1 that budget adjustments
totalling £0.106m have been processed since the previous report. These
adjustments relate to drawdowns from reserves for various service areas of
£0.278m, offset by budget transfers to other services (£0.172m). 
5. Children’s Services Capital
5.1. The Capital Investment Programme 2023/24 to 2027/28 was approved by the
Council on 2 March 2023.
5.2.  The Capital Monitoring report at Appendix 3 indicates changes totalling
(£1.467m) in the approved capital programme for Education and Children’s
Services. This largely relates to budget carried forward from 2022/23 to
2023/24 and budget carried from 2024/25 into 2023/24. The (£1.467m)
comprises changes of (£1.567m) as reported at the previous Education and
Children’s Services Policy Board meeting on 24 August 2023, and a further
£0.100m as described at section 6 below.
5.3. The projected Capital outturn at 31 March 2024 for Children’s Services is an
underspend of £0.143m (1.9%). Further detail, including reasons for
significant variances, can be found at Appendix 3.

Page 3

6. Capital Budget Adjustments
6.1. Since the last report there have been budget changes of £0.100m. This
relates to the inclusion of the Inspiring School Age Childcare Spaces
Programme.
___________________________________________________________________ 
Implications of this report 
1.  Financial 
The projected budget outturn position for Children’s Services’ Revenue
budget is an overspend of £2.478m. Income and expenditure will continue
to be monitored closely for the rest of the financial year and steps will be
taken to mitigate any overspend, including applying flexibility within specific
grant funding as permitted by the Scottish Government, and potential use
of earmarked reserves. 
The projected outturn position for Children’s Services’ Capital budget is an
underspend of £0.143m. The Capital programme will continue to be
monitored closely for the rest of the financial year. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
None directly arising from this report. 
4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
None directly arising from this report. 
6.  Information Technology 
None directly arising from this report. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health and Safety
None directly arising from this report.

Page 4

9. Procurement 
None directly arising from this report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
None directly arising from this report. 
12. 
13.
CoSLA Policy Position 
n/a 
Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers: None
__________________________________________________________________ 
Authors:   Richard Conway, Finance Business Partner
Geoff Borland, Finance Manager

Page 5

Appendix 1 
Subjective Summary
Annual Budget
at Period 3
Budget
Adjustments
Revised Annual
Budget at
Period 6
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 171,204 3,435 174,639 172,009 2,630 1.5% 1,833 797
Premises Related 8,984 (87) 8,897 9,375 (478) (5.4%) (480) 2
Transport Related 4,592 (2) 4,590 6,249 (1,659) (36.1%) (1,485) (174)
Supplies and Services 32,358 (476) 31,882 31,448 434 1.4% 287 147
Third Party Payments 15,198 0 15,198 19,210 (4,012) (26.4%) (2,952) (1,060)
Transfer Payments 14,419 1,148 15,567 15,967 (400) (2.6%) (321) (79)
Support Services 64 0 64 53 11 17.4% (48) 59
GROSS EXPENDITURE 246,819 4,018 250,837 254,311 (3,474) (1.4%) (3,166) (308)
Income (1,467) (3,912) (5,379) (6,376) 997 18.5% 543 454
NET EXPENDITURE 245,352 106 245,458 247,936 (2,478) (1.0%) (2,623) 145
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 15 September 2023

Page 6

Appendix 2 
Objective Summary
Annual Budget
at Period 3
Budget
Adjustments
Revised Annual
Budget at
Period 6
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Directorate 480 0 480 381 99 20.7% 68 31
Early learning and childcare 34,508 39 34,547 33,202 1,345 3.9% 1,273 72
Primary 63,584 201 63,785 63,768 17 0.0% 64 (47)
Secondary 86,078 702 86,780 87,326 (546) (0.6%) (680) 134
ASN (Special) Schools 7,049 (33) 7,016 6,967 49 0.7% 46 3
Additional support for learning (ASL) 16,461 (207) 16,254 17,004 (750) (4.6%) (700) (50)
Psychological services 836 0 836 896 (60) (7.2%) (50) (10)
Education development 1,726 528 2,254 2,254 0 0.0% 0 0
Attainment Challenge 0 (1,182) (1,182) (1,182) 0 0.0% 1 (0)
Facilities management 624 (4) 620 614 6 0.9% 7 (1)
Children & Families 34,006 62 34,068 36,705 (2,637) (7.7%) (2,651) 14
NET EXPENDITURE 245,352 106 245,458 247,936 (2,478) (1.0%) (2,622) 145
Objective Heading
Early Learning and Childcare
Secondary Schools
Additional Support for Learning
Children & Families
An overspend in Third Party Payments is projected, mainly in relation to external residential accommodation placements, where
the number of complex, expensive packages has increased significantly. All external placements are held under continual review
by the service, with options to mitigate cost pressure being examined on an ongoing basis. The Third Party Payments projection
also includes (pending agreement and Board approval) additional estimated costs, net of associated grant income, resulting
from the introduction by the Scottish Government of a national recommended maintenance allowance for foster carers and
kinship carers.
An underspend in Employee Costs is projected due to vacancies within the authority’s Early Learning & Childcare Centres. This
underspend is offset by a projected overspend in Transfer Payments in relation to an increase in the rate paid to funded
providers (private and voluntary sector nurseries and childminders).
Overspends in Premises Costs and Transport Costs are projected. The overspend in Premises Costs is due to an expected
increase in refuse collection and janitorial supplies costs. The overspend in Transport is due to an increase in the cost of the
mainstream school transport contract. These overspends are partly offset by a projected underspend within Employee Costs
mainly in relation to teachers’ salary costs. These will be kept under review during the year.
An overspend in Transport Costs is projected. This is due to increases in the cost of transport contracts for pupils with additional
support needs.
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 15 September 2023
Budget Variance
(Adverse) or Favourable
Key Reasons for Projected Variance
POLICY BOARD :  EDUCATION & CHILDREN'S SERVICES

Page 7

Appendix 3 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2023 2023-24 in 2023-24 2023-24 2023-24 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
EDUCATION & CHILDREN SERVICES
Primary Schools Estate Programme(SEMP) 42,695 0 203 203 60 143 70% 42,898 42,755 143 0%
Paisley Grammar New Campus 4,819 5,000 (2,710) 2,290 2,290 0 0% 75,100 75,100 0 0%
Thorn PS New Build 13 1,000 (13) 987 987 0 0% 10,000 10,000 0 0%
Dargavel Extension (Modular Units) 0 2,000 0 2,000 2,000 0 0% 2,000 2,000 0 0%
Other Schools Investment Programmes 24,188 505 1,027 1,532 1,532 0 0% 25,720 25,720 0 0%
Inspiring School Age Childcare Spaces Programme 0 0 100 100 100 0 0% 100 100 0 0%
Technology Replacement Strategy ICT 0 400 (74) 326 326 0 0% 1,926 1,926 0 0%
PPP Lifecycle 0 0 0 0 0 0% 0 0 0%
TOTAL EDUCATION & CHILDREN'S SERVICES BOARD 71,715 8,905 (1,467) 7,438 7,295 143 2% 157,744 157,601 143 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
Objective Heading
Primary Schools Estate Programme(SEMP)
Paisley Grammar New Campus
Primary Schools Estate Programme(SEMP 2020)
Other Schools Investment Programmes
Technology Replacement Strategy ICT
RENFREWSHIRE COUNCIL
1st April to 15th September 2023
POLICY BOARD: EDUCATION & CHILDEN'S SERVICES
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
Key Reasons for Projected Variance
Minor underspends relate to St Fergus new build and St Anthony refurbishment.
Budget Variance (Adverse) or
Favourable
Current Year 2023-24
Budget Variance (Adverse) or
Favourable
Full Programme - All years