To:  Education and Children’s Services Policy Board
On: 15 May 2025
__________________________________________________________________ 
Report by:  Director of Children’s Services
__________________________________________________________________ 
Heading:  Learning Estate Strategy – Business Case Framework 
__________________________________________________________________
1. Summary
1.1. Renfrewshire Council has committed to planning for the biggest-ever
transformation of the area’s learning estate over the decades ahead 
1.2. At the August 2024 meeting, the Board agreed to the Learning Estate
Strategy, which set the principles, objectives, and vision to improve
Renfrewshire’s Learning Estate.
1.3. Following this, in October 2024, a 10-year pupil projection forecast was
presented for the full learning estate. 
1.4. At the council budget meeting in February 2025, members agreed to set aside
£2.5m this financial year – with a commitment to doing the same again in
future years – unlocking up to £170m of investment capacity to deliver the
initial transformation.
1.5. Most recently, in March 2025, the Board noted the priority establishments
presented by applying the agreed Learning Estate Strategy methodology and
scoring matrix. Within these 14 priority schools, it was noted that Paisley
Grammar is already being addressed through the current construction of the
new Community Campus School, and therefore 13 establishments should
progress to the options appraisal stage, through a business case
development process. 
1.6. At the March 2025 meeting, the Board agreed to take forward the Thorn
Primary project as part of a wider review of the full Johnstone learning estate,
with the aim of the delivering the greatest benefit to the whole community. The
board further noted that an overview of the business case framework with
indicative timelines would be presented back and this report therefore
explores these matters.

Page 2

1.7. A short update on current the current delivery of the Learning Estate
Programme, including the development of the new primary school in
Dargavel, has been provided in Appendix 2 of this report.
__________________________________________________________________
2. Recommendations
Members of the Education and Children’s Services Policy Board are asked to:
2.1. Note the business case development framework set out in this report.
2.2. Note the proposed groupings for progressing business cases, and the
provisional timeline associated with these as shown in Appendix 1.
2.3. Note the update provided in Appendix 2 for the current Learning Estate
Programme. 
3. Business Case Framework 
3.1. When deciding on the recommended option for major investment projects, it is
important that an objective and evidence-based decision-making process is
undertaken. For Renfrewshire’s Learning Estate Strategy, it was noted at the
March 2025 Board this process would follow a four-stage process. This
follows industry-standard, best-practice guidance in the form of HM Treasury
Green Book. The purpose of the Green Book process is to provide objective
advice to allow decisions to be made in public-sector spending. 
3.2. At the March 2025 Board, the four-stage process that business-case
development will follow was presented as follows: 
3.3. Further insight into the framework is presented below. 
Strategic Case for Change 
3.4. The Strategic Case for Change (SCC) will take the facts from the Learning
Estate prioritisation matrix and formulate it into a concise overview of the need
for change. Documentation produced will explain what the problem or
opportunity is, and set the scope for the project, as well as strategic
alignment. This is an important stage to agree a focus for delivery and provide
clear understanding for the parameters of developing options which comes in
the next stage. 
Strategic  Case
for Change
Outline
Business Case
Full Business
Case
Final Delivery
Business Case

Page 3

3.5. Within this stage, a core consideration will be understanding what level and
wider scope considerations should be incorporated into the objectives of the
project. While this stage will not consider specific options to meet the
objective, it will set out the existing offer in terms of wider community facilities
and consider whether there are potential opportunities for change within that
area that should be considered as part of a major learning estate option
appraisal. This stage will link to wider Council strategies including the
Strategic Property Review and placeshaping to determine where future
strategic investment in the learning estate can facilitate local placeshaping
and transformation of future service provision. 
3.6. As this stage will be taking the agreed priority establishments and formalising
the need for change, this will be progressed by officers through the Learning
Estate Delivery Board where the Terms of Reference were presented to the
August 2024 meeting of this Board. Members will be fully updated at relevant
future meetings of this Board moving forward to note progress on SCC
processes. 
Outline Business Case 
3.7. The outline business case (OBC) stage is where the strategic drivers and
problem/opportunity, as articulated in the SCC, are progressed to the long list
options appraisal stage. 
3.8. A long list of options will be established, and these will then be assessed
against a pre-determined set of minimum viability criteria which will be based
on the core objectives of the Learning Estate Strategy. The criteria will allow
options that do not meet this viability criteria to quickly be ruled out to ensure
effort is not wasted on appraising options that are not viable for delivery. 
3.9. It is essential in all projects that follow the Green Book process, that the
option of ‘do nothing’ is assessed and progressed to allow a comparison of
benefits and negatives of any potential option. 
3.10. Within the business case process, starting at OBC stage, the ‘Five Case
Model’ will be adopted to assess options. This is a best-practice process
outlined in the Green Book which support the structured assessment of  viable
options against the following five headings:
• Strategic Case
Why do the project, and how it links to wider strategy 
• Economic Case
What is the value and benefit to the community 
• Commercial Case
Is the project deliverable from a procurement and contract perspective 
• Financial Case
Is the project affordable, and how it will be funded

Page 4

• Management Case 
Is the project achievable from a resource and governance perspective
3.11. During the OBC stage, initial non-viable options will be ruled out. The
remaining potential viable options will then be assessed further against the
Five Case Model which provides further insight into the effectiveness of
remaining options.   
3.12. It is likely at this stage that there will be more than 1 viable option for a
project. The options assessment process will primarily look at whether an
option can meet the minimum viability criteria, and will rule out options that
cannot meet this. Only viable options will then progress to be tested against
the Five Case Model. This will allow the effectiveness of options to be
assessed and will result in a shortlist of preferred options being proposed to
the Education and Children’s Services Policy Board to proceed to Full
Business Case (FBC) stage. 
3.13.  Further information on the approach to communication and engagement is
outlined in section 5 of this report, however, a core component of this stage
will be to begin informal community engagement to understand views on
potential options and ensure that communication takes places to demonstrate
that views have been considered. 
Full Business Case 
3.14. The purpose of the FBC stage is to conduct a full financial appraisal on the
shortlist of options a. The FBC should be viewed as a more detailed
continuation of the OBC and will contain similar sections but assessed in
much greater detail. The overall objective at this stage is to establish a single
recommended option which has been evidenced to achieve the viability
criteria and offer value for money. 
3.15. As noted in the OBC section above, the option of ‘do nothing’ will remain as
the baseline to compare viable options against. 
3.16. As each project will be unique in nature, the importance of the Five Case
Model can be seen when it comes to overlaying the Royal Institute of British
Architects (RIBA) stage development process. By assessing potential options,
alongside the five themes, in particular the ‘Commercial Case’, it will allow
decision to be made on how design development can progress. 
3.17. As a rough guide, it can be assumed that option(s) at FBC stage will progress
through elements of RIBA Stage 1 which is ‘Preparation and Briefing’. This
design stage will consist of tasks such as land/site analysis, compiling
requirements for design and construction, concept and design intent, and
ultimately assessing technical and design viability of constructing the
proposed option. This process will see the first design elements of the
potential output and will enhance the decision making by ensuring the options
are viable from a design and construction perspective before making financial
recommendations and commitments.

Page 5

3.18. At the end of FBC stage, by drawing on the financial investment appraisal,
technical development data, and any further enhanced information within the
Five Case Model, officers will be able to objectively recommend an option to
the Education and Children’s Services Policy Board and ask members to give
approval to proceed to the next stage. It is envisaged at this point, this would
include progressing final consultation on the preferred option, including where
appropriate undertaking a statutory consultation exercise to inform the next
and final business case stage. 
3.19. In many cases, projects will require to undertake Statutory Consultation as per
the Schools (Consultation) (Scotland) Act 2010, and this will act as another
element of evidencing viability, by allowing detailed community feedback to be
captured and considered. However it should be stressed affected
communities will already have been engaged in the project through the OBC
and FBC stages, and more detail on this is set out in Section 5. Situations that
could trigger the need for Statutory Consultation include moving the location
of a school or amending the catchment boundary, whereas a refurbishment
on the same site does not require Statutory Consultation. 
Final Delivery Business Case 
3.20. Following approval by this Board for a project to proceed to deliver the
recommended option at FBC stage, the final stage of the business case
process is to ensure full financial, and technical viability, alongside reinforcing
that requirements and objectives can be met through further design
development and any changes and or considerations informed via the final
consultation stage. This will be achieved through the Final Delivery Business
Case (FDC) process. 
3.21. By following the agreed Commercial Case which has been developed
throughout the OBC and FBC, the procurement route to deliver the project(s)
for the recommended option should be agreed as part of the FDC case. A
fundamental component of the FDC stage will be to evidence financial and
commercial deliverability / viability by completing a procurement exercise.
With the compound effect of a completed statutory consultation process
where required, and a market-tested project, the final recommendation to the
Education and Children’s Services Policy Board to proceed with the project
will be transparent, robust, and evidenced-based. Members should note that
all contracts and results of procurement exercises will be progressed through
the Finance, Resources, and Customer Services Policy Board, as is standard
practice. 
3.22. When considering the design development, at FDC stage, each project will
progress to the most relevant RIBA design stage as is appropriate for that
procurement route. It is expected however, that all projects at FDC stage will
be at RIBA Stage 2 at least. RIBA 2 is concept design stage where a building
footprint and layout will be reasonably well developed with an initial design in
place. This is all dependent however on the agreed route to market with many
variables to be assessed on a project-by-project basis and by considering
procurement strategies developed as part of the Learning Estate Strategy.
Each of this will be evidenced and clearly communicated throughout each
business case process.

Page 6

3.23. This process will also bring a robust and informed process of seeking budget
drawdown. While budget estimates of options will be made throughout the
process, it is only when a project reaches the stage of FDC that Members will
be asked for a commitment on budget drawdown. 
3.24. The above four-stage process will allow Members to make informed decisions
based on value for money and viability, while evidencing the benefit any
project will bring to the whole school and wider community affected by any
change. 
4. Business Case Development Timelines
4.1. The following table was presented to the March 2025 Board and outlines the
priority establishments to be progressed to business case development stage. 
Priority
Ranking
Property
Score Establishment Condition Suitability Capacity Quartile
1 2.2 Paisley Grammar School 0.6 0.8 0.4 0.4
2 2.4 Trinity High School 0.9 0.8 0.1 0.6
3= 2.5 Auchenlodment Primary School 0.6 1.2 0.3 0.4
3= 2.5 Heriot Primary School 0.9 1.2 0.2 0.2
3= 2.5 Johnstone High School 0.6 1.2 0.3 0.4
3= 2.5 St Peter's Primary School 0.6 1.2 0.3 0.4
4= 2.6 Bridge of Weir Primary School 0.6 0.8 0.4 0.8
4= 2.6 Thorn Primary School 0.9 0.8 0.3 0.6
4= 2.6 West Primary School 0.9 1.2 0.3 0.2
4= 2.6 Castlehead High School 0.9 1.2 0.3 0.2
4= 2.6 St Margaret's Primary School 0.9 1.2 0.3 0.2
4= 2.6 Gallowhill Primary School 0.9 1.2 0.3 0.2
4= 2.6 Brediland Primary School 0.9 1.2 0.3 0.2
5= 2.7 St Catherine's Primary School 0.9 1.2 0.4 0.2 
4.2. As has been said consistently throughout the development of the Learning
Estate Strategy, no school will be looked at in isolation – we will consider
where each priority school could be taken forward in conjunction with others
nearby. This has allowed geographical groupings to be created based on the
priority schools identified above. Members are also reminded that throughout
a business case development process, schools further down the list of
establishments and not shown in the priority cohort, may also be included in
options assessment if potential value and greater strategic good can be
delivered by a single project. 
4.3. On this basis, business case development will be progressed using the
following 7 groups of priority schools, with agreement at the last Board in
March 2025 that all schools in Johnstone beyond the priority list identified
below would be in scope for assessment:

Page 7

4.4. When considering the business case framework outlined in section 3 of this
report, it must be recognised that it will take a significant period of time to
complete thorough and appropriate business cases to allow decisions to be
made. Using this framework however and considering the communications
and engagement process outlined in section 5 of this report below, school
communities will be engaged in the design and requirements process from the
OBC stage. While it will take time to be in a position of physically constructing,
a lot of work will already have been conducted to develop options and designs
early in the process, generating many opportunities for stakeholder
involvement throughout. 
4.5. It is not possible at this stage to outline detailed or accurate timelines for
completion of projects as there are many variables and risks that exist. This
includes the fact that until options begin to be identified and assessed, which
could include an array of potential solutions, it will not be possible to articulate
exactly how long a stage will take. An example of this is where an option to
build a new school is being assessed, the land for construction will have to be
identified and sourced. Depending on the circumstances, this could extend a
stage by a lengthy period. 
4.6. A provisional timeline of the priority projects progressing through the business
case process has been outlined in appendix 1 of this report. These timelines
will change and become more robust when work begins on developing
options and assessing these. Full updates will be provided to future Boards to
reassess and present these timelines throughout the process. 
In summary, the development, delivery and consideration of the full business
case process from initial SBC through to the FDC is a significant exercise and
is likely to take a number of years for each project before a project
subsequently progresses into the procurement and thereafter delivery phase.
However, this structured business case process is necessary and appropriate
to support robust and strategically sound decision making when such
significant investment is being made by the Council, ensuring such decisions
are being made based on the very best evidence and fully considered
assessment. 
5. Communications and Engagement 
5.1. Communications and engagement will be a critical component of the business
case development process. This will ensure that the school stakeholders and
wider community are informed and involved and will draw on the recently
approved Consultation and Engagement Policy.

Page 8

5.2. At the outset of each stage, stakeholders will be identified ensuring
opportunity for the views of each to be captured and considered at
appropriate times. The process outlined in this report will allow explanations to
be provided about which options are in/out of scope and why, which is
deemed to be an important aspect in engagement for common understanding
of the route forward.
5.3. While each stage of the business case process will bring different
communication, consultation, and engagement requirements, the overarching
objective of communicating with the right stakeholders at the right time will be
a core concept of planning moving forward. The Council has significant
experience in communication in learning estate projects and this experience
and lessons from it will be brought into this process. 
5.4. Within the OBC stage, it is anticipated that engagement will be targeted to
core audiences such as ward members, school staff, pupils, parent groups,
and other relevant stakeholders such as community let groups where
discussions on viable options can take place. At this stage, there is an
opportunity to capture the views of wider community and parents through
surveys. 
5.5. As noted in section 3, members of this Board will then be presented the
findings of the OBC and asked to agree to preferred option(s) to progress to
the next stage. 
5.6. This process would then progress to more detailed sessions with the relevant
stakeholders identified at the FBC stage. As provisional design intent, site
assessment, and core design requirements will be built at this stage, work to
better understand community views and preferences will be held.
5.7. As noted in section 3, members of this Board will then be presented the
findings of the FBC and asked to agree to a recommended option to deliver. 
5.8. Depending on the specific project and its requirements, statutory consultation
as per the Schools (Consultation) (Scotland) Act 2010, may be required. In
this case, a project will already have been developed to a point where it has
been assessed in great detail to understand its viability, benefit, and value for
money. Considerable engagement will have already taken place with whole
school and wider communities, as well as detailed sessions with core
stakeholder groups to understand views and preferences. 
5.9. This process will ensure that only options that are viable and capable of being
supported progress to a statutory consultation. This approach offers a fully
transparent and collaborative approach with our communities. 
5.10. It is important to recognise communication and engagement will continue for
the full life of the project. As per current learning estate projects ongoing in
advanced design, or construction stages, ongoing communication and
engagement with affected communities will form a key part of the successful
delivery drawing on the views captured from all engagement through OBC,
FBC, and any statutory engagement. Further consultation and engagement
will be required during the planning application process, and communities will
continue to be kept updated throughout the construction and
completion/opening of the project.

Page 9

___________________________________________________________________ 
Implications of this report 
1.  Financial 
Council has agreed to make provision of £2.5m of revenue resource in
2025/26, with similar amounts being committed to on an annual basis each
year over the remaining years of the current Administration. The financial
model underpinning the strategy continues to be developed, along with the
framework and analysis required in the business case process. This
financial provision will fund the programme of work as it progresses through
business case development. 
2.  HR and Organisational Development 
None. 
3. Community/Council Planning 
Our Renfrewshire is thriving -  New, and improved, learning estate
assets will allow our children and
young people to thrive with the best
possible infrastructure to support
their school experience. Staff, and
community users will benefit from
modern and inclusive environments. 
Reshaping our place, our
economy and our future 
-  The learning estate shall be
appropriately scaled and equipped
to meet curriculum expectations and
deliver an appropriate learning and
teaching experience for all. 
4.  Legal 
None. 
5.  Property/Assets 
These projects will deliver significant improvements to the learning estate,
extending the life of assets, and improving the experience of young people,
staff, and the wider community. 
6.  Information Technology 
Digital improvements will be delivered through the learning estate strategy,
where access to technology for all, will be a key priority for projects. 
7.  Equality and Human Rights   
The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the

Page 10

recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
8. Health and Safety
None. 
9. Procurement 
Any procurement work required will be conducted in collaboration with the
Council’s Procurement team and adhere to appropriate regulations. By
developing the business case framework outlined in this report,
procurement and commercial considerations will be conducted throughout. 
10. Risk 
All projects are bound by rigorous governance and supported by detailed
risk registers. Risk is reported and managed at various levels with scrutiny
applied to ensure mitigations and contingency plans are in place. The
business case framework set out in this report will directly work to identify,
manage, and reduce risk. 
11. Privacy Impact
None. 
12.  Climate Risk
New, and improved, learning estate assets will directly contribute to the
Council’s journey towards net zero. Sustainability is a key concept of all
projects. 
13.  Children’s Rights
When considering any future school provision, the impact this will have on
children is a key consideration, and any work will be based around the
direct needs of children to allow their education experience to thrive. Whilst
children have a right to choose where they wish to attend school in
collaboration with their parents, the council’s admissions policy applies to
ensure that schools that are oversubscribed can be managed. 
14. Cosla Policy Position 
None.  
Children’s Services
JL/GM/JO April 2025 
Author: Jack Lochans – Learning Estate Manager, jack.lochans@renfrewshire.gov.uk

Page 11

Appendix 1 – Potential Timeline for Business Case Development 
*Note – for construction periods to complete, it is dependent on scope and chosen option for project. A period of 1-2 years should be allowed for any construction completion,
following the notional construction commencement period in the chart below. 
Q2 2025 Q3 2025 Q4 2025 Q1 2026 Q2 2026 Q3 2026 Q4 2026 Q1 2027 Q2 2027 Q3 2027 Q4 2027 Q1 2028 Q2 2028 Q3 2028 Q4 2028 Q1 2029 Q2 2029 Q3 2029 Q4 2029 Q1 2030 Q2 2030 Q3 2030 Q4 2030 Q1 2031 Q2 2031 Q3 2031 Q4 2031 Q1 2032 Q2 2032 Q3 2032 Q4 2032
APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC
Potential construction period could commence.
This process depends on the option, complexity, land availability, statutory consultation, procurement route
Potential construction period could commence.
This process depends on the option(s), complexity, land availability, statutory consultation, procurement route
Potential construction period for the 1st of 5 business case processes  could commence
Construction start would then stagger from this point into early 2030's
This process depends on the option(s), complexity, land availability, statutory consultation, procurement route
Remaining 5 Business
Cases
(Paisley Foxbar -
Heriot PS, Brediland
PS)
(Paisley Glenburn - St
Paul's PS)
(Bridge of Weir PS)
(Paisley Central/West
- Castlehead HS, West
PS)
(Paisley Gallowhill -
St Catherine's PS,
Gallowhill PS)
Business Case
Framework
Development
Renfrew Business
Case
Johnstone Business
Case
(Johnstone HS,
Auchenlodment PS,
Thorn PS, St
Margaret's PS)
Development of
framework
Resourcing
StrategicCase
for Change
Outineand Full Business Case -Project design commenced
Statutoryconsultation if required
Final Delivery Business Case -design
Final design and contractorpreparation ahead of construction
StrategicCase
for Change
Outineand Full Business Case -Project design commenced
Statutoryconsultation if required
Final Delivery Business Case -design
Final design and contractorpreparation ahead of construction
StrategicCase for Change
Outlineand Full Business Case development
Final Delivery Business Case development
Statutoryconsultations if required
Final design and contactorpreparaton ahead of construction

Page 12

Appendix 2 – Learning Estate Programme Update 
1. Paisley Grammar School Community Campus 
1.1. Work continues on site to deliver the new Paisley Grammar School Community Campus,
with completion remaining on track for the summer of 2026.
1.2. As the project progresses, a series of community benefits are being delivered by the
contractor, Morrison Construction. Recently, a pupil from Paisley Grammar School has
obtained work experience on site with a joinery sub-contractor, whilst Morrison have been
working with Invest in Renfrewshire to offer further work opportunities for local people
moving forward. 
2. Park Mains High School Extension & Internal Interventions
2.1. A contractor is now in place and working in partnership with the Council and a wider design
team to progress the detailed design of the extended Park Mains High School. 
2.2. This design process will see the planning application submitted in the summer of 2025, with
the full design scheduled to complete in early 2026, in preparation for construction, keeping
the project on track for a summer 2027 completion. 
3. New Primary School in Dargavel 
3.1. Civil engineering work has been ongoing on site for a number of weeks, which has begun
the process of preparing the site for the structural load of the school to be built. This work
will continue over the summer, whilst the final detailed design process is complete. 
3.2. A recent community update was circulated which noted the progress of this project and
wider projects in the community. The project to deliver the new primary school in Dargavel
remains on track for a summer 2027 completion.