Page 1

1  
 
 
___________________________________________________________________
To: Education and Children’s Services Policy Board 
On: 18 May 2023
___________________________________________________________________
Report by: Director of Children’s Services
___________________________________________________________________
Heading: Children’s Services Service Improvement Plan 2022/23 Outturn
Report
___________________________________________________________________
1. Summary
1.1. The purpose of this report is to provide an update on performance of Children’s
Services for the twelve-month period covering 1 April 2022 to 31 March 2023
in relation to the Service Improvement Plan approved by this Board in May
2022.
1.2. The plan aligns with the new Council Plan and Community Plan, and provides
the strategic direction for the service. The service is an active partner in
developing and delivering the outcomes contained within both the
Renfrewshire Children’s Services Partnership Plan and the Renfrewshire
Community Justice Outcomes Improvement Plan.
1.3. The action plan (attached at Appendix A) is at the core of the Service
Improvement Plan. It sets out the priorities being addressed, the key tasks to
be implemented, the implementation timetable and the measures of success.
The service scorecard sets out a range of key indicators against which
performance of the service is measured. This report provides a summary of
performance for both the action plan and the service performance indicators,
which are included as appendices to this report.
1.4. Children’s Services has delivered on its priorities over the last twelve months
and service updates and key achievements are highlighted in Section 4 of this
report.

Page 2

2  
 
 
__________________________________________________________________
2. Recommendations
2.1. It is recommended that the Education and Children’s Services Policy Board
note: 
a) the contents of this report; and
b) the achievements of Children’s Services during 2022/23.
___________________________________________________________________  
3. Background
3.1. Children’s Services is responsible for the delivery of social work services to
children and families, justice social work services, and early years, primary
and secondary education. Much of what the service does is statutory; that is,
there is a legal requirement for the Council to deliver. Service delivery is a mix
of universal provision (such as education), targeted provision (such as
children’s houses for accommodated children and young people) and
specialist support (for example, justice social work court services). 
3.2. Our approach is strongly focused on prevention, early intervention and
providing additional support for the most vulnerable. Whilst children’s health
services sit within Renfrewshire’s Health and Social Care Partnership (HSCP),
a key priority of both organisations will be the continuation of effective
integrated working to improve outcomes for children and young people.
3.3. The Service Improvement Plan is a comprehensive statement of the outcomes
the service aims to achieve, and the actions it will take to achieve these. It fits
within the wider planning framework of the Council by taking account of
Community Planning themes and Council priorities. It enables elected
members to have oversight of developments within the service and to consider
and develop policy options which reflect customer need and resource
availability.
3.4. Appendix A details the specific actions the service has achieved and will
continue to progress, to support the Council’s priorities and help deliver
improved outcomes for Renfrewshire children, young people, and families.
___________________________________________________________________
4. Service Update and Key Achievements 
4.1. Opportunities to incorporate The Promise in service planning and delivery is
being facilitated though the active and growing Promise Keeper network.
There are currently 118 Promise Keepers in place across the local authority,
HSCP, and partner agencies. The network ensures cognisance is given to the
needs and voices of those with care experience. This work is complemented
by the development of a Promise Self-Evaluation Tool which, once completed,

Page 3

3  
 
 
will enable services to review progress in #KeepingThePromise in key areas
such as training and development, trauma-informed practice, and risk
management. Evaluation has been completed for education and further
activity around evaluation is taking place with other council areas and with
partners. A Renfrewshire Language Policy, to ensure words and phrases used
to describe care experience are positive and do not further exacerbate stigma,
has been developed and is being disseminated for use across the local
authority. A mapping and action plan tool has also been developed to support
planning and to enable us to map Renfrewshire’s Promise journey and
progress. 
4.2. Progress continues to be made to develop Renfrewshire’s approach to early
and effective whole family support measures. The aim of the whole family
wellbeing approach is to provide appropriate family supports, focussing on
early intervention, and providing opportunities for children, young people,
parents, and carers to shape the services that impact them. Local insight has
presented a strong case that children and young people’s needs are best
understood and met within the context of their families. Through the Scottish
Government’s Whole Family Wellbeing Fund, Children’s Services is engaging
with partners to develop collaborative proposals to address the needs of
Renfrewshire’s families in a way that is non-stigmatising, community-based,
and underpinned by children’s rights. There is recognition of the benefit to
have services linked and access to support being in one place. Positive
learning from the successful implementation of the REN10 mental health and
wellbeing family support service is also being applied to the whole family
wellbeing approach.
4.3. In collaboration with health partners, the West Partnership, and the voluntary
sector we continue to develop consistent, effective and preventative
approaches to support recovery, and improve the mental, social, and
emotional wellbeing of children and young people. A comprehensive
programme for professional learning is in place, covering a wide range of
health and wellbeing topics delivered at local authority level and across the
West Partnership. An example of work undertaken includes the new online
interactive Alcohol and Substance Education Awareness programme which is
being implemented across all our early years establishments and schools.
Renfrewshire’s children and young people have been at the heart of this
development work, as have those with lived experience. 
4.4. Ukrainian pupils have been welcomed by our schools, and pupils were
supplied with resources such as uniforms, and materials to support their
inclusion. The resettlement has been supported by the Families First and
Active Schools teams, and the children and young people have been able to
access supports for wellbeing such as counselling. An opportunity has been

Page 4

4  
 
 
provided for people from Ukraine to join the Council as trainees for a six-month
period, to assist the Council to support Ukrainian refugees. Two people are
participating in programmes located within schools to help Ukrainian children
settle in their new school environment and to assist pupils and staff with
barriers to learning such as language.
4.5. The 2022 exam diet saw a return to the traditional model of assessment. Due
to the COVID-19 pandemic, alternative methods of assessment were put in
place for the 2020 and 2021 exam diet. As such, we should be cautious of
making direct comparisons of 2022 results with previous years which had a
different assessment approach. In 2022, young people across Renfrewshire
have performed exceptionally well and this reflects the considerable effort on
the part of young people, their families, and their school community. 
4.6. Work that is in partnership with Skills Development Scotland, West College
Scotland, Invest in Renfrewshire, and Developing the Young Workforce West
continues to progress to ensure planned, robust approaches are in place to
support the most vulnerable learners into positive destinations. The work
placement programme continues to provide excellent opportunities with
approximately 400 new employers this year who are offering a range of
opportunities such as site visits, training, and long-term work placements for
young people in the senior phase. 
4.7. Following the Council’s declaration of a climate emergency in June 2019, the
delivery of improvements to the school estate to offer a high degree of
environment sustainability and energy efficiency will make a critical
contribution towards Renfrewshire being carbon neutral by 2030.
Considerable progress has been made with the LED lighting programme
largely complete in the Public-Private Partnership (PPP) estate. 
4.8. Work has been successfully undertaken to progress the increased use of
digital technology within learning and teaching to ensure children and young
people have the appropriate digital skills required by employers and that staff
are equipped to keep up-to-date with the pace of change. There have been
29 professional learning sessions with over 300 staff. 
4.9. The recommendations of the Additional Support Needs (ASN) review continue
to be implemented to support children and young people to remain in
mainstream education with their peers. There has been a Getting it Right for
Every Child (GIRFEC) policy refresh, and a full suite of training is underway
to support staff and partners with further training being added due to demand.
The training programme for ASN assistants and classroom assistants has
been successfully embedded and the Education pilot involvement in Initial
Referral Discussions (IRDs) has been successful and is being rolled out
across all localities. An IRD is the start of the formal process of information

Page 5

5  
 
 
sharing, assessment, analysis, and decision-making following reported
concern about abuse or neglect of a child or young person up to the age of 18
years, in relation to familial and non-familial concerns, and of siblings or other
children within the same context. This includes unborn babies who may be
exposed to current or future risk. Prior to the pilot, it was only practitioners in
police, social work and health who participated in IRDs within Renfrewshire
Council. During the introduction of the new Child Protection Guidance for
Scotland 2021 there was an audit carried out of IRDs, which highlighted that
there was often no professional at the IRD who knew the child best. It was
therefore agreed at the Renfrewshire Child Protection Committee (RCPC) that
an Education or Early Learning and Childcare (ELC) representative should be
invited to attend as they have an essential contribution to make. Including
education in IRDs allow education professionals to give a view on the needs
of the child, their assessment on whether a child can be interviewed and any
additional needs they may have. 
4.10. An interim Quality Improvement Framework for Children’s Services social
work was introduced in November 2022. The Quality Improvement Framework
will be evaluated and further developed to support the re-design of children
and justice social work over the next 12 months. 
4.11. Commitment to providing sustainable support and learning opportunities to the
Gaelic community in Renfrewshire has continued. The provision of Gaelic
Medium Primary Education (GMPE) has been established and is located at
West Primary School. 
4.12. During 2022/23, our inspected schools all received positive reports from
Education Scotland. The schools inspected were Auchenlodment Primary
School and Early Learning and Childcare Class, Barsail Primary School,
Cochrane Castle Primary School, Park Mains High School, and St Benedict’s
High School. Children’s Services both celebrate the key strengths identified at
inspection, and recognise the areas for further improvement, providing support
to the schools in their improvement journey. 
4.13. Three of our four children’s houses were inspected by the Care Inspectorate
in 2022/23. Arkleston and Brediland received positive inspections, whilst
Barochan’s inspection highlighted areas for improvement. The inspectors
found that staff in Arkleston have an excellent understanding of trauma-
informed practice and young people are supported to access mental health
services appropriately. The Barochan report highlighted a need for
improvement in the management of the house and staff training. Work has
commenced to address the areas for improvement required by the Care
Inspectorate for Barochan.

Page 6

6  
 
 
4.14. Throughout 2022/23, Children’s Services developed a portfolio management
approach to service improvement planning, to support with balancing new
priorities, core business and moving beyond recovery. The intended impact is
to strengthen our service planning processes, enabling children and young
people to thrive, learn and achieve. The approach will support prioritisation,
integration and joint-planning, reducing duplication and over-reporting. Each
portfolio was developed with a plan to deliver on our agreed service priorities
and align with the remit of our Heads of Service: Curriculum, Learning,
Teaching & Assessment; Inclusion; and Families & Communities.
___________________________________________________________________
5. Actions that have been delayed or cancelled
5.1. Two actions, listed below, have not been progressed owing to a delay in
receiving policy guidance and funding from the Scottish Government. This
was reported to Board in Autumn 2022, but as there has still not been any
further progress, these actions will be discontinued from the Service
Improvement Plan until such time as the Government guidance has been
received:
 CHS.SIP.22.02.07: Plan for the expansion of early learning and
childcare for one-year olds; and
 CHS.SIP.22.02.08: Support with the development of a rights based,
dynamic out of school care offer.
5.2. The action in relation to progressing the work in the priority schools identified
in the School Estate Management Plan has now been separated into two
actions, as requested by Board in Autumn 2022. The new actions are as
coded follows to reflect individual schools:
 CHS.SIP.22.01.01a: Paisley Grammar School Community Campus;
and
 CHS.SIP.22.01.01b:  Thorn Primary School.
___________________________________________________________________
6. Progress against Performance Measures
6.1. Appendices B and C outline the 34 Children’s Service’s performance
indicators which fall under the remit of this policy board. Of these, 14 are
collected quarterly over a fiscal year (1 April to 31 March) and 20 are annual
indicators measured over an academic year (1 August to 31 July). 
6.2. The 2021/22 Achievement of a Curriculum for Excellence Level (ACEL) data
demonstrates that there has been an increase in attainment across all
curricular areas when looking at P1, P4, and P7 combined. This follows the
2020/21 data which saw decreases across all curricular areas because of
pandemic-related disruption. This trend is visible within Renfrewshire and

Page 7

7  
 
 
nationally, although attainment in Renfrewshire remains in line with or above
the national figures across all stages and curricular areas. 
6.3. The number of young people entering a positive destination after leaving
school has continued to show strong performance with 97% of 2022 school
leavers entering a positive destination, exceeding the target of 95%. 
6.4. The service has continued to exceed its target for ensuring looked after
children are cared for in a community setting, with 90% of children cared for
in this way. Although this number represents a small drop in comparison to
the same quarter last year, where the figure was 92%, this can be accounted
for by the needs of a small number of young people who require to be placed
in other settings better aligned to their current needs.
6.5. A high percentage of new unpaid work orders continue to be completed by the
required date. In Q4, 96% of orders were completed on time against a target
of 75%. Performance has been sustained despite increases in the number of
orders stemming from further court activity, highlighting the service’s efforts to
focus resource on priority areas.
6.6. A number of justice-related indicators were reported as below target in the
Mid-Year Monitoring Report. This was due in part to the ongoing changes in
court activity which had disrupted justice service processes, resulting in
challenging tight timescales for initial activity on orders. Justice activity also
continued to be negatively impacted by accommodation issues. These issues
are being addressed on an ongoing basis and the service continues to show
improved performance. 
6.7. The percentage of Stage 1 complaints responded to within timescales agreed
with customers has shown significant improvement since Q4 of 2021/22 where
only 75% of complaints were responded to within timescale. The Q4 2022/23
figure shows 97% of Stage 1 complaints were responded to within timescale.
This highlights the efforts of the service to improve performance in this area. 
6.8. The percentage of Stage 2 complaints responded to within timescales agreed
with customers has also shown some improvement compared to Q4 of
2021/22 where only 60% of complaints were responded to within timescale.
The Q4 2022/23 figure shows 67% of complaints were responded to within
timescale. This remains below the target of 95% and the service will continue
efforts to improve on this area of performance.
6.9. In all cases, the service will always focus on responding to complaints
comprehensively. On occasion this may require staff to liaise closely with the
complainant to fully understand the scope of the issue and thereafter identify
all pertinent information. Complainants are always kept fully informed of

Page 8

8  
 
 
timescales and anything that might impact them, for example managing
responses that will be impacted by school holidays.
___________________________________________________________________
7. Areas requiring improvement and/or review
7.1. The percentage of new unpaid work clients subject to a supervision order seen
by a supervising officer within one week is highlighted as an area for
improvement, with performance being 76% in Q4 against a target of 85%. All
those where the service recommends a supervision order are issued with an
appointment in advance of the court date. Delivering on this target is
dependent on the compliance of those made the subject of the supervision
order. The service is reviewing how the need for compliance is communicated
to the individuals. 
7.2. The average complementary tariff score for Renfrewshire pupils in senior
phase stages has remained higher than the national average; despite
decreasing at every stage since 2021. This can be attributed to the changing
models of assessment which has influenced overall attainment at each
stage.  There has been a decrease in the average complementary tariff for S4
pupils in the 30% most deprived and 70% least deprived cohorts, which has
resulted in an increase in the attainment gap between most- and least-
deprived pupils at this stage. In S5, the average complementary tariff score
has decreased slightly for the 30% most deprived and marginally increased
for the 70% least deprived groups in 2022, which has also resulted in the size
of the attainment gap growing slightly amongst S5 pupils. In S6, the average
complementary tariff for pupils living in the 30% most deprived has increased
since 2021 while performance in the 70% least deprived group has decreased.
As such, the tariff point gap has closed to the smallest it has been in the last
five sessions.
7.3. The percentage of care leavers who have had a period of homelessness in
the six months prior to 31 March 2023 was 4%, representing 7 individuals. We
measure performance against an ambitious target that no care leaver
experiences a period of homelessness, and this continues to be an area
requiring improvement to meet that target.
___________________________________________________________________
8. Monitoring progress 
8.1 We will apply our robust approach to quality improvement across our portfolios
to ensure our practice and provision is driven by the experience of our service
users.  Established processes are in place to ensure our service priorities are
underpinned by appropriate and accessible policy guidance, practice
standards and training/development opportunities.  Data and insight aligned

Page 9

9  
 
 
to our outcomes will undergo thorough analysis and evaluation, with outputs
shaping how we adapt, respond and best effect improvement over time. 
8.2 Progress on the implementation of the Service Improvement Plan is monitored
by the Extended Senior Leadership Team every quarter and will be reported
to the Education and Children’s Services Policy Board on a six-monthly basis. 
___________________________________________________________________
Implications of the Report
1. Financial - The Service Improvement Plan highlights resourcing pressures
arising from increasing demand for services and the current financial
environment.
2. HR & Organisational Development – None.
3. Community/Council Planning – The report details a range of activities which
reflect local council and community planning themes.
4. Legal - None.
5. Property/Assets – None.
6. Information Technology - Service developments relating to information
technology are key enablers of service improvement and modernisation and
support service-level and corporate objectives.
7. Equality & Human Rights - The recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights.
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. If required following implementation,
the actual impact of the recommendations and the mitigating actions will be
reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8. Health & Safety – None.
9. Procurement – None.
10. Risk – Risks related to the delivery and management of services are regularly
monitored and included in Renfrewshire Council’s Corporate and Strategic
Risk Registers. 
11. Privacy Impact – None.
12. COSLA Policy Position – None.
13. Climate change – Actions and performance indicators aligned to Strategic
Priority 4: Green, of Renfrewshire’s Council Plan, highlights activities across
the Council to tackle climate change.

Page 10

10  
 
 
__________________________________________________________________
List of Background Papers: (a) Service Improvement Plan 2022 - 2025
___________________________________________________________________
Authors:      Alasdair Mann and Jacqui Small, Planning & Policy Development
Officers 
Contact:      Linda Butler, Service Planning & Policy Development Manager
Linda.butler@renfrewshire.gov.uk  
___________________________________________________________________

Page 11

1
Children's Services SIP 2022-25 Action Plan 
Action Status 
Cancelled 
Overdue 
Check Progress 
In Progress 
Completed 
Strategic Priority 1: Place 
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.01.01
Progress development work
in relation to the priority
schools identified in the
School Estate Management
Plan - Paisley Grammar
School Community Campus
Pupils and staff enjoy a
modern, fit for purpose,
school estate which supports
learning and achievement. 
31-Aug-2026 
Progress continues to be made in
design development for the new
Paisley Grammar School Community
Campus, which is scheduled to open in
the summer of 2026 for 1,350 pupils.
The project remains on programme
with Royal Institute of British
Architects (RIBA) Stage 2 completed in
February 2023 and Stage 3 is on track
to conclude in May 2023. Regular
governance reviews continue to be
undertaken and status evaluation
updates to Scottish Futures Trust are
submitted on a quarterly basis. As part
of the planning application process,
Education Manager
(Resources)

Page 12

2
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
the project’s design team hosts two
public consultation events to capture
feedback on design development at
this stage. The first session took place
in March 2023, with the planning
submission scheduled for May 2023. 
CHS.SIP.22.01.01
Progress development work
in relation to the priority
schools identified in the
School Estate Management
Plan - Thorn Primary School
Pupils and staff enjoy a
modern, fit for purpose,
school estate which supports
learning and achievement. 
31-Mar-2026 
The decision on Learning Estate
Investment Programme Phase 3
Funding was deferred by Scottish
Government in December 2022. No
update on this position has been
received at this time. 
Education Manager
(Resources) 
CHS.SIP.22.01.02
Progress plans for the roll
out of full Wi-Fi across the
school estate, understanding
the benefits that can be
baselined and measured
Funding in place and
programme developed and
underway. 
31-Dec-2023 
This is part of a corporate roll-out of
new Wi-Fi which includes schools. Wi-
Fi will be installed on a programme
over the next 16 months, and it is
hoped that all schools will be
complete before the end of the
calendar year. Funding has been
agreed and next steps being identified.
Surveys will be completed by the end
of the school term in June 2023. 
Digital Learning
Manager 
CHS.SIP.22.02.13
Progress office
accommodation solutions to
facilitate an improved
contact for all service users,
including groupwork
provision.
A range of interventions
support individuals to
address the reasons for
offending and promote
desistance.
31-Mar-2023 
Current staff and services have
returned full time to all office
buildings which meets current need.
Groupwork has increased numbers in
line with respectable distance, with
ventilation solutions progressed.
Justice Social Work
Services Manager

Page 13

3
Strategic Priority 2: Economy 
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.02.01
Working in partnership with
Skills Development Scotland,
West College Scotland, Invest
in Renfrewshire and
Developing the Young
Workforce West, we will
ensure planned robust
approaches to supporting
our most vulnerable learners
into positive destinations
This will provide a
coordinated approach to
ensuring that all young
people, particularly the most
vulnerable, are given the best
opportunities and supports
to move into positive future
pathways. 
31-Mar-2025 
The Economic Recovery Group
continues to meet regularly with a
robust focus on supporting vulnerable
learners into positive destinations. All
secondary schools and our 2 schools
for pupils with additional support
needs (ASN) have a Developing the
Young Workforce (DYW) coordinator.
The key priority of these staff is to
ensure all young people, particularly
the most vulnerable, are provided with
opportunities to support them into
positive destinations post school
including bespoke work placements
and alternative pathways as
appropriate. Monthly meetings take
place to review the progress of these
young people and to ensure that the
right supports are in place for them. 
The work placement programme
continues to provide excellent
opportunities for our young people.
We have approximately 400 new
employers this year who are offering a
range of opportunities such as site
visits, training, and long-term work
placements for young people in the
senior phase. The 'My Future
Pathways' programme is running
successfully again this session with
almost 40 young people having
embarked on the construction course
Education Manager
(Senior Phase)

Page 14

4
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
from August 2022; 8 of these young
people have now been offered places
on the West College Scotland (WCS)
pre-apprentice construction course
(new this session). 
Strategic Priority 3: Fair 
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.02.02
Develop and extend
bespoke pathways and
programmes on literacy and
numeracy to support all
establishments through a
differentiated approach
Attainment data will
demonstrate improvements
in literacy and numeracy
attainment. 
30-Jun-2023 
Across literacy and numeracy, schools
continue to be supported with aspects
of learning and teaching including
evidence-based pedagogy and
assessment. A range of evaluations
and case studies are currently being
compiled to evaluate the effectiveness
and impact of specific interventions. 
Education Manager
(Curriculum) 
CHS.SIP.22.02.03
Strengthen learning,
teaching, and assessment in
all schools, supported by
high quality professional
learning.
Learners’ experiences are
enriched with the use of new
and innovative approaches to
learning and teaching and are
equipped with the skills to
support them in their
learning in a digital works 
30-Jun-2023 
The first Renfrewshire Learning
Festival took place in February 2023
with over 800 staff attending.
Feedback from staff found that 72%
said they would share what they
learned with colleagues, whilst 89%
would implement the learning in
practice. As part of the work being
undertaken to develop the learning,
teaching, and assessment strategy,
focus groups of learners have been
sharing what learner experiences
should look, sound, and feel like in our
schools. A sketch note is being
designed based on this.
Digital Learning
Manager

Page 15

5
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.02.04
Implement the
recommendations of the
ASN review
Children and young people
are supported to remain in
mainstream education with
their peers 
30-Jun-2023 
Locality development is ongoing
Training following the refresh of the
Getting It Right for Every Child
(GIRFEC) policy is underway with
further training being added due to
demand.  Parent workshops will be set
up this term to share the consistent
approach that has been developed. 
The training programme for additional
support needs assistants and
classroom assistants has started and
has been successfully evaluated.   The
Education pilot for involvement in
Initial Referral Discussions (IRDs) has
been successful and is being rolled out
across all localities. 
Education Manager
(ASN) 
CHS.SIP.22.02.05
In collaboration with Health
partners, the West
Partnership, and the
voluntary sector, continue
to develop consistent,
effective & preventative
approaches to support
recovery and improve the
mental, social, and
emotional wellbeing of
children, young people
Through delivery of high-
quality professional learning,
almost all practitioners have
an enhanced knowledge and
understanding of
programmes, resources, and
strategies available to
support their own wellbeing
and that of children and
young people (CYP). All
practitioners have the skills
to effectively support CYP.
Almost all practitioners
across all sectors use
evidence-based programmes
and preventative approaches
in the learning and teaching
30-Jun-2023 
During Children’s Mental Health week
in February 2023, a series of twilight
sessions was offered each day on
issues that affect mental health e.g.,
understanding sleep, self-harm, and
gender-based violence. All year 1 and
2 PATHs early years and primary
schools are being effectively
supported to deliver effective
emotional literacy through coaching
from Barnardo's. Counselling services
are in place to support all CYP from P1
- S6 and parents where appropriate. In
the period July 22 – Dec 22, 858 CYP
were effectively supported through
counselling. Our new online
interactive Alcohol and Substance
Education Manager
(Quality
Improvement and
Health & Wellbeing)

Page 16

6
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
of mental, emotional, and
social wellbeing. All CYP
requiring specialist health
and wellbeing (HWB)
services. All CYP are
supported to have positive,
healthy, and mutually
respectful relationships. 
Education Awareness programme is
being implemented across all our
early years’ establishments and
schools. Work is underway to evaluate
the early impact of this new resource.
The Mentors in Violence Prevention
(MVP) peer mentoring programme is
providing young people across
Renfrewshire secondary schools with
the skills to challenge attitudes to
gender-based violence. We are
currently working with partners from
Youth Services and OneRen to see how
we can use MVP to support the
primary sector in a universal and
targeted way utilising staff and trainer
expertise. Most secondary schools are
now supported by MVP trained staff
from Youth Services who are funded
by the Scottish Government’s
Delivering Equally Safe Fund. This area
of work is currently focusing on the
development of a campaign designed
by pupils. The Mental Health
Foundation Peer Education
Programme in conjunction with MVP
training was originally piloted in
Paisley Grammar School for Education
Scotland. Training has also taken
place in St Benedict’s High School.
Further roll out will take place across
most of our MVP schools in the new
session.

Page 17

7
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.02.06
Ensure Renfrewshire is a
"child friendly" place where
children's rights are at the
centre of policy decision
making.
All children in Renfrewshire
rights should be protected
and promoted in all areas of
their life
30-Jun-2023 
Multi-agency training to support the
GIRFEC refresh is ongoing.  The new
GIRFEC policy has Rights of the Child
firmly embedded within it and all
partners are ensuring that assessment
of needs are based on rights and
strength-based approaches.  All
partners including partners from third
sector organisations have been
involved in the refreshed training.
There has also been a successful link
up initiative which gave all agencies
an opportunity to share experiences
and successes with the
implementation of GIRFEC. From April
to June there will be parent
workshops and an offer to local
members to join a GIRFEC workshop.  
All future policies that have been
developed reflect fully the Rights of
the Child (UNCRC).  Schools continue
to take forward the Rights Respecting
School programme along with our
Renfrewshire’s Nurturing Relationship
Approaches.  Both of these
programmes enable schools to ensure
children’s rights are centre to school
life.   Also, across Renfrewshire
schools, we are working hard to
ensure that the development of
Personal and Social Education
resources and lessons are led by pupil
voice.  Our new Alcohol and Drug
Awareness Education resource is a
Head of Education
(Inclusion and Quality
Improvement)

Page 18

8
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
very good example; as children and
young people from eight schools,
across the authority, tested out our
new resource, advised on changes and
were the voices presenting the final
lessons. 
CHS.SIP.22.02.07
Plan for the expansion of
early learning and childcare
for one-year olds
Improved outcomes for
targeted children. The
attainment gap is reduced.
Increased family resilience
through improved health and
wellbeing of children and
parents. Parents are
supported into work, study,
or training 
30-Jun-2023 
Owing to a delay in receiving policy
guidance and funding from the
Scottish Government, there has still
not been any further progress with this
action. Therefore, this action will be
discontinued from the Service
Improvement Plan until such time as
the Government guidance has been
received.
Education Manager
(Early Years) 
CHS.SIP.22.02.08
Support with the
development of a rights
based, dynamic out of
school care offer
Improved outcomes for
targeted children. The
attainment gap is reduced.
Increased family resilience
through improved health and
wellbeing of children and
parents. Parents are
supported into work, study,
or training
30-Jun-2023 
Owing to a delay in receiving policy
guidance and funding from the
Scottish Government, there has still
not been any further progress with this
action. Therefore, this action will be
discontinued from the Service
Improvement Plan until such time as
the Government guidance has been
received.
Education Manager
(Early Years) 
CHS.SIP.22.02.09
Ensure that the
Renfrewshire child
protection processes and
guidance are compliant
with the new national
guidance on child
protection.
Child protection practice is
further enhanced and
strengthened in line with
recommendations. Child
protection practice is further
enhanced and strengthened
in line with
recommendations. 
31-Oct-2023 
All work to progress compliance with
the new national guidance has been
progressed and completed. New local
guidance will be issued in May 2023. 
Child Protection
Advisor

Page 19

9
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.02.10
Roll out the Safe and
Together model across
Children’s Services Social
Work and embed the Safe
and Together principles in
practice
Reduce risk of significant
harm to children affected by
domestic abuse. Children and
adult survivors of domestic
abuse will feel safer. Children
and adult survivors of
domestic abuse will recover
from the impact of domestic
abuse 
30-Jun-2023 
Core training has been delivered to 48
Children’s Services Social Workers in
total across two cohorts in 2022. Two
further tranches of four-day core
training are planned for 2023. A multi-
agency one-day briefing was delivered
in December 2022 and a further one-
day briefing is being planned for the
first half of 2023. Awareness of the
course was raised during the '16 days
of action', and ilearn continues to be
promoted for completion by all
Children’s Services Social Work staff.
However, this has been impacted by
current pressures across the teams. A
Champions Group is now in place and
reflective practice sessions are being
offered across Social Work teams. 
Social Work
Children’s Services
Manager 
CHS.SIP.22.02.11
Further develop proposals
for a bail supervision service
within existing resources
i.e., funding, staffing, office
accommodation, and the
capacity of partners to take
forward their requirements
The negative impact of
remand is reduced, and
individuals are supported in
the community to achieve
good life goals.
31-Mar-2023 
Proposals for developing the bail
supervision service have been agreed
and implementation will be taken
forward in the next twelve months,
through action CHS.SIP.23.FAC.04 of
the 2023-26 Service Improvement
Plan.
Justice Social Work
Services Manager 
CHS.SIP.22.02.12
Extend diversionary
opportunities, implement
Structured Deferred
Sentences and electronic
monitoring to support bail
as part of our range of
services to minimise
Vulnerable individuals are
supported to address their
behaviour and avoid
involvement with the justice
system. People are supported
to remain in their community
and the stigma associated
with involvement in the
31-Mar-2023 
The service has signed the Police
custody information sharing protocol
(ISP) in October 2022 and await Police
Scotland commencement so that staff
have access to the court service
database. Diversion is already
increasing in numbers and range of
interventions. Work will continue to
Justice Social Work
Services Manager

Page 20

10
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
involvement with the justice
system
justice system can be
reduced. 
develop and design early
interventions within justice social
work, through action
CHS.SIP.23.FAC.04 of the 2023-26
Service Improvement Plan. 
CHS.SIP.22.04.08
Further embed the
recommendations of The
Promise in service delivery
Care experienced young
people have better outcomes
and a more positive
experience of care; feel
listened to and valued; can
build and maintain good
relationships. 
31-Mar-2025 
Activity is underway across several
services and in line with The Promise
21-24 Plan. The Promise involves all
areas of the council and its partners
and reinforces the importance of
reflecting this in our strategic planning
approach. Renfrewshire’s Promise
Oversight Board and Four Priority
Action Groups, chaired by officers
from the Council and Renfrewshire’s
HSCP and the Scottish Children's
Reporter Administration (SCRA), is
now meeting to deliver on the 21-24
plan. The Promise features in
Children's Services Partnership Plan
as a key high-level Aim and in the
Council Plan 2022-27. Development of
the Renfrewshire Language Policy
work was taken forwards and in March
2023 was completed and
disseminated accordingly. This
document provides guidelines for
acceptable and positive language use
across the local authority. The
Promise Manager and Ambassador are
linking with Local Employability
Partnerships to ensure our care
experienced children and young
Promise Manager

Page 21

11
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
people can reach positive destinations
and are supported through their
career journey. Work is also underway
on a long-term focus with Community
Justice, Scottish Ambulance Service,
Police and Fire to allow us to better
support our care experienced young
people who access these services.
There is currently scoping work taking
place around this with further activity
planned towards the end of 2023. The
Promise Keeper network is active and
growing across the authority, HSCP
and Partners. There are currently 118
Promise Keepers in place from across
the local authority, noting the
diversity of the network. There is
ongoing work to continue to expand
the network further. 
CHS.SIP.22.04.09
Deliver an independent
evaluation of Women and
Children First
Reconnections
Service user voices and
experiences of service will
inform and improve practice
and future service delivery
30-Jun-2023 
The independent researchers have
completed the focus groups and direct
discussions with service users. The
draft evaluation report is complete
with a view to the evaluation being
finalised before the planned date of
June 2023.
Social Work
Children’s Services
Manager
Strategic Priority 4: Green 
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.03.01 Continue to work with other
council services to deliver
Following the Council’s
declaration of a climate 31-Mar-2026  The Energy Management Unit confirm
that the LED lighting programme is
Education Manager
(Resources)

Page 22

12
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
improvements to the school
estate which offer a high
degree of environmental
sustainability and energy
efficiency.
emergency in June 2019, the
delivery of this action will
make a critical contribution
towards Renfrewshire being
carbon neutral by 2030.
now complete in the public-private
partnership (PPP) estate and that CO2
monitors have also been installed in
the PPP estate. 
Strategic Priority 5: Living our Values 
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.04.01
Continue to participate in
school, cluster, and regional
moderation and pilot
engagement with the West
Partnership moderation
portal.
Staff will be skilled and
confident in using a
differentiated approach to
meet learning needs of
children and young people. 
30-Jun-2023 
Establishments have been involved in
cluster/paired schools moderation
activity across this session. The
activity was agreed between schools
depending on staff need and the
journey of the school. Some secondary
practitioners (English and Maths) have
been involved in the West Partnership
moderation event. This included a
piece of work on assessment and
moderation within the broad general
education (BGE) and professional
discussion among practitioners. 
Education Manager
(Curriculum) 
CHS.SIP.22.04.02
Continue to support and
strengthen leadership
capacity of staff at all levels
to support delivery of
establishment programmes
to promote recovery and
accelerated progress
Leadership capacity is
enhanced enabling fulfilment
of establishment recovery
programmes. Distributive
leadership is increasingly
evident across all
establishments. Senior
school leaders feel valued
and supported to carry out
30-Jun-2023 
In April 2022, the Aspiring Principal
Teacher (primary) programme
concluded. Participants shared their
Professional Enquiry and next steps
with their peers. In July, four Masters
Level Learning funding applications
were approved for courses starting
September 2022. A positive response
was achieved recruiting for the
Improving our Classrooms
Education Manager
(Professional
Development and
Leadership)

Page 23

13
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
their role with confidence and
competence. 
Programme, which closed with 17
applications. 
CHS.SIP.22.04.03
Progress work to increase
the use of digital technology
within learning and teaching
and to deliver professional
development opportunities
to support this.
Children and young people
have the appropriate digital
skills required by employers
and staff are equipped to
keep up to date with the pace
of change.
30-Jun-2023 
Work with schools applying for the
Digital Schools Award Scotland (DSAS)
has continued with staff who recently
achieved the award, sharing their
journey. In addition, the Digital
Wellbeing Award session was attended
by 8 schools and was rated 5 out of 5.
All 8 schools said they intended to
register for the award. To date there
have been 29 professional learning
sessions, with over 300 staff attending
and all being rated 4 or more out of 5. 
Digital Learning
Manager 
CHS.SIP.22.04.04
Launch revised Leadership
Strategy which promotes
distributed leadership at all
levels, whilst committing to
the ongoing support of those
in senior leadership
positions.
All staff within our
establishments feel confident
and supported to take on
leadership responsibility at
their own level 
30-Jun-2023 
A programme of professional learning
is in place. Leadership Strategy
launched September 2022. 
Education Manager
(Professional
Development and
Leadership) 
CHS.SIP.22.04.05
Continue to work on making
all aspiring leadership
courses deliverable internally
using the experience and
expertise of our own staff.
Delivery of our aspiring
leadership programmes
becomes fully sustainable
30-Jun-2024 
Dates for all programmes and
presenters confirmed. Working groups
to continue for duration of this term to
finalise all arrangements including
appointment of mentors,
development of course evaluations
and course presentations. 
Education Manager
(Professional
Development and
Leadership) 
CHS.SIP.22.04.06
Develop a 3-year Quality
Improvement Framework
(QIF) to promote recovery
Establishments are
supported and challenged to
recover and improve through
continued implementation of
30-Jun-2023 
During March 2023, Heads of Service
and link Education Managers visited
each secondary school with a focus on
raising attainment. A short-life
Education Manager
(Quality
Improvement and
Health & Wellbeing)

Page 24

14
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To
and accelerated progress
across education
our robust QIF. Senior leaders
are empowered to look
outwards and collaborate
with peers to inform
improvement. Self-evaluation
gradings across key quality
indicators demonstrate
maintenance of ambitious
standards or improvement
across almost all education
establishments.
working group, comprising Head
Teachers from all sectors, met twice
and a QI plan has been agreed for
session 2023/24. A programme of 3-
day establishment reviews, focussing
on leadership, learning, teaching, and
assessment, is currently underway
and will continue until June 2023.
Baseline data for key quality
indicators had been established in
June 2022, while stretch aims have
been identified to be achieved by June
2023. Three primaries and two
secondaries have been inspected by
Education Scotland this session; all
inspections have been positive. 
CHS.SIP.22.04.07
Develop a strategy for career-
long professional learning
(CLPL) for support staff
within Children's Services.
The council has a workforce
confident and capable of
delivering its role. 
31-Mar-2024 
Audit is currently being undertaken to
benchmark training needs. Once
completed a programme of CLPL will
be developed and implemented. 
Education Manager
(Professional
Development and
Leadership) 
CHS.SIP.22.04.10
Review the management and
leadership of social work and
identify options for a new
service model.
The service can efficiently
meet current and future
demands. 
31-Mar-2023 
All work on the redesign has been
taken forward as expected.
Consultation on the new model will be
carried out in the first quarter of
2023/24. 
Head of Childcare
and Criminal Justice 
CHS.SIP.22.04.11
Develop tools to improve
social work staff's access to
key data and insight,
providing training and
support where required.
Social work staff are
confident in their ability to
use data to direct resources
and support the most
vulnerable within our
communities. 
31-Mar-2023 
Social work data dashboard is ready
for implementation. Implementation
and staff training and support
currently underway. 
Quality Assurance &
Practice
Development
Manager

Page 25

15
Status Action Code Action Title Description Due Date Progress Bar Latest status update Assigned To 
CHS.SIP.22.04.12
Implement a new Quality
Improvement Framework for
Children's Services social
work
Social work services are child-
centred and focussed on the
experiences, progress and
outcomes in individual
children and young people.
Policies, procedures, and
processes are effective and
high quality, and protect
children at risk and improve
their care experiences. 
31-Dec-2022 
Interim QIF commenced November
2022. Working towards full
implementation of QIF to coincide
with new service re-design February
2024. 
Quality Assurance &
Practice
Development
Manager

Page 26

1
Children's Services SIP 2022-25 Financial Year 
PI Status 
Alert 
Warning 
OK 
Unknown 
Data Only 
Long Term Trends 
Improving 
No Change 
Getting Worse 
Short Term Trends 
Improving 
No Change 
Getting Worse 
Strategic Priority 3: Fair 
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
Q3 2022/23 Q4 2022/23 2022/23
Latest Note
Value Target Value Target Value Target
CHS/LGBF/01
Percentage of Looked After
Children cared for in the
community   
91% 89.9% 90% 89.9% 90% 89.9%
Performance in Q4 has decreased slightly
from 91.2% in Q3 to 90%. The majority of
all looked after children continue to live in
a community setting either with their own
family or with an alternative family. A
residential house or school can be more
suitable for a small number of children and
young people based on their needs, but
the service will always seek to have a child
live in a family setting where appropriate.
All looked after and accommodated
children are in the setting which has been
identified to best meet their needs. Please
note, this indicator is also reported

Page 27

2
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
Q3 2022/23 Q4 2022/23 2022/23
Latest Note
Value Target Value Target Value Target
annually, and the figure is derived from the
Local Government Benchmarking
Framework indicator CHN9 'Balance of
care for 'looked after children': % of
children being looked after in the
community'. The last data published for
this indicator is for 2020/21. The
percentage of looked after children living
with families in the community in
Renfrewshire in 20/21 was 92.5% and was
above the Scotland average of 90%. 
CHS/CJ/CPO/02
% of NEW unpaid work
orders/requirement
complete by the required
date   
94% 75% 96% 75% Not measured on an
annual target basis
Target has been exceeded in the previous
four quarters. Court services recovering
and the number of new orders imposed
has continued to increase over recent
months. The service continues to prioritise
workloads and deliver unpaid work activity
in accordance with safe working
guidelines. 
CHS/CJ/CPO/01
The percentage of NEW
clients subject to a new
supervision order seen by a
supervising officer within 1
week   
86% 85% 76% 85% Not measured on an
annual target basis
Q4 performance has dipped slightly in
comparison to the previous three quarters.
Where the social worker recommends a
supervision order the detail of the first
contact is contained in the criminal justice
social work report.  This target is
dependent on the compliance of the
person made the subject of the order
attending as directed.
CHS/CJ/CPO/04
Percentage of NEW unpaid
work clients seen within 1
working day of the order   
59% 70% 65% 70% Not measured on an
annual target basis
Significant recovery has been achieved,
exceeding target for Q2 with improvement
gains carrying on into Q4. Service users
should be seen at court on the day of
sentence and directed to an appointment
with unpaid work staff, however court
staffing levels has been impacted by

Page 28

3
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
Q3 2022/23 Q4 2022/23 2022/23
Latest Note
Value Target Value Target Value Target
vacancies which can interrupt this first
crucial stage, causing drift. Ongoing
recruitment of court staff, and increased
access to accommodation for unpaid wok
staff is improving the situation. 
CHS/CJ/CPO/05
Percentage of NEW unpaid
work clients receiving an
induction within 5 working
days of the order   
75% 75% 71% 75% Not measured on an
annual target basis
Performance has significantly improved
over the course of the year, with Q4
performance only slightly below target.
Improvements reflect focussed efforts to
prioritise health and safety inductions to
ensure that service users are ready for
available work placements.
CHS/CJ/CPO/06
Percentage of NEW unpaid
work clients beginning work
placement within 7 working
days of the order   
82% 65% 71% 65% Not measured on an
annual target basis
Performance has significantly improved
over the most recent three quarters,
exceeding target in the previous two
quarters. The demand for weekend work
placements remains high, and the service
continues to adapt in response to this
shift. Staff sickness and vacancies continue
to impact workforce capacity. 
CHS/CPR/01
Percentage of children
registered in this period who
have previously been on the
Child Protection Register   
0% N/A 3% N/A 5% N/A
There were 31 new CP registrations
between January and March 2023. One
child had previously been registered within
the last 2 years. Re-registrations are
monitored as part of the Renfrewshire
Child Protection Committee’s performance
management to ensure that there have
been no inappropriate de-registrations. 
CHS/LAC/02
Percentage of
accommodated Looked After
Children placed with families   
88.1% 83% 86.9% 83% 86.9% 83%
The service aims to ensure that
accommodated children live in a family
setting where this is in their best interest,
and this will continue to be the preferred
option for most children. There are times
when it is more appropriate to support a

Page 29

4
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
Q3 2022/23 Q4 2022/23 2022/23
Latest Note
Value Target Value Target Value Target
looked after and accommodated child in a
residential children’s house or school, or
times when a children’s hearing considers
this necessary. 
CHS/LAC/CL/01
Percentage of care leavers
participating in employment,
training or education   
54% 55% 52% 55% Not measured on an
annual target basis
Performance in Q4 has decreased and is
slightly below the target of 55%. The figure
of 52% reflects that 84 out of 161 care
leavers are in employment, education, or
training.
CHS/LAC/CL/02
Percentage of care leavers
who have had a period of
homelessness in the last 6
months   
6% 0% 4% 0% Not measured on an
annual target basis
The figure of 4% equates to 7 young
people. All individuals were either living
with family members/friends or provided
with temporary homeless accommodation
either in Renfrewshire or in other local
authority areas. Throughcare and Housing
continue to work together to prevent
homelessness and to support young
people in sustaining tenancies. Reduced
movement of housing stock in housing is
resulting in young people remaining in
placements longer. Homelessness can be a
result of breakdown in other living
arrangements whilst waiting on housing
offers.
RCPC/01
Number of children on the
Child Protection Register at
quarter end date   
86 N/A 80 N/A 80 N/A
There were 80 children on the Child
Protection Register as at the reporting
period end date in Q4 of 2022/23,
compared to 86 children as at the
reporting period end date in Q3. During Q4,
there were 31 children newly registered
and 37 children de-registered. Trends in
child protection activity are monitored by
the Renfrewshire Child Protection
Committee which receives a report on a
range of performance measures.

Page 30

5 
Strategic Priority 5: Living our Values 
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
Q3 2022/23 Q4 2022/23 2022/23 Latest Note
Value Target Value Target Value Target
CHS/CORP/01a
% of Stage 1 complaints
responded to within
timescales agreed with
customers   
91% 95% 97% 95% 95.8% 100%
Children's Services received 33 complaints
(33 Education), of which 32 were
completed within target.
CHS/CORP/01b
% of Stage 2 complaints
responded to within
timescales agreed with
customers   
71% 95% 95% 95% 84.8% 95%
Children's Services received 20 complaints
(13 Education and 7 Social Work), of which
19 were completed within target (13
Education and 6 Social Work). As at the
quarter end date, there are 8
investigations (5 Education and 3 Social
Work) still ongoing within timescales that
have been excluded from the figures.
CHS/CORP/03
% of FOI requests
completed within timescale
by Children's Services   
84% 100% 68% 100% 82.6% 100%
Children's Services had 72 FOI responses
due in this quarter; 62 Education and 10
Social Work.  49 were completed within the
required timescale; 39 Education and 10
Social Work. 23 Education FOIs were
completed outwith timescales.

Page 31

1
Children's Services SIP 2022-25 Academic Year 
PI Status 
Alert 
Warning 
OK 
Unknown 
Data Only 
Long Term Trends 
Improving 
No Change 
Getting Worse 
Short Term Trends 
Improving 
No Change 
Getting Worse 
Strategic Priority 3: Fair 
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
CHS/ATT/01a % of Leavers attaining literacy SCQF
Level 4    96% 98%
The percentage of leavers in Renfrewshire achieving
literacy and SCQF level 4 or above has remained high
over the previous three years. The 2021/22 figure of
96.1% is down on the 2020/21 figure of 97.0% but
remains ahead of our virtual comparator, at 95.9%,
and the national figure of 94.4%. The 2022/23 data
will become available in early-2024 through the SQA
Insight website.  
CHS/ATT/01b % of Leavers attaining numeracy SCQF
Level 4    93% 94%
The performance of Renfrewshire school leavers in
numeracy at SCQF level 4 or above has decreased to
93.3% from the previous years figure of 94.5%. This is

Page 32

2
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
slightly ahead of the virtual comparator which is
93.2%, and ahead of the national figure of 91.3%. The
2022/23 data will become available in early-2024
through the SQA Insight website.  
CHS/ATT/01c % of Leavers attaining literacy SCQF
Level 5    87% 88%
Attainment of school leavers in literacy at SCQF level
5 or above has decreased to 87.1% from 90.2% in
2020/21. Renfrewshire has consistently been ahead of
both the national average (82.0%) and its virtual
comparator (85.9%) for the previous 3 years. The
2022/23 data will become available in early-2024
through the SQA Insight website.  
CHS/ATT/01d % of Leavers attaining numeracy SCQF
Level 5    77% 77%
The percentage of school leavers achieving SCQF
level 5 or above in numeracy has decreased to 76.9%
from 80.1% in 2020/21. Renfrewshire remains above
the virtual comparator, which fell to 75.2%, and the
national figure of 70.7%. The 2022/23 data will
become available in early-2024 through the SQA
Insight website.  
CHS/ATT/08 Average Total Tariff Score of Looked
After Children (school leavers)    328 330
The average total tariff of care-experienced school
leavers decreased in 2021/22 to 328 from 471 in
2020/21. However, due to the small number of looked
after pupils in each leavers cohort there can be
considerable variation in the average tariff from year
to year. The 2022/23 data will become available in
early-2024 through the SQA Insight website.  
CHS/ATT/09
Gap between the Average Total Tariff
Score of Looked After Children (school
leavers) and that of the total
Renfrewshire leavers cohort   
67% 63%
The percentage gap between the average total tariff
between looked after school leavers and the general
cohort increased in 2021/22 to 67.3% from 58% in
20/21. The number of looked after pupils in each
leaver’s cohort is small therefore a high degree of
variation is expected in these figures year on year. The

Page 33

3
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
2022/23 data will become available in early-2024
through the SQA Insight website.
CHS/ATT/12 Average Complementary Tariff (S4)    311 320
The average complementary tariff score of S4 pupils
in Renfrewshire has decreased slightly over the
previous 3 years. The 2021/22 figure of 311 is down on
the 2019/20 figure of 317 and the 2020/21 figure of
320. Renfrewshire's score remains greater than that of
the national average and its virtual comparator. The
2022/23 data will become available later in 2023
through the SQA Insight website.  
CHS/ATT/13 Average Complementary Tariff (S5)    604 570
The average complementary tariff score of S5 pupils
in Renfrewshire has decreased slightly against the
figure from 2020/21. Renfrewshire's score remains
above the national average and its virtual
comparator. The 2022/23 data will become available
later in 2023 through the SQA Insight website.  
CHS/ATT/14
Percentage Point Gap in % Pupils
Achieving Expected Level for their stage
in Literacy between pupils living in 30%
Most Deprived areas and those living in
70% Least Deprived Areas (SIMD) 
15.4 7
The percentage point gap between the attainment in
literacy of pupils living in the most and least deprived
areas has increased to 15.4 percentage points, in
comparison to the data last reported in 2018/19. In
2019/20 this data was not collected, while the 2020/21
data collection did not include achievement of a level
at S3. The 2022/23 data will become available later in
2023 through the SQA Insight website.  
CHS/ATT/15
Percentage Point Gap in % Pupils
Achieving Expected Level for their stage
in Numeracy between pupils living in
30% Most Deprived areas and those
living in 70% Least Deprived Areas
(SIMD)     
13.4 6
The percentage point gap between the attainment in
numeracy of pupils living in the most and least
deprived areas has increased to 13.4 percentage
points, in comparison to the data last reported in
2018/19. In 2019/20 this data was not collected, while
the 2020/21 data collection did not include
achievement of a level at S3. The 2022/23 data will

Page 34

4
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
become available later in 2023 through the SQA
Insight website.  
CHS/ATT/16
Percentage Point Gap in % Pupils
Achieving Expected Level for their stage
in Literacy between pupils entitled to
Free School Meals and pupils not
entitled     
21 14
The percentage point gap between the attainment in
literacy of pupils based on their entitlement to free
school meals was 20.7 percentage points, an increase
on the figure of 18 last reported in 2018/19. The figure
for 2021/22 included S3 attainment which was not
collected in 2020/21. The 2022/23 data will become
available later in 2023 through the SQA Insight
website.  
CHS/ATT/17
Percentage Point Gap in % Pupils
Achieving Expected Level for their stage
in Numeracy between pupils entitled to
Free School Meals and pupils not
entitled     
17 14
The percentage point gap between the attainment in
numeracy of pupils based on their entitlement to free
school meals was 17.3 percentage points, an increase
on the figure of 14 last reported in 2018/19. The figure
for 2021/22 included S3 attainment which was not
collected in 2020/21. The 2022/23 data will become
available later in 2023 through the SQA Insight
website.  
CHS/PD/01 % of School leavers in a positive
destination    97% 95%
The percentage of 2021/22 leavers entering a positive
destination has remained similar to 20/21 figures
(96.6 vs 96.5). Renfrewshire is ahead of both the
national figure and the virtual comparator in this
measure - both comparators have also remained
similar to the previous year. The majority of our
school leavers went into higher education. The figure
this year was 43%, above the national average of 41%.
A further 25% of leavers went to further education,
with 25% entering employment after a drop to 17% in
19/20. The 2022/23 data will become available in
early-2024 through the SQA Insight website.

Page 35

5
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
CHS/PD/02. No of foundation apprenticeships
accessed by Renfrewshire school pupils    55 45
During 2021/22, 55 young people from Renfrewshire
schools began Foundation Apprenticeships. It is
intended to grow this number year after year as part
of the wider goal of positive post-school destinations
for all young people. We are also looking to get our
Business Skills up and running due to the excellent
partnership and progression opportunities.
CHS/SCH/07 % of children attending school
(Primary)    92.6% 95.5%
Renfrewshire primary schools have worked hard to
maintain a strong level of attendance despite the
impact of Covid-19. National comparator data for
attendance is compiled biennially and will next be
published in December 2023
CHS/SCH/08 % of children attending school
(Secondary)    87.1% 91%
Renfrewshire secondary schools have worked hard to
maintain attendance. However, the impact of Covid-
19 continues to present significant challenges for
some families resulting in pockets of attendance
falling. This is a picture which is being replicated
across the country. Full National comparator data for
attendance is compiled biennially and will next be
published in December 2023. 
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2022/23 Latest Note Value Target
CHS/SCH/09
% of young people choosing to stay
onto S5 (as % of S4 roll at September
previous year)   
92% 92%
Stay-on rates remain high, and most pupils remain in
school until at least S5. Initiatives such as foundation
apprenticeships and the provision of vocational
education provided by West College Scotland but
delivered in-school give pupils a range of options in
the senior phase.

Page 36

6
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2022/23 Latest Note Value Target
CHS/SCH/10
% of young people choosing to stay
onto S6 (as % of S4 roll at September
two years before)   
66% 70%
Stay on rates for young people choosing to stay on to
S6 have fallen below target. Education for the senior
phase has a strong focus on personal development
and employability skills as well as on academic
attainment, and support is offered to ensure positive
post-school positive destinations for all.   
Strategic Priority 5: Living our Values 
Code Performance Indicator Status Short Term
Trend
Long Term
Trend
2021/22 Latest Note Value Target
CHS/SCH/05
Percentage of pupils satisfied with
establishments Education Scotland
Survey   
N/A 100%
Figures for this indicator are taken from pupil
responses to surveys sent out by inspectors.  Due to
the suspension of inspections during the Covid-19
pandemic, we are unable to report on this indicator
for the 2021/22 school session. Inspections
recommenced in the 2022/23 school session and will
be reported in the mid-year progress report.