Democracy Spraffa

Learning Estate Strategy - Outline Business Cases ECSPB

Renfrewshire Council · 12 March 2026
Back to Education and Children's Services Policy Board — 12 March 2026 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

1 
OFFICIAL 
To:  Education and Children’s Services Policy Board  
On:  12 March 2026 
Report by: Director of Children’s Services 
Heading: Learning Estate Strategy Update – Outline Business Cases 
1. Summary 
1.1 In 2024, Renfrewshire Council agreed a new learning estate strategy with the overall
aim of initiating a strategic programme of investment in schools through detailed
assessment of the entire learning estate. The ambition of the investment programme
is to ‘create the best possible learning estate to allow children and young people to
thrive’ 
1.2 A key output of the assessment was identification of a cohort of 14 priority schools
highlighted as requiring investment to ensure they meet the ambition of the strategy,
from which a business case process began, examining Johnstone primary school
estate, Johnstone High School, and Trinity High School. 
1.3 Following presentation of a Strategic Case for Change in respect of each to the
Education and Children’s Services Policy Board in August 2025, work began to further
investigate options for change, in the form of Outline Business Cases (OBC). The OBC
recommend a shortlist of options for future investment in each case, for Members to
consider.
___________________________________________________________________ 
2. Recommendations  
2.1 It is recommended that members of the Education and Children’s Services Policy
Board: 
a. Note the contents of the three OBC documents in respect of Johnstone
Primary estate, Johnstone High School, and Trinity High School, as outlined
in this report. 
b. Agree to the shortlisted options recommended in the OBC to be taken forward
to Full Business Case stage (FBC).

Page 2

2 
OFFICIAL
c. Note the proposal to further develop the shortlisted options during 2026 as
part of a FBC, and to present the final recommended option for each business
case to this Policy Board early in 2027. 
d. Note the FBC development budget proposed for each project which will
enable technical issues to be progressed to further inform the feasibility of
options, allowing a robust final recommendation for each business case in
early 2027 to be developed. 
_____________________________________________________________ 
3. Background 
3.1 Renfrewshire Council published a new Learning Estate Strategy in 2024, setting out
plans to improve its education infrastructure through a structured approach to
assessment of school buildings. 
3.2 The entire school estate was assessed against numerous criteria including condition,
suitability for delivery of the curriculum, capacity and demand, with schools ranked
using a prioritisation framework. This identified those schools and areas most in need
of inclusion now in long-term investment planning, to ensure that the Council is best
placed to: 
• Secure best value from strategic learning estate decisions around investment 
• Meet the expected long-term demand for education provision across Renfrewshire
whilst delivering improvements in school buildings and learning environments 
• Ensure that the delivery of any new infrastructure complements other key
strategic objectives being progressed by the Council to optimise the use of assets
for communities and support wider redesign of services that better meet the
needs of communities. 
3.3 At the Education and Children’s Services Policy Board of March 2025, 14 priority
schools were agreed, including four schools in Johnstone - Auchenlodment, St
Margeret’s and Thorn Primaries, and Johnstone High School – and Trinity High
School in Renfrew.   
3.4 In May 2025, parameters were set out for examination of the context and potential
solutions for each project area through a business case process, including
agreement that other nearby schools could feature as part of the options where
appropriate. 
3.5 A Strategic Case for Change was created for Johnstone Primary estate, Johnstone
High School and Trinity High School and presented to E&CS Policy Board in August
2025. Members agreed on the context for change and agreed to the subsequent
development of OBC to focus on the development of options for change. 
3.6 An interim update to E&CS Policy Board was presented in October 2025, identifying
viable routes forward in respect of each priority project area. These were informed
through an understanding of the operating context at each school, set against the
business needs, objectives and scope articulated in critical success factors set out in
the Strategic Case for Change.
__________________________________________________________________

Page 3

3 
OFFICIAL 
4. Outline Business Case 
4.1 Officers committed to return to this Board in March 2026 with an OBC for each of the
three priority project areas. These documents are presented as appendices 1, 2 and
3, as follows: 
• Johnstone Primary School Estate – Outline Business Case
• Johnstone High School – Outline Business Case
• Trinity High School – Outline Business Case 
4.2 The business cases are based on the HM Treasury Green Book recommended
structure, using the 5 Case model to set out the rationale for change and to articulate
potential solutions: 
• Strategic case – confirming that strategic objectives remain current and seek
agreement on the recommendation
• Economic Case – helping to determine that the preferred way forward offers
value for money
• Commercial Case – working towards a recommended deal by explaining
potential delivery models, procurement and engagement
• Financial Case – establishing affordability and funding requirements
• Management Case – planning for successful delivery 
4.3 Each OBC recaps the strategic and local context for the priority areas, examining
those factors that contribute to the need for change, clarifying the requirement for
long-term investment, referencing findings from initial community engagement and
highlighting the potential benefits. 
4.4 The documents go on to outline the potential solutions for each project area, building
on the preferred ways forward first outlined to this Board in October 2025. The OBC
discuss indicative costs in each case, before discussing the Council’s approach to
delivering the solutions, including the approach to procurement, financial feasibility
and effective management of the projects.
___________________________________________________________________ 
5.  Shortlisted Options and Indicative Costs 
Johnstone Primary School Estate 
5.1 For Johnstone Primary School Estate, the preferred route forward presented in
October 2025 to this Board, recommended a masterplan approach to the whole of
the primary school estate in the town, acknowledging and addressing the clear
overprovision of school places across Johnstone and the opportunity to make the
most of existing good-quality facilities as follows:

Page 4

4 
OFFICIAL
Address the overprovision of primary school places in Johnstone and the
requirements of the 3 priority schools of Thorn, Auchenlodment, and St
Margaret’s, by:
• Making best use of capacity of existing high-quality buildings including St
Anthony’s, West Johnstone Joint Campus, and Fordbank. 
• Considering the location of any new build school facility that would look to
combine more than one existing school on the same site
• Considering the most appropriate catchment area configurations to support
efficiency and capacity. 
A longlist of potential sites and school catchment configurations was developed in a
structure which aims to meet these requirements. 
5.2 The following shortlist of options emerged:
a) Merge Thorn and Auchenlodment catchment areas, combining both non-     
denominational schools in a single modern building by one of the following
means: 
1. Site 01 - Retrofit and extend the existing Auchenlodment Primary School
building to provide a modern 2 stream primary school, early years provision,
and community space at Aspen Place, Johnstone 
2. Site 01 – Construct a new build 2 stream primary school, early years
provision, and community space at the existing Auchenlodment primary
school site at Aspen Place, Johnstone 
3. Site 04 - Construct a new build 2 stream primary school with capacity, early
years provision, and community space at the site of the existing Thorn
Primary, Thorn Brae, Johnstone 
4. Site 09 - Construct a new build 2 stream primary school, early years
provision, and community space on a new Site at Poplar Avenue, Johnstone 
The above options are proposed to be supported with the following also taking place: 
b) Merge Cochrane Castle and Fordbank catchment areas, combining both
non-denominational schools at the current Fordbank Primary School site. 
c) Merge St Margaret’s and St David’s catchment areas, combining both    
denominational schools at the West Johnstone Joint Campus, creating a
single denominational school. 
5.3 Officers considered the potential cost of delivering a school project to combine
Auchenlodment and Thorn. This produced an overall potential cost for a modern 2
stream primary school as follows:

Page 5

5 
OFFICIAL
Cost scenario  Range
Retrofit Auchenlodment and
extend, for 434 pupils and
early-years facility matching
current provision.
£35 - £45m
Build a new 2 stream primary
for 434 pupils, and early-years
facility that matches current
provision.
£25 - £45m 
Johnstone High School 
5.4 The preferred route forward for Johnstone High School acknowledged the clear over-
capacity and poor condition at the school and the need to provide modern, good
quality facilities for learners as follows:
Address the capacity, school condition and suitability issues facing Johnstone
High School by retrofitting the current school or rebuilding a new school on
the current site, or a new site. 
5.5 For Johnstone High School, it is possible to consider either a new build or major
retrofit to provide a modern fit for purpose school environment. As a result of this, the
three routes forward are all possible:
Route 2 Route 3 Route 4
Retrofit the existing
school 
Rebuild on the
current Johnstone
High site 
Rebuild elsewhere
in the catchment
area 
5.6 To explore the specifics of these routes further, a long list of options to address the
routes forward was compiled. 
For Route 2 – Retrofit the existing school, there is no permutation or longlist of
options as it affects the current building. Variations of this option would be derived
through careful design and requirements. 
For Route 3 – Rebuild on the current Johnstone High site – there are two
possibilities with this option. The first being that the current building could be
demolished with a decant strategy implemented to then rebuild on the same footprint.
The second being to build a new school in a vacant area on the current site to keep
the current school in operation, avoiding the need for a decant. Both variations will be
explored further at the FBC stage. 
For Route 4 – Rebuild elsewhere in the catchment area, several options were
considered and are detailed in the OBC. 
5.7 The findings of the above exercise have resulted in the following shortlist of options
being proposed to be taken forward:

Page 6

6 
OFFICIAL
Option 01
Retrofit Johnstone High School on Site 01 Johnstone High School Beith
Road, Johnstone 
Option 02
New Build on Site 01 Existing Johnstone High School Site, Beith Road,
Johnstone 
Option 03
New Build on Site 03 Beith Road Playing Fields, Johnstone 
5.8 A further exercise was undertaken to produce indicative costs for provision of either a
retrofitted or new-build school:
Cost Scenario Range
Option 1 – Retrofit the existing
school
£122m
Option 2 – Rebuild on the
current Johnstone High site
£85 - £133m
Option 3 – Rebuild elsewhere in
the catchment area
£91 - £144m 
Trinity High School 
5.9 For Trinity High School, the preferred route forward acknowledges that the existing
school site is too small to expand the building to meet demand and would not be
used for a school of such size were it to be built new. This resulted in the only
possible route forward for Trinity to be as follows:
Address the capacity, school condition and suitability issues facing Trinity
High School by building a new school on a suitable site elsewhere in the
catchment area. 
5.10 The shortlist of options therefore is focussed in identifying a suitable site, which
meets the site assessment criteria and is preferably within the ownership of the
Council:

Page 7

7 
OFFICIAL
Site 8 
Rebuild Trinity High School on Site 08 – KGV Playing Fields Renfrew
Site 9 
Rebuild Trinity High School on Site 09 – East Craigend, Erskine
Site 10 
Rebuild Trinity High School on Site 10 – Barwood, Erskine 
5.11 Officers produced indicative costs for a new build school using one of the sites as an                                       
example for costing purposes: 
Cost scenario Range
New build Trinity High
School on a suitable site 
£120 - £180m 
5.12 Within the option of considering a new build Trinity High School at Site 8 – KGV
Playing Fields, officers have considered the wider principles of the Learning Estate
Strategy by considering it holistically with any nearby schools within an option. By
recognising that this site is adjoined to the current site of Renfrew High School,
officers considered whether the option of constructing a new Trinity High School at
this site would constrain the future development of a new Renfrew High School at a
future date. 
5.13 This assessment concluded that there is adequate land available on the KGV to
construct a new Trinity High School without constraining a future potential Renfrew
High School. This assessment has also demonstrated that through careful design
considerations, a new Trinity High School on this site could be designed in such a
way that it supported the basis of how a future shared campus or shared use of
facilities could be implemented, when the appropriate time to invest in a new Renfrew
High School arrives. 
5.14 Given this overview shows that it is possible to construct multiple development
options including a joint campus, it allows further work to be conducted through the
next stage of assessment to assess the development options for the KGV site that
present the best value outcome for the Council, and any further community views,
technical assessments or considerations. 
5.15 However, it should be noted that estimates for delivering a shared campus option
indicated a cost in the region of £220-320m. When set against the wider Learning
Estate priorities and scale of funding that has to date been made available (£170m)
affordability constraints may limit the deliverability of such an option in a single
phase.
5.16 It is important to note that this consideration will only be apply to the option of
constructing a new Trinity High School at Site 8 – KGV Playing Fields, due to the fact
that Renfrew High School currently adjoins this site. A full explanation of this
assessment is included in the OBC.

Page 8

8 
OFFICIAL
Indicative Costs – All Projects 
5.17 The indicative costs are based on preliminary information and should be considered
a framework from which detailed cost plans can be developed. The indicative costs
have been built from high level information, benchmarking from various sources
including the Scottish Futures Trust (SFT) funding metric, cost information from
current Renfrewshire Council education construction projects, costs from other
Council’s similar school projects and adjusting the costings where specific knowledge
has been gained from the desktop assessment of the site options. The BCIS cost
indices have also been used to calculate inflation up to the end of the anticipated
construction period. 
5.18 In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are
the same, for example flood risk mitigation or ground remediation may be more or
less consequential from site to site, with differing impact on the overall construction
costs as to how the design addresses the site. In that sense, the indicative costs
should be taken as a guide only, detailed site options appraisal will be necessary to
fully understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
5.19 The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions
are required to establish indicative costs and clearly indicate what is assumed as
included in the costs and what is excluded at this stage. 
5.20 To project an estimated cost for inflation purposes, the construction cost has been
based on an assumed construction commencement date of 2030. All figures should
be noted as exclusive of VAT. 
5.21 Key assumptions and exclusions were used in compiling the indicative costs in the
absence of any design commencing. This approach recognises that whilst a range of
cost estimates have been presented, these remain volatile, subject to external factors
and site specific detail that will become clearer as sites are investigated, and options
further explored at the next stage. 
5.22 It is important to highlight as part of this process, that no budget for construction will
be requested or crystalised until further work has been undertaken into the validation
of each option, and a recommendation is made thereafter at the conclusion of the
Full Business Case. 
5.23 It is however important to recognise that the validation and robust assessment of the
viability of each option will require detailed assessment and technical consideration.
As such, each business case will require an identified budget to deliver the next
stage of development, the FBC. These budgets are outlined below. It is intended that
the costs of progressing to FBC will be funded from the initial revenue contribution
agreed by Council to support the Learning Estate Strategy in 2025/26, and that this
contribution will be held in a ringfenced revenue reserve for this purpose.

Page 9

9 
OFFICIAL 
5.24 Required indicative budgets to conclusion of FBC process: 
Project  Budget
Johnstone Primary School Estate   £330,000
Johnstone High School  £920,000
Trinity High School  £1,020,000 
5.25 These budget proposals have been developed by considering all internal technical
resource costs and all external professional services and consultant appointments
required to interrogate and validate the shortlist of options. This cost is made up as
follows: 
• Internal technical management costs to deliver project feasibility, cost
management, architectural services and project management
• Flood risk assessments
• Roads and transportation assessments 
• Space planning, and timetabling and demand modelling to develop schedules
of accommodation
• Civil and Structural Engineering for ground investigation surveys and intrusive
surveys on current school structures where required. 
6. Next Steps and Timeline 
6.1 Should the recommendations in these OBC be approved by Members, officers will
commence work to identify and recommend a preferred option in each case. This will
be reported to this Board by means of a Full Business Case (FBC)      
6.2 To properly prepare three FBC that can faithfully recommend a preferred option to
Members, officers will conduct further, detailed site assessments, undertake further
cost modelling to better understand the long-term implications of each shortlisted
option (including a whole life cost model), and a full programme of community
engagement and informal consultation to inform understanding and subsequent
decision making. 
6.3 It is anticipated that the informal consultation with whole school communities will be a
vital component in agreeing the most appropriate option to proceed with, however,
this will be balanced against business, financial, and technical assessments to
conclude the final option. A full programme of engagement is being developed and is
broadly anticipated to be conducted as follows:

Page 10

10 
OFFICIAL
Activity Stakeholders
Preparation and options
development
Senior Officers and SLT
Elected Members
Head Teachers
Targeted Early Engagement Parent Councils/Parents
Community Councils
Local Community Groups
Pupils
Staff
Council Services
Broad Public Engagement  Associated school parents and pupils
General public 
Neighbours 
Analysis and Refinement Project team 
6.4 The FBC would be presented in early 2027, and if approved, work would begin on
any required statutory consultation to be carried out that year. 
Implications of the Report 
1.  Financial – Council has agreed to make provision of £2.5m of revenue resource in
2025/26, with similar amounts being committed to on an annual basis each year over
the remaining years of the current Administration. The financial model underpinning
the strategy continues to be developed, along with the framework and analysis
required in the business case process. This financial provision will fund the
programme of work as it progresses through business case development. As the
FBCs develop, a clear funding strategy for each project will require to be agreed,
including both Council and any potential Scottish Government resource which may
become available via a successor programme to the Learning Estate Investment
Programme (LEIP).  
2.  HR & Organisational Development 
None 
3. Community/Council Planning 
- Our Renfrewshire is thriving   New and improved learning estate assets
will allow our children and young people to
thrive with the best possible infrastructure
to support their school experience. Staff
and community users will benefit from
modern and inclusive environments

Page 11

11 
OFFICIAL
- Reshaping our place, our
economy and our future  
The learning estate shall be appropriately
scaled and equipped to meet curriculum
expectations and deliver an appropriate
learning and teaching experience for all. 
4.  Legal 
None 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate, extending
the life of assets and improving the experience of young people, staff and the wider
community. 
6.  Information Technology  
Digital improvements will be delivered through the learning estate strategy, where
access to technology for all will be a key priority for projects. 
7.  Equality & Human Rights 
The recommendations contained within this report have been assessed in relation to
their impact on equalities and human rights. No negative impacts on equality groups
or potential for infringement of individuals’ human rights have been identified arising
from the recommendations contained in the report. If required following
implementation, the actual impact of the recommendations and the mitigating actions
will be reviewed and monitored, and the results of the assessment will be published
on the Council’s website. 
8.  Health & Safety 
None 
9.  Procurement 
Any procurement work required will be conducted in collaboration with the Council’s
Procurement team and adhere to appropriate regulations. By developing the
business case framework outlined in this report, procurement and commercial
considerations will be conducted throughout. 
10.  Risk – 
All projects are bound by rigorous governance and supported by detailed risk
registers. Risk is reported and managed at various levels with scrutiny applied to
ensure mitigations and contingency plans are in place. The business case framework
set out in Learning Estate Strategy updates will directly work to identify, manage and
reduce risk. 
11.  Privacy Impact 
None 
12.  Children’s Rights 
When considering any future school provision, the impact this will have on children is
key consideration and any work will be based around the direct needs of children to

Page 12

12 
OFFICIAL
allow their education experience to thrive. Whilst children have a right to choose
where they wish to attend school in collaboration with their parents, the Council’s
admission policy applies, to ensure that schools that are oversubscribed can be
managed. 
13.  Climate Risk  
New and improved learning estate assets will directly contribute to the Council’s
journey towards net zero. Sustainability is a key concept of all projects. 
14. COSLA Policy Position 
None 
List of Background Papers - Document.ashx – Strategic Case For Change Documents
for projects included in this report. Presented to the August 2025 Education and
Children’s Services Policy Board 
Children’s Services
JL/JO/GC Feb 2026 
Author: 
Jack Lochans – Strategic Learning Estate Manager
jack.lochans@renfrewshire.gov.uk

Page 13

1
OFFICIAL-SENSITIVE 
Johnstone Primary School Estate
Outline Business Case

Page 14

Johnstone Primary School Estate Outline Business Case  2
OFFICIAL-SENSITIVE
DOCUMENT CONTROL SHEET 
Title: Johnstone Primary School Estate
Version Number 2
Document Type: Outline Business Case
Author: Learning Estate Project Team
Date Published: 18/02/2026
Document Versions: 
Version: Name: Update: Date
V0.1 Project Team Initial draft 28/11/25
V1 Project Team First draft for review  17/12/25
V1.1 Project Team Add site assessments and section 7 19/01/26
V1.2 Project Team Reworking Masterplan configuration
and options  28/01/26
V1.3 Project Team Reworking section 3 and amends
throughout for consistency 30/01/26
V1.4 Project Team Amendments and updates  11/02/26
V2 Project Team Final draft following review by Chief
Officers 18/02/26
Supporting Documentation / Location: 
Document Title: Location:
Strategic Case for Change Document.ashx

Page 15

Johnstone Primary School Estate Outline Business Case  3
OFFICIAL-SENSITIVE
Table of Contents
1. EXECUTIVE SUMMARY ........................................................................ 7
1.1. Introduction .......................................................................................... 7
1.2. Background ........................................................................................... 8
1.3. Opportunity ......................................................................................... 10
1.4. Scope and Objectives .......................................................................... 11
1.5. Summary of Routes Forward ............................................................... 12
1.6. Preferred Route Forward and Options Shortlist .................................. 12
1.7. Indicative Costs ................................................................................... 14
1.8. Timeline ............................................................................................... 15
2. STRATEGIC CASE .............................................................................. 16
2.1. Strategic Context ................................................................................. 16
2.2. The Need for Change ........................................................................... 17
2.3. Investment Objectives ......................................................................... 17
2.4. Existing Arrangements ......................................................................... 18
2.5. Initial Engagement .............................................................................. 21
2.6. Scope and Service Requirements ....................................................... 22
3. ECONOMIC CASE .............................................................................. 24

Page 16

Johnstone Primary School Estate Outline Business Case  4
OFFICIAL-SENSITIVE
3.1. Potential Routes Forward.................................................................... 24
3.2. Preferred Route Forward ..................................................................... 30
3.3. Exploring Issues with the Johnstone Estate and Possible Solutions .. 32
3.4. Masterplan Redesign of Johnstone Learning Estate ........................... 38
3.4.1. Merge Thorn and Auchenlodment at a new build or modernised site (to be
agreed), and merge catchments ............................................................................. 38
3.4.2. Merge Cochrane Castle and Fordbank located at the current Fordbank
Primary School site, and merge catchments ........................................................... 40
3.4.3. Merge St Margaret’s and St David’s, located at the West Johnstone Joint
Campus, and merge catchments. .......................................................................... 43
3.5. Early Years Provision ........................................................................... 46
3.6. Site Assessment Criteria – Replacing Auchenlodment & Thorn
Primaries .......................................................................................................... 47
3.7. Site Options Assessment ..................................................................... 50
3.8. Shortlisted Options for new Thorn / Auchenlodment ......................... 66
3.9. Indicative Costs ................................................................................... 67
3.10. Transport Considerations ................................................................... 69
3.10.1. Merged Thorn and Auchenlodment ......................................................... 69
3.10.2. Merged Cochrane Castle and Fordbank .................................................. 70
3.10.3. Merged St Margaret’s and St David’s........................................................ 71

Page 17

Johnstone Primary School Estate Outline Business Case  5
OFFICIAL-SENSITIVE
3.11. Timeline and Next Steps ..................................................................... 72
4. COMMERCIAL CASE .......................................................................... 73
4.1. Approach ............................................................................................. 73
4.2. Service Requirements ......................................................................... 73
4.3. Project Development .......................................................................... 73
5. FINANCIAL CASE ............................................................................... 75
5.1. Project Funding – Capital Expenditure ............................................... 75
5.2. Approvals Process ............................................................................... 75
5.3. Revenue Expenditure .......................................................................... 76
5.4. Indicative Costs ................................................................................... 77
5.5. Financial Risk / Optimism Bias ............................................................ 78
5.6. Interdependencies .............................................................................. 79
6. MANAGEMENT CASE ........................................................................ 80
6.1. Project Management and Project Governance Overview ................... 80
6.2. Project Roles ........................................................................................ 80
6.3. Reporting Arrangements ..................................................................... 81
6.4. Procurement Strategy ......................................................................... 84
6.5. Overall Project Benefits ....................................................................... 84

Page 18

Johnstone Primary School Estate Outline Business Case  6
OFFICIAL-SENSITIVE
6.6. Community Benefits Realisation Arrangements ................................. 84
6.7. Risk Management Arrangements ........................................................ 85
6.8. Equalities and Human Rights .............................................................. 85
6.9. Communication, Engagement, and Community Voice....................... 85
7. CONCLUSION ................................................................................... 87
7.1. Summary of Shortlist of Options and Next Steps ................................ 87

Page 19

7
OFFICIAL-SENSITIVE
1. EXECUTIVE SUMMARY 
1.1. Introduction
This outline business case (OBC) is required as part of the Council’s new structured
approach to delivering its long-term strategy for the learning estate across
Renfrewshire. It builds on the context set out in a Strategic Case for Change (SCC)
examining the provision of primary schools in Johnstone, which was approved in
August 2025 at the Education and Children’s Services Policy Board (E&CS Policy Board).
In the SCC, 6 of the 7 primary schools in Johnstone were assessed to be working well
below optimal occupancy, with demand for places expected to stay the same or fall
further in the coming years. Further, the condition and suitability of three primary
schools was shown to be such that the schools feature in a priority cohort of
Renfrewshire schools requiring intervention if they are to meet the ambitions and
objectives of the Learning Estate Strategy.
The purpose of this OBC is to articulate a preferred route forward for the project by
identifying a shortlist of investment options likely to optimise value for money in
delivering change. A longlist of options is presented as part of the OBC, along with
analysis and rationale for their inclusion or exclusion from the shortlist. Additionally,
further detail is provided in respect to how the scheme will be prepared for
procurement and how the Council will put in place funding and management
arrangements for the successful delivery of the scheme. 
The OBC uses the following framework to present the preferred way forward, utilising
an adapted HM Treasury Green Book approach which is based on the 5 Case model: 
Strategic case – confirming that strategic objectives remain current and seek
agreement on the recommendation
Economic Case – helping to determine that the preferred way forward offers value for
money
Commercial Case – working towards a recommended deal by explaining potential
delivery models, procurement and engagement

Page 20

Johnstone Primary School Estate Outline Business Case  8
OFFICIAL-SENSITIVE
Financial Case – establishing affordability and funding requirements
Management Case – planning for successful delivery 
Table 1: Business case development process
1.2. Background
The Learning Estate Strategy published by the Council in 2024, aims to initiate a
strategic programme of investment in schools, through detailed assessment of the
entire learning estate. The ambition of the investment programme is to ‘create the best
possible learning estate to allow children and young people to thrive’.
Schools were assessed against various criteria including condition, suitability for
delivering the curriculum, capacity and demand. Using a prioritisation framework, the
strategy assessed the entire learning estate, identifying those schools in need of long-
term investment planning now, to ensure that the Council is best placed to:
• Secure best value from strategic learning estate decisions around investment
Stage: Stage 1 Stage 2 Stage 3 Stage 4
Stage Outcome: Strategic Outline
Case Outline Business Case Full Business Case Final Delivery Business
Case
Stage Activities:
• Highlighting
strategic context
• Making the case
for change
• Agreeing scope
• Considering longlist
options
• Exploring the
preferred way
forward and
presenting a
shortlist
• Determine potential
value for money
• Preparing for the
potential deal
• Planning for
procurement
• Procuring the
solution
• Contracting the deal
• Ensuring successful
delivery
5-Case Model
(stage of
completeness): 
• Strategic 50%
• Economic 40%
• Commercial 10%
• Financial 10%
• Management 10%
• Strategic 80%
• Economic 70%
• Commercial 40%
• Financial 30%
• Management 50%
• Strategic 90%
• Economic 90%
• Commercial 90%
• Financial 75%
• Management 75%
• Strategic 100%
• Economic 100%
• Commercial 100%
• Financial 100%
• Management 100%
Gateway
Review:
Strategic Assessment Business Justification Delivery Strategy
Final Investment
Decision and financial
commitment

Page 21

Johnstone Primary School Estate Outline Business Case  9
OFFICIAL-SENSITIVE
• Meet the expected long-term demand for education provision across
Renfrewshire whilst delivering improvements in school buildings and learning
environments 
• Ensure that the delivery of any new infrastructure complements other key
strategic objectives being progressed by the Council to optimise the use of assets
for communities and support wider redesign of services that better meet the
needs of communities. 
A cohort of 13 priority schools was identified, including three primary schools in
Johnstone - Auchenlodment, St Margeret’s and Thorn - where deteriorating building
condition and building suitability hamper the Council’s ambition to deliver the
curriculum in the best possible learning environments. 
The four remaining primary schools in Johnstone, these being Cochrane Castle and St
David’s Primaries (currently accommodated at the West Johnstone Joint Campus)
Fordbank Primary and St Anthony’s Primary, are all in good condition and provide good
quality, suitable learning environments for pupils. However, it was agreed that these
nearby schools would be taken into consideration, to examine whether existing
capacity is well used and ensure that any Council investment would deliver value for
money and benefit the whole community.
As a result, a Strategic Case for Change was produced, to consider the context of key
issues which, if not addressed, would limit the Council’s ability to deliver the objectives
of the Learning Estate Strategy. The document examined the operating context of the
Johnstone primary learning estate with reference to these objectives:
• Condition
• Suitability
• Sufficiency
• Inclusivity
• Digital
• Sustainability and Net Zero
• Community Facilities and Place shaping
• Active Travel

Page 22

Johnstone Primary School Estate Outline Business Case  10
OFFICIAL-SENSITIVE
The Strategic Case for Change articulates the current baseline position at each school
and identifies areas where existing arrangements are failing to provide the best possible
opportunity to support the Council in delivering against these objectives. 
The Johnstone area is noted as having a larger concentration of primary schools, and
primary school places, than towns of smaller population in Renfrewshire. This
geographical overprovision is borne out by roll projections produced for Renfrewshire
Council, which confirm that capacity exceeds demand, and that demand is expected to
fall further over the next ten years. 
This context was set against the ambition of the Learning Estate Strategy to test how
likely the current schools are to meet its ambition of educating all pupils in the best
possible learning environments.
Following approval of the strategic case for change, significant work has been
undertaken to identify options for change that meet the ambition and align with the
critical success factors articulated in the documents.
1.3. Opportunity
The opportunity to change and improve the provision of primary education in
Johnstone aims to advance the objectives of Renfrewshire Council’s new Learning
Estate Strategy, and to help meet the ambitions of wider Council and Scottish
Government policies. Those ambitions, fully considered in the Strategic Case for
Change, are summarised here:
• Improving the condition of schools
• Sustainability and Energy Efficiency
• Equity and Inclusion
• Adapting to Future Educational Needs
• Community and Public Use
• Strategic Planning and Investment 
• Collaborative Approach with Stakeholders
The ambitions encompass Renfrewshire Council’s determination to invest wisely whilst
reflecting the importance of operational efficiencies and cost avoidance in delivering
the Learning Estate Strategy. Thus, careful consideration of how to bring change to
Johnstone primary school estate, can additionally help increase building operational

Page 23

Johnstone Primary School Estate Outline Business Case  11
OFFICIAL-SENSITIVE
efficiency through provision of improved, modern facilities. A new or refurbished school
can deliver modern standards and design and contribute to the Council’s Net Zero
commitments. 
Above all, this OBC sets out the opportunity for Renfrewshire Council to meet its
overarching aim of ensuring that its schools are modern, accessible to all and support
the delivery of high-quality education for learners.
1.4. Scope and Objectives
The Strategic Case for Change set out five overarching investment objectives for
primary school provision in Johnstone. Any investment in the learning estate must:
• Deliver the best learning environments and facilities possible
• Support improving attainment and ambition
• Maximise operational efficiency across the estate
• Reduce the contribution to the Council’s combined carbon footprint 
• Acknowledge that ageing schools with deteriorating conditions come closer to
the point of being no longer fit for purpose
Thus, primary school provision in Johnstone is noted as:
• Having overall capacity which exceeds current and projected demand.
• Including three schools where building condition and suitability hamper delivery
of a modern curriculum and efforts to raise attainment.
• Having three schools which require considerable on-going investment simply to
maintain the status quo.
• Featuring three schools which cannot contribute to Council’s net zero
commitments in its current form. 
To meet these objectives and help deliver change, this OBC examines viable options for
the delivery of:
• A new two stream primary school to accommodate 434 pupils with consideration
for an early-years facility.
• Reconfigured catchments to address the current underutilisation of the existing
high quality learning facilities in Johnstone.

Page 24

Johnstone Primary School Estate Outline Business Case  12
OFFICIAL-SENSITIVE
1.5. Summary of Routes Forward
Possible options for the future of Johnstone Primary considered 4 potential routes
forward against the requirements for change:
1 – Do Nothing
2 – Retrofit Auchenlodment, St Margaret’s and Thorn Primary Schools
3 – Rebuild Auchenlodment, St Margaret’s and Thorn Primary Schools
4 – Masterplan’ redesign of the primary school estate in Johnstone, reducing the
number of schools in the estate, merge catchments to better use existing quality
facilities, consider provision of a new combined school
Analysis of the routes forward are presented in full in the Economic Case in Section 3.
This was produced following the collation of background information included in the
SCC, technical information, and analysis of the operating context of the Johnstone
primary school estate, as well as engagement with school staff and parents. 
1.6. Preferred Route Forward and Options Shortlist
The preferred route forward for the project has been determined using the critical
success factors identified in the SCC, to assess the viability of the various options under
consideration. This identified that delivery of change for primary school provision in
Johnstone was dependent on making the best use of existing good quality school
buildings to adapt to demand and ensure optimal occupancy across all schools. 
The routes forward and options rationale are discussed in greater detail in Section 3,
Economic Case, below, and this includes an overview of estimated costs for delivering
the project.
The preferred route forward was presented at an update to the ECSPB in October 2025,
as follows:
Route 4:  Masterplan Redesign of the Primary School Estate in Johnstone 
Address the overprovision of primary school places in Johnstone and the requirements of
the 3 priority schools of Thorn, Auchenlodment, and St Margaret’s, by:

Page 25

Johnstone Primary School Estate Outline Business Case  13
OFFICIAL-SENSITIVE
• Making best use of capacity of existing high-quality buildings including St Anthony’s,
West Johnstone Joint Campus, and Fordbank. 
• Considering the location of any new build school facility that would look to combine
more than one existing school on the same site
• Considering the most appropriate catchment area configurations to support efficiency
and capacity. 
Section 3 of this business case provides an analysis of the issues facing the Learning
Estate in Johnstone and the potential solutions. Based on the multiple factors under
consideration, it is recommended that the following options are taken forward for
further detailed exploration at Full Business Case. 
a) Merge Thorn and Auchenlodment catchment areas, combining both non-     
denominational schools in a single modern building by one of the following
means: 
1. Site 01 - Retrofit and extend the existing Auchenlodment Primary School building
to provide a modern 2 stream primary school with capacity for 434 pupils at
Aspen Place, Johnstone 
2. Site 01 – Construct a new build 2 stream primary school with capacity for 434
pupils at the existing Auchenlodment primary school site at Aspen Place,
Johnstone 
3. Site 04 - Construct a new build 2 stream primary school with capacity for 434
pupils, at the site of the existing Thorn Primary, Thorn Brae, Johnstone 
4. Site 09 - Construct a new build 2 stream primary school with capacity for 434
pupils on a new Site at Poplar Avenue, Johnstone 
b) Merge Cochrane Castle and Fordbank catchment areas, combining both non-
denominational schools at the current Fordbank Primary School site. 
c) Merge St Margaret’s and St David’s catchment areas, combining both    
denominational schools at the West Johnstone Joint Campus, creating a single
denominational school.
Note: St Anthony’s Primary is not affected by the proposed options as it is a high quality
building operating at optimal capacity. Further detail is given in section 3.

Page 26

Johnstone Primary School Estate Outline Business Case  14
OFFICIAL-SENSITIVE
1.7. Indicative Costs
To identify an indicative planning cost for delivering options associated with the
preferred route forward, an exercise was conducted to consider the potential cost of
delivering a school project at the identified planning scale (a two-stream primary school
with early years provision, and additional community-use space).
The site of the current Auchenlodment Primary School was used as an example for
costing purposes, being a site wholly owned by the Council. 
The overall potential costs of a new primary school associated with the route forward
are as follows: 
Cost scenario Range
Retrofit Auchenlodment and extend, for 434 pupils and
early-years facility matching current provision. £35 - £45m
Build a 2-stream primary for 434 pupils, and early-years
facility that matches current provision. £25 - £45m
Table 2: Indicative costs 
The indicative costs above are provided for illustrative purposes only. Costs are subject
to change depending on consultation, design changes, planning requirements and
parameters, site locations and geotechnical site characterisation, procurement routes
and other external factors. Further detail can be found within section 3.9 (Economic
Case) and Section 5.4 (Financial Case) of this document.

Page 27

15
OFFICIAL-SENSITIVE
1.8. Timeline
In 2025 a high-level summary of the timeline for completing this business case process was outlined, as shown below. This
timeline is explained in more detail in section 3 of this document to show a potential route to construction.

Page 28

16
OFFICIAL-SENSITIVE
2. STRATEGIC CASE
2.1. Strategic Context
In August 2025, a business case presented to E&CS Policy Board set out the strategic
case for change to primary school provision in Johnstone. The paper outlined the
background and context, highlighting links to local and national strategies for
education, including Renfrewshire Council’s Learning Estate Strategy and Fairer
Renfrewshire policy, and Scottish Government’s National Learning Estate Strategy.
The strategic objective for this project is to ensure delivery of the best quality learning
environments for primary pupils in Johnstone whilst ensuring that capacity matches
demand for school places, both now and in the future. This OBC takes that initial case
for change and begins the process of identifying options for change in response to the
needs and drivers identified. The policy background is summarised below. 
• Renfrewshire Council Learning Estate Strategy – a long-term structured
approach to assessment of the learning estate through a prioritisation
framework which identifies those areas of the estate most in need of investment.
The strategy ensures careful planning to ensure that limited capital investment is
directed where it will have the greatest impact through reshaping, refurbishing
or replacing existing facilities. 
• Scottish Government’s National Learning Estate Strategy – reflecting the
ambition of the Scottish Attainment Challenge, which promotes equity in access
to quality education facilities as part of a drive to tackle the poverty related
attainment gap and promote inclusivity.
• Fairer Renfrewshire – recognising the role of the learning estate in reducing
inequalities and improving the life chances of pupils across Renfrewshire
• Strategic Planning and Investment – recognising the long-term nature of the
strategy for the learning estate, with a clear framework which identifies those
schools that require replacement, refurbishment or upgrading
• Strategic Property Strategy – seeks to ensure that Renfrewshire Council’s
property estate is strategically located and used to its fullest potential,
complementing existing facilities and services wherever possible.

Page 29

Johnstone Primary School Estate Outline Business Case  17
OFFICIAL-SENSITIVE
2.2. The Need for Change
As articulated in the Strategic Case for Change document which preceded this business
case, there is a clear and compelling case for introducing change to primary school
provision in Johnstone, as highlighted by a combination of factors, including: 
• Overprovision of primary school places – Johnstone primary schools have a current
planning capacity of 1,841 pupils, with demand for 1,259 places (68% of capacity) 
• Condition and Suitability – As identified in the Learning Estate priority matrix,
Auchenlodment, St Margaret’s and Thorn suffer from a mixture of poor condition and
poor suitability, challenging the ambition to ensure all pupils have access to modern,
accessible and good-quality learning environments 
• Opportunity to maximise operational efficiency – Provision of a school built to
modern teaching and building standards will help increase building operational
efficiency by replacing ageing facilities which cannot meet modern building
performance standards.
2.3. Investment Objectives
The following objectives have been identified as key to improving primary school
provision in Johnstone and aligning with the ambitions of the Learning Estate Strategy:
• Effectiveness – Meet the aims of the Council’s Learning Estate Strategy to initiate a
strategic programme of investment in schools; Ensure that every school is considered
in terms of Scottish Government Core Facts reporting criteria; Deliver the best
learning environments and facilities possible, exceeding, where able, Scottish
Government recommendations. 
• Efficiency – Provision of modern learning environments to support improving
attainment for pupils in Renfrewshire.
• Economy – Optimise operating costs for the estate through the creation of buildings
which are more energy efficient and through operation of a more efficient overall
school estate; Offer a reduction in the costs incurred maintaining ageing buildings;
Operation of buildings of a size suited to current and projected school rolls.
• Compliance – Careful planning for the replacement or refurbishment of schools to
lessen the impact from older buildings and make a valuable contribution to

Page 30

Johnstone Primary School Estate Outline Business Case  18
OFFICIAL-SENSITIVE
Renfrewshire Council’s net zero commitments through the operation of more
efficient buildings.
• Replacement – The project acknowledges that as buildings age and maintenance
costs increase, they come closer to the point of being no longer fit for purpose as a
Council asset.
2.4. Existing Arrangements
A comprehensive overview of each primary school in Johnstone featured in the
Strategic Case for Change and a link is available at the beginning of this report under
‘Supporting Documentation’. The key facts relating to the operation of primary schools
in Johnstone are outlined in the following tables and narrative.
There are seven primary schools, four non-denominational and three denominational,
presenting a range of condition and age. Two of the primary schools form a joint
campus and are among the three schools built and maintained under public-private
partnership (PPP) in 2007; Four have early learning and childcare provision (ELCC) on-
site. Additionally, Johnstone has a standalone ELCC establishment. Two primary
schools feature a flexible learning resource (FLR), catering to pupils with additional
support needs (ASN) who do not attend either of Renfrewshire’s dedicated ASN schools. 
Whilst this Outline Business Case focuses on primary school provision in the Johnstone
catchment, it recognises that changes to the primary estate will also affect Early Years
provision. This is especially relevant where Early Years facilities are located within
priority primary school sites, such as St Margaret’s and Auchenlodment. The full
implications for Early Years provision will be assessed at the Full Business Case stage.
This will ensure that Early Years facilities remain consistent, appropriate, and aligned
with the Council’s learning estate strategy while improving the overall learning
environment.
The current planning capacity for Johnstone’s primary schools is 1,841 pupils (1143 or
57% non-denominational, 758 or 43% denominational). As of November 2025,
Children’s Services report that the current roll across all seven schools amounts to
1,218 pupils (689 non-denominational, 529 denominational). Therefore, it can be seen
that between them, Johnstone primary schools have 623 unfilled places, or in
percentage terms, can be seen as working at 66% of capacity. 57% of the current roll
attend non-denominational schools, 43% attend denominational schools.

Page 31

Johnstone Primary School Estate Outline Business Case  19
OFFICIAL-SENSITIVE
Key facts and operating costs for Johnstone Primary School Estate are as follows: 
Table 3: Capacity and Roll Information
The following tables sum up key facts and operating costs for primary schools in
Johnstone. 
School Age Suitability Condition ELC FLR
Auchenlodment 64 B C Y N
Fordbank* 17 A B N Y
St Anthony’s 57 B A Y Y
St Margaret's 65 B B Y N
Thorn 36 C C N N
WJJC* 17 A B Y N
*PPP schools
Table 4 – Johnstone Primary Schools Key Facts 
School Capacity Current Roll 2029/30* 2033/34* 2037/38*
Auchenlodment 302 207 (68.5%) 262 (87%) 272 (90%) 270 (89%)
Cochrane Castle 189 103 (54%) 98 (52%) 115 (61%) 109 (58%)
Fordbank 345 245 (71%) 218 (63%) 194 (56%) 185 (54%)
St Anthony’s 302 280 (93%) 286 (94%) 270 (89%) 257 (85%)
St David’s 189 81 (43%) 87 (46%) 109 (57%) 104 (55%)
St Margaret's 272 165 (61%) 155 (57%) 156 (57%) 147 (54%)
Thorn 272 134 (49%) 103 (38%) 90 (33%) 83 (31%)

Page 32

Johnstone Primary School Estate Outline Business Case  20
OFFICIAL-SENSITIVE
School Utilities Hard &
Soft FM Teaching Non-
Teaching* Other^ Rates Total
Auchenlodment £85,022 £247,491 £881,220 £450,653 £7,353 £40,800 £1,712,539
Fordbank £81,499 £1,339,512 £1,394,733 £187,256  £96,000 £3,099,000
St Anthony’s £84,024 £291,433 £1,508,912 £269,934 £74,832 £60,360 £2,294,495
St Margaret’s £30,933 £155,202 £749,005 £667,418 £43,293 £36,000 £1,684,276
Thorn £51,237 £127,568 £744,555 £74,749 £10,888 £25,920 £1,632,586
WJJC £112,838 £2,352,296 £1,320,359 £160,724  £129,600 £4,075,817
*includes ELC where present
^Waste; Grounds Maintenance; Transport; School Crossing Patrollers
£14,498,713
Table 5: Overview of Operating Costs 
School Teaching Non-Teaching Total
Cochrane Castle £759,659 £81,960 £841,649
St David’s £560,700 £639,464 £639,464
ELCC 0 £882,879 £882,879
Table 6: WJJC Staff Costs Breakdown

Page 33

Johnstone Primary School Estate Outline Business Case  21
OFFICIAL-SENSITIVE
Primary School No. of Pupils Cost
Auchenlodment 0 0
Cochrane Castle 0 0
Fordbank 0 0
St Anthony’s 75 £62,912
St David’s 0 0
St Margaret’s 10 £28,425
Thorn 0 0
Total: 104 £91,337
Table 7: School Transport Costs by School 
2.5. Initial Engagement 
Following presentation of the Strategic Case for Change to E&CS Policy Board in August
2025, officers undertook initial community and stakeholder engagement, outlining the
processes involved in identifying opportunities to deliver change.
A survey was issued to parents and carers, members of the community, and all school
staff at primary schools in Johnstone, inviting views around current school provision,
including school condition, location of facilities and what stakeholders feel should be
important to the Council in progressing future school investment.
Analysis of responses from parents, carers and the wider community identified the
following key themes and discussion points:  
• Building Maintenance and Facilities – The need for modern, well maintained school
building and improved sports infrastructure.
• Playground and Outdoor Spaces – An emphasis on the importance of well-
maintained playgrounds and outdoor learning spaces that encourage physical
activity and wellbeing.

Page 34

Johnstone Primary School Estate Outline Business Case  22
OFFICIAL-SENSITIVE
• Accessibility and Inclusivity – The importance of inclusive environments that
support children with additional needs and ensure accessibility for all.
• Safety and Traffic Concerns – Safety during school drop-off and pick-up, especially
regarding traffic congestion and unsafe parking near schools. 
Responses from school staff highlighted recommendations based on similar themes: 
• Invest in modernising outdated buildings and facilities
• Improve outdoor learning and play areas with better drainage and equipment
• Ensure adequate breakout spaces and sensory room for pupils with additional
needs
• Enhance heating, ventilation and lighting systems
• Provide secure and accessible drop-off/pick-up zones
• Engage staff and community in future planning and design decisions
Both parents and staff identified strong appreciation for the modern, bright, and
accessible facilities at Fordbank PS and St Anthony’s PS, reinforcing a clear link
between building quality and positive user experience. Across the estate, stakeholders
consistently emphasised the need for improved outdoor provision, including
resurfaced playgrounds, safer active travel routes, better sports facilities, and sheltered
all weather learning spaces. Families also stressed the importance of inclusive
environments, highlighting a growing need for sensory spaces, regulation areas, and
dedicated support provision for neurodivergent and ASN pupils. Staff reinforced this,
calling for well-designed classroom layouts (avoiding open plan), breakout spaces, and
modernised infrastructure to support learning, wellbeing, and behaviour regulation.   
2.6. Scope and Service Requirements
The scope of this proposal for change is to configure primary school provision in
Johnstone in line with the strategic objectives set out and agreed in the Strategic Case for
Change and informed by an understanding of the operating context at each primary
school. Potential routes forward were set out in an interim update to E&CS Policy Board
in October 2025, based on the broad range of options outlined in the Economic Case,
below. The potential routes are summarised here:

Page 35

Johnstone Primary School Estate Outline Business Case  23
OFFICIAL-SENSITIVE
Route 1 Route 2 Route 3 Route 4 
Do nothing – continue
to operate primary
schools in Johnstone
as they currently are 
Retrofit/Refurbish
Auchenlodment, St
Margaret’s and Thorn
primary schools 
Rebuild
Auchenlodment, St
Margaret’s and Thorn
primary schools on
their current sites
‘Masterplan’ redesign
of the primary school
estate in Johnstone,
reducing the number
of schools in the
estate, merge
catchments to better
use existing quality
facilities, consider
provision of a new
combined school
Table 8: Potential Routes Forward

Page 36

Johnstone Primary School Estate Outline Business Case  24
OFFICIAL-SENSITIVE
3. ECONOMIC CASE
3.1. Potential Routes Forward
Each of the routes forward has now been subject to an assessment process to identify
their broad advantages and disadvantages, to better assess the overall merits of each
option.
This process allows for the identification of recommended viable routes to be
progressed in more detail to establish a long list of options to be considered. In the case
of Johnstone Primaries, the analysis outlined below identifies there is only a single
recommended viable route forward from which a long list of potential options has been
identified. The recommended route forward is: 
Route 4: Masterplan redesign of the Primary School Estate in Johnstone 
The routes forward are examined in detail below.
Route 1: Do nothing
Continue to operate all primary schools in Johnstone as they currently are with minimal
wind and watertight investment. This includes: Auchenlodment, St Margaret’s and
Thorn Primary Schools which have been identified as priorities for investment, as well
St Anthony’s, St David’s, Cochrane Castle, and Fordbank Primary Schools. 
Main Advantages:
Value for money  • Lower capital outlay required, albeit significant future capital outlay will still be
required on building maintenance to secure long term wind and watertight
condition, and to support net zero transition, none of which would support
improvement to configuration or suitability for delivering the curriculum. 
Main Disadvantages:
Strategic Fit  • Does not achieve ambition of Learning Estate Strategy with regards to condition or
suitability of schools. 
• Underestimates the challenges posed by the current condition and layout of the
school buildings and the challenge of improving the learning environments.
• Although St Margaret’s predates minimum space requirements under School
Premises (General Requirements and Standards) (Scotland) Act 1967, and BB103

Page 37

Johnstone Primary School Estate Outline Business Case  25
OFFICIAL-SENSITIVE
Area Guidelines for Mainstream Schools, it should be stressed that the site is
severely constrained, with little usable outdoor space and the school would not be
built to its current size and extent if planned now.
• No benefit to the wider community can be derived from this option. 
Value for Money  • Will create an additional burden on the ongoing maintenance required of these
buildings which will have limited long term life given their age.  In addition, further
investment would be required to support long term net zero ambitions.
• Schools in Johnstone will continue to operate below optimal occupancy offering
poor value for money in the long term.
• This option would continue to see a very high standard of PPP school estate in
Johnstone underutilised, with significant financial outgoings associated with the
ongoing operation of these schools. 
Conclusions:
This option would bring no benefit to the school or wider community and would not serve to improve the
education experience of anyone involved and is likely to provide poor long term value for money given the
age and condition of the existing school.  
The primary school estate in Johnstone would continue to operate at inefficient levels, with roll
projections showing a further decline is to be expected across the area. With regards to the PPP estate
(Fordbank, Cochrane Caste, and St David’s – significant financial outlay is required each year to operate
these, and this option would not work to make best use of these very high standard buildings.  With the
disadvantages outlined above, this is not considered a viable option and will be discounted as a route
forward. 
Route 2: Retrofit Priority Schools in Johnstone
Carry out a comprehensive retrofit of the current buildings of Auchenlodment, St
Margaret’s and Thorn primary schools to bring them up to Net Zero Public Sector
Building Standards (NZPSBS) or better, whilst improving the overall condition and
suitability of the environments. 
Main Advantages: 
Strategic Fit • Contributes towards net zero ambitions through retention of embodied carbon
and improvements in energy consumption.
• Will allow buildings to be fully reconsidered to improve both condition and
suitability.

Page 38

Johnstone Primary School Estate Outline Business Case  26
OFFICIAL-SENSITIVE
Value for Money  •  Subject to detailed costing it may involve a lower capital outlay, although this
would require detailed analysis particularly given the dual costs of normal
wholescale refurbishment coupled with net zero retrofit requirements.
• Greater operational efficiency from a more energy efficient building
Main Disadvantages
Strategic Fit • Improvements to the site and external learning will be limited as any
improvements need to work with and around the existing site. 
• This option to retrofit would not address the over-provision of school capacity in
Johnstone and would result in the school capacity in operation with a declining
population.
• Although St Margaret’s predates minimum space requirements under School
Premises (General Requirements and Standards) (Scotland) Act 1967, and BB103
Area Guidelines for Mainstream Schools, please note that the site is severely
constrained, with little usable outdoor space; school would not be built to its
current size and extent if planned now.
Value for Money  • A net zero retrofit is a complex and demanding project requiring careful planning
and execution. although initial capital costs may be less in comparison to an
equivalent new-build, the costs will still be significant and the overall remaining
life of a refurbished building is likely to be less than a new build placing a level of
constraint on the long term value for money assessment.
Affordability  • The full extent of work required, and therefore cost, may only become fully
apparent as areas of the internal fabric of the building are exposed and a full
understanding of the buildings condition is apparent. This could result in the
divergence between refurbishment cost and new build cost being marginal and
ultimately impacting negatively on the whole life value for money appraisal. 
Achievability  • This option would involve significant disruption to the Johnstone primary school
estate with decants required for all schools during the extent of the works, or for
a very elongated and costly route to construction by working around current
building users. 
Conclusions:
This option is more attractive in terms of making the most of existing assets, retaining embodied carbon
and addressing Council commitments on net zero. However, the option would fail to address the
challenges around under capacity in the wider Johnstone school estate, and would present a missed
opportunity to deliver long term improvement in the learning estate for the community. Additionally,
although there may be the potential for a degree of short term affordability benefits, there is significant
uncertainty as to whether it would necessarily provide long term value for money and it would also be
highly disruptive to the school existing school community during the construction period.

Page 39

Johnstone Primary School Estate Outline Business Case  27
OFFICIAL-SENSITIVE
Further, it is noted that St Margaret’s Primary School does not meet current minimum space
requirements as per legislation, and would therefore be questionable as to why a significant investment
in such a school would be taken forward given it is too small for modern standards.
On this overall basis, this option should not be considered as a viable route forward. 
Route 3: New Build Schools for all identified Priority Schools
Rebuild Thorn, Auchenlodment and St Margaret’s primary schools on their current sites,
to an appropriate reduced capacity, to continue as standalone primary schools. Retain
St David’s, Cochrane Castle, Fordbank and St Anthony’s primary schools as they are
now. 
Main Advantages:
Strategic Fit  • This would deliver a new schools built to modern educational and
building standards, of a size that allows for optimal occupancy and
deliver assets with the longest potential operational life.
• It would directly contribute towards net zero ambitions through
provision of new schools built to NZPBS standard or better.
Value for Money • Creation of buildings with modern heating and power systems will
greatly improve operational efficiency and new build provides the
opportunity to secure learning facilities with the maximum future life to
support long term value for money benefits. 
Main Disadvantages:
Strategic Fit • Provision of 3 new schools and disposal of their predecessors may not
be as sustainable as retrofitting current structures. However, it is
recognised that new buildings would be designed and constructed in a
manner that significantly contributes to the net zero plan with energy
efficiency at the forefront. It is also possible that material from
demolished buildings could be used on new sites as in fill or for levelling
land.  
• Constructing three new schools would not address the ongoing over
provision of school places in Johnstone. To be able to deliver schools to
‘optimal capacity’ would require all three new build schools to be

Page 40

Johnstone Primary School Estate Outline Business Case  28
OFFICIAL-SENSITIVE
smaller than a single stream primary school (i.e. a school with 1 class
from primary 1 to primary 7 which equals a capacity of 217 places). Roll
projections show that all three schools are expected to fall well below
this figure of 217 therefore to build these schools at an ‘optimal’
capacity would require very small schools with combined year groups in
less than 7 classes. This would be a significantly limiting factor for
schools in such a tight urban geography.
• A new build project on the existing St. Margaret’s site would not meet
minimum space requirements under School Premises (General
Requirements and Standards) (Scotland) Act 1967, or BB103 Area
Guidelines for Mainstream Schools, and is therefore not a viable option –
a new site would be required. 
Value for Money  • Existing high-quality facilities at the West Johnstone Joint Campus, and
Fordbank, would remain underutilised, operating below optimal
capacity, therefore presenting poor value for money from the significant
financial outlay on PPP contracts.
Affordability  • This option would require considerable capital investment for single-
stream schools and would not offer best value for money given current
and projected demand across Johnstone as a whole and the wider
commitments of the Learning Estate Strategy.
• The investment required would limit council’s readiness to address
other priority schools identified through the learning estate strategy
Achievability  • This option would involve significant disruption to the Johnstone
primary school estate with decants required for all schools during the
extent of the works.
Conclusions:
Providing a new build property for each of the schools would require a significant capital cost and would
leave existing high-quality facilities underutilised and operating below optimal occupancy levels, with
continued excess capacity across the whole Johnstone Primary School Estate. Committing to the
replacement of three existing primary schools in like-for-like fashion may impact Renfrewshire Council’s
ability to maintain the necessary pace of investment in the Learning Estate Strategy. This route would
require new schools to be very small which will not provide best value with such close proximities of
schools. Further, with St Margaret’s site not meeting modern minimum space requirements, it would
require a new site to be identified for a new build school. This option should not be considered as a
viable route forward. 
Route 4: Masterplan redesign of the Primary School Estate in Johnstone

Page 41

Johnstone Primary School Estate Outline Business Case  29
OFFICIAL-SENSITIVE
This option would see the development of a wider master plan review and associated
proposals that would deliver a  reduced number of establishments and right-sized
overall school capacity across Johnstone This masterplan approach would secure the 
ambition of accommodating all primary school children in Johnstone in good quality
school accommodation, with high suitability for delivering the curriculum, that will
sustainably meet the educational needs across Johnstone over the long term and
support wider community needs. This option must consider the priority establishments
that require intervention as part of the Learning Estate Strategy prioritisation matrix.
These schools are Thorn, Auchenlodment, and St Margaret’s and options will consider: 
• Making best use of capacity of existing high-quality buildings including St
Anthony’s, West Johnstone Joint Campus, and Fordbank. 
• Consider the location of any proposed new build school facility that would look
to combine more than one existing school on the same site
• Consider the most appropriate catchment area configurations to support overall
efficiency and capacity to support the delivery of the best educational outcomes. 
Main Advantages:
Strategic Fit • Ensures that every pupil in Johnstone will be educated in modern, high-
quality condition schools. 
• Meets the requirements of Renfrewshire Council’s vision for education
and the objectives of the Learning Estate Strategy
• Contributes towards net zero ambitions through provision of a new
school built to NZPBS standard or better, with significant improvements
in energy consumption to the existing schools.
• Ensures all schools can work at optimal occupancy, reflecting changing
school rolls and demand.
• The sale of disused sites could bring capital receipts to the council.
Value for Money • Makes the most of existing high condition facilities including PPP estate
which attracts a high financial output each year to operate, offering
better value for money from the learning estate in Johnstone
• Offers opportunities to improve Early Years and additional support
needs provision in Johnstone through better use of existing space.
• Greater operational efficiency from a more energy efficient building of a
size that allows for optimal occupancy
Affordability • Appropriate levels of capital spend required through the provision of a
whole area master planned new build option, and making better use of
existing high-quality assets provides the best opportunity to
strategically develop and identify the most effective solution to meet the

Page 42

Johnstone Primary School Estate Outline Business Case  30
OFFICIAL-SENSITIVE
long term needs of Johnstone in a manner that consider need across the
whole geography and will minimise unnecessary spend. 
Main Disadvantages:
Achievability • Potential need to decant pupils during new build element if a current
school site was selected, could bring disruption during this period,
albeit the scale of disruption of this option is significantly lower than
alternative options presented.
• Proposals to merge schools and or catchments areas present concerns
linked to the expectations and aspirations of parts of the school
community.
Conclusions:
This holistic master planned option provides the opportunity to identify a more efficient use of existing
quality learning environments, whilst addressing overprovision of capacity in Johnstone as a whole. The
implementation of a new build school option to accommodate more than one existing school will also
directly support addressing all objectives of the Learning Estate Strategy and works to significantly
improve the experience of all users of current poor condition buildings. 
This option would see current high-quality buildings utilised in an efficient way, making best use of the
assets, and ultimately will work to ensure that every primary pupil in Johnstone is educated in a high-
quality building, suitable for delivering the modern curriculum. 
This option and specific configurations within it should be further considered in the OBC process as
the preferred route forward. 
3.2. Preferred Route Forward
A qualitative assessment of the potential routes has provided commentary on their
practicality, adaptability and desirability, aligned to the critical success factors outlined
in the Strategic Case for Change. This identified those that do not offer a viable means
of delivering the required change and confirmed a preferred way forward for the
project:
Route 4:  Masterplan Redesign of the Primary School Estate in Johnstone

Page 43

Johnstone Primary School Estate Outline Business Case  31
OFFICIAL-SENSITIVE
Address the overprovision of primary school places in Johnstone and the requirements of
the 3 priority schools of Thorn, Auchenlodment, and St Margaret’s, by:
• Making best use of capacity of existing high-quality buildings including St Anthony’s,
West Johnstone Joint Campus, and Fordbank. 
• Considering the location of any new build school facility that would look to combine
more than one existing school on the same site
• Considering the most appropriate catchment area configurations to support efficiency
and capacity. 
This route forward was recommended and agreed following an update to the ECSPB in
October 2025.
One of the objectives of the Learning Estate Strategy is to have Renfrewshire schools,
where possible, operating at between 80-95% of capacity. As noted in the assessment of
the option to retrofit all priority schools, this would not address capacity and would
leave the same number of schools in the town in very close proximity operating
significantly under capacity and would require vast capital outlay. 
The question can therefore be asked as to why the option to rebuild all priority schools
as new, smaller schools, is not viable. The reason for this is that by building schools to a
smaller size to match projected future rolls, which are largely expected to continue to
drop, and have these schools working to ‘optimal capacity’ the size of schools would
require to be very small. In some cases, smaller than a single stream primary school (i.e.
a school with a single P1-P7 class, per year). To be working efficiently against capacity
in this scenario, schools would need to be built with classes working in combined year
groups in the same classroom. This would be a significant limiting factor for schools in
such a tight urban setting. 
By way of an example, Thorn Primary School projected school roll is expected to drop
as low as 82 pupils. A new build school for less than 100 pupils in a populated core town
of Renfrewshire, costing multiple millions of pounds, could not be justified as best value
considering there are currently 7 primary schools operating in the area. 
This confirms that there is a compelling case to focus attention on options within Route
4 – Masterplan redesign of the primary estate in Johnstone.

Page 44

Johnstone Primary School Estate Outline Business Case  32
OFFICIAL-SENSITIVE
3.3. Exploring Issues with the Johnstone Estate and Possible Solutions
When redesigning the Johnstone Primary Estate, it is essential to consider the following
elements holistically, as any change to school building condition, locations, catchments
and pupil rolls may have an impact elsewhere:
• Making best use of capacity at existing high-quality buildings including St Anthony’s,
West Johnstone Joint Campus, and Fordbank. 
• Considering the location of any new build school facility that would look to combine
more than one existing school on the same site
• Considering the most appropriate catchment area configurations to support efficiency
and capacity. 
Current School Estate
To address the issues facing the Johnstone school estate and identify options from the
preferred route forward, it is important to consider the current location and makeup of
the primary schools in Johnstone.
Of the six primary school buildings in Johnstone, highlighted on the map below, it can
be seen that the existing modern and high quality school buildings are clustered to the
centre/south-west of the town. These comprise of 2 non-denominational, and 2
denominational schools - St Anthony’s and St David’s primary schools, and Cochrane
Castle and Fordbank. Cochrane Castle and St David’s Primaries share the modern West
Johnstone Joint Campus. 
The three priority school buildings, identified through the Learning Estate Strategy all
lie to the north and east of Johnstone - Auchenlodment, Thorn and St Margaret’s. This
strongly indicates that any new build facility should be located to the north or east of
the town to address the need for a modern facility in this area of Johnstone and avoid
over concentration of the majority of primary schools to the south and west of the
town.

Page 45

Johnstone Primary School Estate Outline Business Case  33
OFFICIAL-SENSITIVE 
Map 1:Existing School Locations 
The second factor to consider is the current catchment areas of primary schools in
Johnstone which is detailed below:  
Non-Denominational Catchment Areas
The maps below show the current catchment areas and concentration of those who
attend both Auchenlodment and Thorn Primaries in relation to the location of the
schools.
Current high quality
school building
School building on
priority list

Page 46

Johnstone Primary School Estate Outline Business Case  34
OFFICIAL-SENSITIVE
Map 2: Pupil concentrations - Thorn Primary School 
Map 3: Pupil concentrations - Auchenlodment Primary School

Page 47

Johnstone Primary School Estate Outline Business Case  35
OFFICIAL-SENSITIVE
The maps illustrate that the catchments of Thorn and Auchenlodment Primary Schools
are adjoining, with the majority of pupil draw residing within the catchment areas. Both
schools are at the eastern extremity of Johnstone, supporting the proposal that any
potential new school facility  to replace these priority schools should be located within
the current catchment area. 
Denominational Catchment Areas
The map below shows the current catchment area for St Margaret’s Primary, and the
concentration of pupils who attend the school. 
Map 4: Pupil concentrations – St Margaret’s Primary School
In line with the majority of denominational schools in the authority, the catchment area
serves a wide geographical area. St Margaret’s catchment is particularly large as it
includes a rural area with fewer residences. 
However, as illustrated in Map 4, above, the majority of the pupil draw for St Margaret’s,
whilst towards the centre and east of the town, is adjacent to the St David’s catchment
area and close to St David’s primary itself.

Page 48

Johnstone Primary School Estate Outline Business Case  36
OFFICIAL-SENSITIVE
Reflecting that the centre and south-west of Johnstone is already served by four
modern, high quality schools, and none of the priority schools to be addressed through
investment are in this area, it would not be considered appropriate for any option of a
further new build facility to be located in this geographical area of the town. Therefore,
it is recommended that any new build school to be constructed as part of the route
forward, should serve the north and east of the town. 
This approach will also better serve the wider Johnstone community by avoiding an
over concentration of school buildings, which are core community assets, in the centre
or southwest of the town. 
Taking account of these factors, this presents two possibilities for the new build
element of this masterplan route forward : 
a) A single new build joint campus for denominational and non-denominational
provision for the catchments of St Margaret’s, Thorn, and Auchenlodment primary
schools, clearly distinguishing the different non-denominational/denominational
schools with their own identity (on a site to be determined) 
b) A single new build non-denominational school for Thorn and Auchenlodment
Primary School catchment areas, on a site to be determined (see section 3.6) 
Considering a) above, moving St Margaret’s catchment to a new build joint campus
school would not address the overarching principles; of making best use of current
existing modern, high quality schools. At present the St Margarets catchment area
borders other denominational primary schools housed in high quality modern facilities,
which are currently operating significantly below capacity.
Therefore, it is recommended to further investigate options for a single new build non-
denominational school for Thorn and Auchenlodment Primary School catchment areas
only. This recommendation addresses the issue of the non-denominational Thorn and
Auchenlodment buildings.  
In this context, St Margarets remains a high priority school that requires attention.
However, analysis clearly demonstrates this priority can be addressed without the need
for provision of a new or refurbished building given the St Margaret’s catchment
borders that of St David’s, located at the West Johnstone Joint (WJJC) campus.

Page 49

Johnstone Primary School Estate Outline Business Case  37
OFFICIAL-SENSITIVE
St David’s is a high quality modern teaching environment however it is operating at only
43% of capacity.  To address the issue of undercapacity at St Davids and the WJJC as a
whole, it is possible to merge St Margaret’s Primary with St David’s Primary at the
West Johnstone Joint Campus, making better use of the high quality WJJC.
The section of the WJJC currently occupied by St Davids Primary is not sufficient to
accommodate both St Davids and St Margarets pupils together. The required capacity
can however be achieved by moving the non-denominational cohort of Cochrane Castle
out of the WJJC, allowing the WJJC to become a single denominational primary
housing both St Margarets and St Davids Cohorts. This is the only denominational
primary school building that is of high quality, with an adjoining catchment that can
accommodate the St Margarets cohort. 
St Anthony’s Primary school building is condition A and is not on the priority list.  The
school has a capacity of 302 and with 280 pupils it is currently at 93% capacity. 
Projections show the school roll is expected to drop slightly in the next decade;
however, capacity is projected to remain at above 85%. There is therefore no additional
capacity that would  allow any future  relocation or merger  within this existing facility.
Another of the town’s newer, high quality schools, Fordbank Primary, in the southwest
of Johnstone is currently operating at 70% of capacity, with this expected to drop to
56% by 2033-34. Given the very close proximity (0.7 mile) between Fordbank and
Cochrane Castle (WJJC), and to make better use of the Fordbank school, it is
recommended to merge Cochrane Castle with Fordbank primary housing both
cohorts at the existing Fordbank Primary School Building.  This has the added benefit
of releasing space at the West Johnstone Joint Campus to accommodate a single
denominational primary (as described above) and also leave additional space for
further flexible use. 
Summary of analysis
Based on this analysis of school locations, catchments, rolls and condition, officers
from Education and Children’s Services and Technical Services, have concluded that
the following 3 options should be explored in order to progress the masterplan
reconfiguration of the Johnstone Learning Estate.  These are:
1. Merge Auchenlodment and Thorn at a new-build or modernised site (to be
agreed), and merge catchments.

Page 50

Johnstone Primary School Estate Outline Business Case  38
OFFICIAL-SENSITIVE
2. Merge Cochrane Castle and Fordbank, at the current Fordbank Primary School
site, and merge catchments. 
3. Merge St Margaret’s and St David’s at the West Johnstone Joint Campus, creating
a single denominational school building, and merge catchments.
The following section looks at each option in more detail.
3.4. Masterplan Redesign of Johnstone Learning Estate
3.4.1. Merge Thorn and Auchenlodment at a new build or modernised site (to be agreed),
and merge catchments
Both Auchenlodment and Thorn Primary Schools have been identified as part of the
prioritisation list in the Learning Estate Strategy as both buildings are not viable in their
current form for the future of education provision. A rationale has been provided as part
of the assessment of the potential routes forward for why it is not appropriate to
consider constructing two new replacement schools for these catchments. This option
proposes to bring together both school catchments and merge the existing schools into
a single non-denominational school. 
The key consideration as part of this option, is the size and location of the school to be
constructed. Potential locations are set out with full analysis in following sections. To
inform the potential size of the single school, the following information has been
considered. 
Table 9: Auchenlodment and Thorn capacity and roll 
School Current
Capacity
Current Roll Projected
Roll 2029/30*
Projected
Roll 2033/34*
Projected
Roll 2037/38*
Auchenlodment 302 207 (68.5%) 262 (87%) 272 (90%) 270 (89%)
Thorn 272 134 (49%) 103 (38%) 90 (33%) 83 (31%)
Combined Totals 574 341 (59%) 365 (63% 362 (63%) 353 (61%)

Page 51

Johnstone Primary School Estate Outline Business Case  39
OFFICIAL-SENSITIVE
The above information demonstrates that whilst the Auchenlodment school population
is expected to grow reflecting the latest housing construction data that has been
included, the overall picture for non-denominational school places in the east of the
town of Johnstone between Thorn and Auchenlodment, is expected to continue to
operate significantly below optimal capacity. 
It should also be recognised that currently there are over 40 pupils who attend
Auchenlodment from out with the catchment through a placing request. Future
projection figures take into account the same volume of placing requests continuing to
be received for this school which contributes to a rising school roll. Whilst parental
choice exists for placing a child in a school where a space exists, school planning, and
admissions policies exist to protect this, where prioritisation should be given to those
who live in the catchment.  It is also widely recognised that schools should be built
based on the most efficient size and scale to serve its defined catchment, and schools
should not be built to an unnecessary oversized scale to accommodate historic placing
request patterns. 
Analysis of current primary school makeup of the town of Johnstone illustrates, where
schools are oversized for demand, this creates anomalies in catchment school
attendance where over 30% of children do not attend their catchment school. 
In the instance above, when considering the size and scale of the new build non-
denominational school for Johnstone, a definitive size will not be agreed until later
stages of project design and agreement. However, for the purpose of site selection, and
provisional analysis, all assumptions will be based on the following: 
• A ‘2-stream’ primary school which means a school that has two classes per year stage
(i.e. P1a, P1b, P2a, P2b etc.) 
• An early years provision of at least the scale of the current provision in Auchenlodment
Primary School. 
• Additional space to support community use, of which the use will be defined through
project development and engagement. 
Based on this information and provisional ‘2-stream’ primary school scope, this would
equate to 434 pupil places. This metric will be fully agreed as the project develops, as
this would suggest circa 80 places in excess of the projected demand. Equally, it is fully
recognised that contingency and flexibility are core elements of school planning, and
the final size of the school development will be defined at a later stage.

Page 52

Johnstone Primary School Estate Outline Business Case  40
OFFICIAL-SENSITIVE
3.4.2.  Merge Cochrane Castle and Fordbank located at the current Fordbank Primary
School site, and merge catchments
The second aspect of the masterplan reconfiguration promotes Cochrane Castle
Primary School catchment merging with the Fordbank Primary School catchment. 
Fordbank and Cochrane Castle are existing non-denominational schools and ‘gate to
gate’, each school sits in very close proximity at approximately 0.7 miles from each
other. 
The catchment areas border each other and are illustrated below: 
Map 5: Fordbank and Cochrane Castle Catchments

Page 53

Johnstone Primary School Estate Outline Business Case  41
OFFICIAL-SENSITIVE
In considering the relocation of Cochrane Castle pupils, to Fordbank, current pupil
residences were considered, as illustrated below. A significant portion of the school
population resides in close proximity to Fordbank, and the distance between each
school is largely insignificant in terms of distance compared to pupil residences:
Map 6: Pupil concentrations – Cochrane Castle 
Should catchment areas be merged, relocating Cochrane Castle to Fordbank, a revised
catchment area would be required, as illustrated below, with the dashed line
representing the current boundary between school catchments.

Page 54

Johnstone Primary School Estate Outline Business Case  42
OFFICIAL-SENSITIVE
Map 7: Meged catchment for Fordbank and Cochrane Castle 
Whilst proximity of schools and catchment areas is shown to be supportive of this
proposed change, the most important factor thereafter is the size and scale of the
revised Fordbank Primary school roll by accommodating Cochrane Castle school
catchment. The following table indicates the forecasted pupil projections for both
schools, and their combined total: 
Table 10: Cochrane Castle Fordbank capacity and roll
School Current
Capacity
Current Roll Projected
Roll 2029/30*
Projected
Roll 2033/34*
Projected
Roll 2037/38*
Cochrane Castle   189 103 98 115 109
Fordbank 345 245 218 194 185
Combined Totals 345 348 (100%) 316 (91%) 309 (89%) 294 (85%)

Page 55

Johnstone Primary School Estate Outline Business Case  43
OFFICIAL-SENSITIVE 
This information shows that currently, combining both schools with no intervention,
Fordbank would be at, or slightly in excess of 100% capacity based on the current
school rolls. There are however multiple factors that would support this move, as
follows: 
• The timing of any change would be subject to full statutory consultation and
conclusion of the business case process, meaning no change will take place
imminently. As time progresses, the school roll of both schools is expected to drop
which would help facilitate any change and as demonstrated above, the projected roll
suggests that the over the next 5-10 years the school capacity will move towards the
optimal 85% position.   
• Catchment areas would be fully reviewed and proposed as part of the next stage (Full
Business Case) and it could be possible to make minor adjustments to the catchment
boundary that sits on the eastern edge of the town, prior to any proposal of it
becoming the catchment of the new non-denominational primary school (currently
Thorn and Auchenlodment Primary School). A section of this catchment area could be
repurposed to be part of the new build school catchment, creating a better and more
efficient balance between both schools, and reducing the demand on Fordbank. 
• Currently Fordbank Primary School capacity does not account for three full size class
bases that accommodate a Flexible Learning Resource (FLR) for pupils with additional
support needs. It would be possible to relocate this provision to the West Johnstone
Joint Campus, which, as analysis shows, would have adequate surplus capacity even
when considering the proposed merging of both denominational schools (St
Margaret’s and St David’s). 
These factors will be fully explored as the business case process continues, however
they highlight that multiple avenues of flexibility exist to support this proposal, and it is
a viable masterplan option.
3.4.3. Merge St Margaret’s and St David’s, located at the West Johnstone Joint Campus,
and merge catchments.
The third aspect of the masterplan reconfiguration would follow on the merging of
Cochrane Castle Primary School catchment with Fordbank Primary School, allowing
West Johnstone Joint Campus, which houses St David’s Primary School, to become a
single denominational school. This would subsequently allow the catchment of St

Page 56

Johnstone Primary School Estate Outline Business Case  44
OFFICIAL-SENSITIVE
Margaret’s to merge with St David’s and be placed at the current St David’s Primary
School building. 
St Margaret’s and St David’s are existing denominational schools and again are in very
close proximity to each other. ‘Gate to gate’, each school sits approximately 0.6 miles
apart . 
The current catchment areas border each other and are illustrated below: 
Map 8: St Margarets and St Davids Catchment areas
In considering the relocation of St Margaret’s pupils to St David’s, the current pupil
draw for St Margaret’s Primary School has been considered, shown below. The
proximity of the schools is marked. Given the location of pupil residences, this change
would not impact the vast majority of pupils. 
Additionally, a significant portion of pupils who attend St Margaret’s do not live within
the catchment of the school, living within the St David’s or St Anthony’s catchment
areas.

Page 57

Johnstone Primary School Estate Outline Business Case  45
OFFICIAL-SENSITIVE 
Map 9: St Margaret’s catchment area
Should a merged catchment be progressed, to relocate St Margaret’s, a revised
catchment area for St David’s Primary School would be required, which would look as
follows, with the dashed line representing the current boundary of catchment between
schools, that would be removed:
Map 10: Merged catchment St Margaret’s and St David’s

Page 58

Johnstone Primary School Estate Outline Business Case  46
OFFICIAL-SENSITIVE
Whilst proximity of schools and catchment areas is shown to be supportive of this
proposed change, the most important factor thereafter is the size and scale of the
revised St David’s Primary school roll in accommodating St Margaret’s school
catchment. The following figures represent the forecasted pupil projections of both
schools, and what these would look like combined:
Table 11: St Davids and St Margarets capacity and roll 
The above information shows that, should Cochrane relocate to Fordbank Primary
School, the remaining capacity at West Johnstone Joint Campus would double to 378. 
These figures indicate that St Margaret’s could be comfortably merged with St David’s
today and still be significantly under current capacity. 
This additional space also offers further flexibility in the overall masterplan
consideration. As noted in Fordbank appraisal above, it would be possible to relocate
the existing FLR resource from Fordbank to St David’s, to utilise excess space, and
support accommodating Cochrane Castle to Fordbank. Additionally, a move of the FLR
to the WJJC would allow for an expansion of the FLR resource to meet any increase in
demand.
3.5. Early Years Provision
Whilst this Outline Business Case focuses on primary school provision across the
Johnstone area catchments, it is acknowledged that any proposed changes to the
existing Primary School learning estate will have an impact on the Early Years provision
across the catchment.  This will be of particular significance where provision forms part
School Current
Capacity
Current Roll Projected Roll
2029/30*
Projected
Roll 2033/34*
Projected Roll
2037/38*
St David’s 189 81 87 109 104
St Margaret's N/A 165 155 156 147
Combined Totals 189 + 189 of
vacant Cochrane
Castle capacity =
378
246 (65%) 242 (64%) 265 (70%) 251 (66%)

Page 59

Johnstone Primary School Estate Outline Business Case  47
OFFICIAL-SENSITIVE
of existing primary school sites which are listed as priority schools for investment. In
this case the existing St Margarets and Auchenlodment Primary Schools have dedicated
Early Years facilities on site.
The impacts on Early Years provision across the Johnstone area will be considered in
full at the Full Business Case Stage for the Johnstone Primary Schools. This will ensure
that provision of Early Years facilities remains consistent and appropriate whilst
delivering the aspirational outcomes of the Council’s learning estate strategy, creating
the best learning environments and facilities possible for both the Primary Schools and
Early Years provision across the Estate.
The above measures will be fully explored as the business case process continues,
however it confirms that it is a viable masterplan proposal. 
3.6. Site Assessment Criteria – Replacing Auchenlodment & Thorn Primaries
The preferred route forward indicates that viable options are dependent on
identification of a suitable site for the creation of a new school building for
Auchenlodment and Thorn. To identify potentially viable sites, a list of site assessment
criteria has been derived by considering core legislative, policy, and technical
considerations. A long list of potential site options has been assessed to identify sites
that present potential viability and warrant further investigation and feasibility
assessment. Note that this stage of the process is a broad pass / fail assessment of long
list options for viability purposes and is not a weighted scored assessment. A more
detailed assessment approach of this nature will form part of the next stage of the
business case process. The assessment criteria utilised are as follows: 
Ownership  Sites wholly within the ownership of Renfrewshire Council will be prioritised
over those owned by others recognising this provides greater certainty of
site deliverability. Consideration will be given to brown field sites where
remediation and use will be of benefit to the community, or where sites can
provide for the retention and or improvement of community facilities,
amenities or green spaces.
Site size/area Sites will be assessed against the median area requirements set out in BB103
as sufficient for a school of the following size and description:

Page 60

Johnstone Primary School Estate Outline Business Case  48
OFFICIAL-SENSITIVE
a) Accommodate a primary school of 434 pupils + early years facility and
additional community space, equating to 18,973m2 
Active Travel A review of sites in relation to their potential to support Active Travel,
proximity to public transport, road networks, cycling and walking routes; the
potential for increased pupil transport requirements.
Planning Sites will be assessed against current local & national planning policies and
current land area designation.
Placemaking Consideration will be given to potential for place making benefits, such as
community and green public spaces. Areas will be assessed for their context
within and connection to the local community and how strategic use of the
site could bring wider, long-term benefits to the area.
Flood Risk Sites will be assessed in line the guidance set out in Policy 22 of the NPF4.
Flood risk potential is common and significant across the Renfrewshire
estate and dependent on the scale of risk, will not necessarily result in the
rejection of a site. The level of risk and site history, along with the impact of
remediation and flood protection will all be considered in the assessment of
the site.
An assessment of site topography will examine factors that may affect the
efficient use of the site, including shape, gradients across and adjoining the
site, features such as water ways, culverts & previous uses. Previous
industrial use may bring issues of ground contamination or existing
buildings that need to be factored into site remediation.
Budget Budget considerations will principally be concerned with highlighting
potential additional costs for abnormal site issues.  For example,
construction on brown-field sites requiring ground remediation works for
ground contaminations. Projects in green or rural areas incurring additional
costs associated with installing utilities, and the construction or upgrade of
local road and pedestrian routes.
Commentary Any additionally significant issues that require consideration, such as
location within the catchment area. 
Table 12: Site Assessment Criteria 
The following 11 sites were identified as being within Council ownership and located in
Johnstone. The sites were considered against the criteria and the requirements for
change. A desktop assessment was completed for each site, which has concluded that
there are 3 options that have strong viability potential and are appropriate for further

Page 61

Johnstone Primary School Estate Outline Business Case  49
OFFICIAL-SENSITIVE
detailed examination and assessment at the next stage. A high level overview of all 11
sites is outlined below. This represents the longlist of site options to deliver the project.
Whilst the detail included in this business case has shown that it is not viable to
consider sites for a new build primary school to the centre or southwest of Johnstone, a
comprehensive exercise has been conducted across the breadth of Johnstone,
including sites that ultimately are not appropriate due to their location in the town.
Whilst these sites have been assessed, and the findings are presented below; they will
not be supported as viable options to proceed with.
Additionally, an exercise was also conducted to analyse areas of land in private
ownership in the town, to determine their potential viability to develop a new primary
school. It was concluded that there is no additional land in private ownership that offers
a better option than those sites in Council ownership and was therefore not progressed
any further.

Page 62

Johnstone Primary School Estate Outline Business Case  50
OFFICIAL-SENSITIVE
3.7. Site Options Assessment
11 sites within Council ownership have been identified and assessed. The location of the sites is shown on the map below. A full
assessment of all 11 sites then follows.
Map 11: Site Options

Page 63

Johnstone Primary School Estate Outline Business Case  51
OFFICIAL-SENSITIVE

Page 64

Johnstone Primary School Estate Outline Business Case  52
OFFICIAL-SENSITIVE

Page 65

Johnstone Primary School Estate Outline Business Case  53
OFFICIAL-SENSITIVE

Page 66

Johnstone Primary School Estate Outline Business Case  54
OFFICIAL-SENSITIVE

Page 67

Johnstone Primary School Estate Outline Business Case  55
OFFICIAL-SENSITIVE

Page 68

Johnstone Primary School Estate Outline Business Case  56
OFFICIAL-SENSITIVE

Page 69

Johnstone Primary School Estate Outline Business Case  57
OFFICIAL-SENSITIVE

Page 70

Johnstone Primary School Estate Outline Business Case  58
OFFICIAL-SENSITIVE

Page 71

Johnstone Primary School Estate Outline Business Case  59
OFFICIAL-SENSITIVE

Page 72

Johnstone Primary School Estate Outline Business Case  60
OFFICIAL-SENSITIVE

Page 73

Johnstone Primary School Estate Outline Business Case  61
OFFICIAL-SENSITIVE

Page 74

Johnstone Primary School Estate Outline Business Case  62
OFFICIAL-SENSITIVE
Site Summary 
Site No Site Name Strategy (New
build/Retrofit)
Recommended
to take forward
to FBC
Rationale
1 Existing Auchenlodment Primary
School Site, 
New Build/ Extend &
Retrofit
Yes The site benefits from being the established focal point for the local
community, providing primary school teaching, as well as nursery
and after school care. The heavy grading across the site raises
design challenges that may compromise design options; however,
the overall site area can accommodate this development through
careful design consideration. As this school lies in a tight
neighbourhood area, particular attention will be required on the
views of the local community for the impact this development may
have, and what benefits can be brought. 
2 Existing Johnstone High School
Site
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC
3 Existing St Margaret’s Primary
School Site, 
Extend / Renovate / New
Build
No The existing site is significantly undersized to accommodate a
modern primary school under BB103. Although a two-story design
or refurbishment of the existing school may improve the condition

Page 75

Johnstone Primary School Estate Outline Business Case  63
OFFICIAL-SENSITIVE
or sufficiency of the school, the external area is insufficient to
accommodate external learning, social and sports spaces that are
standard in education provision. This option is not recommended
for further consideration at FBC Stage
4 Existing Thorn Primary School
Site
New Build Yes The central location of the site within its catchment helps to
promote active travel, however the access point to the site requires
improvement. The triangular shape of the site places design
challenges to the development of an optimised design.
Development of the site will likely require compromise on the scale
of external learning, social and sports spaces. 
5 Former primary school site &
housing disposal site, Beith
Road – Greenend Avenue,
Johnstone
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC
6 Beith Road Playing Fields,
Johnstone 
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC

Page 76

Johnstone Primary School Estate Outline Business Case  64
OFFICIAL-SENSITIVE
7 Sites at Spateston Road
/ Hallhill Road, Johnstone 
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC
8 King George V Playing Fields,
Miller Street, Johnstone 
New Build No There is significant flood risk at the proposed site which would
require major engineering works to ensure that both the land and
buildings are sufficiently protected from flood risks - The cost of
such measures is considered prohibitive compared to alternative
options. This Site is not recommended for further consideration at
FBC
9 Poplar Avenue Playground,
Johnstone 
New Build Yes The site is well placed centrally within the Johnstone Castle
community and sits between the current Thorn and
Auchenlodment schools. It has a high level of permeability that
would support active travel routes. However, additional works,
interventions may be required to improve safe pupil routes
particularly where pupils need to cross Beith Road. Although there
is a gradient across the site it is not significant and should not
compromise design development.  Although a change of use in the
site would be a direct loss of amenity for the local community this
could be offset by the incorporation of shared space in the
development of a proposal. There is a high prevalence of on street

Page 77

Johnstone Primary School Estate Outline Business Case  65
OFFICIAL-SENSITIVE
parking which may need assessment, monitoring and additional
controls during a construction phase. 
10 Tannahill Playground, Tannahill
Crescent, Johnstone 
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC
11 Thomas Shanks Park,
Johnstone 
New Build No This site is located out with the catchment areas of Thorn and
Auchenlodment primaries and is therefore considered unsuitable
as part of the wider estate masterplan and reconfigured
catchments. This Site is not recommended for further
consideration at FBC
Table 13: site assessment summary 
Any site which is recommended for further investigation as a viable option will be subject to thorough legal checks around
ownership to ensure a full understanding of any constraints on development and its likely impact. Should any site require legal
processes to amend land designation this would be fully considered at the next stage of assessment and reflected in project
timelines where necessary.

Page 78

66
OFFICIAL-SENSITIVE
3.8. Shortlisted Options for new Thorn / Auchenlodment 
Based on the assessments, the following options can be deemed potentially viable
locations for a new build school merging Thorn and Auchenlodment. 
Option 01
Extend and refurbish the Existing Auchenlodment at Site 01 - Existing Auchenlodment Primary
School, Aspen Place, Johnstone
Option 02
New Build at Site 01 - Existing Auchenlodment Primary School, Aspen Place, Johnstone
Option 03
New Build at Site 04 - Existing Thorn Primary School, Thorn Brae, Johnstone
Option 04
New Build at Site 09 - Poplar Avenue Playground, Johnstone 
Table 14: Options Shortlist 
It is recommended that these options are taken forward to the next stage of assessment
at Full Business Case, to be considered as part of extensive engagement, and further
technical and cost analysis.
Of the four options above, two are variations of the same site, resulting in a shortlist of
three sites. These three shortlisted sites are shown in Map 12, below:

Page 79

Johnstone Primary School Estate Outline Business Case  67
OFFICIAL-SENSITIVE
Map 12: Shortlisted Sites
Any site which is recommended for further investigation as a viable option will be
subject to thorough legal checks around ownership to ensure a full understanding of
any constraints on development and its likely impact. Should any site require legal
processes to amend land designation this would be fully considered at the next stage of
assessment and reflected in project timelines where appropriate.
3.9. Indicative Costs
The indicative costs are based on preliminary information and should be considered a
framework from which detailed cost plans can be developed. The indicative costs have
been built from high level information, benchmarking from various sources including
the Scottish Futures Trust (SFT) funding metric, cost information from current
Renfrewshire Council education construction projects, costs from other Council’s
similar school projects and adjusting the costings where specific knowledge has been
gained from the desktop assessment of the site options. The BCIS cost indices have also
been used to calculate inflation up to the end of the anticipated construction period.

Page 80

Johnstone Primary School Estate Outline Business Case  68
OFFICIAL-SENSITIVE
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicate what is assumed as included
in the costs and what is excluded at this stage.
To project an estimated cost for inflation purposes, the construction cost has been
based on an assumed construction commencement date of 2030. All figures should be
noted as exclusive of VAT.
Key assumptions and exclusions were used in compiling the indicative costs in the
absence of any design commencing. This approach recognises that whilst a range of
cost estimates have been presented, these remain volatile, subject to external factors
and site specific detail that will become clearer as sites are investigated, and options
further explored at the next stage.
It is important to highlight as part of this process, that no budget will be requested or
crystalised until further work has been undertaken into the validation of each option,
and a recommendation is made thereafter at the conclusion of the Full Business Case. 
As shown previously in Table 3, the indicative costs are as follows:

Page 81

Johnstone Primary School Estate Outline Business Case  69
OFFICIAL-SENSITIVE
Cost scenario  Range
Retrofit Auchenlodment and
extend, for 434 pupils and early-
years facility matching current
provision.
£35 - £45m
Build a 2 stream primary for 434
pupils, and early-years facility
that matches current provision
£25 - £45m 
3.10. Transport Considerations
Renfrewshire Council policy states that primary school pupils who live more than one
mile away from their catchment school by the shortest safe walking route, are eligible
for home to school transport. 
The following tables shows current rates of eligibility for school transport on the basis
of the options proposed in the OBC, for the existing school sites and the potential new
sites outlined above. 
3.10.1. Merged Thorn and Auchenlodment
Based on pupil census data for 2025/6, of the pupils who reside within the catchment
and attend the catchment school, no pupils are eligible for school transport for either
Auchenlodment or Thorn Primaries.  If the catchments were to merge, based on this
data it would change as shown below. This does not take into account the expected roll
increase at a new merged school and is based on 2025-26 data for comparison only.

Page 82

Johnstone Primary School Estate Outline Business Case  70
OFFICIAL-SENSITIVE
Current School Site Pupils Eligible
Thorn PS 0
Auchenlodment PS 0
Proposed School Site Pupils Eligible
New school at site 1 –
Auchenlodment  36
New school at site 4 –
Thorn 53
New school at site 9 –
Poplar Avenue 0
Table 15: Transport eligibility Thorn/Auchenlodment   
3.10.2. Merged Cochrane Castle and Fordbank
Based on pupil census data for 2025/6, of the pupils who reside within the catchment
that attend the catchment school, no pupils are eligible for school transport for either
Cochrane Castle or Fordbank Primaries.  If the catchments were to merge, based on this
data it would change as shown below.  This does not take into account the expected roll
increase at a new merged school and is based on 2025-6 data for comparison only. 
Table 16: Transport eligibility Cochrane Castle/Fordbank 
Current School Site Pupils Eligible
Cochrane Castle 0
Fordbank 0
Proposed School Site Pupils Eligible
Fordbank, incorporating
Cochrane Castle 36

Page 83

Johnstone Primary School Estate Outline Business Case  71
OFFICIAL-SENSITIVE
3.10.3. Merged St Margaret’s and St David’s
Based on pupil census data for 2025/6, of the pupils who reside within the catchment
that attend the catchment school, 10 pupils are eligible for school transport for St
Margarets and none for St Davids.  If the catchments were to merge, based on this data it
would change as shown below. This does not take into account the expected roll
variation at a new merged school and is based on 2025-26 data. 
Current School Site Pupils Eligible
St Margaret’s 10
St David’s 0
Proposed School Site Pupils Eligible
West Johnstone Joint Campus 57 
Table 17: Transport Eligibility St Margaret’s/St David’s

Page 84

72
OFFICIAL-SENSITIVE
3.11. Timeline and Next Steps
Should the recommendations contained in this OBC be approved, officers will commence work to identify and recommend
a preferred option for a new building for Auchenlodment and Thorn Primaries. 
The next steps in that process are to complete a Full Business Case articulating the recommended option by the end of
2026, for presentation and agreement early in 2027. If approved by Council, work would begin on Statutory Consultation to
be carried out during 2027. Timescales would be dependent on timing around Local Government elections scheduled for
May 2027 and completion of the associated RIBA stages, with the current anticipated timeline showing that construction
could commence by 2030.

Page 85

73
OFFICIAL-SENSITIVE
4. COMMERCIAL CASE
4.1. Approach
An overarching procurement strategy will be prepared as the Project develops, and a
preferred option for delivery is identified. The strategy will set out the various contracts
required to deliver the project including the proposed procurement route, contract
objectives, tender methodology and timelines. Pre-market engagement and
consultation will be undertaken to ensure a detailed market analysis is completed to
test the suitability of the proposed approach to procurement and ensure proposals are
attractive and viable for the competitive market. 
The Project procurement strategy will remain a live document, updated to reflect the
outcomes of each stage of the project’s development and responsive to changes in
market conditions identified through analysis and ongoing engagement. Bespoke
contract strategies will be developed for each requirement detailing the specific
requirements and tendering methodology adopted for that contract while aligning with
the overall aims and objectives set out in the overarching strategy.
4.2. Service Requirements
The project team require external consultants to provide specialist services and works
to support the development of the Full Business Case. Services required may include
support with space planning, site surveys, intrusive building surveys, legal and planning
advisers and cost consultants.  The Project team will work with dedicated procurement
officers to develop strategies for each contract requirement with consideration to the
Council’s standing orders relating to Contracts and principles of best value.
4.3. Project Development
Procurement strategy will be developed for the FBC stage that will discuss in detail the
most beneficial route to market depending on the proposed final recommendation.

Page 86

Johnstone Primary School Estate Outline Business Case  74
OFFICIAL-SENSITIVE
The procurement process for the detailed design and construction stages of the project
is subject to development. The Council is looking at a range of options including
framework routes for procurement of consultants and/ or contractors. In the event
there are no suitable existing arrangements to use, it is anticipated options will be as
follows:
• Multi- disciplinary design team (MDDT) procured using Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. 
• Construction works contract, likely to follow a Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. It is likely to be a 2-stage
contract model with pre-construction services agreement (PCSA) to allow early
contractor involvement followed by award of main works contract once detailed
design is complete. 
• Ad-hoc/specialist consultant support may be required to support the project
team. The project team will work with dedicated procurement officers to
develop a strategy for each contract with consideration to the Council’s standing
orders relating to Contracts and principles of best value.

Page 87

Johnstone Primary School Estate Outline Business Case  75
OFFICIAL-SENSITIVE
5. FINANCIAL CASE
5.1. Project Funding – Capital Expenditure
Until such time that a specific option has been decided to proceed with at the
conclusion of the business case process, no formal project exists and therefore no full
capital budget exists. The purpose of this business case process is to allow a decision to
be made on the best option to commit capital expenditure on, and only at the
conclusion of the process will a request be made to Council to commit to the required
project budget. 
This OBC has outlined the current estimated cost to deliver on the agreed route
forward, and this estimate will continue to be refined and updated as more detail
becomes available at the next stage of assessment. 
5.2. Approvals Process
To date, work to develop proposals to reconfigure primary school provision in
Johnstone has not incurred any external costs, with all spend being incurred on already
budgeted internal resources. To take the project forward through to approval of the
FBC further costs will be incurred on both internal and external resource. This spend is
required to ensure the Council is presented with a robust and tested recommendation
with professional advice on the specifics of the option.
To conclude and present the FBC for this project, a budget will be required and will be
progressed through established budget setting processes. This budget is made up of all
internal technical resource costs and all external professional services and consultant
appointments required to interrogate and validate the shortlist of options. This cost is
made up as follows:
• Internal technical management costs to deliver project feasibility, cost
management, architectural services and project management
• Flood risk assessments
• Roads and transportation assessments 
• Space planner to produce timetabling and demand modelling to develop
schedule of accommodation 
• Civil engineering to conduct ground investigation surveys on shortlist of sites

Page 88

Johnstone Primary School Estate Outline Business Case  76
OFFICIAL-SENSITIVE
• Structural engineer to conduct intrusive survey of existing asset as required
Approvals for spending this development budget will be agreed through current project
governance to ensure accountability and transparency. 
5.3. Revenue Expenditure
The new primary school will be owned and operated by Renfrewshire Council. The
operating model will align with current arrangements for Renfrewshire Council assets
and learning establishments. 
Potential operating costs for a new school will be further explored as part of the Full
Business Case which will be developed throughout 2026. Whole life cost modelling will
capture elements of future revenue spend across the expected lifetime of the proposed
new school.  Operating costs for the current school have been captured and are
indicated in the Strategic Case, above. Initial indication shows that the cost of operating
a new primary school would be broadly reflective of current operational costs including
staffing, and facilities management. 
It should however be noted that depending on the specific location of the shortlist of
options, the cost of school transport could vary, albeit this cannot be seen as a single
measure of value in an option. The cost of delivering home to school transport has to be
considered in the broader context of the educational and community value that can be
derived through the development of a new school. This matter will be explored in more
detail at the FBC stage where each of the shortlisted options will be investigated in
greater detail for the estimated revenue costs associated with it. 
When considering the wider context of this business case and the preferred route
forward, it is anticipated that significant financial savings can be achieved through the
redesign of the Johnstone Primary Learning Estate. This matter will be fully
investigated throughout the next stage of the process as part of the Full Business Case.

Page 89

Johnstone Primary School Estate Outline Business Case  77
OFFICIAL-SENSITIVE
5.4. Indicative Costs
The indicative cost information outlined in sections 1.7 and 3.6 was prepared using
current market cost information, including Scottish Futures Trust (SFT) benchmark
data, cost information associated with current Council education construction projects,
and BCIS cost forecast indices to underpin indexing current construction cost metrics to
anticipated future construction date. Indicative costs are based on an assumed
construction commencement date of 2030 and all costs should be considered as
exclusive of VAT. 
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicates what is assumed as included
in the costs and what is excluded at this stage.
The cost range, as shown previously in Table 2, gives a high-level indicative estimate
based on a number of key assumptions and exclusions which may be subject to change,
given the early stage of the project. These will be further refined as the project
develops. 
Cost scenario Range
Retrofit Auchenlodment and extend, for 434 pupils and
early-years facility matching current provision. £35 - £45m
Build a 2-stream primary for 434 pupils, and early-years
facility that matches current provision. £25 - £45m

Page 90

Johnstone Primary School Estate Outline Business Case  78
OFFICIAL-SENSITIVE 
The key assumptions and exclusions used in compiling potential costs help ensure full
financial transparency. The following are highlighted as examples:
Assumptions:
• It is assumed that Auchenlodment, St Margaret’s and Thorn shall remain operational
while the new primary school construction works are ongoing, apart from the option to
rebuild/retrofit on the site of Auchenlodment where a decant allowance has been
required.
• Estimated costs are based on construction costs at prices (4th Qtr. 2025)
• It is assumed services and utility connections are available locally
• Inflationary allowances have been made in accordance with current published BCIS
Tender Price Indices
Exclusions:
• Refurbishment works costs to the existing St Margaret’s and Thorn Primary Schools
during construction or retrofit works have been excluded
• Legal Costs 
• Planning Conditions
• Section 75 Planning works/contributions
• Operational costs, Hard FM or Lifecycle/Whole Life costs
These potential costs were produced for a new build/retrofit primary school for the
provisional scope identified as part of this business case, which is a school of 434
capacity, with early years provision, and a level of additional community use space.
5.5. Financial Risk / Optimism Bias
In calculating potential costs, the estimate includes an allocation for risk and
uncertainty. For example, it must be acknowledged that cost indications are based on
an indicative programme that includes a construction period, commencing in 2030.
Where a delay occurs and the programme slips, costs would inevitably change as
factors such as inflation are brought to bear.
Optimism bias allows for mitigation of any unexpected increases or changes
throughout the process but cannot account for all external factors.

Page 91

Johnstone Primary School Estate Outline Business Case  79
OFFICIAL-SENSITIVE
5.6. Interdependencies
As indicated, the project examining the future of Johnstone Primary School Estate is
developing concurrently with two other Learning Estate capital projects. All three
projects are working to an overall aspirational budget commitment that will continue to
be defined and will require Council commitment to secure the required budget at the
conclusion of the Full Business Case process. 
Different requirements, circumstances and context for each project will have a bearing
on the final cost requirements and their share of the overall funding available, making
them highly dependent on each other.

Page 92

Johnstone Primary School Estate Outline Business Case  80
OFFICIAL-SENSITIVE
6. MANAGEMENT CASE
6.1. Project Management and Project Governance Overview
Currently, Renfrewshire Council is undertaking several capital projects focussed on
learning estate improvements, covering both primary and secondary schools. This work
has built on existing expertise within the key teams likely to be involved in any project
to improve the provision of the Johnstone primary learning estate, giving the Council
an experienced pool of resources to draw from. Work is underway within Children’s
Services to create a dedicated Learning Estate Programme Team to deliver on the
ambition of the Learning Estate Strategy.
6.2. Project Roles
Learning Estate projects will be overseen at Chief Officer level by the Director of
Children’s Services who acts as the Programme Sponsor for all projects. Senior
accountability is assumed by the Head of Education for Strategy and Improvement who
takes the position of Senior Responsible Owner (SRO). 
In common with all Learning Estate projects, delivery of change for the Johnstone
Primary School Estate will be led by the Strategic Learning Estate Manager who holds
senior accountability of project delivery to the SRO with day-to-day project leadership
guiding the project teams through all aspects from inception, through to construction
execution and handover. This leadership hierarchy will ensure that projects are
successfully delivered upholding quality across project time, cost, and scope, ultimately
delivering the intended outcomes and high-quality learning establishments for all.  The
Strategic Learning Estate Manager will be guided by subject matter experts who will
control and resource the programme with the appropriate skillsets, with professional
technical management in construction and the built environment coming from the
Council’s Technical Services. 
It is crucial to note however, that whilst leadership roles have been established,
appropriate officer level programme governance has been established to ensure that
there is no single source of programme decision making. This process ensures
accountability and robust decision making with representation covering all key Council
services.

Page 93

Johnstone Primary School Estate Outline Business Case  81
OFFICIAL-SENSITIVE
Each project will require bespoke levels of resource depending on the scale and
complexity but will follow a consistent approach. A dedicated Programme Manager will
lead the overall success and delivery of the programme by implementing and executing
full governance and control across all projects, supporting the Strategic Learning Estate
Manager. 
Project management resource will be provided by the Council’s Programme
Management Unit to cover business case development, business change processes, and
fundamental client-side project management throughout the lifecycle. Technical
expertise will be provided by the Councils’ Technical Services who will provide
construction project management, contract management, and subject matter expert
roles where appropriate through design and delivery. 
Additional resources will be required for each project with ongoing resource allocation
covering critical services such as Finance, Communications, Education, Procurement,
and Legal. 
All resources allocated to Learning Estate projects will report to the Strategic Learning
Estate Manager for their involvement in these projects, with decision making being
made by the appropriate authority level, either the Project Board, or Delivery Board, as
noted below in section 6.3. 
The Council has developed significant experience over the past 15 years delivering
major and complex investment programmes across the learning estate (which includes
three major projects currently in delivery), leisure estate, cultural estate as well as
major transport infrastructure. This experience places the Council in a strong position
to understand the resource and governance arrangements required to deliver
investment programmes of scale and this will be invaluable to support the Council’s
investment focus shifting to a long-term strategic learning estate investment
programme.
6.3. Reporting Arrangements
This project will be monitored using current project management tools to record
progress against timelines, monitor risk, and track change etc. Reporting will be used to
manage and drive the project and ensure accountability to the public more generally.
Beyond day-to-day project management activity, reporting will occur at regular

Page 94

Johnstone Primary School Estate Outline Business Case  82
OFFICIAL-SENSITIVE
intervals to established boards, with key decisions and milestones signed off at an
appropriate level. 
At Council level, this project will be reported to the Education & Children’s Services
Policy Board for all decision making and progress updates. Where financial decisions on
matters such as high value contract awards are required, this project will report to the
Finance, Resources & Customer Services Policy Board as per agreed Council
governance.
At officer level, this project will be reported to both a Project Board, and a Delivery
Board. The Delivery Board holds the senior officer level decision making authority for
the project and will act as the ultimate officer level decision making body within its
terms of reference and agreed scope/authority. This Board consist of Director / Head of
Service representation of all key Council services. 
The Project Board will consist of Senior Managers / Heads of Service of all key Council
services and will act as the operational decision making body for all matters as agreed
in the scope, budget, and timeline of the project. 
This governance is illustrated in the image below:

Page 95

83
OFFICIAL-SENSITIVE 
Education & Children s Services Policy Board
Learning Estate Delivery Board
Chair – Director of Children s Services
Director / Head of Service Representation
Strategic Learning Estate Manager (Strategy & Delivery Lead)
Learning Estate Project Board
Chair – Head of Education Strategy & Improvement
Head of Service / Senior Manager Representation
Finance, Resources & Customer Services Policy Board (FRCS)
All Learning Estate High Value Project Contract Awards
Senior Managers and Specialist Advisers
Project Delivery Team
Council Decision Making Level
Officer Decision Making Level
Project Delivery Level

Page 96

84
OFFICIAL-SENSITIVE
6.4. Procurement Strategy
The project team has a dedicated specialist procurement officer who will take the lead
in developing an overarching Learning Estate Project Procurement Strategy. 
In the short term, initial assessment of the project will identify any requirement for
consultant services to assist with technical aspects of project development. If the OBC
is approved at E&CS Policy Board, consultants will be required to support the project
team as it develops a Full Business Case (FBC). This work will be led by the specialist
procurement officer and has been referenced in the Commercial Case, above.
6.5. Overall Project Benefits
Delivery of change to primary school provision in Johnstone would deliver key project
benefits to local schools and stakeholders as well as the wider community:
• Ensuring the most productive use of the primary school estate across Johnstone is
achieved to ensure all pupils will be educated in the best possible learning
environments over the long term
• A reduction in operational cost and increased efficiency through provision of a school
estate that fits demand and can operate at optimal occupancy
• Maximise operational efficiency through modern, sustainable and efficient buildings
with a reduced need for maintenance of dilapidated buildings. 
• A reduction in Renfrewshire Council’s carbon footprint through the operation of a
school better equipped to meet energy performance targets through more efficient
operation.
• Securing community anchor sites in the catchment area providing facilities for public
use outside of school hours.
6.6. Community Benefits Realisation Arrangements
Renfrewshire Council has an established and successful Community Benefits approach
which aims to deliver social, economic and environmental benefits for Renfrewshire’s
communities as part of contract delivery. Community benefits are considered for
inclusion on all regulated procurement over £50,000 and are delivered by suppliers and
contractors in partnership with local organisations and supported by the Council’s

Page 97

Johnstone Primary School Estate Outline Business Case  85
OFFICIAL-SENSITIVE
Community Benefit Forum and Delivery Partners. Monitoring of community benefits will
be managed through project and delivery boards and a benefits realisation strategy will
be aligned with the overarching procurement strategy.
6.7. Risk Management Arrangements
The project team has commenced a risk register to capture and monitor risk on behalf
of the Council. Risk management will remain an active part of the project management
process for the duration of this project with regular dedicated sessions focussing on the
risk register to complement its inclusion as a standing agenda item in project working
groups and meetings at all levels.
6.8. Equalities and Human Rights
Any equality impact on current users and staff at all schools in Johnstone, as well as the
wider community, as a consequence of this project, will be considered at all stages it
develops. Initial Equality and Human Rights Impact Assessments (EQHRIA) have been
carried out at programme level. This will inform the basis of all future assessments,
where individual impact assessments will be conducted, specifically relating to the
upcoming community engagement and consultation. All proposals outlined in this
business case would be subject to formal statutory consultation where impacts will
again be considered in detail.
6.9. Communication, Engagement, and Community Voice
Informal community and stakeholder engagement commenced in August this year,
following publication of the SCC. Engagement has included meetings with
headteachers, ward members and the parent council for all Johnstone primary schools,
to keep all interested parties informed of progress and likely timelines for this project. 
A survey was issued to parents and staff, inviting their views on the school and what
they would improve, what should be important for any future investment. Those
findings are referenced in the Strategic Case (section 2.6, above). Responses to the
survey helped shape analysis of the routes forward and options considered in this OBC.

Page 98

Johnstone Primary School Estate Outline Business Case  86
OFFICIAL-SENSITIVE
Engagement with key stakeholders and the wider community will be key to the
successful determination of the overall best value option to proceed with at the
conclusion of the Full Business Case. To ensure clear communication and stakeholder
input to the process, the project team will carry out an informal consultation on the
short-listed options described in section 3.5 from April 2026.  More detail is provided in
section 7.1 Summary of Shortlisted Options and Next Steps

Page 99

Johnstone Primary School Estate Outline Business Case  87
OFFICIAL-SENSITIVE
7. CONCLUSION
7.1. Summary of Shortlist of Options and Next Steps 
This OBC confirms that current capacity, future roll projections and the varying
conditions of the school estate in Johnstone can only be resolved by a masterplan
reconfiguration of the Johnstone learning estate which takes account of the following
aims: 
Route 4:  Masterplan Redesign of the Primary School Estate in Johnstone 
Address the overprovision of primary school places in Johnstone and the requirements of
the 3 priority schools of Thorn, Auchenlodment, and St Margaret’s, by:
• Making best use of capacity of existing high-quality buildings including St Anthony’s,
West Johnstone Joint Campus, and Fordbank. 
• Considering the location of any new build school facility that would look to combine
more than one existing school on the same site
• Considering the most appropriate catchment area configurations to support efficiency
and capacity. 
The business case concludes that the following 3 elements should be included in a masterplan
approach, capturing those options that should be progressed to the Full Business Case stage: 
a) Merge Thorn and Auchenlodment catchment areas, combining both non-     
denominational schools in a single modern building by one of the following
means: 
1. Site 01 - Retrofit and extend the existing Auchenlodment Primary School building
to provide a modern 2 stream primary school with capacity for 434 pupils at
Aspen Place, Johnstone 
2. Site 01 – Construct a new build 2 stream primary school with capacity for 434
pupils at the existing Auchenlodment primary school site at Aspen Place,
Johnstone 
3. Site 04 - Construct a new build 2 stream primary school with capacity for 434
pupils, at the site of the existing Thorn Primary, Thorn Brae, Johnstone 
4. Site 09 - Construct a new build 2 stream primary school with capacity for 434
pupils on a new Site at Poplar Avenue, Johnstone

Page 100

Johnstone Primary School Estate Outline Business Case  88
OFFICIAL-SENSITIVE 
b) Merge Cochrane Castle and Fordbank catchment areas, combining both non-
denominational schools at the current Fordbank Primary School site. 
c) Merge St Margaret’s and St David’s catchment areas, combining both    
denominational schools at the West Johnstone Joint Campus, creating a single
denominational school.
Note: St Anthony’s Primary is not affected by the proposed options as it is a high quality
building operating at sufficient capacity. Further detail is given in section 3.
To prepare the Full Business Case, more detailed site assessments, further cost
modelling, and community consultation are required to recommend a single best value
option to proceed with on conclusion of the next stage of the business case process. 
Taking into account the Council’s commitment to include communities in decision
making, the project team will conduct an informal consultation on the options outlined
above.  The purpose of carrying out an informal consultation during the Full Business
Case stage is to:
• Comply with recommended best practice in ensuring that the public are involved
in decision making
• Comply with UNCRC to involve children in making decisions that affect them
• Explain the options clearly to stakeholders and the public
• Understand early in the process local views on the options
• Refine options based on local views and feedback
• Present a final option that is the most suitable for the community and the council
• Reduce the potential for community objections at a later stage
• Enhance relationships with local communities/individuals
Key stakeholder groups that will be engaged in the informal consultation include:
• Pupils and parents – parent councils, all parents and pupils
• Local community – Community councils, youth groups, local development
groups, local interest groups, general population in school catchment
• School staff - Head teachers, teaching staff, admin staff, support staff.  
• Local early years children and parents
• Politicians – local ward members, ECSPB members, local MPs, local MSPs, 
• Council Services – all council services who contribute to the creation, running and
maintenance of school facilities
• Future building users – groups with letting arrangements 
• Neighbours – current and potential neighbours to school buildings/sites.

Page 101

Johnstone Primary School Estate Outline Business Case  89
OFFICIAL-SENSITIVE
• Statutory bodies – Education Scotland, Police Scotland, Scottish Fire and Rescue
Service, Sport Scotland. 
Activity Stakeholders Methods
Preparation and
options
development
Senior Officers and SLT
Elected Members
Head Teachers
Briefings
Workshops
1-1 interviews
Targeted Early
Engagement
Parent Councils/Parents
Community Councils
Local Community Groups
Pupils
Staff
Council Services
Roud table meetings
Briefings
Workshops
Focus Groups
Surveys
Broad Public
Engagement 
Associated school parents
and pupils
General public 
Neighbours
Surveys
Public events
Analysis and
Refinement
Project team 
Table 18: Engagement Activity
The Full Business Case process is expected to take the remainder of 2026 to complete
and will be presented back to a future cycle of the Education and Children’s Services
Policy Board in 2027 for approval of a final recommended option.

Page 102

Johnstone Primary School Estate Outline Business Case  90
OFFICIAL-SENSITIVE 
Children’s Services
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR

Page 103

1
OFFICIAL-SENSITIVE 
Johnstone High School
Outline Business Case

Page 104

Johnstone High School Outline Business Case  2
OFFICIAL-SENSITIVE
DOCUMENT CONTROL SHEET 
Title: Johnstone High School
Version Number 2
Document Type: Outline Business Case
Author: Learning Estate Project Team
Date Published: 18/02/2026
Document Versions: 
Version: Name: Update: Date
V0.1 Project Team Initial draft 28/11/2025
V0.2 Project Team Amendments and further draft 16/12/2025
V1 Project Team First draft for review  17/12/2025
V1.1 Project Team Amendments and further draft 19/01/2026
V1.2 Project Team Further amendments 13/02/2026
V2 Project Team Final draft following review by Chief
Officers 18/02/26
Supporting Documentation / Location: 
Document Title: Location:
Strategic Case for Change Document.ashx

Page 105

Johnstone High School Outline Business Case  3
OFFICIAL-SENSITIVE 
Table of Contents
1. EXECUTIVE SUMMARY ........................................................................ 6
1.1. Introduction .......................................................................................... 6
1.2. Background ........................................................................................... 7
1.3. Opportunity ........................................................................................... 9
1.4. Scope and Objectives ............................................................................ 9
1.5. Summary of Routes Forward ............................................................... 10
1.6. Preferred Route Forward and Options Shortlist .................................. 11
1.7. Indicative Costs ................................................................................... 11
1.8. Timeline ............................................................................................... 13
2. STRATEGIC CASE .............................................................................. 14
2.1. Strategic Context ................................................................................. 14
2.2. The Need for Change ........................................................................... 15
2.3. Investment Objectives ......................................................................... 15
2.4. Existing Arrangements ......................................................................... 16
2.5. Initial Engagement .............................................................................. 17
2.6. Scope and Service Requirements ....................................................... 18

Page 106

Johnstone High School Outline Business Case  4
OFFICIAL-SENSITIVE
3. ECONOMIC CASE .............................................................................. 20
3.1. Potential Routes Forward.................................................................... 20
3.2. Preferred Route Forward ..................................................................... 25
3.3. Site Assessment Criteria ...................................................................... 26
3.4. Site Options Assessment ..................................................................... 29
3.5. Shortlisted Options ............................................................................. 36
3.6. Indicative Costs ................................................................................... 37
3.7. Transport Considerations ................................................................... 39
3.8. Timeline and Next Steps ..................................................................... 40
4. COMMERCIAL CASE .......................................................................... 41
4.1. Approach ............................................................................................. 41
4.2. Service Requirements ......................................................................... 41
4.3. Project Development .......................................................................... 41
5. FINANCIAL CASE ............................................................................... 43
5.1. Project Funding – Capital Expenditure ............................................... 43
5.2. Approvals Process ............................................................................... 43
5.3. Revenue Expenditure .......................................................................... 44
5.4. Indicative Costs ................................................................................... 44

Page 107

Johnstone High School Outline Business Case  5
OFFICIAL-SENSITIVE
5.5. Financial Risk / Optimism Bias ............................................................ 46
5.6. Interdependencies .............................................................................. 46
6. MANAGEMENT CASE ........................................................................ 47
6.1. Project Management and Project Governance Overview ................... 47
6.2. Project Roles ........................................................................................ 47
6.3. Reporting Arrangements ..................................................................... 48
6.4. Procurement Strategy ......................................................................... 51
6.5. Overall Project Benefits ....................................................................... 51
6.6. Community Benefits Realisation Arrangements ................................. 51
6.7. Risk Management Arrangements ........................................................ 52
6.8. Equalities and Human Rights .............................................................. 52
6.9. Communication, Engagement, and Community Voice....................... 52
7. CONCLUSION ................................................................................... 53
7.1. Summary of Shortlist of Options and Next Steps ................................ 53

Page 108

6
OFFICIAL-SENSITIVE
1. EXECUTIVE SUMMARY 
1.1. Introduction
This outline business case (OBC) is required as part of the Council’s new structured
approach to delivering its long-term strategy for the learning estate across
Renfrewshire. It builds on the context set out in a Strategic Case for Change (SCC)
examining the future of Johnstone High School in Johnstone, which was approved in
August 2025 at the Education and Children’s Services Policy Board (E&CS Policy Board).
In the SCC, Johnstone High school was assessed as working far below optimal
occupancy with demand for places likely to remain at or below 60% of capacity over the
next 10-15 years. Further, the school building was noted as being in poor condition,
with suitability also impacting delivery of a modern school curriculum and efforts to
improve the learning environment in line with the ambitions of Renfrewshire Council’s
Learning Estate Strategy.
The purpose of the OBC is to articulate a preferred way forward for the project by
identifying a shortlist of investment options likely to optimise value for money in
delivering change. A longlist of options is presented as part of the OBC, along with
analysis and rationale for their inclusion or exclusion from the shortlist. Additionally,
further detail is provided in respect to how the scheme will be prepared for
procurement and how the Council will put in place funding and management
arrangements for its successful delivery.
The OBC uses the following framework to present the preferred way forward, utilising
an adapted HM Treasury Green Book approach which is based on the 5 Case model:
Strategic case – confirming that strategic objectives remain current and seek
agreement on the recommendation
Economic Case – helping to determine that the preferred way forward offers value for
money
Commercial Case – working towards a recommended deal by explaining potential
delivery models, procurement and engagement
Financial Case – establishing affordability and funding requirements

Page 109

Johnstone High School Outline Business Case  7
OFFICIAL-SENSITIVE
Management Case – planning for successful delivery 
Table 1: Business case development process
1.2. Background
The learning estate strategy published by the Council in 2024, aims to initiate a strategic
programme of investment in schools through detailed assessment of the entire learning
estate. The ambition of the investment programme is to ‘create the best possible
learning estate to allow children and young people to thrive’.
Renfrewshire’s schools were assessed against various criteria including condition,
suitability for delivering the curriculum, capacity and demand. Using a prioritisation
framework, the strategy assessed the entire learning estate, identifying those schools in
need of long-term investment planning now, to ensure that the Council is best placed
to: 
• Secure best value from strategic learning estate decisions around investment
Stage: Stage 1 Stage 2 Stage 3 Stage 4
Stage Outcome: Strategic Outline
Case Outline Business Case Full Business Case Final Delivery Business
Case
Stage Activities:
• Highlighting
strategic context
• Making the case
for change
• Agreeing scope
• Considering longlist
options
• Exploring the
preferred way
forward and
presenting a
shortlist
• Determine potential
value for money
• Preparing for the
potential deal
• Planning for
procurement
• Procuring the
solution
• Contracting the deal
• Ensuring successful
delivery
5-Case Model
(stage of
completeness): 
• Strategic 50%
• Economic 40%
• Commercial 10%
• Financial 10%
• Management 10%
• Strategic 80%
• Economic 70%
• Commercial 40%
• Financial 30%
• Management 50%
• Strategic 90%
• Economic 90%
• Commercial 90%
• Financial 75%
• Management 75%
• Strategic 100%
• Economic 100%
• Commercial 100%
• Financial 100%
• Management 100%
Gateway
Review: Strategic Assessment Business Justification Delivery Strategy
Final Investment
Decision and financial
commitment

Page 110

Johnstone High School Outline Business Case  8
OFFICIAL-SENSITIVE
• Meet the expected long-term demand for education provision across
Renfrewshire whilst delivering improvements in school buildings and learning
environments
• Ensure that the delivery of any new infrastructure complements other key
strategic objectives being progressed by the Council to optimise the use of assets
for communities and support wider redesign of services that better meet the
needs of communities. 
A cohort of 13 priority schools was identified, highlighting Johnstone High School as a
key site where deteriorating building conditions and the suitability of the school
buildings hamper the Council’s ability and ambition to deliver the curriculum in the
best possible learning environment. 
A further consideration identified at Johnstone High School was based on analysis of
pupil roll projections. Thus, Johnstone High School is noted as operating significantly
below planning capacity. Further, demand for places is projected to remain well below
planning capacity over the next 10-15 years.
In response, officers produced a Strategic Case for Change, to consider the context of
key issues which, if not addressed, would limit the ability to deliver the strategic
objectives of the Learning Estate Strategy for Johnstone High School. The document
examined the operating context at the school with reference to the objectives of the
strategy:
• Condition
• Suitability
• Sufficiency
• Inclusivity
• Digital
• Sustainability and Net Zero
• Community Facilities and Place shaping
• Active Travel 
The Strategic Case for Change sets out the current baseline position at the school. It
highlights the challenges presented by the physical environment and excess capacity,
and how this hampers the Council’s desire to ensure future delivery of the modern
curriculum.

Page 111

Johnstone High School Outline Business Case  9
OFFICIAL-SENSITIVE
Following approval of the strategic case for change, significant work has been
undertaken to identify options for change that meet these ambitions and align with the
critical success factors articulated in the documents.
1.3. Opportunity
The opportunity to change and improve the provision of Johnstone High School aims to
advance the objectives of Renfrewshire Council’s new Learning Estate Strategy, and to
help meet the ambitions of wider Council and Scottish Government policies. Those
ambitions, fully considered in the Strategic Case for Change, are summarised here:
• Improving the condition of schools
• Sustainability and Energy Efficiency
• Equity and Inclusion
• Adapting to Future Educational Needs
• Community and Public Use
• Strategic Planning and Investment 
• Collaborative Approach with Stakeholders
The ambitions encompass Renfrewshire Council’s determination to invest wisely whilst
reflecting the importance of operational efficiencies and cost avoidance in delivering
the Learning Estate Strategy. Thus, careful consideration of how to bring change to
Johnstone High School, can additionally help increase building operational efficiency
through provision of improved, modern facilities. A new or refurbished school can
deliver modern standards and design and contribute to the Council’s Net Zero
commitments. 
Above all, this OBC sets out the opportunity for Renfrewshire Council to meet its
overarching aim of ensuring that its schools are modern, accessible to all and support
the delivery of high-quality education for learners.
1.4. Scope and Objectives
The Strategic Case for Change set out five overarching investment objectives for
Johnstone High School. Any investment in the learning estate must:
• Deliver the best learning environments and facilities possible
• Support improving attainment and ambition

Page 112

Johnstone High School Outline Business Case  10
OFFICIAL-SENSITIVE
• Maximise operational efficiency across the estate
• Reduce the contribution to the Council’s combined carbon footprint 
• Acknowledge that ageing schools with deteriorating conditions come closer to
the point of being no longer fit for purpose
Thus, Johnstone High School is identified as a school which does not match current or
future demand; whose building condition and layout hamper delivery of a modern
curriculum and efforts to raise attainment further; whose buildings require
considerable on-going investment simply to maintain the status quo; and which cannot
contribute to Council’s net zero commitments in its current form.
To meet these objectives and deliver change, this OBC will examine viable options for
the delivery of a new-build or major retrofit secondary school for a roll of circa 1,000
pupils (revised up or down based on detailed project development), with sufficient
space for community or partner facilities to be considered. with consideration of any
associated community facilities in line with the Council’s wider strategic property
strategy. The school should remain within the current catchment area.
1.5. Summary of Routes Forward
Possible options for the future of Johnstone High School considered 4 potential routes
forward against the requirements for change:
1 – Do Nothing
2 – Retrofit and Refurb
3 – Rebuild Johnstone High on the current site
4 – Rebuild Johnstone High on another site 
Analysis of the routes forward are presented in full in the Economic Case in Section 3.
This was produced following the collation of background information included in the
SCC, technical information, and analysis of the operating context at Johnstone, as well
as engagement with school staff and parents.

Page 113

Johnstone High School Outline Business Case  11
OFFICIAL-SENSITIVE
1.6. Preferred Route Forward and Options Shortlist
The preferred route forward for the project has been determined using the critical
success factors identified in the SCC, to assess the viability of the various options under
consideration. This recommended delivery of change by addressing the capacity and
school condition issues facing Johnstone High School by refurbishing the current
school or rebuilding it at the current site or elsewhere in the catchment: 
Route 2 Route 3 Route 4
Retrofit the existing
school
Rebuild on the current
Johnstone High site
Rebuild elsewhere in
the catchment area
Table 2: Preferred Routes Forward 
This OBC appraises the routes forward, proposing and assessing various site options
and recommending an options shortlist. This process and analysis are presented in the
Economic Case, section 3, below. The shortlisted options are: 
Option 01
Retrofit Johnstone High School on Site 01 Johnstone High School Beith Road, Johnstone
Option 02
New Build on Site 01 Existing Johnstone High School Site, Beith Road, Johnstone
Option 03
New Build on Site 03 Beith Road Playing Fields, Johnstone
Table 3: Options Shortlist
1.7. Indicative Costs
To identify an indicative planning cost for delivering options associated with the
preferred route forward, an exercise was conducted to consider the potential cost of
delivering a school project at the identified planning scale (a secondary school of 1,000
capacity with additional community-use space).

Page 114

Johnstone High School Outline Business Case  12
OFFICIAL-SENSITIVE
These costs are discussed in greater detail at section 3.6 (Economic Case) and 5.4
(Financial Case), below. 
The overall potential costs of a new Johnstone High School built to the set criteria are
shown here: 
Cost Scenario Range
Option 1 – Retrofit the existing
school
£121m
Option 2 – Rebuild on the current
Johnstone High site
£85 - £133m
Option 3 – Rebuild elsewhere in
the catchment area
£91 - £144m   
Table 4: Indicative Costs 
The indicative costs above are provided for illustrative purposes only. Costs are subject
to change depending on consultation, design changes, planning requirements and
parameters, site locations and geotechnical site characterisation, procurement routes
and other external factors.

Page 115

13
OFFICIAL-SENSITIVE
1.8. Timeline
In 2025 a high-level summary of the timeline for completing this business case process was outlined, as shown below. This
timeline is explained in more detail in section 3 of this document to show a potential route to construction.

Page 116

14
OFFICIAL-SENSITIVE
2. STRATEGIC CASE
2.1. Strategic Context
In August 2025, a business case presented to E&CS Policy Board set out a strategic case
for change at Johnstone High School. The paper outlined the background and context,
highlighting links to local and national strategies for education, including Renfrewshire
Council’s Learning Estate Strategy and Fairer Renfrewshire policy, and Scottish
Government’s National Learning Estate Strategy.
The strategic objective for this project is to ensure delivery of the best quality learning
environments for secondary pupils in the Johnstone High School catchment area,
whilst ensuring that capacity matches demand for school places, both now and in the
future. This OBC takes that initial case for change and begins the process of identifying
options for change in response to the needs and drivers identified. The policy
background is summarised below. 
• Renfrewshire Council Learning Estate Strategy – a long-term structured
approach to assessment of the learning estate through a prioritisation
framework which identifies those areas of the estate most in need of investment.
The strategy ensures careful planning to ensure that limited capital investment is
directed where it will have the greatest impact through reshaping, refurbishing
or replacing existing facilities. 
• Scottish Government’s National Learning Estate Strategy – reflecting the
ambition of the Scottish Attainment Challenge, which promotes equity in access
to quality education facilities as part of a drive to tackle the poverty related
attainment gap and promote inclusivity.
• Fairer Renfrewshire – recognising the role of the learning estate in reducing
inequalities and improving the life chances of pupils across Renfrewshire
• Strategic Planning and Investment – recognising the long-term nature of the
strategy for the learning estate, with a clear framework which identifies those
schools that require replacement, refurbishment or upgrading
• Strategic Property Strategy – seeks to ensure that Renfrewshire Council’s
property estate is strategically located and used to its fullest potential,
complementing existing facilities and services wherever possible

Page 117

Johnstone High School Outline Business Case  15
OFFICIAL-SENSITIVE
2.2. The Need for Change
As articulated in the Strategic Case for Change document which preceded this business
case, there is a clear and compelling case for introducing change to Johnstone High
School, as highlighted by a combination of factors, including: 
• Operating below optimal capacity – Johnstone High School has a planning capacity
of 1380 pupils and a pupil roll this year of 867; roll projections indicate that demand
will remain low and potentially fall further over the next 10-15 years.
• Condition and Suitability – ‘Core Facts’ reporting indicates that the condition (rated
‘C’) and suitability (rated ‘B’) of the of the building should be improved and that
£13.29m of spending will be required over the next 20 years simply to keep the
building operating at its current level. Accessibility is an issue in some parts of the
building.
• Opportunity to maximise operational efficiency – Provision of a school built to
modern teaching and building standards will help increase building operational
efficiency by replacing ageing facilities which cannot meet modern building
performance standards.
2.3. Investment Objectives
The following objectives have been identified as key to improving learning
environments across Renfrewshire through investment, and aligning with the ambitions
of the Learning Estate Strategy:
• Effectiveness – Meet the aims of the 2024 Learning Estate Strategy to initiate a
strategic programme of investment in schools; Ensure that every school is considered
in terms of Scottish Government Core Facts reporting criteria; Deliver the best
learning environments and facilities possible, exceeding, where able, Scottish
Government recommendations. 
• Efficiency – Provision of modern learning environments to improve attainment for
pupils in Renfrewshire
• Economy – Optimise operating costs for the estate through the creation of buildings
which are more energy efficient and through operation of a more efficient overall
school estate; Offer a reduction in the costs incurred maintaining ageing buildings;
Operation of buildings of a size suited to current and projected school rolls.

Page 118

Johnstone High School Outline Business Case  16
OFFICIAL-SENSITIVE
• Compliance – Careful planning for the replacement or refurbishment of schools to
lessen the impact from older buildings and make a valuable contribution to
Renfrewshire Council’s net zero commitments through the operation of more
efficient buildings.
• Replacement – The project acknowledges that as schools age and maintenance
costs increase, they come closer to the point of being no longer fit for purpose as a
Council asset.
2.4. Existing Arrangements
A comprehensive overview of Johnstone High School was included in the Strategic Case
for Change and is summarised below. The key facts relating to its operation are outlined
in following tables and narrative.
Johnstone High School is a non-denominational secondary school whose catchment
area covers all of Johnstone as well as surrounding villages as far as Lochwinnoch.
Johnstone serves seven primary schools in the catchment area and circa 5% of current
pupils attend from outside the catchment area. The planning capacity for Johnstone
High is 1,380 and the current roll is 867. 
School Age Suitability Condition
Johnstone
High 64 B C
Table 6: Key Facts 
School Capacity Current Roll 2029/30* 2033/34* 2037/38*
Johnstone
High 1,380 867 (63%) 908 (66%) 813 (59%) 772 (56%)
Table 7: Capacity and Roll Information (‘Sufficiency’) 
School Utilities Hard &
Soft FM
Teaching Non-
Teaching
Other* Rates Total
Johnstone
High £297,641 £476,690 £5,160,214 £404,279 £269,256 £136,800 £6,744,880
* Waste, Grounds Maintenance; Transport
Table 8: Overview of Operating Costs

Page 119

Johnstone High School Outline Business Case  17
OFFICIAL-SENSITIVE 
Location No. of Pupils Annual
Cost
JOHNSTONE HS –
W.AUCHENGOWAN/BELLTREES/WINDYHILL/MID HARTFIELD /
NETHER BROADFIELD/BOWFIELD/E.MUIRDYKES/LADESIDE
3 £16,963
JOHNSTONE HS – NEWTON OF BELLTREES /
HARTFIELD/BOWFIELD / E.MUIRDYKES/MERCHANT’S CLOSE 9 £24,700
JOHNSTONE HS (LINK)/LOCHWINNOCH PS – LOC 20 £9,942
JOHNSTONE HS / LOCHWINNOCH PS – (LINK) LOCHWINNOCH
AREA FARMS AND COTTAGES 28 £20,693
JOHNSTONE HS – BROOKFIELD / KILBARCHAN 15 £8,593
JOHNSTONE HS – CHURCH STREET, WOODISDE COTTAGE,
PADDOCK WARDEND, KILBARCHAN 8 £3,800
JOHNSTONE HS – CHURCH STREET,  KILBARCHAN 9 £6,333
JOHNSTONE HS – LOCHWINNOCH AND HOWWOOD 7 £28,025
JOHNSTONE HS – LOCHWINNOCH AND HOWWOOD 4 £79,800
JOHNSTONE HS – LOCHWINNOCH FARMS 1 £7,600
JOHNSTONE HS – LOCHWINNOCH FARMS 2 £16,401
Total: 106 £255,229
Table 9: Breakdown of Transport Costs
2.5. Initial Engagement 
Following presentation of the Strategic Case for Change to E&CS Policy Board in August
2025, officers undertook informal community and stakeholder engagement, outlining the
processes involved in identifying opportunities to deliver change.

Page 120

Johnstone High School Outline Business Case  18
OFFICIAL-SENSITIVE
A survey was issued to parents, carers and school staff at Johnstone High School, inviting
views around current school provision, including school condition, location of facilities
and what stakeholders feel should be important to the Council in progressing future
school investment. 
Analysis of responses from parents, carers and the wider community suggested that
whilst there is general happiness with the location of the school and the facilities on offer,
most respondents acknowledged the challenges the building poses to users. The survey
identified the following key themes and discussion points: 
• Good location within Johnstone
• Deteriorating, run-down building condition
• Modernisation of classroom facilities to support contemporary learning
• Need for improved toilet facilities
• Need for improved windows and ventilation 
Responses from school staff highlighted similar themes: 
• The building is rundown and unfit for modern education, but the school ethos is
strong
• There is a lack of ICT and classroom conditions need improvement
• Families in the community require a better environment to support their
education 
In summary, both groups identify issues with ventilation, heating, windows, and air
quality, alongside inadequate toilets, dated classrooms, and insufficient indoor social
and dining spaces that lead to congestion and reduced pupil morale. Corridor widths
and general circulation were raised as recurring issues by parents and staff, with both
describing overcrowding at transitions as challenging. Outdoor areas are viewed as
underused, poorly maintained or lacking in purposeful design, with calls for greener,
more inviting and sheltered spaces for socialising, recreation and structured learning.
2.6. Scope and Service Requirements
The scope of this proposal for change is to provide an improved Johnstone High School
in line with the strategic objectives set out and agreed in the Strategic Case for Change,
informed by an understanding of the operating context. Potential routes forward were
set out in an interim update to E&CS Policy Board in October 2025, based on the broad

Page 121

Johnstone High School Outline Business Case  19
OFFICIAL-SENSITIVE
range of options outlined in the Economic Case, below. The potential routes were
articulated as follows and are set out in section 3, Economic Case: 
Route 1 Route 2 Route 3 Route 4
Do nothing – continue
to operate Johnstone
High
Retrofit/Refurbish
Johnstone High
Rebuild Johnstone
High at current site
Rebuild Johnstone
High at alternative site
Table 10: Potential Routes Forward

Page 122

Johnstone High School Outline Business Case  20
OFFICIAL-SENSITIVE
3. ECONOMIC CASE
3.1. Potential Routes Forward
In line with the summary of routes forward that are outlined above as part of the
Strategic Case each has now been subject to an assessment process to identify the
broad advantages and disadvantages to assess the overall merits of each option.
This process allows in the first instance, identification of recommended viable routes to
be considered in more detail to establish a long list of options to be considered. In the
case of Johnstone High, the analysis outlined below identifies three viable routes
forward from which a long list of potential options has been identified. The potential
viable routes from the list below are: 
Route 2 – Retrofit the existing Johnstone High
Route 3 – New Build Johnstone High at the Current Site
Route 4 – New Build Johnstone High at an Alternative Site 
All routes forward are examined in detail below. 
Route 1: Do nothing
Retain the building as-is with minimal wind and watertight investment and continue to
operate the high school in its current format 
Main Advantages:
Value for money  • Lower capital outlay required, albeit significant future capital outlay will still be required
on building maintenance to secure long term wind and watertight condition and to
support net zero transition, none of which would support improvement to configuration
or suitability for delivering the curriculum.

Page 123

Johnstone High School Outline Business Case  21
OFFICIAL-SENSITIVE
Main Disadvantages:
Strategic Fit  • Maintaining the current building will not help ensure delivery of the best possible
learning environments for all users, nor would it meet the objectives of the Learning
Estate Strategy or help future proof against further developments in technology or
curriculum.
Value for Money  • The most recent condition report in 2022 assessed the buildings as ‘C- Poor’ (exhibiting
major defects/not operating efficiently) with a maintenance cost of £13.29m over the
next 20 years to maintain the building as it is now at a poor standard. This would not
bring any improvement to the overall suitability and layout of the building or its grounds
to support curriculum delivery, and the building would have a limited long term life
given its age. In addition, further investment would be required to support long term net
zero ambitions.
• The building is, and would remain in future, too big for its current and projected roll,
making operation less efficient and operationally more expensive 
Conclusions:
With the disadvantages outlined above, this is not considered a viable option and will be discounted as a
route forward. This option would bring no material benefit to the school or wider community and would not serve
to improve the education experience of anyone involved and is likely to provide poor long term value for money
given the age and condition of the existing school. Johnstone High School would continue to operate at inefficient
levels. This option will not be considered further. 
Route 2 – Retrofit the existing Johnstone High  
Carry out a comprehensive retrofit of Johnstone High School to bring it up to Net Zero
Public Sector Building Standards (NZPSBS) or better, whilst improving the overall
condition and suitability of the environments.
Main Advantages
Strategic Fit  • Contributes towards net zero ambitions through retention of embodied carbon and
significant improvements in energy consumption.
• Spaces within the building can be redesigned to reduce overall capacity of school to
meet decline in demand, making better use of the asset in a layout reconfiguration. 
Value for Money • Greater operational efficiency from a more energy efficient building of a size that allows
for optimal occupancy. 
Affordability  • Continued use of existing sports facilities at the adjacent sports hub and therefore fewer
design considerations

Page 124

Johnstone High School Outline Business Case  22
OFFICIAL-SENSITIVE 
Main Disadvantages:
Strategic Fit  • The most appropriate location and provision within the asset could be compromised by
being constrained with current configuration and location of building on site. 
Value for Money  • A deep retrofit is a complex and demanding project requiring careful planning and
execution. Initial capital costs for a retrofit may be higher in comparison to an
equivalent new-build, and the overall remaining life of a refurbished building is likely to
be less than a new build, placing a level of constraint on the long term value for money
assessment.
• Due to the design of current building and inefficient layout, large portions of the
building may require to be demolished and rebuilt as part of a retrofit, leading to the
question of whether better overall value would be gained in a new build.
• Initial estimates indicate a higher outlay for this option than building new, as outlined
above.
• Coupled with the higher initial outlay, the whole life value for money would be further
undermined by a shorter long-term life associated with a refurbished as opposed to new
build structure.
Affordability • Refurbishment projects carry inherently higher risk than new build due to latent defects
and the uncertain scale of works that will be required. The full extent of work required,
and therefore cost and timeline, may only become fully apparent as areas of the internal
fabric of the building are exposed and a full understanding of the building condition is
apparent. This could result in the further divergence between refurbishment cost and
new build ultimately impacting negatively on the whole life value for money appraisal. 
Achievability  • A decant would be required for pupils of the school over a long spanning construction
period. In a secondary school this would present significant challenge in terms of
maintaining curriculum delivery and retaining access to specialist equipment or
workshops. Construction work taking place during term time would add a higher level of
complexity and extra cost to the project.
Conclusions:
This option has attraction in terms of making the most of existing assets, retaining embodied carbon and
addressing Council commitments on net zero. The overall cost and challenges associated may represent poorer
up-front affordability as well as poorer whole life value for money if the building cannot meet critical success
factors and the ambition of the Learning Estate Strategy around longevity, for example, if the superstructure even
with a deep retrofit, has a limited lifespan. This option could simply delay the inevitable requirement of a new build
school being required when considered over a whole lifetime period. 
Although the option can facilitate layout and configuration changes which would deliver improved suitability and
capacity in line with the Learning Estate Strategy, it would unlikely offer an optimal outcome as the existing
building would provide a level of constraint on flexibility.

Page 125

Johnstone High School Outline Business Case  23
OFFICIAL-SENSITIVE
Whilst this option presents a range of significant challenges, it is credible and viable and it is proposed to be
retained and investigated further, paying particular attention to potential decant logistics, and associated
costings of the project. Notwithstanding a commitment to investigate further, it is not expected at this stage
this option is likely to present an optimal solution. It is important as part of the overall business case process
that, as a viable option, it is considered and if discounted the reasoning is transparently and clearly set out
when compared against alternative options to clearly demonstrate best value decision making. 
Route 3: New Build Johnstone High at Current Site 
Rebuild Johnstone High School at the current site, either on the current footprint, or
elsewhere within the site; with the potential for decanting current pupils during
building works, depending on school placement on site.
Main Advantages:
Strategic Fit • This would deliver a new school built to modern educational and building standards, of
a size that allows for optimal occupancy and deliver an asset with the longest potential
operational life.
• Meets the requirements of Renfrewshire Council’s vision for education and the
objectives of the Learning Estate Strategy.
• It would directly contribute towards net zero ambitions through provision of a new
school built to NZPBS standard or better, with significant improvements in energy
consumption to the existing school.
Value for Money • Creation of a building with modern heating and power systems will greatly improve
operational efficiency and a new build provides the opportunity to secure a learning
facility with the maximum future life to support long term value for money benefits.
Affordability • Continued use of existing sports facilities at the adjacent sports hub meaning lower
design and build costs
• If rebuilding elsewhere on a suitable position on the current site, decant costs could be
avoided and disruption to the school environment significantly mitigated.
Main Disadvantages:
Strategic Fit • If rebuilding on the existing footprint, the short-term disruption associated with a
decant may outweigh longer term gain for all stakeholders. 
• If rebuilding on the existing footprint, decanting pupils and staff may not align with
resourcing constraints especially around available space or demand for modular
classrooms and could therefore attract significant costs to provide a suitable decant
facility.
Achievability • A decant would be required to rebuild the school on its existing footprint. In a secondary
school this would pose significant challenges in terms of maintaining curriculum

Page 126

Johnstone High School Outline Business Case  24
OFFICIAL-SENSITIVE
delivery and retaining access to specialist equipment or workshops. This would add
another level of complexity and cost to the project. 
• Finding suitable premises in which to base the school during decant may be an onerous
task, whilst the option of decanting the school community throughout other secondary
schools in Renfrewshire risks additional upheaval for other school communities.
Conclusions:
This option would be able to deliver on all objectives associated with the Learning Estate Strategy with the ability
to offer an enhanced education experience through provision of a much-improved asset with greater operational
efficiency in a more sustainable fashion. However, if rebuilding on the existing footprint, rather than elsewhere on
the site, this option would involve decanting of the school community to facilitate a rebuild.  Careful consideration
of the decant strategy would have to be undertaken to determine the overall impact of this option on the learning
and teaching experience for the period of the decant, and of the additional cost involved in facilitating the decant.
The viability of this option will become clearer in the investigation of a decant strategy (if required), which
will inform costs and assess the likely disruption to the working of the school. This option (and the sub-
option of the specific location of the new school within the existing site) should continue to be assessed
further and can then be compared against alternative options to determine the option with overall best
value. 
Route 4: New Build Johnstone High at an Alternative Site
Build a new Johnstone High School elsewhere in the catchment on a suitable site; on
completion, demolish the current building and sell or develop the land.
Main Advantages:
Strategic Fit • This would deliver a new school built to modern educational and building standards,
of a size that allows for optimal occupancy and greater operational efficiency,
delivering an asset with the longest potential operational life.
• Meets the requirements of Renfrewshire Council’s vision for education and the
objectives of the Learning Estate Strategy
• It would directly contribute towards net zero ambitions through provision of a new
school built to NZPBS standard or better, with significant improvements in energy
consumption to the existing school.
• Would allow repurposing of the existing site for Council use or sale.
Value for Money • Creation of a building with modern mechanical and electrical systems will greatly
improve operational efficiency, and a new build provides the opportunity to secure a
learning facility with the maximum future life to support long term value for money
benefits.

Page 127

Johnstone High School Outline Business Case  25
OFFICIAL-SENSITIVE
• The overall cost may be less than that for a retrofit of the existing school.
Achievability  • Flexibility of timescale through the continued operation of the existing school during
the design and build process 
• Avoids decanting of the school community with all associated cost and upheaval
Main Disadvantages:
Value for Money • The cost of buying suitable land for the new school if suitable Council-owned land
cannot be identified.
• Depending on the location chosen, the potential for increased school transport
budgets due to increased travel distances for pupils
Achievability • Finding a suitable site for a new school could potentially present some challenges.
Conclusions:
This option would address condition, sufficiency and suitability and would be able to meet most if not all of the
objectives of the Learning Estate Strategy. As outlined above an alternative site may introduce wider
considerations including meeting active travel objectives if appropriate land cannot be sourced in an appropriate
location of the catchment area coupled with the scale of requirement associated with the number of pupils
requiring home to school transport. Such implications will become clearer through specific site assessment
process. However, this route forward should continue to be progressed further to identify alternative
delivery options to determine the shortlisted options which present the overall best value. 
3.2. Preferred Route Forward
Qualitative assessment of the potential routes provided commentary on their
practicality, adaptability and desirability, aligned to the critical success factors outlined
in the Strategic Case for Change. This identified the route that does not offer a viable
means of delivering the required change and confirmed preferred routes forward to
address the capacity, condition and suitability of Johnstone High. The preferred routes
forward are: 
Route 2 – Retrofit the existing Johnstone High
Route 3 – New Build Johnstone High at the Current Site
Route 4 – New Build Johnstone High at an Alternative Site

Page 128

Johnstone High School Outline Business Case  26
OFFICIAL-SENSITIVE
These routes forward were recommended to Members of this Board and agreed
following an update to the E&CS Policy Board in October 2025. 
3.3. Site Assessment Criteria 
The preferred route forward indicates that viable options are dependent on
identification of a suitable site for the construction of a new Johnstone High School. To
identify potentially viable sites, a list of site assessment criteria has been derived by
considering core legislative, policy, and technical considerations. A long list of potential
site options has been assessed to identify sites that present potential viability and
warrant further investigation and feasibility assessment. Note that this stage of the
process is a broad pass / fail assessment of long list options for viability purposes and is
not a weighted scored assessment. A more detailed assessment approach of this nature
will form part of the next stage of the business case process. The utilised assessment
criteria are as follows: 
Ownership  Sites wholly within the ownership of Renfrewshire Council will be prioritised
over those owned by others recognising this provides greater certainty of
site deliverability. Consideration will be given to brown field sites where
remediation and use will be of benefit to the community, or where sites can
provide for the retention and or improvement of community facilities,
amenities or green spaces.
Site size/area Sites will be assessed against the median area requirements set out in BB103
as sufficient for a school of the following size and description:
a) Accommodate a secondary school of 1,000 pupils and additional
community space, equating to 58,800m2 
Active Travel A review of sites in relation to their potential to support Active Travel,
proximity to public transport, road networks, cycling and walking routes; the
potential for increased pupil transport requirements.
Planning Sites will be assessed against current local & national planning policies and
current land area designation.
Placemaking Consideration will be given to potential for place making benefits, such as
community and green public spaces. Areas will be assessed for their context

Page 129

Johnstone High School Outline Business Case  27
OFFICIAL-SENSITIVE
within and connection to the local community and how strategic use of the
site could bring wider, long-term benefits to the area.
Flood Risk Sites will be assessed in line the guidance set out in Policy 22 of the NPF4.
Flood risk potential is common and significant across the Renfrewshire
estate and dependent on the scale of risk, will not necessarily result in the
rejection of a site. The level of risk and site history, along with the impact of
remediation and flood protection will all be considered in the assessment of
the site.
An assessment of site topography will examine factors that may affect the
efficient use of the site, including shape, gradients across and adjoining the
site, features such as water ways, culverts & previous uses. Previous
industrial use may bring issues of ground contamination or existing
buildings that need to be factored into site remediation.
Budget Budget considerations will principally be concerned with highlighting
potential additional costs for abnormal site issues.  For example,
construction on brown-field sites requiring ground remediation works for
ground contaminations. Projects in green or rural areas incurring additional
costs associated with installing utilities, and the construction or upgrade of
local road and pedestrian routes.
Commentary Any additionally significant issues that require consideration, such as
location within the catchment area. 
Table 11: Site Assessment Criteria 
The following five sites were identified as within Council ownership and located in the
catchment area and were therefore subject to assessment. The sites were considered
against the criteria and the requirements for change. A desktop assessment was
completed for each site, which has concluded that three sites, including the current site
of the school, have strong viability potential and are appropriate for further detailed
examination and assessment at the next stage. A high level overview of the viability
assessment for each site is outlined below and represent the longlist of site options to
deliver the project.
Any site which is recommended for further investigation as a viable option will be
subject to thorough legal checks around ownership to ensure a full understanding of
any constraints on development and its likely impact. Should any site require legal

Page 130

Johnstone High School Outline Business Case  28
OFFICIAL-SENSITIVE
processes to amend land designation this would be fully considered at the next stage of
assessment and reflected in project timelines where appropriate.
Over and above this long list of Council owned sites, an exercise was also conducted to
analyse additional areas of land in private ownership in the town, to determine
potential viability to develop a new secondary school. This process concluded there are
no additional parcels of land in private ownership that offer a better option than those
identified in Council ownership and was therefore not progressed any further given the
added complexity lack of ownership would bring.

Page 131

29
OFFICIAL-SENSITIVE 
3.4. Site Options Assessment
5 sites within Council ownership have been identified and assessed. The location of the sites is shown on the map below. A
full assessment of all 5 sites then follows.
Map 1: Site Options

Page 132

Johnstone High School Outline Business Case  30
OFFICIAL-SENSITIVE

Page 133

Johnstone High School Outline Business Case  31
OFFICIAL-SENSITIVE

Page 134

Johnstone High School Outline Business Case  32
OFFICIAL-SENSITIVE

Page 135

Johnstone High School Outline Business Case  33
OFFICIAL-SENSITIVE

Page 136

Johnstone High School Outline Business Case  34
OFFICIAL-SENSITIVE

Page 137

Johnstone High School Outline Business Case  35
OFFICIAL-SENSITIVE
Site Summary
Site
Ref. Site Name Strategy (Extend/New
build/Renovate/Dispose)
Recommended
to take
forward to FBC
Rationale
1 Existing Johnstone High School New Build Yes
The viability of this option will become clearer in the investigation of a
potential decant strategy, which will inform costs and assess the likely
disruption to the working of the school. This option should continue to be
assessed further and can then be compared against alternative options to
determine the option with overall best value.
1 Existing Johnstone High School Renovate Yes
Whilst challenges exist with this option, it is proposed to be retained and
investigated further, particularly around potential decant logistics, and
associated costings of the project. This can then be compared against
alternative options to determine the options with overall best value. 
2
Site at Johnstone / Howwood By-Pass,
Johnstone New Build No
Loss / Destruction of green space, Hazards including Black Cart Water, Existing
Overhead High Voltage Power Infrastructure, Significant earthworks required
to allow development of site. Construction of road access routes are
challenging.
3 Beith Road Playing Fields, Johnstone New Build No
Site Size may be too small to develop a modern high school to the full potential
that could be realised on a larger site. 
4 Site at Midton Road, Howwood New Build No
Agricultural land requires change of use; the existing road infrastructure would
require significant upgrading and volume of traffic may be detrimental to the
surrounding area. Position of site away from urban population would require
significant increase in transport requirement
5 Thomas Shanks Park, Johnstone New Build No
As a public park gifted to the people of Johnstone in 1926, Thomas Shanks Park
has significant legal protection as an open space within the town. It will not be
taken further as a potential site.
Table 12: Option Recommendations

Page 138

36
OFFICIAL-SENSITIVE
3.5. Shortlisted Options 
Based on the site assessments, the following options can be deemed potentially viable
locations for a new build Johnstone High School, as shown previously in Table 3: 
Option 01
Retrofit Johnstone High School on Site 01 Johnstone High School Beith Road, Johnstone
Option 02
New Build on Site 01 Existing Johnstone High School Site, Beith Road, Johnstone
Option 03
New Build on Site 03 Beith Road Playing Fields, Johnstone 
It is recommended that these options are taken forward to the next stage of assessment
at Full Business Case, to be considered as part of extensive engagement, and further
technical and cost analysis.
Any site which is recommended for further investigation as a viable option will be
subject to thorough legal checks around ownership to ensure a full understanding of
any constraints on development and its likely impact. Should any site require legal
processes to amend land designation this would be fully considered at the next stage of
assessment and reflected in project timelines where appropriate.

Page 139

Johnstone High School Outline Business Case  37
OFFICIAL-SENSITIVE
Map 2: Shortlisted Sites 
3.6. Indicative Costs
The indicative costs are based on preliminary information and should be considered a
framework from which detailed cost plans can be developed. The indicative costs have
been built from high level information, benchmarking from various sources including
the Scottish Futures Trust (SFT) funding metric, cost information from current
Renfrewshire Council education construction projects, costs from other Council’s
similar school projects and adjusting the costings where specific knowledge has been
gained from the desktop assessment of the site options. The BCIS cost indices have also
been used to calculate inflation up to the end of the anticipated construction period. 
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the

Page 140

Johnstone High School Outline Business Case  38
OFFICIAL-SENSITIVE
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicate what is assumed as included
in the costs and what is excluded at this stage.
To project an estimated cost for inflation purposes, the construction cost has been
based on an assumed construction commencement date of 2030. All figures should be
noted as exclusive of VAT.
Key assumptions and exclusions were used in compiling the indicative costs in the
absence of any design commencing. This approach recognises that whilst a range of
cost estimates have been presented, these remain volatile, subject to external factors
and site specific detail that will become clearer as sites are investigated, and options
further explored at the next stage.
It is important to highlight as part of this process, that no budget will be requested or
crystalised until further work has been undertaken into the validation of each option,
and a recommendation is made thereafter at the conclusion of the Full Business Case. 
As shown previously in Table 4, the indicative costs are highlighted below: 
Cost Scenario Range
Option 1 – Retrofit the existing
school
£122m
Option 2 – Rebuild on the current
Johnstone High site
£85 - £133m
Option 3 – Rebuild elsewhere in
the catchment area
£91 - £144m

Page 141

Johnstone High School Outline Business Case  39
OFFICIAL-SENSITIVE
3.7. Transport Considerations
Renfrewshire Council policy states that secondary school pupils who live more than two
miles away from their catchment school by the shortest safe walking route, are eligible
for home to school transport. 
Based on pupil census data for 2025/6, 106 pupils (13%) are eligible for transport to and
from school.  If the location of the school were to change, based on this data it would
change as shown below. This does not take into account any expected roll variation at a
new school and is based on 2025-6 data and is shown for comparison only. 
Current School Pupils Eligible
Johnstone High 106
Possible School Site Pupils Eligible
Site 01 – Existing
Johnstone High 106
Site 3 - Beith Road
Playing Fields 185  
Table 13: Transport Eligibility

Page 142

40
OFFICIAL-SENSITIVE
3.8. Timeline and Next Steps
Should the recommendations contained in this OBC be approved, officers will commence work to identify and recommend
a preferred option for the replacement of Johnstone High School. 
The next steps in that process are to complete a Full Business Case articulating the recommended option by the end of
2026, for presentation and agreement early in 2027. If approved by Council, should it be required, based on the option,
work would begin on Statutory Consultation to be carried out during 2027. Timescales would be dependent on timing
around Local Government elections scheduled for May 2027 and completion of the associated RIBA stages, with the current
anticipated timeline showing that construction could commence by 2030.

Page 143

41
OFFICIAL-SENSITIVE
4. COMMERCIAL CASE
4.1. Approach
An overarching procurement strategy will be prepared as the Project develops, and a
preferred option for delivery is identified. The strategy will set out the various contracts
required to deliver the project including the proposed procurement route, contract
objectives, tender methodology and timelines. Pre-market engagement and
consultation will be undertaken to ensure a detailed market analysis is completed to
test the suitability of the proposed approach to procurement and ensure proposals are
attractive and viable for the competitive market. 
The Project procurement strategy will remain a live document, updated to reflect the
outcomes of each stage of the project’s development and responsive to changes in
market conditions identified through analysis and ongoing engagement. Bespoke
contract strategies will be developed for each requirement detailing the specific
requirements and tendering methodology adopted for that contract while aligning with
the overall aims and objectives set out in the overarching strategy.
4.2. Service Requirements
The project team require external consultants to provide specialist services and works
to support the development of the Full Business Case. Services required may include
support with space planning, site surveys, intrusive building surveys, legal and planning
advisers and cost consultants.  The Project team will work with dedicated procurement
officers to develop strategies for each contract requirement with consideration to the
Council’s standing orders relating to Contracts and principles of best value.
4.3. Project Development
Procurement strategy will be developed for the FBC stage that will discuss in detail the
most beneficial route to market depending on the proposed final recommendation.

Page 144

Johnstone High School Outline Business Case  42
OFFICIAL-SENSITIVE
The procurement process for the detailed design and construction stages of the project
is subject to development. The Council is looking at a range of options including
framework routes for procurement of consultants and/ or contractors. In the event
there are no suitable existing arrangements to use, it is anticipated options will be as
follows:
• Multi- disciplinary design team (MDDT) procured using Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. 
• Construction works contract, likely to follow a Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. It is likely to be a 2-stage
contract model with pre-construction services agreement (PCSA) to allow early
contractor involvement followed by award of main works contract once detailed
design is complete. 
• Ad-hoc/specialist consultant support may be required to support the project
team. The project team will work with dedicated procurement officers to
develop a strategy for each contract with consideration to the Council’s standing
orders relating to Contracts and principles of best value.

Page 145

Johnstone High School Outline Business Case  43
OFFICIAL-SENSITIVE
5. FINANCIAL CASE
5.1. Project Funding – Capital Expenditure
Until such time that a specific option has been decided to proceed with at the
conclusion of the business case process, no formal project exists and therefore no full
capital budget exists. The purpose of this business case process is to allow a decision to
be made on the best option to commit capital expenditure on, and only at the
conclusion of the process will a request be made to Council to commit to the required
project budget. 
This OBC has outlined the current estimated cost to deliver on the agreed route
forward, and this estimate will continue to be refined and updated as more detail
becomes available at the next stage of assessment. 
5.2. Approvals Process
To date, work to develop proposals for a new Johnstone High School has not incurred
any external costs, with all spend being incurred on already budgeted internal
resources. To take the project forward through to approval of the FBC further costs will
be incurred on both internal and external resource. This spend is required to ensure the
Council is presented with a robust and tested recommendation with professional
advice on the specifics of the option.
To conclude and present the FBC for this project, a budget will be required and will be
progressed through established budget setting processes. This budget is made up of all
internal technical resource costs and all external professional services and consultant
appointments required to interrogate and validate the shortlist of options. This cost is
made up as follows:
• Internal technical management costs to deliver project feasibility, cost
management, architectural services and project management
• Flood risk assessments
• Roads and transportation assessments 
• Space planner to produce timetabling and demand modelling to develop
schedule of accommodation 
• Civil engineering to conduct ground investigation surveys on shortlist of sites

Page 146

Johnstone High School Outline Business Case  44
OFFICIAL-SENSITIVE
• Structural engineer to conduct intrusive survey of existing asset as required
Approvals for spending this development budget will be agreed through current project
governance to ensure accountability and transparency. 
5.3. Revenue Expenditure
The new Johnstone High School will be owned and operated by Renfrewshire Council.
The operating model will align with current arrangements for Renfrewshire Council
assets and learning establishments. 
Potential operating costs for a new school will be further explored as part of the Full
Business Case which will be developed throughout 2026. Whole life cost modelling will
capture elements of future revenue spend across the expected lifetime of the proposed
new school.  Operating costs for the current school have been captured and are
indicated in the Strategic Case, above. Initial indication shows that the cost of operating
a new high school would be broadly reflective of current operational costs including
staffing, and facilities management. 
It should however be noted that depending on the specific location of the shortlist of
options, the cost of school transport could vary, albeit this cannot be seen as a single
measure of value in an option. The cost of delivering home to school transport has to be
considered in the broader context of the educational and community value that can be
derived through the development of a new school. This matter will be explored in more
detail at the FBC stage where each of the shortlisted options will be investigated in
greater detail for the estimated revenue costs associated with it. 
5.4. Indicative Costs
The indicative cost information outlined in sections 1.7 and 3.6 was prepared using
current market cost information, including Scottish Futures Trust (SFT) benchmark
data, cost information associated with current Council education construction projects,
and BCIS cost forecast indices to underpin indexing current construction cost metrics to
anticipated future construction date. Indicative costs are based on an assumed
construction commencement date of 2030, and all costs should be considered as
exclusive of VAT.

Page 147

Johnstone High School Outline Business Case  45
OFFICIAL-SENSITIVE
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicates what is assumed as included
in the costs and what is excluded at this stage.
The cost range, as shown previously in Table 4, gives a high-level indicative estimate
based on a number of key assumptions and exclusions which may be subject to change,
given the early stage of the project. These will be further refined as the project
develops. 
Cost scenario Range
Retrofit the existing school  £121m
Rebuild on the current site  £89 - £128m
Rebuild elsewhere in the
catchment area 
£96 - £139m 
The key assumptions and exclusions used in compiling potential costs help ensure full
financial transparency. The following are highlighted as examples:
Assumptions:
• It is assumed the works shall be phased to allow the retrofit of the existing Johnstone
High School. Maximum of 5 phases.
• Estimated costs are based on construction costs at prices (4th Qtr. 2025).
• It is assumed services and utility connections are available locally.
• Inflationary allowances have been made in accordance with current published BCIS
Tender Price Indices.

Page 148

Johnstone High School Outline Business Case  46
OFFICIAL-SENSITIVE
Exclusions:
• Refurbishment works costs to the existing Johnstone High School during the new high
school construction have been excluded
• Legal Costs 
• Planning Conditions
• Section 75 Planning works/contributions
• Operational costs, Hard FM or Lifecycle/Whole Life costs
Cost estimates for this project assume that Johnstone High School must be rebuilt on a
suitable site wholly owned by Renfrewshire Council, to preclude the cost of land
purchase. The estimates were developed on the basis of provision for 1,000 pupils.
Whilst the project may not build to this exact number of pupils, it provides a realistic
baseline to analyse costings. 
5.5. Financial Risk / Optimism Bias
In calculating potential costs, the estimate includes an allocation for risk and
uncertainty. For example, it must be acknowledged that cost indications are based on
an indicative programme that includes a construction period, commencing in 2030.
Where a delay occurs and the programme slips, costs would inevitably change as
factors such as inflation are brought to bear.
Optimism bias allows for mitigation of any unexpected increases or changes
throughout the process but cannot account for all external factors. 
5.6. Interdependencies
As indicated, the project examining the future of Johnstone High School is developing
concurrently with two other Learning Estate capital projects. All three projects are
working to an overall aspirational budget commitment that will continue to be defined
and will require Council commitment to secure the required budget at the conclusion of
the Full Business Case process. 
Different requirements, circumstances and context for each project will have a bearing
on the final cost requirements and their share of the overall funding available, making
them highly dependent on each other.

Page 149

Johnstone High School Outline Business Case  47
OFFICIAL-SENSITIVE
6. MANAGEMENT CASE
6.1. Project Management and Project Governance Overview
Currently, Renfrewshire Council is undertaking several capital projects focussed on
learning estate improvements, covering both primary and secondary schools. This work
has built on existing expertise within the key teams likely to be involved in any project
to improve the provision of Johnstone High, giving the Council an experienced pool of
resources to draw from. Work is underway within Children’s Services to create a
dedicated Learning Estate Programme Team to deliver on the ambition of the Learning
Estate Strategy.
6.2. Project Roles
Learning Estate projects will be overseen at Chief Officer level by the Director of
Children’s Services who acts as the Programme Sponsor for all projects. Senior
accountability is assumed by the Head of Education for Strategy and Improvement who
takes the position of Senior Responsible Owner (SRO). 
In common with all Learning Estate projects, delivery of change for Johnstone High
School will be led by the Strategic Learning Estate Manager who holds senior
accountability of project delivery to the SRO with day-to-day project leadership guiding
the project teams through all aspects from inception, through to construction
execution and handover. This leadership hierarchy will ensure that projects are
successfully delivered upholding quality across project time, cost, and scope, ultimately
delivering the intended outcomes and high-quality learning establishments for all.  The
Strategic Learning Estate Manager will be guided by subject matter experts who will
control and resource the programme with the appropriate skillsets, with professional
technical management in construction and the built environment coming from the
Council’s Technical Services. 
It is crucial to note however, that whilst leadership roles have been established,
appropriate officer level programme governance has been established to ensure that
there is no single source of programme decision making. This process ensures
accountability and robust decision making with representation covering all key Council
services.

Page 150

Johnstone High School Outline Business Case  48
OFFICIAL-SENSITIVE
Each project will require bespoke levels of resource depending on the scale and
complexity but will follow a consistent approach. A dedicated Programme Manager will
lead the overall success and delivery of the programme by implementing and executing
full governance and control across all projects, supporting the Strategic Learning Estate
Manager. 
Project management resource will be provided by the Council’s Programme
Management Unit to cover business case development, business change processes, and
fundamental client-side project management throughout the lifecycle. Technical
expertise will be provided by the Councils’ Technical Services who will provide
construction project management, contract management, and subject matter expert
roles where appropriate through design and delivery. 
Additional resources will be required for each project with ongoing resource allocation
covering critical services such as Finance, Communications, Education, Procurement,
and Legal. 
All resources allocated to Learning Estate projects will report to the Strategic Learning
Estate Manager for their involvement in these projects, with decision making being
made by the appropriate authority level, either the Project Board, or Delivery Board, as
noted below in section 6.3. 
The Council has developed significant experience over the past 15 years delivering
major and complex investment programmes across the learning estate (which includes
three major projects currently in delivery), leisure estate, cultural estate as well as
major transport infrastructure. This experience places the Council in a strong position
to understand the resource and governance arrangements required to deliver
investment programmes of scale and this will be invaluable to support the Council’s
investment focus shifting to a long-term strategic learning estate investment
programme.
6.3. Reporting Arrangements
This project will be monitored using current project management tools to record
progress against timelines, monitor risk, and track change etc. Reporting will be used to
manage and drive the project and ensure accountability to the public more generally.
Beyond day-to-day project management activity, reporting will occur at regular

Page 151

Johnstone High School Outline Business Case  49
OFFICIAL-SENSITIVE
intervals to established boards, with key decisions and milestones signed off at an
appropriate level. 
At Council level, this project will be reported to the Education & Children’s Services
Policy Board for all decision making and progress updates. Where financial decisions on
matters such as high value contract awards are required, this project will report to the
Finance, Resources & Customer Services Policy Board as per agreed Council
governance.
At officer level, this project will be reported to both a Project Board, and a Delivery
Board. The Delivery Board holds the senior officer level decision making authority for
the project, and will act as the ultimate officer level decision making body within its
terms of reference and agreed scope/authority. This Board consist of Director / Head of
Service representation of all key Council services. 
The Project Board will consist of Senior Managers / Heads of Service of all key Council
services and will act as the operational decision making body for all matters as agreed
in the scope, budget, and timeline of the project. 
This governance is illustrated in the image below:

Page 152

50
OFFICIAL-SENSITIVE 
Education & Children s Services Policy Board
Learning Estate Delivery Board
Chair – Director of Children s Services
Director / Head of Service Representation
Strategic Learning Estate Manager (Strategy & Delivery Lead)
Learning Estate Project Board
Chair – Head of Education Strategy & Improvement
Head of Service / Senior Manager Representation
Finance, Resources & Customer Services Policy Board (FRCS)
All Learning Estate High Value Project Contract Awards
Senior Managers and Specialist Advisers
Project Delivery Team
Council Decision Making Level
Officer Decision Making Level
Project Delivery Level

Page 153

51
OFFICIAL-SENSITIVE
6.4. Procurement Strategy
The project team has a dedicated specialist procurement officer who will take the lead
in developing an overarching Learning Estate Project Procurement Strategy. 
In the short term, initial assessment of the project will identify any requirement for
consultant services to assist with technical aspects of project development. If the OBC
is approved at E&CS Policy Board, consultants will be required to support the project
team as it develops a Full Business Case (FBC). This work will be led by the specialist
procurement officer and has been referenced in the Commercial Case, above.
6.5. Overall Project Benefits
Provision of a new or extensively refurbished high school in Johnstone would deliver
key project benefits to the school and local community. 
• The modernisation of Johnstone High School, making it fit for purpose, with the
intention that in future, pupils will be educated in the best possible learning
environments
• Maximise operational efficiency through modern, sustainable and efficient buildings
with a reduced need for maintenance of dilapidated buildings.
• A reduction in Renfrewshire Council’s carbon footprint through the operation of a
school better equipped to meet energy performance targets through more efficient
operation
• A community anchor site in west Johnstone providing facilities for public use outside
of school hours, complementing public use of the shared sports facilities of
Johnstone Community Sports Hub
6.6. Community Benefits Realisation Arrangements
Renfrewshire Council has an established and successful Community Benefits approach
which aims to deliver social, economic and environmental benefits for Renfrewshire’s
communities as part of contract delivery. Community benefits are considered for
inclusion on all regulated procurement over £50,000 and are delivered by suppliers and
contractors in partnership with local organisations and supported by the Council’s

Page 154

Johnstone High School Outline Business Case  52
OFFICIAL-SENSITIVE
Community Benefit Forum and Delivery Partners. Monitoring of community benefits will
be managed through project and delivery boards and a benefits realisation strategy will
be aligned with the overarching procurement strategy.
6.7. Risk Management Arrangements
The project team has commenced a risk register to capture and monitor risk on behalf
of the Council. Risk management will remain an active part of the project management
process for the duration of this project with regular dedicated sessions focussing on the
risk register to complement its inclusion as a standing agenda item in project working
groups and meetings at all levels.
6.8. Equalities and Human Rights
Any equality impact on current users and staff at Johnstone High School, as well as the
wider community, as a consequence of this project, will be considered at all stages it
develops. Initial Equality and Human Rights Impact Assessments (EQHRIA) have been
carried out at programme level. This will inform the basis of all future assessments,
where individual impact assessments will be conducted, specifically relating to the
upcoming community engagement and consultation. 
6.9. Communication, Engagement, and Community Voice
Informal community and stakeholder engagement commenced in August this year,
following publication of the SCC. Engagement has included meetings with
headteachers, ward members and the parent council for Johnstone High School, to
keep all interested parties informed of progress and likely timelines for this project. 
A survey was issued to parents and staff, inviting their views on the school and what
they would improve, what should be important for any future investment. Those
findings are referenced in the Strategic Case (section 2.6, above). Responses to the
survey helped shape analysis of the routes forward and options considered in this OBC. 
Engagement with key stakeholders and the wider community will be key to the
successful determination of the overall best value option to proceed with at the

Page 155

Johnstone High School Outline Business Case  53
OFFICIAL-SENSITIVE
conclusion of the Full Business Case. To ensure clear communication and stakeholder
input to the process, the project team will carry out an informal consultation on the
short-listed options described in section 3.5 from April 2026.  More detail is provided in
section 7.1 Summary of Shortlisted Options and Next Steps 
7. CONCLUSION
7.1. Summary of Shortlist of Options and Next Steps 
This outline business case confirms that there is a need to either retrofit the current
Johnstone High, or build a new Johnstone High, either on the current site or elsewhere.
The provisional scope to allow progression of site assessment, costing, and options
analysis is to consider a school of 1,000 pupils. 
The minimum site area required for a high school for 1,000 pupils is 56,656m² as per
Building Bulletin BB103 and 69,746m² as per The School Premises Regulations
(Scotland) 1967.
This business case concludes that from the longlist of options that have been assessed
against the preferred route forward to construct a new high school on a suitable
alternative site. As shown previously in Table 3, the following options should be
progressed to a Full Business Case Process. 
Option 01
Retrofit Johnstone High School on Site 01 Johnstone High School Beith Road, Johnstone
Option 02
New Build on Site 01 Existing Johnstone High School Site, Beith Road, Johnstone
Option 03
New Build on Site 03 Beith Road Playing Fields, Johnstone

Page 156

Johnstone High School Outline Business Case  54
OFFICIAL-SENSITIVE
To prepare the Full Business Case, more detailed site assessments, further cost
modelling, and community consultation are required to recommend a single best value
option to proceed with on conclusion of the next stage of the business case process. 
Taking into account Audit Scotland’s recommendations that the Council include
communities in decision making, the project team will conduct an informal
consultation on the options outlined above.  The purpose of carrying out an informal
consultation during the Full Business Case stage is to:
• Comply with recommended best practice in ensuring that the public are involved
in decision making
• Comply with UNCRC to involve children in making decisions that affect them
• Explain the options clearly to stakeholders and the public
• Understand early in the process local views on the options
• Refine options based on local views and feedback
• Present a final option that is the most suitable for the community and the council
• Reduce the potential for community objections at a later stage
• Enhance relationships with local communities/individuals
Key stakeholder groups that will be engaged in the informal consultation include:
• Pupils and parents – parent councils, all parents and pupils
• Local community – Community councils, youth groups, local development
groups, local interest groups, general population in school catchment
• School staff - Head teachers, teaching staff, admin staff, support staff.  
• Associated schools - parents, pupils and staff of associated primary, secondary or
nursery schools
• Politicians – local ward members, ECSPB members, local MPs, local MSPs, 
• Council Services – all council services who contribute to the creation, running and
maintenance of school facilities
• Future building users – groups with letting arrangements 
• Neighbours – current and potential neighbours to school buildings/sites.
• Statutory bodies – Education Scotland, Police Scotland, Scottish Fire and Rescue
Service, Sport Scotland.

Page 157

Johnstone High School Outline Business Case  55
OFFICIAL-SENSITIVE
Activity Stakeholders Methods
Preparation and
options
development
Senior Officers and SLT
Elected Members
Head Teachers
Briefings
Workshops
1-1 interviews
Targeted Early
Engagement
Parent Councils/Parents
Community Councils
Local Community Groups
Pupils
Staff
Council Services
Roud table meetings
Briefings
Workshops
Focus Groups
Surveys
Broad Public
Engagement 
Associated school parents
and pupils
General public 
Neighbours
Surveys
Public events
Analysis and
Refinement
Project team 
Table 14: Engagement Activity 
The Full Business Case process is expected to take the remainder of 2026 to complete
and will be presented back to a future cycle of the Education and Children’s Services
Policy Board in 2027 for approval of a final recommended option.

Page 158

Johnstone High School Outline Business Case  56
OFFICIAL-SENSITIVE 
Children’s Services
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR

Page 159

1
OFFICIAL-SENSITIVE 
Trinity High School 
Outline Business Case

Page 160

Trinity High School Outline Business Case  2
OFFICIAL-SENSITIVE
DOCUMENT CONTROL SHEET 
Title: Trinity High School
Version Number 2
Document Type: Outline Business Case
Author: Learning Estate Project Team
Date Published: 18/02/2026
Document Versions: 
Version: Name: Update: Date
V0.1 Project team Initial draft 17/11/25
V0.2 Project team Amendments 21/11/25
V0.3 Project team Further draft 25/11/25
V1 Project team First draft for review  17/12/25
V1.1 Project team Update site assessments and section 7 20/01/26
V1.2 Project team Amendments and updates 10/02/26
V2 Project team Final draft following review by Chief
Officers 18/02/26
Supporting Documentation / Location: 
Document Title: Location:
Strategic Case for Change Document.ashx

Page 161

Trinity High School Outline Business Case  3
OFFICIAL-SENSITIVE
Table of Contents
1. EXECUTIVE SUMMARY ........................................................................ 6
1.1. Introduction .......................................................................................... 6
1.2. Background ........................................................................................... 7
1.3. Opportunity ........................................................................................... 9
1.4. Scope and Objectives ............................................................................ 9
1.5. Summary of Routes Forward ............................................................... 10
1.6. Preferred Route Forward and Options Shortlist .................................. 10
1.7. Indicative Costs ................................................................................... 11
1.8. Timeline ............................................................................................... 13
2. STRATEGIC CASE .............................................................................. 14
2.1. Strategic Context ................................................................................. 14
2.2. The Need for Change ........................................................................... 15
2.3. Investment Objectives ......................................................................... 15
2.4. Existing Arrangements ......................................................................... 16
2.5. Initial Engagement .............................................................................. 17
2.6. Scope and Service Requirements ....................................................... 18
3. ECONOMIC CASE .............................................................................. 20

Page 162

Trinity High School Outline Business Case  4
OFFICIAL-SENSITIVE
3.1. Potential Routes Forward.................................................................... 20
3.2. Preferred Route Forward ..................................................................... 25
3.3. Site Assessment Criteria ...................................................................... 26
3.4. Site Options Assessment ..................................................................... 28
3.5. Shortlisted Options ............................................................................. 42
3.6. Site 2, Netherton Avenue, Renfrew – Advanced Manufacturing .......... 43
3.7. Site 8, King George V Playing Fields, Renfrew – Renfrew High School
Consideration .................................................................................................. 44
3.8. Indicative Costs ................................................................................... 45
3.9. Transport Considerations ................................................................... 47
3.10. Timeline and Next Steps ..................................................................... 48
4. COMMERCIAL CASE .......................................................................... 49
4.1. Approach ............................................................................................. 49
4.2. Service Requirements ......................................................................... 49
4.3. Project Development .......................................................................... 49
5. FINANCIAL CASE ............................................................................... 51
5.1. Project Funding – Capital Expenditure ............................................... 51
5.2. Approvals Process ............................................................................... 51
5.3. Revenue Expenditure .......................................................................... 52

Page 163

Trinity High School Outline Business Case  5
OFFICIAL-SENSITIVE
5.4. Indicative Costs ................................................................................... 52
5.5. Financial Risk / Optimism Bias ............................................................ 54
5.6. Interdependencies .............................................................................. 54
6. MANAGEMENT CASE ........................................................................ 55
6.1. Project Management and Project Governance Overview ................... 55
6.2. Project Roles ........................................................................................ 55
6.3. Reporting Arrangements ..................................................................... 57
6.4. Procurement Strategy ......................................................................... 59
6.5. Overall Project Benefits ....................................................................... 59
6.6. Community Benefits Realisation Arrangements ................................. 59
6.7. Risk Management Arrangements ........................................................ 60
6.8. Equalities and Human Rights .............................................................. 60
6.9. Communication, Engagement, and Community Voice....................... 60
7. CONCLUSION ................................................................................... 62
7.1. Summary of Shortlist of Options and Next Steps ................................ 62

Page 164

6
OFFICIAL-SENSITIVE
1. EXECUTIVE SUMMARY 
1.1. Introduction
This outline business case (OBC) is required as part of the Council’s new structured
approach to delivering its long-term strategy for the learning estate across
Renfrewshire. It builds on the context set out in a Strategic Case for Change (SCC)
examining the future of Trinity High School in Renfrew, which was approved in August
2025 at the Education and Children’s Services Policy Board (E&CS Policy Board).
In the SCC, Trinity High School was assessed as working beyond optimal occupancy,
with demand for places projected to outweigh current capacity in the coming years.
Further, the school buildings and the site of the school cannot expand in a way that
would meaningfully improve the learning environment due to space constraints.
Consequently, the condition and suitability of the school cannot be addressed utilising
the current building. As a result, the strategic assessment concluded that the school
cannot meet the ambitions of the Learning Estate Strategy without change.
The purpose of this OBC is to articulate a preferred route forward for the project by
identifying a shortlist of investment options likely to optimise value for money in
delivering change. A longlist of options is presented as part of the OBC, along with
analysis and rationale for their inclusion or exclusion from the shortlist. 
The OBC uses the following framework to present the preferred way forward, utilising
an adapted HM Treasury Green Book approach which is based on the 5 Case model:
Strategic case – confirming that strategic objectives remain current and seek
agreement on the recommendation
Economic Case – helping to determine that the preferred way forward offers value for
money
Commercial Case – working towards a recommended deal by explaining potential
delivery models, procurement and engagement
Financial Case – establishing affordability and funding requirements
Management Case – planning for successful delivery

Page 165

Trinity High School Outline Business Case  7
OFFICIAL-SENSITIVE 
Table 1: Business case development process
1.2. Background
The Learning Estate Strategy published by the Council in 2024, aims to initiate a
strategic programme of investment in schools, through detailed assessment of the
entire learning estate. The ambition of the investment programme is to ‘create the best
possible learning estate to allow children and young people to thrive’.
Schools were assessed against various criteria including condition, suitability for
delivering the curriculum, capacity and demand. Using a prioritisation framework, the
strategy assessed the entire learning estate, identifying those schools in need of long-
term investment planning now, to ensure that the Council is best placed to:
• Secure best value from strategic learning estate decisions around investment 
• Meet the expected long-term demand for education provision across
Renfrewshire whilst delivering improvements in school buildings and learning
environments 
Stage: Stage 1 Stage 2 Stage 3 Stage 4
Stage Outcome: Strategic Outline
Case Outline Business Case Full Business Case Final Delivery Business
Case
Stage Activities:
• Highlighting
strategic context
• Making the case
for change
• Agreeing scope
• Considering longlist
options
• Exploring the
preferred way
forward and
presenting a
shortlist
• Determine potential
value for money
• Preparing for the
potential deal
• Planning for
procurement
• Procuring the
solution
• Contracting the deal
• Ensuring successful
delivery
5-Case Model
(stage of
completeness): 
• Strategic 50%
• Economic 40%
• Commercial 10%
• Financial 10%
• Management 10%
• Strategic 80%
• Economic 70%
• Commercial 40%
• Financial 30%
• Management 50%
• Strategic 90%
• Economic 90%
• Commercial 90%
• Financial 75%
• Management 75%
• Strategic 100%
• Economic 100%
• Commercial 100%
• Financial 100%
• Management 100%
Gateway
Review: Strategic Assessment Business Justification Delivery Strategy
Final Investment
Decision and financial
commitment

Page 166

Trinity High School Outline Business Case  8
OFFICIAL-SENSITIVE
• Ensure that the delivery of any new infrastructure complements other key
strategic objectives being progressed by the Council to optimise the use of assets
for communities and support wider redesign of services that better meet the
needs of communities.
A cohort of 13 priority schools was identified, with Trinity High School in Renfrew, being
identified as the number one priority school for investment in Renfrewshire. This was
based on the condition and suitability of the school building, driven by constraints on
the size of the school’s site, which hampers the Council’s ability and ambition to deliver
an evolving curriculum in the best possible learning environment. A further influence on
the prioritisation of this school was pupil projection forecasts showing the school
capacity being exceeded in the years to come through greater demand from housing
development in the catchment.
As a result, a Strategic Case for Change was produced, to consider the context of key
issues which, if not addressed, would limit the Council’s ability to deliver the objectives
of the Learning Estate Strategy. The document examined the operating context at
Trinity with reference to those objectives:
• Condition
• Suitability
• Sufficiency
• Inclusivity
• Digital
• Sustainability and Net Zero
• Community Facilities and Place shaping
• Active Travel
The Strategic Case for Change articulates the current baseline position at the school
and identifies areas where the limitations of the site mean that the school cannot
expand to meet demand or ensure future delivery of the modern and evolving
curriculum. This context was set against the aims of the Learning Estate Strategy, to
test how likely the current school is to meet the ambition of educating pupils in the best
possible learning environments.
Following approval of the strategic case for change, significant work has been
undertaken to identify options for change that meet these ambitions and align with the
critical success factors articulated in the documents.

Page 167

Trinity High School Outline Business Case  9
OFFICIAL-SENSITIVE
1.3. Opportunity
The opportunity to change and improve the provision of secondary education for pupils
in the Trinity High School catchment area, aims to advance the objectives of
Renfrewshire Council’s new Learning Estate Strategy, and to help meet the ambitions of
wider Council and Scottish Government policies. Those ambitions, fully considered in
the Strategic Case for Change, are summarised here:
• Improving the condition of schools
• Sustainability and Energy Efficiency
• Equity and Inclusion
• Adapting to Future Educational Needs
• Community and Public Use
• Strategic Planning and Investment 
• Collaborative Approach with Stakeholders
The ambitions encompass Renfrewshire Council’s determination to invest wisely whilst
reflecting the importance of operational efficiencies and cost avoidance in delivering
the Learning Estate Strategy. Thus, careful consideration of how to bring change to
Trinity High School, can additionally help increase building operational efficiency
through provision of improved, modern facilities. A new or refurbished school can
deliver modern standards and design and contribute to the Council’s Net Zero
commitments. 
Above all, this OBC sets out the opportunity for Renfrewshire Council to meet its
overarching aim of ensuring that its schools are modern, accessible to all and support
the delivery of high-quality education for learners.
1.4. Scope and Objectives
The Strategic Case for Change set out five overarching investment objectives for Trinity
High School. Any investment in the learning estate must:
• Deliver the best learning environments and facilities possible
• Support improving attainment and ambition
• Maximise operational efficiency across the estate
• Reduce the contribution to the Council’s combined carbon footprint 
• Acknowledge that ageing schools with deteriorating conditions come closer to
the point of being no longer fit for purpose

Page 168

Trinity High School Outline Business Case  10
OFFICIAL-SENSITIVE
Thus, Trinity High School is identified as a school which cannot match current or future
demand; whose building condition and layout hampers delivery of a modern
curriculum and efforts to raise attainment further; whose buildings require
considerable on-going investment simply to maintain the status quo; and which cannot
contribute to Council’s net zero commitments in its current form.
To meet these objectives and deliver change, this OBC will examine viable options for
the delivery of a new-build secondary school for a roll of circa 1400 pupils (to be revised
up or down based on detailed project development) with consideration of any
associated community facilities, in line with the Council’s wider strategic property
strategy. The school should remain within the current catchment area.
1.5. Summary of Routes Forward
Possible options for the future of Trinity High School considered 4 potential routes
forward against the requirements for change:
1 – Do Nothing
2 – Retrofit and Refurb
3 – Rebuild Trinity on the current site
4 – Rebuild Trinity on another site
Analysis of the routes forward are presented in full in the Economic Case in Section 3.
This was produced following the collation of background information included in the
SCC, technical information, and analysis of the operating context at Trinity, as well as
engagement with school staff and parents. 
1.6. Preferred Route Forward and Options Shortlist
The preferred route forward for the project has been determined using the critical
success factors identified in the SCC, to assess the viability of the various options under
consideration. This identified that delivery of change for Trinity High School was
dependent on moving the school from its current location and, consequently, on the
identification of a new site for the school.

Page 169

Trinity High School Outline Business Case  11
OFFICIAL-SENSITIVE
The routes forward and options rationale are discussed in greater detail in the
Economic Case in Section 3 and includes an overview of estimated costs for delivering
the project. 
The preferred route forward can be described as follows:
Address the capacity, school condition and suitability issues facing Trinity High
School by building a new school on a suitable site elsewhere in the catchment area.
This OBC appraises potential site options that have been identified to deliver this
preferred route forward. The shortlisted sites are: 
Site 8 
Rebuild Trinity High School on Site 8 – KGV Playing Fields Renfrew
Site 9
Rebuild Trinity High School on Site 9 – East Craigend, Erskine
Site 10 
Rebuild Trinity High School on Site 10 – Barwood, Erskine
Table 2: Shortlisted Options 
1.7. Indicative Costs
To identify an indicative planning cost for delivering options associated with the
preferred route forward, an exercise was conducted to consider the potential cost of
delivering a school project at the identified planning scale (a secondary school of 1,400
capacity with additional community-use space).
The site at East Craigend, Erskine from the options shortlist and used as an example for
costing purposes, being a site wholly owned by the Council. The total includes the cost
of demolition of the existing Trinity High School building.
The overall potential costs of a new Trinity High School have been estimated as follows:

Page 170

Trinity High School Outline Business Case  12
OFFICIAL-SENSITIVE 
Cost scenario Range
New build stand-alone
Trinity High School on a
suitable site 
£120 - £180m
Table 3: Indicative costs 
The indicative costs above are provided for illustrative purposes only. Costs are subject
to change depending on consultation, design changes, planning requirements and
parameters, site locations and geotechnical site characterisation, procurement routes
and other external factors. Further detail can be found within section 3.7 (Economic
Case) and Section 5.4 (Financial Case) of this document.

Page 171

13
OFFICIAL-SENSITIVE
1.8. Timeline
In 2025 a high-level summary of the timeline for completing this business case process was outlined, as shown below. This
timeline is explained in more detail in section 3 of this document to show a potential route to construction.

Page 172

14
OFFICIAL-SENSITIVE
2. STRATEGIC CASE
2.1. Strategic Context
In August 2025, a business case presented to E&CS Policy Board set out a strategic case
for change at Trinity High School. The paper outlined the background and context,
highlighting links to local and national strategies for education, including Renfrewshire
Council’s Learning Estate Strategy and Fairer Renfrewshire policy, and Scottish
Government’s National Learning Estate Strategy.
The strategic objective for this project is to ensure delivery of the best quality learning
environments for secondary pupils in the Trinity High School catchment area, whilst
ensuring that capacity matches demand for school places, both now and in the future.
This OBC takes that initial case for change and begins the process of identifying options
for change in response to the needs and drivers identified. The policy background is
summarised below.
• Renfrewshire Council Learning Estate Strategy – a long-term structured
approach to assessment of the learning estate through a prioritisation
framework which identifies those areas of the estate most in need of investment.
The strategy ensures careful planning to ensure that limited capital investment is
directed where it will have the greatest impact through reshaping, refurbishing
or replacing existing facilities. 
• Scottish Government’s National Learning Estate Strategy – reflecting the
ambition of the Scottish Attainment Challenge, which promotes equity in access
to quality education facilities as part of a drive to tackle the poverty related
attainment gap and promote inclusivity.
• Fairer Renfrewshire – recognising the role of the learning estate in reducing
inequalities and improving the life chances of pupils across Renfrewshire
• Strategic Planning and Investment – recognising the long-term nature of the
strategy for the learning estate, with a clear framework which identifies those
schools that require replacement, refurbishment or upgrading
• Strategic Property Strategy – seeks to ensure that Renfrewshire Council’s
property estate is strategically located and used to its fullest potential,
complementing existing facilities and services wherever possible.

Page 173

Trinity High School Outline Business Case  15
OFFICIAL-SENSITIVE
2.2. The Need for Change
As articulated in the Strategic Case for Change document which preceded this OBC,
there is a clear and compelling case for introducing change to Trinity High School, as
highlighted by a combination of factors, including:
• Operating beyond optimal capacity – Trinity High School has a planning
capacity of 1,032 pupils and pupil roll this year of 1,026; roll projections indicate
that demand will rise and remain at or over-capacity across the next 10-15 years. 
• Condition and Suitability – ‘Core Facts’ reporting indicates that the condition
(rated ‘B’) and suitability (rated ‘C’) of the of the building should be improved,
and that £10m of spending will be required over the next 20 years simply to keep
the building operating at its current level. The school is built on a site which is
too small for an establishment of its size and population. The school has
expanded over the years through additional buildings but still offers poor
suitability for delivery of the curriculum. It cannot expand further on its current
site. Provision of a school tailored to modern teaching requirements will better
meet the demands of the curriculum. 
• Opportunity to maximise operational efficiency – Provision of a school built to
modern teaching and building standards will help increase building operational
efficiency by replacing ageing facilities which cannot meet modern building
performance standards.
2.3. Investment Objectives
The following objectives have been identified as key to improving school provision in
for Trinity and aligning with the ambitions of the Learning Estate Strategy:
• Effectiveness – Meet the aims of the Council’s Learning Estate Strategy to initiate a
strategic programme of investment in schools; Ensure that every school is considered
in terms of Scottish Government Core Facts reporting criteria; Deliver the best
learning environments and facilities possible, exceeding, where able, Scottish
Government recommendations. 
• Efficiency – Provision of modern learning environments to support improving
attainment for pupils in Renfrewshire.
• Economy – Optimise operating costs for the estate through the creation of buildings
which are more energy efficient and through operation of a more efficient overall

Page 174

Trinity High School Outline Business Case  16
OFFICIAL-SENSITIVE
school estate; Offer a reduction in the costs incurred maintaining ageing buildings;
Operation of buildings of a size suited to current and projected school rolls.
• Compliance – Careful planning for the replacement or refurbishment of schools to
lessen the impact from older buildings and make a valuable contribution to
Renfrewshire Council’s net zero commitments through the operation of more
efficient buildings.
• Replacement – The project acknowledges that as buildings age and maintenance costs
increase, they come closer to the point of being no longer fit for purpose as a Council asset.
2.4. Existing Arrangements
A comprehensive overview of Trinity High School was included in the Strategic Case for
Change and is summarised below. The key facts relating to its operation are outlined in
the following tables and narrative.
Trinity High School is a denominational secondary school serving a catchment area
stretching from the northwest of Renfrewshire on the river Clyde, across Langbank,
Erskine and on to Renfrew and north Paisley. Trinity serves four primary schools in the
catchment area and 5% of current pupils attend from outside the catchment area. The
planning capacity for Trinity High is 1,032. The current roll is 1,026 pupils.
Key facts and operating costs for Trinity High:
School Age Suitability Condition
Trinity High 61 C B
Table 4: Key Facts 
School Capacity Current Roll 2029/30 2033/34
Trinity High 1032 1,026 (99%) 1,010 (97%) 1,030 (99.8%)
Table 5: Capacity and Roll Projection Information (‘Sufficiency’) 
School Utilities Hard &
Soft FM
Teaching Non-
Teaching
Other* Rates Total
Trinity High £283,861 £473,053 £5,143,877 £466,093 £211,004* £139,200 £6,717,088
* Waste, Grounds Maintenance, Transport
Table 6: Overview of Operating Costs

Page 175

Trinity High School Outline Business Case  17
OFFICIAL-SENSITIVE
Location No. of Pupils Current Annual Cost
TRINITY HS - ERSKINE (MAINS
HILL/GARNIEL 40 £33,411
TRINITY HS - BISHOPTON (DARGAVEL
VILLAGE NORTH & SOUTH) /
BARHILL, ERSKINE
(LINBURN/MILLFIELD)/INCHINNAN
144 £73,333
TRINITY HS - BISHOPTON (DARGAVEL
VILLAGE) 10 £57,185
TRINITY HS - INCHINNAN (INDIA
DR)/ERSKINE 50 £33,796
Total: 244 £197,727
Table 7: Transport Costs Breakdown
2.5. Initial Engagement 
Following presentation of the Strategic Case for Change to E&CS Policy Board in August
2025, officers undertook some initial engagement, outlining the processes involved in
identifying opportunities to deliver change.
A survey was issued to parents, carers, and all school staff at Trinity High School,
inviting views around current school provision, including school condition, location of
facilities and what stakeholders feel should be important to the Council in progressing
future school investment.
Analysis of responses from parents, carers and the wider community suggested a
community affection and connection for the school and its location whilst most
respondents acknowledged the challenges the building poses to users. The survey
identified the following key themes and discussion points:
• Modernisation/refurbishment is the most persistent theme: many describe
the building as old, dated, tired and want a significant upgrade. 
• Toilets and hygiene are frequent cited issues: (cleanliness, locks, capacity,
safety/vaping).

Page 176

Trinity High School Outline Business Case  18
OFFICIAL-SENSITIVE
• Social and dining space is viewed as insufficient: calls for more seating,
sheltered areas, and quiet/regulated spaces (including for neurodivergent
learners)
• Sports and outdoor facilities are widely seen as under-provisioned (requests
range from full-size pitches and MUGAs to a swimming pool). 
• Parking/drop-off is problematic; parents want safer, more orderly
arrangements. 
• Location is valued for centrality and transport links, though many note the site
is constrained for growth.
Responses from school staff at Trinity again highlighted some positive aspects of the
school and its location but described issues and challenges posed by the building’s size
and constraints.
• Physical Condition – Significant concerns include inadequate toilets, poor
social spaces, leaks, ventilation problems, and outdated infrastructure.
• Central Location Benefits - The school’s central location offers convenient
transport links and access to local amenities, praised by all staff groups.
• Staff Workspace Challenges - Teaching staff face fragmented departments
impacting efficiency; office staff lack sufficient administrative space and
facilities.
• Security and Safety Concerns - Multiple entry and exit points complicate
monitoring, raising staff concerns about school security and safety.
Both parents and staff strongly support investment in modern, high-quality learning
environments, and highlight the need for buildings in good condition, modern
teaching facilities, improved sports and outdoor learning areas, and robust digital
infrastructure as top priorities for any future redevelopment
2.6. Scope and Service Requirements
The scope of this proposal for change is to provide an improved Trinity High School in
line with the strategic objectives set out and agreed in the Strategic Case for Change,
informed by an understanding of the operating context. Potential routes forward were
set out in an interim update to E&CS Policy Board in October 2025, based on the broad
range of options outlined in the Economic Case, below. This included an accompanying
assessment of advantages and disadvantages as well as a narrative description of the
preferred way forward.

Page 177

Trinity High School Outline Business Case  19
OFFICIAL-SENSITIVE
To provide a basis on which to consider potential options to invest in Trinity High
School, a provisional scale was set as a secondary school of 1,400 pupils, with an
additional 500m2 of community space that can be developed into an appropriate
community offer, following engagement. (500m2 total site space, 300m2 gross internal
floor area). To allow this scale to be translated into building footprint and site size
metrics, BB103 guidance was utilised as the best practice metric for sizing. 
The outputs of this indicate that a secondary school of 1,400 pupils plus community
space equates to an ideal site requirement of 79,310 m2 (19.6 acres). 
The potential routes forward were informed through consideration of a broad range of
options for change with an accompanying assessment of their advantages and
disadvantages, concluding with a narrative description of the preferred way forward. 
The routes are summarised here: 
Route 1 Route 2 Route 3 Route 4
‘Do nothing’ – Retain
the building as-is and
continue to operate
the high school in its
current format
Retrofit/Refurbish
Trinity High School to
improve its overall
condition and
suitability
Rebuild Trinity High
School at the current
site
Rebuild Trinity at a
new site elsewhere in
the catchment area
Table 8: Potential Routes Forward

Page 178

Trinity High School Outline Business Case  20
OFFICIAL-SENSITIVE
3. ECONOMIC CASE
3.1. Potential Routes Forward
In line with the summary of routes forward that are outlined as part of the Strategic
Case, each has now been subject to an assessment process to identify the broad
advantages and disadvantages to assess the overall merits of each option. 
This process allows in the first instance, identification of recommended viable routes to
be considered in more detail to establish a long list of options to be considered. In the
case of Trinity, the analysis outlined below identifies there is only a single
recommended viable route forward from which a long list of potential options has been
identified. The recommended route forward is: 
Route 4 - Rebuild Trinity HS at a new site within in the catchment area. 
An overview of the rationale of why Route 4 has been identified as the only
recommended viable route is outlined in the detailed assessments below: 
Route 1: Do nothing
Retain the building as-is, with minimal wind and watertight investment, and continue to
operate the high school in its current format.
Main Advantages:
Value for money  • Lower capital outlay required, albeit significant future capital outlay will still be
required on building maintenance to secure long term wind and watertight
condition, and to support net zero transition, none of which would support
improvement to configuration or suitability for delivering the curriculum. 
• Long term demand on places for Trinity could potentially be managed through
strict application of Renfrewshire Council admissions policy for schools.
Main Disadvantages:
Strategic Fit  • Maintaining the current building will not help ensure delivery of the best possible
learning environments for all users, nor would it meet the objectives of the
Learning Estate Strategy or help future proof against further developments in
technology or curriculum.
• Although Trinity predates minimum space requirements under School Premises
(General Requirements and Standards) (Scotland) Act 1967, and Area Guidelines
for Mainstream Schools (BB103) it should be stressed that the site is severely

Page 179

Trinity High School Outline Business Case  21
OFFICIAL-SENSITIVE
constrained, with little usable outdoor space and the school would not be built to
its current size and extent if planned now.
• School capacity is not sufficient for demand, making operation less efficient and
more expensive
• The current building does not meet the ambition of the Learning Estate Strategy in
that it will not help ensure delivery of the best possible learning environments for
all users or help future proof against further developments in technology and
curriculum. 
• Does not contribute to Renfrewshire Council ambitions for sustainability and
energy efficiency.
Value for Money  • The most recent condition report shows that remedial maintenance cost of at least
£10m over the next 20 years will be required to simply maintain the building as it is
now. This would not bring any improvement to the overall suitability and layout of
the building or its grounds to support curriculum delivery, and the building would
have a limited long term life given its age. In addition, further investment would be
required to support long term net zero ambitions.
• The building is, and would remain in future, too small for its current and projected
roll, making operation less efficient.
Conclusions:
With the disadvantages outlined above, this is not considered a viable solution and will be
discounted as a route forward. This option would bring no benefit to the school or wider community
and would not serve to improve the education experience of anyone involved and is likely to provide
poor long term value for money given the age and condition of the existing school.   
Route 2: Retrofit and Refurbish
Carry out a comprehensive retrofit of Trinity High School to bring it up to Net Zero Public
Sector Building Standards (NZPSBS) or better, whilst improving the overall condition and
suitability of the environments. 
Main Advantages:
Strategic Fit  • Contributes towards net zero ambitions through retention of embodied carbon
and significant improvements in energy consumption.
Value for Money • Creation of a building that is more energy efficient and may improve operational
efficiency
• Potentially, less capital outlay required than for a new-build option, although this
would require detailed analysis particularly given the dual costs of normal
wholescale refurbishment coupled with climate retrofit requirements.

Page 180

Trinity High School Outline Business Case  22
OFFICIAL-SENSITIVE
Main Disadvantages:
Strategic Fit  • Although Trinity predates minimum space requirements under School Premises
(General Requirements and Standards) (Scotland) Act 1967, and Area Guidelines
for Mainstream Schools (BB103) it should be stressed that the site is severely
constrained, with little usable outdoor space and the school would not be built to
its current size and extent if planned now.
• The site constraints would limit the design in being able to deliver the full
ambition of the Learning Estate Strategy. 
Value for Money  • A deep retrofit is a complex and demanding project requiring careful planning
and execution. Although initial capital costs may be less in comparison to an
equivalent new build, the costs will still be significant and the overall remaining
life of a refurbished building is likely to be less than a new build placing a level of
constraint on the long term value for money assessment.
• Due to the design of current building and inefficient layout, large portions of the
building may require to be demolished and rebuilt as part of a retrofit, leading to
the question of whether better overall value would be gained in a new build.
Affordability • The full extent of work required, and therefore cost and timeline, may only
become fully apparent as areas of the internal fabric of the building are exposed
and a full understanding of the buildings condition is apparent.
Achievability  • A decant would be required for pupils of the school over a long spanning
construction period. In a secondary school this would pose significant challenge
in terms of maintaining curriculum delivery and retaining access to specialist
equipment or workshops. This would add a level of complexity and cost to the
project.
• Finding suitable premises in which to base the school during decant may be an
onerous task, whilst the option of decanting the school community throughout
other secondary schools in Renfrewshire risks additional upheaval for other
school communities.
Conclusions:
This option is more attractive in terms of making the most of existing assets, retaining embodied
carbon and addressing Council commitments on net zero. However, the option would fail to
address challenges around suitability and sufficiency, with the footprint of the current site falling
significantly short of current required space metrics for a secondary school of this size and would
present a missed opportunity to deliver long term improvement in the learning estate for the
community. Additionally, although there may be the potential for a degree of short term
affordability benefits, there is significant uncertainty as to whether it would necessarily provide
long term value for money and it would also be highly disruptive to the school existing school
community during the construction period. On this overall basis, this option should not be
considered as a viable route forward.

Page 181

Trinity High School Outline Business Case  23
OFFICIAL-SENSITIVE
Route 3: New Build Trinity High School at Current Site
Rebuild Trinity High School at the current site on its existing footprint with consideration
for partner/community facilities, while decanting pupils elsewhere for the duration of the
demolition and building works. 
Main Advantages:
Strategic Fit  • This would deliver a new school built to modern educational and building
standards, of a size that allows for optimal occupancy.
• It would directly contribute towards net zero ambitions through provision of a
new school built to NZPBS standard or better
Value for Money • Creation of a building with modern mechanical and electrical systems will greatly
improve operational efficiency and a new build provides the opportunity to
secure a learning facility with the maximum future life to support long term value
for money benefits.
Main Disadvantages:
Strategic Fit  • Although Trinity predates minimum space requirements under School Premises
(General Requirements and Standards) (Scotland) Act 1967, and Area Guidelines
for Mainstream Schools (BB103) it should be stressed that the site is severely
constrained, with little usable outdoor space and the school would not be built to
its current size and extent if planned now.
• The site constraints would limit the design in being able to deliver the full
ambition of the Learning Estate Strategy. 
Achievability  • A decant would be required for pupils of the school over a long spanning
construction period. In a secondary school this would pose significant challenge
in terms of maintaining curriculum delivery and retaining access to specialist
equipment or workshops. This would add a level of complexity and cost to the
project.
• Finding suitable premises in which to base the school during decant may be an
onerous task, whilst the option of decanting the school community throughout
other secondary schools in Renfrewshire risks additional upheaval for other
school communities.
Conclusions:
The current site of Trinity High School is unsuitable for construction of a modern school due to the
footprint of the current site falling significantly short of required space metrics for a modern
secondary school of this size. Any option involving decanting of the school community to facilitate
a rebuild or refurbishment of the school would bring considerable challenges and disbenefits. This
option would fail to achieve improvements to the suitability of the school environment due to

Page 182

Trinity High School Outline Business Case  24
OFFICIAL-SENSITIVE
constrained site space. This option should not be considered as part of the preferred way
forward. 
Route 4: New Build Trinity High School at Alternative Site
Build a new High School elsewhere in the catchment area on a suitable site with
consideration for partner/community facilities; on completion, demolish the current
building and sell or develop the land. 
Main Advantages:
Strategic Fit  • This would deliver a new school built to modern educational and building
standards, of a size that allows for optimal occupancy.
• Contributes towards net zero ambitions through provision of a new school built
to NZPBS standard or better, with significant improvements in energy
consumption to the existing school.
Value for Money • Creation of a building with modern mechanical and electrical systems will greatly
improve operational efficiency.
Achievability  • Flexibility of timescale through the continued operation of the existing school
during the design and build process
• Avoids decanting the school community with all associated cost and
complication.
• A secondary school building project on a new site would prove highly attractive
to the market increasing the opportunity to secure best value through the
procurement phase.
Main Disadvantages:
Achievability  • Finding a suitable site for a new school could potentially present some
challenges.
• The cost of buying suitable land to house the new school if suitable Council-
owned land cannot be identified would add to the costs.
• An alternative site could potentially introduce wider considerations such as the
scale of required transport that would need to be factored into the overall
options appraisal process. 
Conclusions:
This option would address condition, sufficiency and suitability and would be able to meet most if
not all of the objectives of the Learning Estate Strategy. As outlined above an alternative site may
introduce wider considerations including meeting active travel objectives if appropriate land
cannot be sourced in an appropriate location of the catchment area coupled with the scale of
requirement associated with the number of pupils requiring home to school transport. Such

Page 183

Trinity High School Outline Business Case  25
OFFICIAL-SENSITIVE
implications will become clearer through specific site assessment process. However, this route
forward should continue to be progressed further to identify alternative delivery options to
determine the shortlisted options which present the overall best value.
3.2. Preferred Route Forward
A qualitative assessment of the potential routes has provided commentary on their
practicality, adaptability and desirability, aligned to the critical success factors outlined
in the Strategic Case for Change. This identified those that do not offer a viable means
of delivering the required change and confirmed a preferred way forward for the
project:
Address the capacity, school condition and suitability issues facing Trinity High
School by building a new school on a suitable site elsewhere in the catchment area.
This route forward was recommended and agreed following an update to the ECSPB in
October 2025.
Whilst the qualitative narrative associated with each route forward clarifies its viability,
further rationale for not considering certain options involving the current Trinity High
School and its site is as follows. 
By considering minimum legislative site sizing, for Trinity High School to accommodate
its current number of pupils with no growth, would require a site of circa 57,000m2. The
current Trinity site is only 19,000m2, falling significantly short of current legislative
requirements. As the school predates the introduction of these current standards, it has
continued to operate, but there could be no justification to rebuild or refurb the current
school on a site that is so constrained in size. By considering potential growth, and
scope of project sizing, up to 1,400 pupils, the site size would require to be 79,000m2 by
following the BB103 sizing requirements. This shows that the current site is circa
60,000m2 too small.
This concludes that there is a compelling case to focus attention on options generation
against Route 4 – to build a new Trinity High School on a suitable alternative site in the
catchment area.

Page 184

Trinity High School Outline Business Case  26
OFFICIAL-SENSITIVE
3.3. Site Assessment Criteria
The preferred route forward indicates that viable options are dependent on
identification of a suitable site for the construction of a new Trinity High School. To
identify potentially viable sites, a list of site assessment criteria has been derived by
considering core legislative, policy, and technical considerations. A long list of potential
site options has been assessed to identify sites that present potential viability and
warrant further investigation and feasibility assessment. Note that this stage of the
process is a broad pass / fail assessment of long list options for viability purposes and is
not a weighted scored assessment. A more detailed assessment approach of this nature
will form part of the next stage of the business case process. The assessment criteria
utilised are as follows:
Ownership  Sites wholly within the ownership of Renfrewshire Council will be prioritised
over those owned by others recognising this provides greater certainty of
site deliverability. Consideration will be given to brown field sites where
remediation and use will be of benefit to the community, or where sites can
provide for the retention and or improvement of community facilities,
amenities or green spaces.
Site size/area Sites will be assessed against the median area requirements set out in BB103
as sufficient for a school of the following size and description:
a) Accommodate a secondary school of 1400 pupils + community space,
equating to 79,310m2 (19.6acres)
Active Travel A review of sites in relation to their potential to support Active Travel,
proximity to public transport, road networks, cycling and walking routes; the
potential for increased pupil transport requirements.
Planning Sites will be assessed against current local & national planning policies and
current land area designation.
Placemaking Consideration will be given to potential for place making benefits, such as
community and green public spaces. Areas will be assessed for their context
within and connection to the local community and how strategic use of the
site could bring wider, long-term benefits to the area.
Flood Risk Sites will be assessed in line the guidance set out in Policy 22 of the NPF4.
Flood risk potential is common and significant across the Renfrewshire
estate and dependent on the scale of risk, will not necessarily result in the
rejection of a site. The level of risk and site history, along with the impact of
remediation and flood protection will all be considered in the assessment of
the site.

Page 185

Trinity High School Outline Business Case  27
OFFICIAL-SENSITIVE
An assessment of site topography will examine factors that may affect the
efficient use of the site, including shape, gradients across and adjoining the
site, features such as water ways, culverts & previous uses. Previous
industrial use may bring issues of ground contamination or existing
buildings that need to be factored into site remediation.
Budget Budget considerations will principally be concerned with highlighting
potential additional costs for abnormal site issues.  For example,
construction on brown-field sites requiring ground remediation works for
ground contaminations. Projects in green or rural areas incurring additional
costs associated with installing utilities, and the construction or upgrade of
local road and pedestrian routes.
Commentary Any additionally significant issues that require consideration, such as
location within the catchment area. 
Table 9: Site Assessment Criteria
The following 11 sites were identified as being within Council ownership and in the
catchment area and were subject to assessment. The sites were considered against the
criteria and the requirements for change. A desktop assessment was completed for
each site, which has concluded that there are 3 options that have strong viability
potential and are appropriate for further detailed examination and assessment at the
next stage. A high level overview of the viability assessment for each site is outlined
below and represent the longlist of site options to deliver the project.
Any site which is recommended for further investigation as a viable option will be
subject to thorough legal checks around ownership to ensure a full understanding of
any constraints on development and its likely impact. Should any site require legal
processes to amend land designation this would be fully considered at the next stage of
assessment and reflected in project timelines where appropriate.

Page 186

Trinity High School Outline Business Case  28
OFFICIAL-SENSITIVE
3.4. Site Options Assessment
11 sites within Council ownership have been identified and assessed. The location of the sites is shown in Map 1, below:  
Map 1: Potential Sites

Page 187

Trinity High School Outline Business Case  29
OFFICIAL-SENSITIVE
The three areas highlighted with a yellow circle represent locations considered as potential sites that are in private ownership, with
the majority already in use.  Having considered these areas, it is clear that there is no additional benefit to either the location, or
the site’s suitability that is greater than any site in Council ownership identified through the list of site assessments contained
within this business case. For that reason, as well as the fact that a financial outlay and significant, lengthy, legal process would be
required to obtain private land, it has been determined that there is no benefit to progressing the consideration of any site in these
locations. 
The 11 site assessments for land in Council ownership are outlined below:

Page 188

Trinity High School Outline Business Case  30
OFFICIAL-SENSITIVE
Option 1: New build Trinity High School on Site 01 Cockels Loan, Renfrew

Page 189

Trinity High School Outline Business Case  31
OFFICIAL-SENSITIVE
Option 2: New build Trinity High School on Site 02 Netherton Avenue

Page 190

Trinity High School Outline Business Case  32
OFFICIAL-SENSITIVE
Option 3: New build Trinity High School on Site 03 Erskine Town Centre North

Page 191

Trinity High School Outline Business Case  33
OFFICIAL-SENSITIVE
Option 4: New build Trinity High School on Site 04 Kilpatrick Avenue, Erskine

Page 192

Trinity High School Outline Business Case  34
OFFICIAL-SENSITIVE
Option 5: New build Trinity High School on Site 05 Kilpatrick Drive, Erskine

Page 193

Trinity High School Outline Business Case  35
OFFICIAL-SENSITIVE
Option 6: New build Trinity High School on Site 06 Bargarran, Erskine

Page 194

Trinity High School Outline Business Case  36
OFFICIAL-SENSITIVE
Option 7: New build Trinity High School on Site 07 Broomhill, Erskine

Page 195

Trinity High School Outline Business Case  37
OFFICIAL-SENSITIVE
Option 8 New build Trinity High School on Site 08 KGV Playing Fields, Renfrew

Page 196

Trinity High School Outline Business Case  38
OFFICIAL-SENSITIVE
Option 9: New build Trinity High School on Site 09 East Craigend, Erskine

Page 197

Trinity High School Outline Business Case  39
OFFICIAL-SENSITIVE
Option 10: New Build Trinity High School on Site 10 Barwood, Erskine

Page 198

Trinity High School Outline Business Case  40
OFFICIAL-SENSITIVE
Option 11: New build Trinity High School on Site 11 Robertson Park, Renfrew

Page 199

Trinity High School Outline Business Case  41
OFFICIAL-SENSITIVE
Site
No Site Name Strategy (Extend/New
build/Renovate/Dispose)
Recommended to
take forward to
FBC
Rationale
0 Existing Trinity High Retrofit or New Build No The footprint of the current site falls significantly short of required space metrics for a secondary school of this
size. This option should therefore not be considered as part of the preferred way forward.
1 Cockles Loan, Renfrew New Build No The existing site is significantly undersized to accommodate a modern High School with the required Capacity under BB104. Site is of
irregular geometry compromising potential.
2 Netherton Avenue New Build No Site is within key strategic area for economic growth; education falls outside of these key factors. Noise from adjacent Glasgow
airport could prohibit external learning opportunities
3 Kilpatrick Drive, Erskine
Town, North New Build No The flood risks associated with this site drastically reduce the practical useable area of the site, effectively brining it below
the minimum requirements of BB103.
4 Kilpatrick Avenue, Erskine New Build No The flood risks associated with this site drastically reduce the practical useable area of the site, effectively brining it below
the minimum requirements of BB103.
5 Kilpatrick Drive, Erskine New Build No The site is considerably undersized to provide minimum secondary school accommodation
6 Bargara, Erskine New Build No
This site is unsuitable for major development with no established publicly accessible routes or adjacencies to suitable
routes.  Providing suitably sized utility connections would likely require a significant development programme to make connections
to existing utility routes on public roads. 
7 Broomhill, Erskine New Build No Significant challenges with topography requiring significant earthworks to allow development which is considered cost and time
prohibitive. Also, significant challenges in creating pedestrian links as there is no existing pedestrian footpath infrastructure
8 King George 5th, Playing
Fields, Renfrew New Build YES
This site has the potential to provide multiple benefits, including positive impacts on active travel, potential for place making and
efficiencies though shared facilities with Renfrew High School, Site Is Located within the existing Trinity High Catchment and is of
adequate size for construction of a Modern High School 
9 East Craigend, Erskine New Build YES
The overall scale of the site and its central location represent potential significant place making opportunities with its proximity to
Park Mains School and the wider Erskine area. Addressing the existing SINC classifications may impact on the planning and statutory
approvals process. The existing overhead power line will restrict potential building development either side of the line, however the
site is sufficiently large enough that building development could be accommodated out with an exclusion zone. 
10 Barwood, Erskine New Build YES
Site is sufficiently large enough to accommodate. Design development, for this site would need to carefully consider how public
amenities are maintained and enhanced by the project, particularly the existing community play and sports facilities. Potential
vehicular access to the site is restricted to the southeast boundary with Barhill Road. However, the site benefits from good existing
pedestrian routes to and around the site that could be expanded to create links via the adjoining residential area to the southwest of
the site.
11 Robertson Park, Renfrew New Build No Requires closure of existing community assets and removal of existing well used public green space
Table 10: Site Summaries

Page 200

42
OFFICIAL-SENSITIVE
3.5. Shortlisted Options
Based on the site assessments and as shown previously in the executive summary, the
following options, as previously shown in Table 2, can be deemed potentially viable
locations for a new build Trinity High School.
Site Option 08
New build Trinity High School on Site 08 – KGV Playing Fields Renfrew
Site Option 09
New build Trinity High School on Site 09 – East Craigend, Erskine
Site Option 10
New build Trinity High School on Site 10 – Barwood, Erskine 
It is recommended that these options are taken forward to the next stage of assessment
at Full Business Case, to be considered as part of extensive engagement, and further
technical and cost analysis. These three shortlisted sites are shown in Map 2, below:

Page 201

Trinity High School Outline Business Case  43
OFFICIAL-SENSITIVE
Map 2: Shortlisted Sites
3.6. Site 2, Netherton Avenue, Renfrew – Advanced Manufacturing
This site was included as a long list option to ensure that all available Council-owned
sites in the catchment area were considered before inclusion or exclusion from the
shortlist. 
The site falls entirely within the Advanced Manufacturing and Innovation District
Scotland (AMIDS), developed by Renfrewshire Council and key partners to bring high-
value jobs to Renfrewshire. AMIDS is a UK national asset, designed to deliver a world-
leading cluster of innovative businesses. There are two anchor tenants in place with
further development commencing this year. 
Funding agreements with partners to develop the site include restrictions on how the
land can be used, to protect the integrity of the asset and the delivery of long term
economic growth targets. The Council has committed to ensure consistency in how
AMIDS is developed and to protect the expected benefits of innovation clustering and
the long-term investment in the site.

Page 202

Trinity High School Outline Business Case  44
OFFICIAL-SENSITIVE
Development of a school at AMIDS would not comply with the restrictions on land use
agreed by the Council, would not meet the Council’s ambitions for the site and would
limit its ability to deliver the benefits of development. 
3.7. Site 8, King George V Playing Fields, Renfrew – Renfrew High School Consideration
Renfrewshire Council has committed to addressing its entire learning estate holistically,
following the principles of the Learning Estate Strategy. Thus, where a priority school
has been identified, officers should consider whether other local facilities could be
improved or upgraded as part of the solution. 
Given that one of the shortlisted sites (Site 8 – KGV Playing Fields) is adjoined to the
location of Renfrew High School, consideration was given to what impact a new Trinity
High School on the same location may bring. 
The primary consideration at this stage of the business case process was to determine if
there was adequate land available on the site of KGV to develop a new Trinity High
School without constraining a future development of a new Renfrew High School. This
desktop assessment concluded that there is adequate land available across the
expanse of KGV to construct a new Trinity High School, without constraining options for
a future potential Renfrew High School on the same site. This assessment has also
demonstrated that through careful design considerations, a new Trinity High School on
this site could be designed in such a way that it supported the basis of how a future
shared campus or shared use of facilities could be implemented, when the appropriate
time to invest in a new Renfrew High School arrives. 
At the point of agreeing the prioritisation of the Learning Estate Strategy, Renfrew High
School was identified as a ‘middle cohort’ school, meaning that it would move to
business case stage for investment over the next 10-20 years. However, in considering
one of the principles of the strategy, neighbouring schools close to options for
development of a priority school could be considered to determine if there is a benefit
of constructing within the same development. 
When considering the option of rebuilding Trinity High on site 08 – King George V
Playing Fields, its size and proximity to the current Renfrew High supported the need for
a desktop exercise to be carried out to consider the feasibility of the site to

Page 203

Trinity High School Outline Business Case  45
OFFICIAL-SENSITIVE
accommodate two school campus. This exercise confirmed that the size and
configuration of the site provided significant flexibility that could accommodate several 
future development options ranging from two separate school campuses with or
without some shared facilities developed independently from each other or at the same
time through to a fully integrated joint campus 
Given this overview shows that it is possible to construct multiple development options
including a joint campus, it allows further work to be conducted through the next stage
of assessment to assess the development options for the KGV site that present the best
value outcome for the Council, and any further community views, technical
assessments or considerations. 
However, it should be noted that estimates for delivering a shared campus option
indicated a cost in the region of £220-320m. When set against the wider Learning
Estate priorities and scale of funding that has to date been made available (£170m)
affordability constraints may limit the deliverability of such an option in a single phase.
It is important to note that this consideration will only be apply to the option of
constructing a new Trinity High School at Site 8 – KGV Playing Fields, due to the fact
that Renfrew High School currently adjoins this site. The process of completing the Full
Business Case, at the next stage, will take an objective view by considering the financial
affordability, technical assessments, and community views on all options presented in
the shortlist. 
3.8. Indicative Costs
The indicative costs are based on preliminary information and should be considered a
framework from which detailed cost plans can be developed. The indicative costs have
been built from high level information, benchmarking from various sources including
the Scottish Futures Trust (SFT) funding metric, cost information from current
Renfrewshire Council education construction projects, costs from other Councils’
similar high school projects and adjusting the costings where specific knowledge has
been gained from the desktop assessment of the site options. The BCIS cost indices
have also been used to calculate inflation up to the end of the anticipated construction
period.

Page 204

Trinity High School Outline Business Case  46
OFFICIAL-SENSITIVE
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicate what is assumed as included
in the costs and what is excluded at this stage.
To project an estimated cost for inflation purposes, the construction cost has been
based on an assumed construction commencement date of 2030. All figures should be
noted as exclusive of VAT.
Key assumptions and exclusions were used in compiling the indicative costs in the
absence of any design commencing. This approach recognises that whilst a range of
cost estimates have been presented, these remain volatile, subject to external factors
and site specific detail that will become clearer as sites are investigated, and options
further explored at the next stage.
It is important to highlight as part of this process, that no budget will be requested or
crystalised until further work has been undertaken into the validation of each option,
and a recommendation is made thereafter at the conclusion of the Full Business Case. 
As shown previously in Table 3, the indicative costs are as follows: 
Cost scenario Range
New build stand-alone
Trinity High School on a
suitable site 
£120 - £180m

Page 205

Trinity High School Outline Business Case  47
OFFICIAL-SENSITIVE
3.9. Transport Considerations
Renfrewshire Council policy states that secondary school pupils who live more than two
miles away from their catchment school by the shortest acceptable walking route, are
eligible for home to school transport. 
Based on pupil census data available for 2025/6, of the current roll, 929 pupils are from
the catchment area, of whom, 244 pupils (26%) are eligible for home to school
transport.  If the location of the school were to change, based on this data it would
change as shown below. This does not take into account the future projected roll
increase and is based on 2025-6 data for comparison only. 
Current School Pupils Eligible
Trinity High 244
Possible School Site Pupils Eligible
Site 8 – KGV Playing Fields,
Renfrew 245
Site 9 – East Craigend,
Erskine 750
Site 10 – Barwood, Erskine 767           
Table 11 – Trinty High - Pupil travel eligibility

Page 206

48
OFFICIAL-SENSITIVE
3.10. Timeline and Next Steps
Should the recommendations contained in this OBC be approved, officers will commence work to identify and recommend
a preferred option for the replacement of Trinity High School. 
The next steps in that process are to complete a Full Business Case articulating the recommended option by the end of
2026, for presentation and agreement early in 2027. If approved by Council, work would begin on Statutory Consultation to
be carried out during 2027. Timescales would be dependent on timing around Local Government elections scheduled for
May 2027 and completion of the associated RIBA stages, with the current anticipated timeline showing that construction
could commence by 2030.

Page 207

49
OFFICIAL-SENSITIVE
4. COMMERCIAL CASE
4.1. Approach
An overarching procurement strategy will be prepared as the Project develops, and a
preferred option for delivery is identified. The strategy will set out the various contracts
required to deliver the project including the proposed procurement route, contract
objectives, tender methodology and timelines. Pre-market engagement and
consultation will be undertaken to ensure a detailed market analysis is completed to
test the suitability of proposed approach to procurement and ensure the proposals are
attractive and viable for the competitive market. 
The Project procurement strategy will remain a live document, updated to reflect the
outcomes of each stage of the project’s development and responsive to changes in
market conditions identified through analysis and ongoing engagement. Bespoke
contract strategies will be developed for each requirement detailing the specific
requirements and tendering methodology adopted for that contract while aligning with
the overall aims and objectives set out in the overarching strategy.
4.2. Service Requirements
The project team require external consultants to provide specialist services and works
to support the development of the Full Business Case. Services required may include
support with timetable and demand modelling, site surveys, intrusive building surveys,
legal and planning advisers and cost consultants.  The Project team will work with
dedicated procurement officers to develop strategies for each contract requirement
with consideration to the Council’s standing orders relating to Contracts and principles
of best value.
4.3. Project Development
Procurement strategy will be developed for the FBC stage that will discuss in detail the
most beneficial route to market depending on the proposed final recommendation.

Page 208

Trinity High School Outline Business Case  50
OFFICIAL-SENSITIVE
The procurement process for the detailed design and construction stages of the project
is subject to development. The Council is looking at a range of options including
framework routes for procurement of consultants and/or contractors. In the event there
are no suitable existing arrangements to use, it is anticipated options will be as follows:
• Multi- disciplinary design team (MDDT) procured using Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. 
• Construction works contract, likely to follow a Restricted Procedure in
accordance with Council’s Standing Orders relating to Contracts and Public
Contracts (Scotland) Regulations 2015 as amended. It is likely to be a 2-stage
contract model with pre-construction services agreement (PCSA) to allow early
contractor involvement followed by award of main works contract once detailed
design is complete. 
• Ad-hoc/specialist consultant support may be required to support the project
team. The project team will work with dedicated procurement officers to
develop a strategy for each contract with consideration to the Council’s standing
orders relating to Contracts and principles of best value.

Page 209

Trinity High School Outline Business Case  51
OFFICIAL-SENSITIVE
5. FINANCIAL CASE
5.1. Project Funding – Capital Expenditure
Until such time that a specific option has been decided to proceed with at the
conclusion of the business case process, no formal project exists and therefore no full
capital budget exists. The purpose of this business case process is to allow a decision to
be made on the best option to commit capital expenditure on, and only at the
conclusion of the process will a request be made to Council to commit to the required
project budget. 
This OBC has outlined the current estimated cost to deliver on the agreed route
forward, and this estimate will continue to be refined and updated as more detail
becomes available at the next stage of assessment. 
5.2. Approvals Process
To date, work to develop proposals for a new Trinity High School has not incurred any
external costs, with all spend being incurred on already budgeted internal resources. .
To take the project forward through to approval of the FBC further costs will be incurred
on both internal and external resource. This spend is required to ensure the Council is
presented with a robust and tested recommendation with professional advice on the
specifics of the option.
To conclude and present the FBC for this project, a budget will be required and will be
progressed through established budget setting processes. This budget is made up of all
internal technical resource costs and all external professional services and consultant
appointments required to interrogate and validate the shortlist of options. This cost is
made up as follows:
• Internal technical management costs to deliver project feasibility, cost
management, architectural services and project management
• Flood risk assessments
• Roads and transportation assessments 
• Space planner to produce timetabling and demand modelling to develop
schedule of accommodation 
• Civil engineering to conduct ground investigation surveys on shortlist of sites

Page 210

Trinity High School Outline Business Case  52
OFFICIAL-SENSITIVE 
Approvals for spending this development budget will be agreed through current project
governance to ensure accountability and transparency. 
5.3. Revenue Expenditure
The new Trinity High School will be owned and operated by Renfrewshire Council. The
operating model will align with current arrangements for Renfrewshire Council assets
and learning establishments. 
Potential operating costs for a new school will be further explored as part of the Full
Business Case which will be developed throughout 2026. Whole life cost modelling will
capture elements of future revenue spend across the expected lifetime of the proposed
new school.  Operating costs for the current school have been captured and are
indicated in the Strategic Case, above. Initial indications are that the cost of operating a
new Trinity High School would be broadly reflective of current operational costs
including staffing, and facilities management. 
It should however be noted that depending on the specific location of the shortlist of
options, the cost of school transport could vary significantly, albeit this cannot be seen
as a single measure of value in an option. The cost of delivering home to school
transport must be considered in the broader context of the educational and community
value that can be derived through the development of a new school. This matter will be
explored in more detail at the FBC stage where each of the shortlisted options will be
investigated in greater detail for the estimated revenue costs associated with it. 
5.4. Indicative Costs
The indicative cost information outlined in sections 1.7 and 3.7 was prepared using
current market cost information, including Scottish Futures Trust (SFT) benchmark
data, cost information associated with current Council education construction projects,
and BCIS cost forecast indices to underpin indexing current construction cost metrics to
anticipated future construction date. Indicative costs are based on an assumed
construction commencement date of 2030, and all costs should be considered as
exclusive of VAT.

Page 211

Trinity High School Outline Business Case  53
OFFICIAL-SENSITIVE
In considering the potential construction costs, it should be noted that all construction
sites are unique and will differ from site to site in ways that will impact construction
costs. This is as a result of ‘abnormal’ factors exclusive to every site. No two sites are the
same, for example flood risk mitigation or ground remediation may be more or less
consequential from site to site, with differing impact on the overall construction costs
as to how the design addresses the site. In that sense, the indicative costs should be
taken as a guide only, detailed site options appraisal will be necessary to fully
understand the geotechnical characteristics and construction cost impact before
making any final recommendations. 
The project is currently at RIBA Plan of Works Stage 0 where at this stage it is key to
define vision and goals, identify needs and opportunities and to establish a strategy.
Therefore, there is no current design information. Key assumptions and exclusions are
required to establish indicative costs and clearly indicates what is assumed as included
in the costs and what is excluded at this stage.
The cost range, as shown previously in Table 3, gives a high-level indicative estimate
based on a number of key assumptions and exclusions which may be subject to change,
given the early stage of the project. These will be further refined as the project
develops. 
Cost scenario Range
New build stand-alone Trinity
High School on a suitable site  £120 - £181m 
The key assumptions and exclusions used in compiling potential costs help ensure full
financial transparency. The following are highlighted as examples: 
Assumptions:
• It is assumed the existing Trinity High School shall remain open while new build
construction works are ongoing
• Estimated costs are based on construction costs at prices (4th Qtr. 2025)
• It is assumed services and utility connections are available locally
• Inflationary allowances have been made in accordance with current published BCIS
Tender Price Indices

Page 212

Trinity High School Outline Business Case  54
OFFICIAL-SENSITIVE 
Exclusions:
• Refurbishment works costs to the existing Trinity High School during the new high
school construction have been excluded
• Legal Costs 
• Planning Conditions
• Section 75 Planning works/contributions
• Operational costs, Hard FM or Lifecycle/Whole Life costs 
These potential costs were produced for a new build high school for the provisional
scope identified as part of this business case, which is a secondary school of 1,400
capacity, with a level of additional community use space.
5.5. Financial Risk / Optimism Bias
In calculating potential costs, the estimate includes an allocation for risk and
uncertainty. For example, it must be acknowledged that cost indications are based on
an indicative programme that includes a construction period, commencing in 2030.
Where a delay occurs and the programme slips, costs would inevitably change as
factors such as inflation are brought to bear.
Optimism bias allows for mitigation of any unexpected increases or changes
throughout the process but cannot account for all external factors. 
5.6. Interdependencies
As indicated, the project examining the future of Trinty High School is developing
concurrently with two other Learning Estate capital projects. All three projects are
working to an overall aspirational budget commitment that will continue to be defined
and will require Council commitment to secure the required budget at the conclusion of
the Full Business Case process.
Different requirements, circumstances and context for each project will have a bearing
on the final cost requirements and their share of the overall funding available, making
them highly dependent on each other.

Page 213

Trinity High School Outline Business Case  55
OFFICIAL-SENSITIVE 
6. MANAGEMENT CASE
6.1. Project Management and Project Governance Overview
Currently, Renfrewshire Council is undertaking several capital projects focussed on
learning estate improvements, covering both primary and secondary schools. This work
has built on existing expertise within the key teams likely to be involved in any project
to improve the provision of Trinity, giving the Council an experienced pool of resources
to draw from. Work is underway within Children’s Services to create a dedicated
Learning Estate Programme Team to deliver on the ambition of the Learning Estate
Strategy.
6.2. Project Roles
Learning Estate projects will be overseen at Chief Officer level by the Director of
Children’s Services who acts as the Programme Sponsor for all projects. Senior
accountability is assumed by the Head of Education for Strategy and Improvement who
takes the position of Senior Responsible Owner (SRO). 
In common with all Learning Estate projects, delivery of change for Trinity High School
will be led by the Strategic Learning Estate Manager who holds senior accountability of
project delivery to the SRO with day-to-day project leadership guiding the project
teams through all aspects from inception, through to construction execution and
handover. This leadership hierarchy will ensure that projects are successfully delivered
upholding quality across project time, cost, and scope, ultimately delivering the
intended outcomes and high-quality learning establishments for all.  The Strategic
Learning Estate Manager will be guided by subject matter experts who will control and
resource the programme with the appropriate skillsets, with professional technical
management in construction and the built environment coming from the Council’s
Technical Services. 
It is crucial to note however, that whilst leadership roles have been established,
appropriate officer level programme governance has been established to ensure that

Page 214

Trinity High School Outline Business Case  56
OFFICIAL-SENSITIVE
there is no single source of programme decision making. This process ensures
accountability and robust decision making with representation covering all key Council
services. 
Each project will require bespoke levels of resource depending on the scale and
complexity but will follow a consistent approach. A dedicated Programme Manager will
lead the overall success and delivery of the programme by implementing and executing
full governance and control across all projects, supporting the Strategic Learning Estate
Manager. 
Project management resource will be provided by the Council’s Programme
Management Unit to cover business case development, business change processes, and
fundamental client-side project management throughout the lifecycle. Technical
expertise will be provided by the Councils’ Technical Services who will provide
construction project management, contract management, and subject matter expert
roles where appropriate through design and delivery. 
Additional resources will be required for each project with ongoing resource allocation
covering critical services such as Finance, Communications, Education, Procurement,
and Legal. 
All resources allocated to Learning Estate projects will report to the Strategic Learning
Estate Manager for their involvement in these projects, with decision making being
made by the appropriate authority level, either the Project Board, or Delivery Board, as
noted below in section 6.3. 
The Council has developed significant experience over the past 15 years delivering
major and complex investment programmes across the learning estate (which includes
three major projects currently in delivery), leisure estate, cultural estate as well as
major transport infrastructure. This experience places the Council in a strong position
to understand the resource and governance arrangements required to deliver
investment programmes of scale and this will be invaluable to support the Council’s
investment focus shifting to a long-term strategic learning estate investment
programme.

Page 215

Trinity High School Outline Business Case  57
OFFICIAL-SENSITIVE
6.3. Reporting Arrangements
This project will be monitored using current project management tools to record
progress against timelines, monitor risk, and track change etc. Reporting will be used to
manage and drive the project and ensure accountability to the public more generally.
Beyond day-to-day project management activity, reporting will occur at regular
intervals to established boards, with key decisions and milestones signed off at an
appropriate level. 
At Council level, this project will be reported to the Education & Children’s Services
Policy Board for all decision making and progress updates. Where financial decisions on
matters such as high value contract awards are required, this project will report the
Finance, Resources & Customer Services Policy Board as per agreed Council
governance.
At officer level, this project will be reported to both a Project Board, and a Delivery
Board. The Delivery Board holds the senior officer level decision making authority for
the project and will act as the ultimate officer level decision making body within its
terms of reference and agreed scope/authority. This Board consist of Director / Head of
Service representation of all key Council services. 
The Project Board will consist of Senior Managers / Heads of Service of all key Council
services and will act as the operational decision making body for all matters as agreed
in the scope, budget, and timeline of the project. 
This governance is illustrated in the image below:

Page 216

58
OFFICIAL-SENSITIVE 
Education & Children s Services Policy Board
Learning Estate Delivery Board
Chair – Director of Children s Services
Director / Head of Service Representation
Strategic Learning Estate Manager (Strategy & Delivery Lead)
Learning Estate Project Board
Chair – Head of Education Strategy & Improvement
Head of Service / Senior Manager Representation
Finance, Resources & Customer Services Policy Board (FRCS)
All Learning Estate High Value Project Contract Awards
Senior Managers and Specialist Advisers
Project Delivery Team
Council Decision Making Level
Officer Decision Making Level
Project Delivery Level

Page 217

59
OFFICIAL-SENSITIVE
6.4. Procurement Strategy
The project team has a dedicated specialist procurement officer who will take the lead
in developing an overarching Learning Estate Project Procurement Strategy. 
In the short term, initial assessment of the project will identify any requirement for
consultant services to assist with technical aspects of project development. If the OBC
is approved at E&CS Policy Board, consultants will be required to support the project
team as it develops a Full Business Case (FBC). This work will be led by the specialist
procurement officer and has been referenced in the Commercial Case, above.
6.5. Overall Project Benefits
Provision of a new Trinity High School would deliver key project benefits to the school
and the wider community including the following: 
• The modernisation of Trinity High School, making it fit for purpose, with the intention
that in future, pupils will be educated in the best possible learning environments
• Maximise operational efficiency through modern, sustainable and efficient buildings
with a reduced need for maintenance of dilapidated buildings.
• A reduction in Renfrewshire Council’s carbon footprint through the operation of a
school better equipped to meet energy performance targets through more efficient
operation.
• A community anchor site in the catchment area providing facilities for public use
outside of school hours.
6.6. Community Benefits Realisation Arrangements
Renfrewshire Council has an established and successful Community Benefits approach
which aims to deliver social, economic and environmental benefits for Renfrewshire’s
communities as part of contract delivery. Community benefits are considered for
inclusion on all regulated procurement over £50,000 and are delivered by suppliers and
contractors in partnership with local organisations and supported by the Council’s
Community Benefit Forum and Delivery Partners. Monitoring of community benefits will

Page 218

Trinity High School Outline Business Case  60
OFFICIAL-SENSITIVE
be managed through project and delivery boards and a benefits realisation strategy will
be aligned with the overarching procurement strategy.
6.7. Risk Management Arrangements
The project team has commenced a risk register to capture and monitor risk on behalf
of the Council. Risk management will remain an active part of the project management
process for the duration of this project with regular dedicated sessions focussing on the
risk register to complement its inclusion as a standing agenda item in project working
groups and meetings at all levels.
6.8. Equalities and Human Rights
Any equality impact on current users and staff at Trinity High School, as well as the
wider community, as a consequence of this project, will be considered at all stages it
develops. Initial Equality and Human Rights Impact Assessments (EQHRIA) have been
carried out at programme level. This will inform the basis of all future assessments,
where individual impact assessments will be conducted, specifically relating to the
upcoming community engagement and consultation. All proposals outlined in this
business case would be subject to formal statutory consultation where impacts will
again be considered in detail.
6.9. Communication, Engagement, and Community Voice
Informal community and stakeholder engagement commenced in August this year,
following publication of the SCC. Engagement has included meetings with
headteachers, ward members and the parent council for Trinity High School, and all
associated primary school parent councils to keep all interested parties informed of
progress and likely timelines for this project. 
A survey was issued to parents and staff, inviting their views on the school and what
they would improve, what should be important for any future investment. Those
findings are referenced in the Strategic Case (section 2.5, above). Responses to the
survey helped shape analysis of the routes forward and options considered in this OBC.

Page 219

Trinity High School Outline Business Case  61
OFFICIAL-SENSITIVE
Engagement with key stakeholders and the wider community will be key to the
successful determination of the overall best value option to proceed with at the
conclusion of the Full Business Case.  To ensure clear communication and stakeholder
input to the process, the project team will carry out an informal consultation on the
short-listed options described in section 3.5 from April 2026.  More detail is provided in
section 7.1 Summary of Shortlisted Options and Next Steps

Page 220

Trinity High School Outline Business Case  62
OFFICIAL-SENSITIVE
7. CONCLUSION
7.1. Summary of Shortlist of Options and Next Steps 
This outline business case confirms that there is a need to construct a new build Trinity
High School at an alternative site within the catchment. The provisional scope to allow
progression of site assessment, costing, and options analysis is to consider a school of
1,400 pupils with an additional allowance for community use. 
The minimum site area required for a high school for 1,400 pupils plus an additional
space left over for community or partner facilities (500m² site additional) is 79,310m² as
per Building Bulleting BB103 and 69,746m² as per The School Premises Regulations
(Scotland) 1967.
This business case has therefore concluded that from the longlist of options that have
been assessed against the preferred route forward to construct a new high school on a
suitable alternative site, that the following options, previously show in Table 2, should
be progressed to the Full Business Case Process.
Site Option 08
New build Trinity High School on Site 08 – KGV Playing Fields Renfrew
Site Option 09
New build Trinity High School on Site 09 – East Craigend, Erskine
Site Option 10
New build Trinity High School on Site 10 – Barwood, Erskine
To prepare the Full Business Case, more detailed site assessments, further cost
modelling, and community consultation are required to recommend a single best value
option to proceed with on conclusion of the next stage of the business case process. 
Taking into account the Council’s commitment to include communities in decision
making, the project team will conduct an informal consultation on the options outlined
above.  The purpose of carrying out an informal consultation during the Full Business
Case stage is to:

Page 221

Trinity High School Outline Business Case  63
OFFICIAL-SENSITIVE
• Comply with recommended best practice in ensuring that the public are involved
in decision making
• Comply with UNCRC to involve children in making decisions that affect them
• Explain the options clearly to stakeholders and the public
• Understand early in the process local views on the options
• Refine options based on local views and feedback
• Present a final option that is the most suitable for the community and the council
• Reduce the potential for community objections at a later stage
• Enhance relationships with local communities/individuals
Key stakeholder groups that will be engaged in the informal consultation include:
• Pupils and parents – parent councils, all parents and pupils
• Local community – Community councils, youth groups, local development
groups, local interest groups, general population in school catchment
• School staff - Head teachers, teaching staff, admin staff, support staff.  
• Associated schools - parents, pupils and staff of associated primary, secondary or
nursery schools
• Politicians – local ward members, ECSPB members, local MPs, local MSPs, 
• Council Services – all council services who contribute to the creation, running and
maintenance of school facilities
• Future building users – groups with letting arrangements 
• Neighbours – current and potential neighbours to school buildings/sites.
• Statutory bodies – Education Scotland, Police Scotland, Scottish Fire and Rescue
Service, Sport Scotland.

Page 222

Trinity High School Outline Business Case  64
OFFICIAL-SENSITIVE
Activity Stakeholders Methods
Preparation and
options
development
Senior Officers and SLT
Elected Members
Head Teachers
Briefings
Workshops
1-1 interviews
Targeted Early
Engagement
Parent Councils/Parents
Community Councils
Local Community Groups
Pupils
Staff
Council Services
Roud table meetings
Briefings
Workshops
Focus Groups 
Broad Public
Engagement 
Associated school parents
and pupils
General public 
Neighbours 
Surveys
Public events 
Analysis and
Refinement
Project team 
Table 12: Engagement Activity
The Full Business Case process is expected to take the remainder of 2026 to complete
and will be presented back to a future cycle of the Education and Children’s Services
Policy Board in 2027 for approval of a final recommended option.

Page 223

Trinity High School Outline Business Case  65
OFFICIAL-SENSITIVE 
Children’s Services
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR