Page 1

PUBLIC
To: Education and Children’s Services Policy Board
On: 20 August 2026
Report by: Director of Finance and Resources and Director of Children’s Services
Heading: Revenue and Capital Budget Monitoring as at 19 June 2026
1. Summary of Financial Position
1.1. The projected Revenue outturn at 31 March 2027 for Children’s Services is an
overspend of £1.496m (0.5%) against the revised budget for the year.
1.2. The projected Capital outturn at 31 March 2027 for Children’s Services is a
break-even position.
1.3. This is summarised in the table below and further analysis is provided in the
Appendices.
Table 1: Revenue
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 295.184 296.679 (1.496) (0.5%)
Table 2: Capital
Division
Revised
Annual Budget
£m
Projected
Outturn
£m
Budget
Variance
£m
Budget
Variance
%
Children’s Services 46.867 46.867 0 0%
2. Recommendations
Members are requested to:
2.1. Note the projected Revenue outturn position for Children’s Services detailed
in Table 1 above;
2.2. Note the projected Capital outturn position for Children’s Services detailed in
Table 2 above; and
2.3. Approve the Premises Related budget virements totalling £0.017m set out at
section 6.3.

Page 2

PUBLIC 
3. Revenue Budget Projection - overspend of £1.496m by 31 March 2027
3.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
annual overspend of £1.496m (0.5% of total budget).
3.2. It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. Any changes to this projection are updated at each board cycle.
Budget holders are obliged to seek mitigating action to minimise significant
budget variances.
4. Objective Analysis - Significant Variances
4.1. Early Learning & Childcare - £0.804m overspend
Non-teaching employee costs are currently projected to overspend, however
savings options continue to be implemented by the service and are expected
to reduce the level of this overspend as the year progresses. Transfer
Payments are expected to overspend due to projected payments to partner
providers.
4.2. Primary Schools - £0.066m overspend
Premises costs, Transport costs and Supplies & Services are currently
projected to overspend. This overspend is partly offset by an underspend in
Employee costs. The projected overspend in Premises costs is due to
increased refuse collection charges and janitorial supplies being greater than
budget. The projected overspend in Transport costs is due to the SPT school
transport contract being greater than available budget. The underspend in
Employee costs relates to teaching staffing, and this will be kept under review
as the year progresses.
4.3. Secondary Schools - £0.300m overspend
Premises costs and Transport costs are currently projected to overspend. This
is partly offset by a small underspend in Employee costs. The Premises costs
overspend relates to increased refuse collection charges and the Transport
costs overspend is due to the SPT school transport contract being greater
than available budget. The underspend in Employee costs relates to teaching
vacancies, and this will be kept under review as the year progresses.
4.4. ASN Schools - £0.073m overspend
Employee costs are currently projected to overspend. This is due to teaching
staffing, and will be kept under review as the year progresses.
4.5. Additional Support for Learning - £0.605m overspend
Employee costs and Transport costs are currently projected to overspend.
The overspend in Employee costs mainly arises from an increase in demand
for Additional Support Needs Assistants (ASNAs) within mainstream schools.
The overspend in Transport costs is partly due to demand and partly due to
increased cost of provision. This is partly offset by a projected underspend in
Supplies & Services due to turnover in external placements. This is a

Page 3

PUBLIC 
demand-led service and will be continually reviewed for any movements in the
demand for support as the year progresses.
4.6. Facilities Management - £0.155m underspend
Employee costs are currently projected to underspend, mainly due to
vacancies within the division. 
4.7. Children & Families - £0.203m underspend
Employee costs and Transfer Payments are currently projected to
underspend, and these are partly offset by projected overspends in Premises
costs, Transport costs and Supplies & Services. 
The underspend in Employee costs is mainly due to turnover. The overspend
in Premises costs relates to rents payable and increased refuse collection
charges. The overspend in Transport costs is mainly related to costs
associated with family time arrangements and transport to health, nursery and
school for children who are looked after away from home. The Supplies &
Services projected overspend occurs across several service areas and will be
continually monitored as the year progresses.
5. Subjective Analysis - Significant Variances
5.1. Employees - £0.044m overspend
Underspends are currently projected in teaching staffing in Primary and
Secondary Schools, offset by a projected overspend in ASN Schools. 
Overspends are projected in non-teaching staffing in Additional Support for
Learning, due to the demand for Additional Support Needs Assistants, and in
Early Learning & Childcare. This is offset by underspends in Children &
Families and in Facilities Management, due to turnover.
Teaching and non-teaching staffing will be kept under constant review and
changes reported as the year progresses. 
5.2. Premises Related - £0.264m overspend
The overspend in Premises costs is mainly due to increased janitorial costs
and refuse collection charges across the school estate.
5.3. Transport Related - £0.755m overspend
The overspend in Transport costs is due to SPT contracts for both
mainstream school transport and ASN transport being higher than available
budget, predominantly caused by price inflation and, to a lesser extent, by an
increasing number of children requiring transport.
5.4. Supplies & Services - £0.317m overspend
Projected overspends across various budgets in Children & Families are
partly offset by underspends in Early Learning & Childcare and Additional
Support for Learning.

Page 4

PUBLIC 
5.5. Third Party Payments - £0.068m underspend
This budget covers essential care placements, such as fostering and kinship
allowances, external residential care and short breaks. The forecast is highly
sensitive to changes in demand, and therefore subject to a degree of
uncertainty; it will be kept under review by management throughout the year.
Projected underspends within short breaks and within fostering, adoption &
kinship are offset by projected overspends on external residential placements
and throughcare.
5.6. Transfer Payments - £0.167m overspend
The projected overspend in Transfer payments relates to Early Learning &
Childcare in relation to payments to partner providers and is offset by
projected underspends in Children & Families mainly in relation to Direct
Payments which are demand-driven. These will be kept under review
throughout the year.
6. Revenue Budget Adjustments
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’.
6.2. Transfers between divisions of the same service / department in excess of
£100,000 and transfers between services / departments must be authorised
by the respective service Director and the Director of Finance and Resources
for submission to the relevant policy board for approval.
6.3. The Director now seeks approval from the Board for the following virements:
Revenue Budget Adjustments
Objective
Heading
Subjective
Heading
Amount
(£m) Reason
Children’s Services Premises Related (0.017) Transfers to Environment,
Housing and Infrastructure
relating to small repair projects
6.4. The remaining budget adjustments are either within delegation, or in line with
the earmarking of funds set aside in the 2026/27 budget motion and the
allocation of centrally held budgets already approved.
7. Capital Budget Projection - break-even position by 31 March 2027
7.1. The Capital Investment Programme 2026/27 to 2030/31 was approved by the
Council on 26 February 2026. Education and Children’s Services’ revised
Capital spend for 2026/27 is £46.867m.

Page 5

PUBLIC
7.2. The in-year Capital budget is forecast to break even by 31 March 2027.
However, this will be monitored as the projects progress. Further details of the
programme can be found in the Capital Monitoring report at Appendix 3.
7.3. Several budget adjustments between years have taken place, to reflect
revised programming of some capital projects. Details of these adjustments,
which amount to £(4.240)m, are as follows:
Project Amount (£m)
Budget carried forward from 2025/26 into 2026/27
Early Years Expansion Programme 0.060
Primary Schools Estate Programme (SEMP) 0.080
Paisley Grammar New Campus 0.678
Dargavel Extension (modular units) 0.012
Dargavel Primary School ‘C1’ Drop-off 0.025
Schools Estate (including Early Years) Programme 0.365
Park Mains High School Extension (new build) 0.401
Technology Replacement Strategy (ICT) 0.013
Budget brought forward into 2025/26 from 2026/27
Thistle Primary School (new build) (4.474)
Budget reallocation in 2026/27
Paisley Grammar New Campus: committed to
Lifecycle Maintenance for pitch upgrades * (1.400)
Total (4.240)
* Per the budget Motion approved at Council on 26 February 2026, £1.400m has
been committed to upgrade existing pitches at Linwood and St Benedict’s High
Schools, funded from the potential Paisley Grammar New Campus underspend.

Page 6

PUBLIC
___________________________________________________________________
Implications of this report
1. Financial
The projected budget outturn position for Children’s Services’ Revenue
budget is an overspend of £1.496m. Income and expenditure will continue
to be monitored closely for the rest of the financial year and steps will be
taken to mitigate any overspend, including virement, applying flexibility
within specific grant funding as permitted by the Scottish Government, and
potential use of earmarked reserves.
The projected outturn position for Children’s Services’ Capital budget is a
break-even position. The Capital programme will continue to be monitored
closely for the rest of the financial year.
2. HR and Organisational Development
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations
in this report.
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well
Our Renfrewshire is fair
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy, and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe, and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal
There are no direct implications arising from the recommendations in this
report.

Page 7

PUBLIC
5. Property/Assets
The capital expenditure noted in this report will result in lifecycle
maintenance improvements to existing properties and replacement of ICT
assets and infrastructure.
6. Information Technology
While ICT assets and revenue costs are included within these reported
budgets, there are no direct implications arising from the recommendations
in this report.
7. Equality and Human Rights
While new areas of spend may impact on particular groups, any such
impact would be assessed prior to the spend being incurred, therefore
there are no direct implications arising from the recommendations in this
report.
8. Health and Safety
The capital expenditure noted in this report will result in lifecycle
maintenance improvements to existing properties and replacement of ICT
assets, which may in some cases improve health and safety arrangements.
9. Procurement
While Procurement is an important consideration prior to the Council
incurring any revenue or capital spend, there are no direct implications
arising from the recommendations in this report.
10. Risk
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors.
11. Privacy Impact
There are no direct implications arising from the recommendations in this
report.
12. Children’s Rights
There are no direct implications arising from the recommendations in this
report.
13. Climate Risk
The Council aims to reduce its carbon and other emissions to net zero by
2030, however there are no direct implications arising from the
recommendations in this report.
14. CoSLA Policy Position
n/a

Page 8

PUBLIC
_________________________________________________________________
List of Background Papers: 
• Revenue Budget and Council Tax 2026/27, Council 26 February 2026
• Capital Investment Programme 2026/27 to 2030/31, Council 26 February 2026
Authors: Richard Conway, Finance Business Partner
Linsey McGregor, Capital Accountant

Page 9

Appendix 1 PUBLIC
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2026/27
1 April 2026 to 19 June 2026
POLICY BOARD:  EDUCATION & CHILDREN’S SERVICES
Objective Summary Approved
Annual Budget
Budget
Adjustments
Revised Annual
Budget at
Period 3
Projected
Outturn
Budget Variance
(Adverse) or
Favourable
£000 £000 £000 £000 £000 %
Directorate 1,484 1 1,485 1,491 (6) (0.4%)
Early learning and childcare 40,142 178 40,320 41,124 (804) (2.0%)
Primary schools 74,147 (456) 73,691 73,757 (66) (0.1%)
Secondary schools 100,827 (213) 100,614 100,914 (300) (0.3%)
ASN schools 8,953 11 8,964 9,037 (73) (0.8%)
Additional support for learning (ASL) 20,936 896 21,832 22,437 (605) (2.8%)
Psychological services 1,128 22 1,150 1,150 0 0.0%
Education development 2,247 1 2,248 2,248 0 0.0%
Attainment Challenge 0 0 0 0 0 0.0%
Facilities management 612 (19) 593 438 155 26.1%
Children and families 43,877 410 44,287 44,084 203 0.5%
NET EXPENDITURE 294,353 831 295,184 296,680 (1,496) (0.5%)

Page 10

No embedded text on this page.

Page 11

Appendix 2 PUBLIC
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2026/27
1 April 2026 to 19 June 2026
POLICY BOARD:  EDUCATION & CHILDREN’S SERVICES
Subjective Summary Approved
Annual Budget
Budget
Adjustments
Revised Annual
Budget at
Period 3
Projected
Outturn
Budget Variance
(Adverse) or
Favourable
£000 £000 £000 £000 £000 %
Employees 204,803 1,081 205,884 205,928 (44) 0.0%
Premises Related 12,408 (1) 12,407 12,671 (264) (2.1%)
Transport Related 8,096 10 8,106 8,861 (755) (9.3%)
Supplies and Services 33,228 665 33,893 34,210 (317) (0.9%)
Third Party Payments 19,260 664 19,924 19,856 68 0.3%
Transfer Payments 17,916 203 18,119 18,286 (167) (0.9%)
Support Services 427 84 511 526 (15) (2.9%)
GROSS EXPENDITURE 296,138 2,706 298,844 300,338 (1,494) (0.5%)
Income (1,785) (1,875) (3,660) (3,658) (2) (0.1%)
NET EXPENDITURE 294,353 831 295,184 296,680 (1,496) (0.5%)

Page 12

No embedded text on this page.

Page 13

Appendix 3 PUBLIC
Prior Years Approved  Budget Revised Projected Total Approved Projected
Expenditure Budget Adjustments Budget Outturn Budget Outurn
Project Title to 31/03/2026 2026-27 since previous 2026-27 2026-27 to 31-Mar-31 to 31-Mar-31
Board report
£000 £000 £000 £000 £000 £000 £000
EDUCATION & CHILDREN SERVICES
Total Early Years 1140 Expansion Programme 0 0 60 60 60 0 0% 88 88 0 0%
Total Primary Schools Estate Programme(SEMP) 10,544 0 80 80 80 0 0% 10,623 10,623 0 0%
Paisley Grammar New Campus 75,903 9,019 (721) 8,298 8,298 0 0% 84,200 84,200 0 0%
Learning Estate 332 0 0 0 0 0 0% 98,438 98,438 0 0%
Dargavel Extension (Modular Units) 2,237 0 12 12 12 0 0% 2,250 2,250 0 0%
Thistle New Build 12,595 25,375 (4,474) 20,901 20,901 0 0% 44,371 44,371 0 0%
C1, Dargavel Primary School Drop off 604 0 25 25 25 0 0% 629 629 0 0%
Total Schools Estate(inc Early Years) Programme 0 0 365 365 365 0 0% 365 365 0 0%
PMHS Extension(New Build) 2,021 15,512 401 15,913 15,913 0 0% 36,894 36,894 0 0%
Technology Replacement Strategy ICT 16,349 1,200 13 1,213 1,213 0 0% 21,662 21,662 0 0%
PPP Lifecycle 20,829 0 0 0 0 0 0% 20,829 20,829 0 0%
TOTAL EDUCATION & CHILDREN'S SERVICES BOARD 141,414 51,106 (4,240) 46,867 46,867 0 0% 320,349 320,349 0 0%
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
Current Year 2026-27 Full Programme - All years
Budget Variance
(Adverse) or
Favourable
RENFREWSHIRE COUNCIL
1st April to 19th June 2026
POLICY BOARD: EDUCATION & CHILDEN'S SERVICES
Budget Variance
(Adverse) or
Favourable

Page 14

No embedded text on this page.