To:  Education and Children’s Services Policy Board
On: 12 March 2026
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________
1. Summary
1.1. The current phase of the Learning Estate Delivery Programme is ongoing with the following
live projects:
• Paisley Grammar School Community Campus 
• Park Mains High School Extension & Internal Interventions
• Thistle Primary School 
1.2. This report provides a short update on the latest development of project construction and
design progress. 
__________________________________________________________________
2. Recommendations 
Members of the Education and Children’s Services Policy Board are asked to: 
2.1. Note the progress of project delivery in the Learning Estate Programme.

Page 2

OFFICIAL
3. Paisley Grammar School Community Campus 
3.1. The project to deliver a new Paisley Grammar School Community Campus continues to
deliver on time, and on budget, and is scheduled to complete by the summer of 2026. 
3.2. Construction is progressing at pace, with many areas in the building now fully complete
including decoration and furniture fit out. 
3.3. Digital fit out has now also commenced with interactive teaching boards now implemented
throughout the school, and all ICT equipment progressing through the order and
preparation stages. 
3.4. Work continues on the major construction of the new Advanced Manufacturing Innovation
District (AMIDS) South project that will deliver core travel infrastructure supporting the
school including a new link road that connects Renfrew Road to Harbour Road, facilitating
alternative travel routes for both active travel and vehicular access to the new school. 
3.5. Work also continues to complete the new underpass connecting Gallowhill to existing active
travel routes by utilising a former railway underpass. This work is scheduled to be
completed by spring 2026. 
3.6. The Council’s Roads Department is also progressing a number of identified improvement
works to the critical roads and footpath network in the vicinity of the new school. 
3.7. Recently, the Scottish Government approved exceptional closure days for Paisley Grammar
School. A request was made to allow vital preparation by staff for moving to the new school
at the end of this school year, and for set up time at the start of the new school year. This
means that pupils attending Paisley Grammar School will finish two days earlier in June
2026, and open two days later at the start of the new term in August 2026. As part of this
process, the school will advise pupils how to source any relevant learning material, and will
provide payments to all families of pupils who are in receipt of free school meals to account
for these days. 
4. Park Mains High School Extension & Internal Interventions 
4.1. The design process of the extended Park Mains High School is largely complete with some
final contractor and sub-contractor design portions that will follow at the point of
construction. The contractor is now completing the market testing process where all sub-
contractors, specialists, and materials will be procured and costed. 
4.2. At the Finance, Resources and Customer Service Policy Board in February 2026, a
contract recommendation was agreed to award Morrison Construction with the initial
construction contract to begin work to deliver the extension and internal intervention works. 
4.3. This process will allow the Contractor to begin construction work on site in March 2026 to
prepare the site and begin critical ground works in preparation of the full construction
beginning thereafter. 
4.4. Following commercial agreement and market testing of the remaining work packages, the
full construction contract is anticipated to be proposed to the same Board in April 2026 to
allow the main works construction to continue seamlessly from the work which will begin in
March 2026. This process has been planned to allow all works to complete by August 2027
as outlined in the project timelines.

Page 3

OFFICIAL
4.5. This market testing process will allow a final contract price for construction to be agreed
ahead of formally awarding both an advanced works contract, and a main works contract in
early 2026 ahead of construction. 
5. Thistle Primary School 
5.1. Work has now commenced on site to construct the new Thistle Primary School in Dargavel.
This initial phase of work has seen a substantial amount of groundworks including drainage,
foundations, and hard landscaping to be progressed. The structure of the new school
building is progressing and is now a visible feature. 
5.2. The project remains on track to complete in the summer of 2027 and updates will be
provided to this Board on the progress of construction as it progresses. 
5.3. A Head Teacher has been appointed for Thistle Primary School, and will take up post
shortly to ensure all operational and policy matters for the school are planned and
implemented within appropriate timelines. 
6. Business Case Development 
6.1. A separate report is being presented to this Board which includes the Outline Business
Case documents for the three initial projects agreed to proceed (Johnstone Primary School
Estate, Johnstone High School, and Trinity High School). 
6.2. These business cases have been produced to allow a decision to be made on the next
phase of delivery with a recommended shortlist of options presented. Please refer to
relevant report for full detail. 
______________________________________________________________ 
Implications of this report 
1.  Financial 
All budgets associated with the capital projects discussed in this report
have been agreed by Council and undergo rigorous management and
quality assurance on a regular basis. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and

Page 4

OFFICIAL
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights  
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement 
Any procurement work required is conducted in collaboration with the
Council’s Procurement team and adheres to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place.   
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the direct
needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed.

Page 5

OFFICIAL
14. Cosla Policy Position 
None.     
Children’s Services
JL/JO Feb 2026 
Author: 
Jack Lochans – Strategic Learning Estate Manager
jack.lochans@renfrewshire.gov.uk