Democracy Spraffa

Early Learning and Childcare - Payment of Sustainable Rates to Funded Providers

Renfrewshire Council · 20 August 2026
Back to Education and Children's Services Policy Board — 20 August 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

OFFICIAL 
To: Education and Children’s Services Policy Board 
On:                         20 August 2026 
Report by: Director of Children’s Services 
Heading: Early Learning and Childcare – Payment of Sustainable Rates to
Funded Providers 
1. Summary
1.1 Renfrewshire Council has a statutory duty to provide early learning and childcare
(“ELC”) places to all eligible children. The Council continues to observe this duty
through the provision of places in local authority, private and voluntary sector
nurseries and with childminders. Renfrewshire Council’s Flexible Framework for
Early Learning and Childcare Places, reference RC-CPU-20-113 (“Council’s
Framework") enables the Council to purchase placements in private and voluntary
sector nurseries and with childminders (these private and voluntary services and
childminders are identified as “Approved Funded Providers” or “AFP”). 
1.2 The purpose of this report is to provide an update on a further review of the
sustainable rate paid to AFP for the provision of ELC and to seek approval for the
payment of the new rate from 1 April 2026. 
2. Recommendations 
2.1 The Education and Children’s Services Policy Board is asked to: 
(i) Note the position of COSLA and the Scottish Government with regards to
the sustainable rate paid to AFP.
(ii) approve an increase in the sustainable hourly rate paid to Renfrewshire
Council’s AFP for the provision of funded early learning and childcare from
£6.74 to £7.09 effective from 1 April 2026 for any child aged 3 to 5 years
accepted for funding under the Council’s Framework; and
(iii) approve an increase in the sustainable hourly rate paid to Renfrewshire
Council’s AFP for the provision of funded early learning and childcare from

Page 2

OFFICIAL
£8.88 to £9.13 effective from 1 April 2026 for any eligible child aged 2 to 3
years accepted for funding under the Council’s Framework. 
3. Background 
3.1 Section 1 of the Education (Scotland) Act 1980, as amended by the Standards in
Schools etc. Act 2000 and The Children and Young People (Scotland) Act 2014
(“2014 Act”), directs authorities on their duty to provide pre-school education.
Renfrewshire Council has continued to observe this duty through the provision of
places in local authority, private and voluntary sector nurseries and with
childminders. 
3.2 All 3 and 4-year-old children and eligible 2-year-old children have a statutory
entitlement of up to 1140 hours of funded ELC each year. 
3.3 The Scottish Government published updated guidance on the Funding Follows the
Child and National Standard for ELC Providers: Operating Guidance in August
2025. 
3.4 The Scottish Government’s Funding Follows the Child Policy tasks Councils with
the responsibility of ensuring flexibility and choice, ensuring that there is a range of
options for families in their area.  Renfrewshire Council continues to ensure
families have flexibility in the way they wish to access their child’s entitlement to
ELC. In each geographical area parents can choose from a range of Providers,
including Council and AFP; and a range of options such as term time and 52
weeks per year, full day, and part-time places. 
3.5 The National Standard sets out the required standards for AFP and local authority
establishments; with Councils required to be guarantors of quality in ensuring the
provision of high quality ELC in AFP settings.  The National Standard also sets out
a requirement for AFP to have a financially sustainable setting and to pay those
staff delivering funded ELC the real Living Wage, with the aim of supporting
recruitment and retention of staff, professional learning and investment in their
services. 
3.6 The Council’s Framework provides a robust scrutiny and assessment process to
ensure quality ELC provision and AFP commitment to meeting the National
Standards in relation to quality of provision, payment of the real Living Wage,
quality staffing and staff retention. 
3.7 In Renfrewshire, approximately 1620 eligible children currently access their funded
ELC placement in an AFP setting. The Council is dependent on AFP to fulfil its
statutory duty to deliver high quality ELC to all eligible children. Private, voluntary
sector nurseries and childminders settings in this sector need to remain financially
viable and meet the required standards set to ensure the provision of high-quality
ELC services. 
3.8 The rate paid for the provision of the statutory entitlement to ELC is known as the
sustainable rate.  Each local authority is responsible for setting their own rate and
national guidance produced by COSLA and the Scottish Government provided to
support local authorities with this exercise.

Page 3

OFFICIAL 
3.9 Guidance for Setting Sustainable Rates for the Delivery of Funded ELC in 2026-27
was published by the Scottish Government and COSLA in March 2026.  This
updated guidance, replaced previous versions of the sustainable rates guidance,
sets out the process for local authorities to set sustainable rates for 2026-27. 
3.10 The Scottish Government confirmed an additional £11 million funding across
Scotland in 2026-27 to enable childcare workers delivering funded ELC in private and
third sector services to be paid at least the new real Living Wage rate of £13.45 per
hour from April 2026. 
3.11 The Council also continues to provide additional benefits to AFP as part of the
Council’s Framework.  This is in addition to the sustainable rate paid to AFP.  The
additional benefits include high quality continued professional learning; a
designated link Partnership Support Officer; professional advice and support on
quality improvement; access to an Early Years Graduate (in line with SIMD status)
and to an Early Years Teacher; an enhanced programme of support for services
during a Service Improvement Period due to inspection grades falling below the
requirements set within the National Standard; financial support towards external
workforce training costs to assist in the compliance with SSSC requirements; and
other support services such as Educational Psychology and the Education
Inclusion Team for support and advice on supporting children with additional
support needs, which may also include ASNA support. These forms of in-kind
support enables the Council to discharge its duty as guarantor of quality. 
4. Payment of a Sustainable Rate – 2026-27 
4.1 The Scottish Government and COLSA updated guidance on setting the sustainable
rate for funded ELC in 2026-27. 
4.2 Through national agreement between the Scottish Government and COSLA, it has
been determined that local authorities should apply a minimum 5.2% uplift to all
2025-26 rates to reflect the estimated increase in the average staff cost element of
the sustainable rate required to meet the real Living Wage uplift from April 2026. This
reflects staffing costs accounting for, on average, 77% of the sustainable rate. In line
with this guidance non-staffing costs are estimated to account for, on average, 23%
of the sustainable rate. 
4.3 The guidance also encourages local authorities to: 
- Set a higher rate for eligible 2-year-olds for 2026-27, reflecting the differences in
the staff ratio requirements and that the cost for delivering funded ELC to eligible
2-year-olds being higher than for 3–5-year-olds.
- Set a separate payment rate for the free meal commitment for 2026-27. 
4.4 Additionally, the sustainable rate guidance for 2026-27 requires that the overall rate
agreed must be affordable for local authorities in terms of the budgets available. Also
advised in the guidance is that sustainable rate uplifts for 2026-27 which are set after
1 April 2026 are expected to be backdated to 1 April 2026 to reflect, from this date,
the increased real Living Wage.

Page 4

OFFICIAL
4.5 A proposed uplift from 1 April 2026 for Renfrewshire Council’s AFP, from £6.74 to
£7.09 per hour, for an eligible child aged 3 to 5 years reflects the requirements
detailed at 4.2 above and represents a 5.2% uplift to the sustainable rate. In addition,
a 2.8% uplift aligned to the Consumer Price Index (CPI) inflationary rate is proposed
from 1 April 2026 for Renfrewshire Council’s AFP, from £8.88 to £9.13 per hour, for
an eligible 2-year-old. 
4.6 The increase proposed in paragraph 4.5 is linked to a commitment by AFP to pay
their ELC staff providing direct care to children who are receiving funded hours with a
minimum of £13.45 per hour from 1 April 2026. 
4.7 AFP will continue to receive £3 per meal for any eligible child in accordance with the
1140 hours of ELC entitlement and in addition to the hourly rate. The continuation of
a rate of £3 per meal is in line with the funding allocated to the Council for meal
provision. AFP will also continue to be paid £0.58 for each child, per session, as part
of the Scottish Milk and Healthy Snack Scheme. 
4.8 Council officers have continued to work collaboratively with a representative group of
AFP on the sustainable rate setting process. The AFP representative group were
consulted during the preparation on the proposal for the sustainable rate for session
2026-27 being presented to this August 2026 Policy Board. 
4.9 The other additional in-kind services the Council provides to AFP, as outlined in
paragraph 3.11 above will continue to be provided; this is also in addition to the
hourly rate paid to AFP. 
Implications of this report 
1. Financial
The overall cost of the proposed increase to the hourly rate payable to AFP for ELC is
expected to be in the region of £629,000. This is based on a projected amount of charged
hours from AFP for 2026-27 for external placements. 
An additional £11 million has been provided for 2026-27 nationally by the Scottish
Government to fund the increase in the sustainable rate required to meet the commitment to
pay at least £13.45 per hour from 1 April 2026 and, along with other finance settlement
adjustments, this leads to an increase in funding for Renfrewshire Council for financial year
2026-27 of £452,000. 
The implementation of this uplift will therefore represent an estimated additional net cost
pressure to Renfrewshire Council Children’s Services of £177,000. 
The overall budget shortfall for the year is estimated to be in the region of £429,000. 
As the number of families choosing to access their child’s entitlement in AFP settings
varies on an annual basis, the service will continue to closely monitor ongoing
affordability. 
The findings of the joint review of the sustainable rate setting process notes the
continued challenges facing the sector. It also notes that any sustainable rate must
also be financially sustainable from the perspective of the local authority. Council
officers will continue to engage with AFP across Renfrewshire to inform future
reviews of the sustainable rate.

Page 5

OFFICIAL 
2. HR and Organisational Development                                                                  
None directly arising from this report as it relates to AFP costs. 
3. Community/Council Planning
Our Renfrewshire is thriving -  Ensuring the best start in life for
children and young people. 
Our Renfrewshire is well -  Early intervention will lead to
healthier outcomes for children and
young people. 
Our Renfrewshire is safe -  Local services will benefit children,
young people and members of the
community.     
Building strong, safe and
resilient communities 
-  The quality of community life is
enhanced by supporting parents,
children and young people. 
Tackling inequality, ensuring
opportunities for all 
-  Effective governance arrangements
ensure that the organisations
receiving funding comply with
legislative requirements. 
Creating a sustainable
Renfrewshire for all to enjoy 
Working together to improve
outcomes 
Support to families and flexible
childcare placements will support
parents into and sustain
employment, training or enter
education. 
Ensuring children have a high quality
ELC experience. 
4. Legal 
Services from AFP will continue to be procured in accordance with the Council’s
Framework and the Council’s Standing Orders Relating to Contracts.  
The Scottish Government and COSLA guidance on setting sustainable rates for the
delivery of funded ELC provides guidance for Councils, this is not a statutory
requirement.  Additional funded is provided to support an increase, therefore placing
an expectation on Councils to increase rates in accordance with their guidance.
5. Property/Assets                                                                                                                                   
None directly arising from this report

Page 6

OFFICIAL
6. Information Technology                                                                                           
None directly arising from this report
7. Equality and Human Rights
No negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in
the report because the sustainable rate is being increased. If required, the actual
impact of the recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the Council’s
website. 
AFP are required to comply with the Equality Act 2010 
8. Health and Safety                                                                                                                              
None directly arising from this report
9. Procurement
Services from AFP will continue to be procured in accordance with the Council’s
Framework and the Council’s Standing Orders Relating to Contracts. The process for
the proposed variation to the rate will be dealt with in accordance with the Council’s
Framework and formal letter issued by the Corporate Procurement Unit to each of
the appointed AFP for their agreement.
10. Risk
If the Council does not increase the hourly rate to a level that enables AFP to be
sustainable and to fulfil the commitment to pay staff £13.45 per hour, there is the risk
that: 
i.   There will be a reduction in the level of choice and local provision for parents
and possibly impact on the Council’s ability to fulfil its statutory duty and
compliance with the Funding Follows the Child Policy and National Standard of
ensuring sufficient ELC places.  This could result in additional cost for the
Council as it will need to expand existing Council ELC services and/or open
new Council operated ELC services. 
ii. There may be reputational damage to the Council if ELC services close due to not
being sustainable, leading to disruption to children and families’ lives, loss of local
provision, choice and flexibility for families, loss of employment and community-
based services. 
iii. Providers in the private, voluntary and independent sector may not be able to
meet the National Standard, recruit and retain staff if they are not able to pay the
real Living Wage to those staff delivering funded ELC. 
iv. Potential reduction in the quality of service provided if qualified and experienced
staff cannot be recruited.
11. Privacy Impact                                                                                                                   
None directly arising from this report 
12. Climate Risk 
None directly arising from this report

Page 7

OFFICIAL 
13. Children’s Rights
Article 3 (best interests of the child) - the best interests of the child must be
a top priority in all decisions and actions that affect children.  Article 28 (right
to education) - every child has the right to an education. Article 29 (goals of
education) - education must develop every child’s personality, talents and
abilities to the full. It must encourage the child’s respect for human rights, as
well as respect for their parents, their own and other cultures, and the
environment.  Article 31 (leisure, play and culture) - every child has the right
to relax, play and take part in a wide range of cultural and artistic activities.
14. COSLA Policy Position
The joint review of the sustainable rate setting process was undertaken by COSLA
and the Scottish Government.  COSLA and the Scottish Government jointly
agreed on the sustainable rate setting process as outlined in this report. 
List of Background Papers 
- Early Learning and Childcare – sustainable rates for funded providers: overview
2024 to 2025, Scottish Government, March 2026 –
https://www.bing.com/search?q=march+2026+funding+follows+the+child+operating+
guidance&cvid=7aa048bbeabb48bab27f8727d2be737b&gs_lcrp=EgRlZG 
- Funding Follows the Child and the National Standard for Early Learning and
Childcare Providers: operating guidance August 2025 -                                                                             
Funding Follows the Child and the National Standard for Early Learning and
Childcare Providers: operating guidance - gov.scot
- Early Learning and Childcare – sustainable rates for funded providers: overview
2024 to 2025, Scottish Government, March 2025 – 
https://www.gov.scot/publications/early-learning-childcare-sustainable-rates-funded-
providers-overview-2024-2025/ 
- Guidance for setting sustainable rates for the delivery of funded early learning and
childcare (ELC) in 2025-26, Scottish Government and COSLA, February 2025 - 
https://www.gov.scot/publications/guidance-setting-sustainable-rates-delivery-
funded-early-learning-childcare-elc-2025-26/ 
- Funding Follows the Child and the National Standard for ELC Providers: Operating
Guidance, Scottish Government, December 2023. - 
Funding Follows The Child and The National Standard for Early Learning and Childcare
Providers: Operating Guidance - gov.scot (www.gov.scot). 
The foregoing background papers will be retained within children’s services for inspection
by the public for the prescribed period of four years from the date of the meeting.
The contact officer within the service is Jennifer O’Hara, Education Manager. 
JO’H
22 July 2026

Page 8

OFFICIAL 
Author: Jennifer O’Hara, Education Manager                      
jennifer.ohara@renfrewshire.gov.uk