To:  Education and Children’s Services Policy Board
On: 20 August 2026
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________
1. Summary
1.1. The current phase of the Learning Estate Delivery Programme is ongoing with the
following live projects:
• Paisley Grammar School Community Campus 
• Park Mains High School Extension & Internal Interventions
• Thistle Primary School 
1.2. This report provides a short update on the latest development of project construction
and design progress. 
1.3. Concurrently, the Learning Estate Strategy continues to progress with the
development of the Full Business Case (FBC) process for the following three projects:
• Trinity High School 
• Johnstone Primary School Estate 
• Johnstone High School
__________________________________________________________________
2. Recommendations
Members of the Education and Children’s Services Policy Board are asked to:
2.1. Note the progress of project delivery in the Learning Estate Programme. 
2.2. Note the school badge chosen by the children for the new Thistle Primary School.

Page 2

PUBLIC
2.3. Note the intention to make best use of space flexibility within Thistle Primary School,
by introducing an early years provision 
3. Paisley Grammar School Community Campus
3.1. The project to deliver a new Paisley Grammar School Community Campus has
delivered on time, and on budget through to formal project closure. The new school
will open to pupils and staff in August 2026 with pupils arriving through the doors on
the 20th of August. 
3.2. The construction of the new school building is now complete with supporting
infrastructure as part of the Advanced Manufacturing Innovation District Scotland
(AMIDS) South project ongoing in the vicinity of the new school campus to create
further road and active travel opportunities. 
3.3. The school is ready to deliver a high quality learning and teaching environment with a
significant amount of work undertaken to fit the building out with all equipment and
provisions, as well as undertaking a comprehensive move management process from
the former Paisley Grammar school building, to the new school and community
campus on Renfrew Road. 
3.4. Members should note that officers have been working to explore all avenues for
retaining and relocating the War Memorial situated within the existing Paisley
Grammar School. Following engagement with various organisations, community
groups, and Historic Environment Scotland, officers intend to progress with plans to
relocate the War Memorial to Paisley Abbey. The Abbey have worked with officers to
outline a plan to situate the Memorial on display that will be available for public
viewing. 
3.5. Having considered multiple options, this is the most appropriate for the long term
viability of the Memorial and aligns with the historical connection of the Abbey with the
school. This option will support public viewing of the Memorial for the first time,
something which has not been possible to date, with the Memorial having been
located in an operational school setting. 
3.6. Members should note that a recommendation will be made to the Planning and
Climate Change Policy Board in August 2026 to receive consent to remove and
relocate the Memorial away from the existing Paisley Grammar School prior to the
ownership of the building passing over to a private third party. 
3.7. During the appraisal of options, it was considered whether the Memorial could move to
the new Paisley Grammar School Community Campus. As the Memorial has not been
designed into the newly constructed building, there is no place that can support a
structure of its size that would not impede on space planned layouts for the school, or
on operational fire escape routes. The only solution to being able to house the
Memorial at the new school would be to lose educational teaching space and locate
the Memorial into a classroom. This option is therefore considered not viable when
balancing it against the option to relocate to the Abbey.

Page 3

PUBLIC
4. Park Mains High School Extension & Internal Interventions
4.1. Construction work is progressing on track for an August 2027 completion. Phase 1 of
the project has now completed which delivered all ground works and site setup. 
4.2. The Main Works of construction have been ongoing since June 2026, which is seeing
the creation of the two new teaching blocks in the grounds of the school. An additional
car park has been created as well as significant alterations and increase to the bus
drop off/pick up point. 
4.3. The first phase of internal reconfiguration and move management has also been
ongoing over the summer holiday period, with future phases planned in collaboration
with the school operational requirements.  
__________________________________________________________________ 
5. Thistle Primary School
5.1. The Main Works construction for Thistle Primary continues to progress on track for
summer 2027 completion. 
5.2. The building is progressing towards being fully wind and watertight with windows,
brickwork, and cladding progressing. Work is also commencing on the full-size
artificial pitch construction. 
5.3. Members are asked to note that following an engagement process with local young
people, a school badge has now been developed and chosen. This forms an important
step in the development of the school identity, being led by the Head Teacher. An
image of the school badge is shown below:  
5.4. The Head Teacher is in the process of establishing a parent/carer steering group
where the intention is to further develop the school identity through discussions
around   uniform, vision and values, as well as operational aspects, for example out of
school care. 
5.5. Officers are continuing to plan for the wider benefit that the new primary school can
deliver for the community. Recently, revised statutory guidance has been issued by
the Scottish Government, increasing the eligibility for 2 year olds to access free early
years provision. The Council has a requirement to meet this, and subsequently a
benefit could be gained by increasing access to early years provision in the area.
Officers have considered the flexible design of Thistle Primary School building and

Page 4

PUBLIC
have the opportunity to establish an early years provision in a section of the school
with minimal alterations. 
5.6. Developing an early years provision in Thistle Primary School through a flexible and
agile use of the space, will allow this position to remain under review, and be
considered alongside any long term strategic estate plans for the years ahead.
Operationally, officers will work with the existing Dargavel ELCC to determine the
most appropriate operating model between Dargavel ELCC and Thistle Primary
School early years provision. 
__________________________________________________________________ 
6. Business Case Updates
6.1. A significant and comprehensive engagement process has been underway since May
for the Johnstone learning estate, which has seen officers facilitate events for all
school staff, parents/carers, pupils, and the local community. This has been
supplemented with a survey offering the ability for anyone to provide their views.
Officers have also been engaging internally with all Council services to understand
operational views on any of the shortlisted options for Johnstone projects, which will
be vital to understand any implications of shortlisted sites at this early stage. 
6.2. Work is underway to analyse and understand all views that have been presented
through the initial engagement process, to help shape the next phase of engagement
to follow. 
6.3. Note that following the decision at the May 2026 Education & Children’s Services
Policy Board, the engagement process for Trinity High School will commence
following the August Policy Board, where a decision will be made on the final shortlist
of sites. 
6.4. Officers have been working to appoint a number of specialist technical consultants as
presented in the Outline Business Case. These consultants will analyse essential
information that will be compiled into the final decision making process for each
process at the conclusion of the FBC process. 
______________________________________________________________ 
Implications of this report 
1.  Financial 
All budgets associated with the capital projects discussed in this report
have been agreed by Council and undergo rigorous management and
quality assurance on a regular basis. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and

Page 5

PUBLIC
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights  
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement 
Any procurement work required is conducted in collaboration with the
Council’s Procurement team and adheres to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place.   
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the direct
needs of children to allow their education experience to thrive. Whilst

Page 6

PUBLIC
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14. Cosla Policy Position 
None.     
Children’s Services
JL/GM
Aug 2026 
Author: 
Jack Lochans – Strategic Learning Estate Manager