Democracy Spraffa

10, Learning Estate Programme Update ECSPB 21 08 25

Renfrewshire Council · 21 August 2025
Back to Education and Children's Services Policy Board — 21 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

To:  Education and Children’s Services Policy Board
On: 21 August 2025
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Programme Update 
__________________________________________________________________ 
1. Summary 
1.1. The current phase of the Learning Estate Delivery Programme is ongoing with the following
projects: 
• Paisley Grammar School Community Campus 
• Park Mains High School Extension & Internal Interventions
• Thistle Primary School 
1.2. This report provides a short update on the latest development of each project. 
__________________________________________________________________ 
2. Recommendations 
Members of the Education and Children’s Services Policy Board are asked to: 
2.1. Note the progress of project delivery in the Learning Estate Programme. 
3. Paisley Grammar School Community Campus 
3.1. The project to deliver a new Paisley Grammar School Community Campus continues to
deliver on track and is scheduled to complete in summer 2026. Construction is slightly beyond
the halfway point now, and the progress is evident when witnessing the current stage of
construction. 
3.2. The building now features a large amount of its external cladding, bringing the building closer
to its finished look. From an internal perspective, work is beginning on the fit out with some
areas now at the point of having aspects such as flooring, and fixed furniture such as cabinets
and worktops. 
3.3. The formation of the external pitches has commenced and will soon be visible.

Page 2

4. Park Mains High School Extension & Internal Interventions 
4.1. The design process has now concluded the RIBA Stage 3 process which is ‘Spatial
Coordination’ and has progressed into the final design stage, RIBA 4, which is ‘Technical
Design’. The project is currently at the point of having a design that is coordinated from a
structural and space perspective. The next step of the process is to add all elements of detail
including mechanical and electrical services, finished, and specialist sub-contractor design
input. 
4.2. Due to the stage of the design, the major planning application has now also been submitted.
It is anticipated that a decision will be made on the application at the relevant policy board
later this year. 
4.3. The project will progress through the final design stage for the remainder of this year and it
is anticipated that all commercial arrangements will be in place to allow a final contract award
to the contractor in early 2026 for construction. 
4.4. The project remains on track to complete in the summer of 2027 with close monitoring and
management being applied to these current stages of design and commercial agreement. 
5. Thistle Primary School
5.1. The design process for the new Thistle Primary School in Dargavel is at the same formal
stage of design as Park Mains High School project – ‘Technical Design’ – albeit it is at a
slightly more advanced stage of the final design. 
5.2. With planning permission already granted, the project is progressing through the building
warrant process, and it is intended that a contract recommendation for the first major phase
of the construction contract will be submitted to the September Finance, Resources and
Customer Services Policy Board for approval. This will allow the contractor to begin the formal
construction of the school and all supporting provisions in the months to come towards the
end of 2025. 
5.3. A period of civil engineering works to prepare the site for building has been ongoing for a
number of months and has now successfully complete on time. This will allow the project to
progress to formal construction as noted above, on track, as per the required timeline for
completion in summer 2027. 
5.4. A further two important projects have been ongoing in the Dargavel area this summer with
the construction of a new pick up and drop off facility adjacent to the current Dargavel Primary
School progressing well. This facility will be complete in August and operational thereafter to
alleviate pressure on the road infrastructure outside the school. The school itself is also
undergoing improvement works to the multi use games area, with an astroturf surface
installed for both the school and wider community to benefit from. 
___________________________________________________________________ 
Implications of this report 
1.  Financial 
All budgets associated with the capital projects discussed in this report
have been agreed by Council and undergo rigorous management and
quality assurance on a regular basis.

Page 3

2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights  
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement 
Any procurement work required is conducted in collaboration with the
Council’s Procurement team and adheres to appropriate regulations. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place.

Page 4

11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the direct
needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14.   Cosla Policy Position 
None.     
Children’s Services
JL/GM/JO July 2025 
Author: 
Jack Lochans – Strategic Learning Estate Manager
jack.lochans@renfrewshire.gov.uk