Page 1

Page 1 of 4 
To:  Education and Children’s Services Policy Board
On: 15 May 2025
___________________________________________________________________ 
Report by:  Director of Children’s Services
___________________________________________________________________ 
Heading:  Naming of New Primary School in Dargavel 
___________________________________________________________________
1. Summary
1.1 In March 2025, an engagement exercise was carried out with school pupils
from both Bishopton and Dargavel Primary Schools, in order to begin the
naming process for the new primary school in Dargavel Village, Bishopton. 
1.2 This process was carried out in line with the agreed policy procedures for the
naming of new schools (originally approved by the Lifelong Learning & Work
Policy Board on 4 August 2005). 
___________________________________________________________________
2. Recommendations
Members of the Education and Children’s Services Policy Board are asked to:
2.1. Approve Thistle Primary School as the name for the new non-denominational
primary school in Dargavel Village, Bishopton. 
___________________________________________________________________ 
3. Background
3.1. On 23 May 2024, approval to proceed with the design and construction of a
new Primary School in Dargavel was granted at the Education & Children’s
Services Policy Board.

Page 2

Page 2 of 4 
3.2. The requirement to name the school is an important first step in a wider
exercise to develop the overall school identity.
3.3. In March 2025, local young people from Bishopton Primary School and
Dargavel Primary School took part in an engagement exercise to put forward
suggestions for suitable names for the new Primary School. 
3.4. Pupils were asked to consider the wider historical context of the local area, as
well as the surrounding nature and wildlife. A total of 10 names (five from
each school) were put forward.
3.5. Under the terms of the School Naming Policy, the Director of Children’s
Services and the convener of the Education and Children’s Services Policy
Board are required to put forward three names for further consideration. 
3.6. The three chosen names were: 
• Thistle Primary School (this option relates to the nature surrounding the
new school)
• Craigton Primary School (the school is on Craigton Drive and is in
proximity of the Craigton burn).
• Rossland Primary School (this option relates to a historic area name) 
3.7. An electronic vote was opened for a period of two weeks from 18 March 2025,
and the local community were encouraged to vote for their preferred name,
choosing from the three shortlisted. Votes were encouraged across various
stakeholder groups, and participants were asked to share across the local
community to encourage participation and allow as many people to have their
say in the naming of the new school. 
3.8. The stakeholder groups approached to participate were as follows:
• Pupils from Bishopton and Dargavel Primary Schools
• School Staff 
• Parents and carers of Bishopton and Dargavel & Bishopton Primary
School Pupils 
• Elected Members 
• Parent Councils 
• Community Councils 
• Dargavel Mailing List (800 members)
• Local Early Years Providers

Page 3

Page 3 of 4 
3.9. All groups listed above voted electronically apart from the pupils from
Bishopton and Dargavel Primary schools, who placed their vote manually in
classrooms, with schools compiling a total count to be added to electronic
vote totals.
___________________________________________________________________ 
4. Outcome
4.1. The two-week timeframe to vote closed on 31 March 2025, and thereafter a
final count was undertaken.
4.2. The final vote was submitted across two categories – the Pupils Vote (a total
count across pupils from Bishopton Primary and Dargavel Primary), and a
People’s Vote (a total count across all other stakeholder groups listed above). 
4.3. The final count is provided in the table below: 
Pupil's Vote  People's Vote Totals  %  
BISH DARG      
Craigton Primary School 136 238 349 723 37.4%
Rossland Primary School 115 70 291 476 24.6%
Thistle Primary School 130 255 350 735 38%         
Total number of votes
cast    1934 
4.4. Thistle Primary School received the highest number of votes (38%) and
relates to the nature surrounding the new school. 
4.5. Members are asked to approve Thistle Primary School as the name for the
new non-denominational primary school in Dargavel Village, Bishopton.       
___________________________________________________________________ 
Implications of this report 
1.  Financial 
None. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is fair -  Involving the wider community such
as pupils, parents, staff and other
interested parties invites
participation in the consultation

Page 4

Page 4 of 4 
process and promotes a sense of
ownership and pride across the
community.                               
4.  Legal 
None. 
5.  Property/Assets 
None. 
6.  Information Technology 
None. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. 
8. Health and Safety
None. 
9. Procurement 
None. 
10. Risk 
None. 
11. Privacy Impact
None. 
12.  Climate Risk
None. 
13. Children’s Rights
Whilst this paper doesn’t directly impact on Children’s Rights, the consultation
process included engagement with children. This ensured that they had their
voices heard, felt a sense of ownership, and ultimately played a leading role in
the naming of the new primary school. 
14. Cosla Policy Position 
None.     
Children’s Services
NT/JL/CO 
Author:  Jack Lochans – Learning Estate Manager 
Jack.lochans@renfrewshire.gov.uk