1 - Cultural Infrastructure Programme Update - Final

Renfrewshire Council · 29 August 2023
Back to Economy and Regeneration Policy Board — 29 August 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy & Regeneration Policy Board
On: 29th August 2023
___________________________________________________________________
Report by: Programme Director, City Deal & Infrastructure
___________________________________________________________________
Heading: Cultural Infrastructure Programme Update
___________________________________________________________________
1. Summary 
1.1. This report is to update the Board on the progress of Renfrewshire Council’s
Cultural Infrastructure Programme, being delivered on behalf of the Council by the
City Deal & Infrastructure Team (with project management expertise from the
Council’s Property Services team) with the Paisley Museum Project being
delivered by OneRen. 
1.2. The Cultural Infrastructure Programme investment in Paisley town centre will use
our internationally significant cultural and heritage story to transform our future for
visitors and events within Scotland. This programme of work will bring new footfall
and life to the town centre, new homes for top class cultural events, whilst preserving
the heritage of the town. 
1.3. As noted previously, the Cultural Infrastructure Programme has experienced significant
impact from recent global events including the pandemic and war in Ukraine which has
resulted in an economic challenge, particularly noticed in the construction industry.
Completion of these projects are central to the recovery and inclusive growth of
the Renfrewshire economy and Paisley Town Centre. 
1.4. The programme continues to make positive progress through challenging times, and a
significant milestone has been achieved with the completion of the main works
construction at Paisley Town Hall. This project is now the first to progress to a carefully
planned fit out period with the remainder of the projects following in a phased approach
to ensure that resources internally at both Renfrewshire Council and OneRen, as well as
specialist contractors, can deliver a high quality and efficient opening programme. This
approach also allows each venue to be launched in its own right and contribute both
individually and collectively to maximise the impact on Renfrewshire’s cultural, events
and heritage opportunities.

Page 2

1.5. The very significant scale of the construction phase, coupled with the
unprecedented challenges faced across the wider construction sector over the
past number of years, has meant there has been an inevitable shift in the
construction completion dates of each venue in contrast to that planned at the
outset of the programme. However, projects continue to move at pace, and the Town
Hall has successfully achieved the re-baselined completion date to allow a complex fit
out period to deliver well in advance of hosting the Royal National Mòd in October 2023.
The Paisley learning & Cultural Hub is expected to open later this year with the Arts
Centre following thereafter. 
________________________________________________________________________
2. Recommendations 
2.1. The Economy & Regeneration Board is asked to: 
i) Note the progress and current stage of construction of the projects outlined in
this paper. 
ii) Note the financial implications outlined at the end of this paper. 
________________________________________________________________________ 
3. Project Updates 
3.1. Whilst each of the Cultural Infrastructure projects individually contribute to economic
growth in Renfrewshire, it is important to note that the combined social and economic
outcomes from across these investments are greater than the sum of the individual
parts. Coupled with the Councils wider economic investments in city Deal, AMIDS,
housing, and other regeneration projects, these social and economic outcomes for our
local residents and visitors is enhanced further. 
________________________________________________________________________
4. Paisley Town Hall Redevelopment 
4.1. Paisley Town Hall main works construction contract successfully completed on 10th July
2023. The contractor retains a presence on site to complete finishing and snagging
works and will complete all works by the end of August 2023. This is a major milestone
which brings the completion of the first cultural infrastructure project within the ambitious
programme.   
4.2. The building has been carefully modernised whilst retaining its historic features and
grand look. The capabilities of the building have been brought up to date to make it a
digitally connected venue able to host various events that have never been possible in
the town before. A full mechanical and electrical replacement has taken place
throughout the building making it more efficient and capable of supporting both staff and
customers. 
4.3. The venue offers significantly improved access for events, including greater access to
back of house to load event provisions and for operational matters, as well as new stage
lifts and retractable seating. Accessibility has been a key design feature for staff and
customers, with the building now widely accessible to all.

Page 3

4.4. New spaces in the building have been created, and all original areas have been
completely refreshed. This has delivered a remarkable heritage building that is grand in
stature but operates and functions as a modern building. New spaces that have been
delivered as part of this project include, but are not limited to, a new bar capable of
hosting guests before and after shows; a new digital lounge which will be able to stream
film and broadcasts or host seminars; a new dance studio; and new artist areas for
performers including private rooms and a green room for before and after performances.
The design has unlocked and made use of the entire building enabling efficient delivery
of multiple types of performance. 
4.5. With main works construction now complete, the project team has transitioned to focus
on a complex fit out period to install all elements of furniture, equipment, and provisions
to allow the building to be operated and the doors opened. This process will equip the
building with the required provisions for digital functionality including multimedia, ICT,
and all network provisions including brand new staff and public Wi-Fi. The building is
also being fitted with state-of-the-art audio visual equipment including stage lighting and
sound systems which make the building attractive to global artists.   
4.6. The fit out process also captures all catering, crockery, bar, and function equipment
which will allow a new offer, not previously possible, to be made. 
4.7. OneRen have planned a number of test events that will be taking place in the coming
months to ensure the building, its contents, functionality, and staff are ready for the first
major event, the Royal National Mòd, in October 2023. 
________________________________________________________________________
5. Paisley Learning and Cultural Hub 
5.1. Paisley Learning and Cultural Hub is a 21st century community hub and a modern home
for library services at the heart of Paisley High Street, bringing new footfall into the town
centre. The construction of this building which is taking place in a previously vacant and
derelict building in the centre of the High Street, will become a modern educational
resource for people of all ages to learn and be inspired. 
5.2. Construction of the building is moving at pace and helps the council’s ambition to
improve the High Street with the new modern façade and glazing in place. Construction
is approaching completion with finishing touches now being applied including paintwork
and final fixings. 
5.3. The main element to be completed is the bespoke children’s play structure which will be
a key attraction to integrate play and education. The project team has also
commissioned renowned Paisley born artist, Claire Barclay, to complete bespoke
artwork as part of this, which ensures a unique and effective finish to the building. 
5.4. A vast amount of work is taking place to plan the fit out of the library which will see the
building become a digital hub in the heart of Paisley. ICT kit is being prepared which will
includes PCs, laptops, carefully integrated audio visual equipment, as well as sensory
equipment. This will be coupled with new Wi-Fi being installed to ensure public and staff
have efficient network access. 
5.5. A key feature of the library is of course books. The project team have designed
appropriate library shelving and furniture to host the vast amount of books on offer and a
contractor has been appointed for the manufacture and install of this equipment which
will ensure the building retains one if its prominent purposes.

Page 4

5.6. Construction work is due to complete in September 2023 with the fit out process then
beginning to allow staff to move into the building ahead of the planned opening in late
2023. To achieve this, a short period of closure will be required at the current temporary
library at the Lagoon Leisure Centre which will be coordinated and communicated in
advance. This closure was recently approved at the June 2023 Leadership Board.
Existing stock and provisions will be transferred to the new venue, and the planning for
this has already begun with a tender process underway to appoint a specialist removal
company. 
________________________________________________________________________
6. Paisley Arts Centre 
6.1. Paisley Arts Centre is being extended and upgraded into a unique and intimate
performance venue and creative hub, driving new life and footfall into the heart of the
town centre. This refurbishment project includes a complete replacement of the
building’s mechanical, electrical and plant equipment, a full refurbishment throughout,
new retractable seating, accessibility improvements and a new extension to improve the
number of covers in the bar. These improvements will be further supplemented by the
creation of a new external public realm space to provide additional event capacity. 
6.2. Work to date has been slow due to various issues with the nature of the historic building
and the confined spaces to work in. The contractor has faced challenging working
conditions with the building, which has been coupled with the economic impact on the
construction industry, resulting in a requirement to re-plan the project timeline. This
means that construction completion is now expected in late 2023. The pace of
construction is now significantly improved with good progress made in areas including
the new extension and mechanical and electrical elements. 
6.3. Progress has been made to install a new tension wire grid which is a key element of
what this project will deliver. This new grid is suspended at ceiling height to allow access
to the audio-visual stage lighting and sound equipment by technicians without the need
to lower the equipment due to the confined space in the building. 
6.4. Work will continue to progress with the delivery of construction to allow the project team
to begin considering the fit out process which will require the delivery of all furniture,
catering, ICT, audio visual, and many other provisions.  
________________________________________________________________________
7. Paisley Museum Reimagined 
7.1. Paisley Museum Reimagined will deliver a world-class destination telling the
inspirational stories of Paisley’s people and pattern and showcasing its internationally
significant collections. This project includes repairing and renovating all buildings on the
museum campus delivering a 20% increase in the overall area. The construction also
includes a new extension housing a visitor reception and café, the installation of new
mechanical, electrical and plant systems, as well as the introduction of a public
courtyard. Importantly, this work enables an increase in the interpretation of the
collections and number of objects on display, with a strong focus on digital
interpretation.

Page 5

Construction Work 
7.2. Despite pressures and delays to programme there has been positive progress on site
with the major concrete pours completed in the West extension including level 1 and 3
walkways leading to the café space from the new lift. In addition, the Factory Hall 1
balcony area above the new entrance and Factory Hall 2 floor slabs have also been
cast. This, in addition to the previous concrete works to the east extension, completes
the fully accessible circular route through the building meeting a key objective of the
approved design. 
7.3. Significant progress has also been made on the completion of roof works on the main
museum building. So far, roof works that are complete have resolved all water
penetration issues in these areas. 
7.4. The red glazing for the new entrance is due to be delivered to site and Kier are
anticipating this will be erected by the end of August leading to the west extension
building being wind and watertight. 
7.5. A number of other key works are complete to the Observatory and Oakshaw properties
which is allowing scaffolding to be stripped and works to move internal. Historic
Environment Scotland Architects continue to liaise with our design team on site as
required 
7.6. Construction has been delayed for the Museum partly to do with the condition of the
building being much worse than originally expected. The result of this is the
construction is expected to complete around Easter 2024, with an opening date
expected in late 2024. 
Exhibition Fitout
7.7. Following the appointment of specialist exhibition fitout contractor, The Hub, in May
2022, 96% of display pre-production drawings are now complete. Prototypes indicating
materials, junctions, robustness and quality have been produced, tested and signed-
off. Production of standard flexible display elements has begun. 
Digital Interactives 
7.8. Work is progressing well with digital display interactive development with 80% of
software contracts now awarded and in progress. 
Collections and Conservation Work
7.9. Conservation of 850 objects has now been completed with the remainder of works due
for completion by December 2023 ahead of the object installation. 
7.10. OneRen has secured additional external funding of £103,000 from 12 Trusts and
Societies has been secured towards this work. 16 conservation contracts have been
awarded to companies across the UK. 
7.11. New photography of all works is currently underway with approximately 800 objects
photographed for use in displays, publications and media coverage. 
Fundraising
7.12. In July, a sum of £200,000 was awarded by an organisation who supports world
leading cultural venues. The specifics around the organisation must remain
confidential for the time being until all paperwork has been agreed. It should however
be noted that this is only the second time in their history this foundation has chosen to
support a project in Scotland, showing the significance of what is being delivered by
this project.

Page 6

7.13. The above award takes the total amount raised from Trusts and Foundations to over
£1,234,000. This includes support from prestigious funders such as: The Garfield
Weston Foundation (£300k), The Hugh Fraser Foundation (£250k) and The Wolfson
Foundation (£200k). 
7.14. The original Fundraising Strategy, which was written prior to the pandemic, stated that
£1.5m would be raised from Trust and Foundations. There is confidence that the
remaining £266,000 will be secured ahead of Paisley Museum re-opening. 
________________________________________________________________________
8. Abbey Quarter 
8.1. Abbey Quarter is a high quality public realm project to support the investment in the
Town Hall facilities and provide an accessible outdoor events space for Paisley Town
Centre. The project extends over the area in front of, and to the side of the Town Hall. 
8.2. Design of the area in front of the Town Hall extending into the green area is at RIBA
Stage 3 (ready for planning). Consideration has been given to the Paisley Abbey which
is captured in this area of design to ensure it remains fully accessible. Previously, a
public consultation was carried out for this element in November and December 2021
which obtained wide public support. 
8.3. Historic records and recent trial excavations indicates that there could be a risk of finding
human remains in carrying out the public realm works at the identified locations. To allow
these works to proceed, the Council intends to submit a Disinterment Application to
Paisley Sheriff Court. The granting of the application will allow the Council to proceed
with the planned works and if any human remains are discovered, these will be treated
with care and compassion in accordance with the Council’s Code of Practice on
Exhumations and reinterred, into Hawkhead Cemetery. 
8.4. The relevant paperwork required for the court order has now been prepared and
correspondence has taken place with the Minister of Paisley Abbey, who is in support
of the proposed process and wishes to be the nominated Minister to conduct any
reinterment if required. It is intended that the application will soon be submitted to the
Sheriff Court, in August 2023. 
8.5. Assuming approval is granted to proceed by Paisley Sheriff Court, the project will
progress with a planning application and then onto the procurement process to appoint
a contractor. It is expected that work will begin in spring 2024, and work will begin shortly
with OneRen to plan for full access to the newly refurbished Paisley Town Hall during
the works. 
________________________________________________________________________ 
9. Townscape Heritage and Conservation Area Regeneration Scheme 2 (TH.CARS2) 
9.1. Paisley TH.CARS2 is now complete apart from the outstanding work to upgrade the
Liberal Club on Paisley High Street. This programme has delivered Building Repair
projects, Shopfront improvements and a Small Grant programme to historic properties
in Paisley Town Centre. The project is funded by the National Lottery Heritage Fund
(NLHF), Historic Environment Scotland (HES) and Renfrewshire Council, with combined
project funding of over £4.1 million, and additional contributions from owners. The
project is also delivering public realm improvements and a successful programme of
heritage related activities and events has now completed. 
9.2. Grant support for external repairs has been awarded to ten larger building repair projects
with nine projects completed. Works to the final project, 32 High St (Liberal Club), are

Page 7

currently on site. However, completion has been delayed largely due to significant
additional rot works discovered on site and the project is not expected to complete until
November 2023. 
9.3. The current TH.CARS2 scheme completion date is 30 September 2023.  An extension
until March 2024 has been discussed with the funders to allow completion of the Liberal
Club and submission of final reports and evaluation and a formal request has been
submitted. 
9.4. A significant difference has been made to the condition and appearance of a number of
prominent properties in Paisley Town Centre including: 2/3 County Place opposite
Paisley Gilmour St, now restored and converted to flats, 20 New St (Vienna’s night club),
41 High St (Right Way Credit Union offices), Sma Shot  Cottages, 9 Gilmour St (Walker
Laird’s offices), 28 High St, 18 Georges Gate, 10 Shuttle St and 5 George Place, (Paisley
Trophy Centre) which was recently used as a set location for a BBC Agatha Christie
production. 
9.5. Shopfront Improvements grants have supported ten projects in the High Street with nine
shopfronts completed. These include:  30 High St (White Cart Company and Sinclair
Jewellers), 36 High St, (Shelter), 61 High St (Print and Copy it), 41 High St (Right Way
Credit Union), 44 High St (Uptown Barbers), 63A High Street (Nomads) and 18 High
Street where two shopfronts have recently completed.  Works will shortly complete at
67 High St (Houston’s Kilts). The TH.CARS2 project has also supported a Small Grants
programme mainly for traditional window repair projects in the Town Centre. 
9.6. Public realm works have also been funded through the project with works completed at
George Place. Public Realm works to pavements in the High Street area opposite the
Museums are now complete. This has been a complex project with private basements
below the High Street pavements and additional structural repairs required. However,
the works have made a significant difference to the quality of the public realm in this
area and support the improvements to the Museum. Works to resurface Weighhouse
Close where it meets the High Street have completed. 
9.7. TH.CARS2’s community engagement programme of Heritage Education, Training and
events has also now concluded. Comprising 42 projects, it has seen delivery of 630
workshops and over 115 separate events. Over 2,500 participants, trainees and
volunteers have been engaged and estimated audiences of over 50,000 reached. More
than 100 partners have been involved locally and nationally, and over 150 job
opportunities have been created for consultants and freelancers.
________________________________________________________________________
10. St James’ Playing Fields & Ferguslie Sports Centre 
10.1. These projects will work towards delivering Renfrewshire’s vision to ‘make sport a way
of life’. In 2018, Council approved the upgrading of changing facilities at Ferguslie Sports
Centre and for the demolition and replacement of the existing pavilion at St James
Playing Fields. When the Covid-19 pandemic hit, a decision was made to put these
projects on hold until such time that it was appropriate to proceed. 
Ferguslie Sports Centre 
10.2. In July 2022, approval was given to resume the planning of the Ferguslie Sports Centre
upgrades. This work will completely refurbish all existing changing facilities to the sports
centre, bringing a greater experience to the already well utilised facility. The work will
also ensure that the building is future proofed by fixing all issues with the roof to ensure
no leaks, which has been an ongoing issue. The building will also receive upgraded

Page 8

boilers as part of this process making it more efficient and of better quality to customers
and staff. 
10.3. Tenders to appoint a contractor for Ferguslie Sports Centre have recently been
submitted and the project team will now work to complete the process to recommend a
bidder, to be presented to the September 2023 Finance, Resources and Customer
Services Policy Board. This will then allow a contractor to mobilise and begin works in
2023, completing works in the first half of 2024. 
St James’ Playing Fields 
10.4. An update was provided at the January 2023 Economy & Regeneration Policy Board to
note that it was not viable to proceed with the single bid that was received to construct
the new pavilions at St James’ Playing Fields due to being significantly over budget. 
10.5. A commitment was made to conduct value engineering on the design to bring this in line
with budget and return to tender in May 2023. This was achieved and the project
successfully went back out to the first stage of the tender process in May 2023. This
process was completed, and the project has now proceeded to the final stage of
tendering with bidders able to submit prior to September 2023. 
10.6. Following the bidding process, a recommendation will be made to the November 2023
Finance, Resources and Customer Services Policy Board to appoint a contractor. A
period of mobilisation, manufacture and preparation work will then take place by the
contractor with works due to commence on site in spring 2024 with construction
completion expected in September 2024.   
10.7. The project team recently met with the Paisley North Community Council to discuss the
plans for this project which was well received and allowed a constructive discussion
around what will be delivered, and how the views of the Community Council could be
incorporated. 
___________________________________________________________________
Implications of the Report 
1. Financial – There are a number of significant risks associated with capital investment on the
scale outlined in the report, many of which have been previously advised to members.
Construction and refurbishment works in historic buildings are intrinsically subject to a higher
degree of cost volatility due to the nature of the works and the fact that the complexity and
detail of the works required are in many instances not fully known until the works are in
progress and the building condition is fully understood. The existing capital budgets for those
works in progress – Paisley Town Hall , Paisley Museum and Paisley Arts Centre – are under
considerable pressure due to these issues and also due to the extended timescales of the
works which were severely affected by the pandemic closedown and subsequent modified
working practice period.
Council agreed in June 2023 to pause elements of the wider cultural venues and town centre
infrastructure programme in order to release funding towards those projects whose budgets
are under pressure; and as these projects conclude and final costs are clarified, further
updates to Board will be provided. It should be noted however that even with the above
Council decision there remains a significant degree of risk and potential cost which could place
further pressure on total capital resource.
There has been ongoing discussion and updating of the business cases for each of the cultural
venue with colleagues in OneRen, including critically the updating of base assumptions in
terms of operating costs and potential income generation. While core assumptions and the

Page 9

projected revenue operating position of Paisley Town Hall and the Arts Centre currently
remain consistent with original projections, the updating of assumptions is indicating that
there is likely to be revenue funding pressures associated with Paisley Museum which are
above original business case assumptions. These predominantly relate to a revised catering
offer and emerging clarity on potential income from touring exhibitions; as well as updated
projections of utilities, maintenance and soft FM costs. The Council will continue to discuss
with OneRen options to mitigate these additional costs, however it would also be prudent for
the Council to build these updated cost projections into future revenue plans. 
2. HR & Organisational Development - none 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – These projects will link our communities and
facilitate a significant increase in footfall to Paisley and surrounding areas. The
infrastructure will enable Renfrewshire to host world class performances and
attract new footfall from far beyond the local area. 
• Our Renfrewshire is well - The outputs of these projects will enable safe and
inspiring locations for all. From arts and performances to learning and
educational space, Renfrewshire will offer anyone the ability to engage and take
interest in either a new subject matter or an existing passion that is now much
more accessible. Driving world class performances to the area and having 21st
century work and education spaces will support people from Renfrewshire to
engage in beneficial activities that will in turn support education and interest. 
• Reshaping our place, our economy and our future – These infrastructure
projects allow access to new and existing jobs for people in our communities.
Significant increase in footfall will benefit local businesses who can grow as a
result and in turn support their ongoing viability in the area. An increase in arts
and performances will allow a platform for Paisley becoming a cultural hub in
Scotland which can be used to drive new educational agendas with greater
access to this subject matter. 
• Tackling inequality, ensuring opportunities for all – A specific focus has been
applied to the redevelopment and construction of these projects to ensure
accessibility is a key feature. A significant amount of thought has gone into
making historic, and predominantly inaccessible buildings, available for anyone
to enjoy and utilise. There are no barriers to utilising any of these buildings, and
One Ren will continue to deliver an events programme that caters for everyone
including those in more deprived areas. 
• Creating a sustainable Renfrewshire for all to enjoy – With these buildings being
in the heart of Paisley Town centre, it means they are accessible sustainably
due to the well-connected nature of the town centre. Limited town centre parking
will force the use of public transport which will work towards the net zero
ambitions of the Council. Recently completed infrastructure through AMIDS,
including the shared cycle and walkway, also enhances the connectivity, and in
future years with the opening of the Clyde Waterfront and Renfrew Riverside
bridge, Paisley will become a vastly accessible route by sustainable travel. 
• Working together to improve outcomes - Officers and contractors continue to
work closely with local businesses and a business engagement programme will
commence shortly to bring this to focus.

Page 10

Throughout the development of these projects, several organisations were
engaged to design the outputs including accessibility groups, the Scottish
Government, Historic Environment Scotland, multiple private sector
organisations and the local community. 
4. Legal - none 
5. Property/Assets – note the improvements being delivered to current assets. 
6. Information Technology - none 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts on
equality groups or potential for infringement of individuals’ human rights have
been identified arising from the recommendations contained in the report
because it is for noting only. If required following implementation, the actual
impact of the recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the Council’s
website. 
8. Health & Safety - none 
9. Procurement – all contracts are tendered in accordance with Council procurement
procedures and where relevant taken to FRCS Board for approval. 
10. Risk – Project specific and Programme level risk registers have been established for
all projects. These are kept under regular review and reported to the Council’s internal
City Deal and Infrastructure Programme Board. 
11. Privacy Impact - none 
12. COSLA Policy Position – not applicable 
13/ Climate Risk – these projects will significantly improve all mechanical, electrical and
plant systems within existing and new buildings affected. This, coupled with improved
efficiency in windows and doors will drive down the requirement for heating, in turn
lowering the carbon footprint from key council buildings. 
_________________________________________________________
List of Background Papers 
none
__________________________________________________________________ 
BW 
July 2023 
Author: Barbara Walker, City Deal and Infrastructure Programme Director; Email
Barbara.walker@renfrewshire.gov.uk