Page 1

___________________________________________________________________
To:  Economy and Regeneration Policy Board 
On:  14 March 2023
___________________________________________________________________
Report by:  Chief Executive
___________________________________________________________________
Heading: Cultural Infrastructure Programme Update
___________________________________________________________________
1. Summary 
1.1 This report provides an update on the progress of the Cultural Infrastructure
Programme to develop the Council’s four premier cultural assets in Paisley town
centre.  The investment programme builds on the significant cultural and heritage
foundations of the town for current and future generations to experience, treasure
and enjoy.  Renfrewshire Council is working closely with OneRen to ensure that
the projects progress through each project phase from construction, to building
fit-out, into operational readiness, before delivering test events and public
programming.   
1.2 This programme of work will bring new visitors, cultural performances and
activities and life-changing cultural experiences to the town.  Due to the scale
and complexity of the cultural infrastructure programme, a managed programme
of phased venue openings will take place to enable each venue to be
successfully launched and celebrated. 
1.3 The significant scale of the construction phase, together with the unprecedented
challenges faced across the wider construction sector over the past number of
years, has resulted in an inevitable shift in the construction completion timelines
for each venue.  As the construction phase progresses, there is greater
confidence in the revised construction completion dates which is allowing the
opening venue timelines to be developed.

Page 2

1.4 There are significant operational demands involved in planning, preparing and
implementing each venue opening which are being actively managed to ensure
that organisational capacity of both the Council and OneRen is available to
appropriately support the associated demands of each venue.  This report details
the approach being undertaken by OneRen, in partnership with the Council,
across Paisley Town Hall, Paisley Learning and Cultural Hub, Paisley Arts
Centre and Paisley Museum as part of the building fit-out, operational readiness
and delivery of test and opening activities and public programming.
___________________________________________________________________ 
2. Recommendations 
2.1 The Economy and Regeneration Policy Board is asked to note the contents of
this report.
_________________________________________________________ 
3. Background 
3.1 Governance: 
The work programme undertaken by OneRen for the building fit-out, operational
readiness, test events, opening activities and public programming is being
undertaken through cross venue workstreams, to ensure efficient and consistent
delivery across the programme.  Workstream leads are responsible for ensuring
that their area is delivered to programme and reported to the cultural
infrastructure opening programme board on a regular basis to ensure emerging
issues can be addressed by all partners.   
3.2 Timescales 
The chart below outlines the indicative timescales and milestones for each of the
projects.  The chart shows that the construction phase is still underway for each
of the four venues.

Page 3

No embedded text on this page.

Page 4

3.3 Building Commissioning – Pre-handover works 
Several actions require to be completed before the buildings are handed over to
OneRen by the contractors. The operational pre-handover works for Paisley
Town Hall (PTH), Paisley Learning & Cultural Hub (PLCH), and Paisley Arts
Centre (PAC) include: 
• Development of Safe Operating Procedures, Risk Assessments and
Operating documents in line with building operations, relevant guidelines and
technical information available prior to post-handover access.
• Operational mapping to ensure staff operating models are created to reflect
core operational hours at PTH, PLCH and PAC. 
• Recruitment/resourcing for Paisley Town Hall, through consultation with
existing venue employees to identify those with a preference to return to their
core location and further internal canvassing of other employees who would
like to relocate to PTH. Identifying appropriate skillsets in line with respective
operating model. 
• Creation of training needs in preparation of building handover. 
• Familiarisation training for employees in PTH delivered by the contractor 
• Recruitment timeline in place for external recruitment based on operational
need. Academy training concept set up in partnership with Invest which may
provide future employment following work placement exposure and
employability sessions.
• Multi-partner Soft Landings Team project meetings to manage and update
project progress. Attended by Renfrewshire Council, contractors and
OneRen. 
• FFE procurement planning in partnership with OneRen and Renfrewshire
Council. 
While many of these elements will be the same for Paisley Museum, there is a
further requirement for exhibition fit-out and installation which will take place after
the main building contractors have departed.  At this point, the building is handed
over to the specialist exhibition contractors to construct and install objects and
displays, including specialist lighting and digital and AV equipment. 
3.4 Building Commissioning – Post-handover works 
To ensure that the buildings can be operated safely, several actions require to
be completed after the buildings are handed over to OneRen by the contractors.
The operational pre-handover works include for PTH, PLCH, PAC and Paisley
Museum include: 
• Staff familiarisation and induction training programme to navigate the venue
(existing/new staff and contingency teams from other venues/services).
• Systems training on air handling units/energy management/ audio visual
equipment and ICT kit.  
• Review of existing completed Standard Operating Procedures and
systems.

Page 5

• Completion of fire risk assessment 
• Evacuation training and testing. 
• Safety system training on alarm systems. 
• Completion of site-specific documentation including safe systems of
work / risk assessments. 
• Completion of emergency action and all associated compliance
documentation.  
• Staff training of equipment / fixings / set ups. 
• FFE installation and commissioning. 
• Event set up testing. 
• Clean down.  
• Building cleaning operational systems. 
3.5 Public Programming Approach 
The public and private events programme for cultural venues can be defined by
three key periods:   
Pre-opening Events  
Two test events at full capacity to include funder and stakeholders along with
industry-specific activities to promote the commercial portfolio prior to the
official public opening (PTH and PAC). 
Opening Events 
First large-scale event over a weekend to mark the public opening of the venue,
animating the interior and exterior of the venue. 
Post-opening events 
Events programming following the Opening event, during the first year of
opening for OneRen and Renfrewshire Council curated events and commercial
business. 
3.6 Branding, Marketing & Engagement 
OneRen is currently working with Scottish branding agency Stand to develop a
distinctive strong brand for Paisley Town Hall, Paisley Arts Centre and Paisley
Learning and Cultural Hub. Workshops attended by key staff and stakeholders
are well underway with new brand options to be presented by the end of March.
The new brand will appear on signage and all marketing and communication
activity. A brand awareness campaign will be integrated into the marketing and
communication plans for pre-opening, opening and post opening activities. 
A marketing and communications plan is being created, a media buying agency
will be appointed and a fully integrated digital strategy will be rolled out for pre-
opening, opening and post opening activities.  An integrated stakeholder
engagement plan has been created to ensure continuous engagement with the
community, private sector, media, internal stakeholders, industry and partner
associations.

Page 6

A similar approach is being planned for Paisley Museum, with a separate
tender brief for branding being developed and the roll-out of a tailored
communications plan which will re-introduce audiences to the project and
share its aims, ambitions and tell the stories of the collection and the people
behind them. 
3.7 Paisley Town Hall 
3.7.1 Re-opening later in 2023, Paisley Town Hall will once again be the striking
centrepiece at the heart of the town’s life. Building on its 140-year history, the
new and improved town hall will attract more and bigger performances,
bringing with it more people to Paisley. The works will transform the inside of
the 19th-century Grade-A listed building into a 21st-century entertainment
venue for the West of Scotland. 
3.7.2 The timescale is outlined in the table below:

Page 7

No embedded text on this page.

Page 8

3.8 Paisley Town Hall will be a new home for headline acts and intends to establish
itself as a go-to venue for top musicians, bands and performers in the country.
The ambition is for performers to aspire to play here and once experiencing it,
like our customers, will want to return again and again. More than that, it will be
a place which the people of Paisley and beyond take to their hearts – a place
where memories are made that last a lifetime. 
3.9 Public Programming Paisley Town Hall in 2023 
Pre-opening events 
OneRen is currently working with experienced Scottish operators to deliver
events that will fully test the venue, equipment, infrastructure and operational
planning, offering an opportunity for stakeholders, funders and partners to gain
exclusive access prior to public opening.  A civic moment will be considered in
this phase and delivered if timescales allow, taking a variety of factors into
consideration.   
Opening events 
The Royal National Mod is anticipated to be one of the first events to take place
in Paisley Town Hall in October.  In addition to the Mod, OneRen is working in
collaboration with operators to deliver a music experience that animates both the
interior and exterior of the venue to mark the opening of the venue to the public. 
The private events programme will focus on engaging corporate clients with
bespoke experiences that highlight the premium offer available in this venue.   
Post-opening events 
OneRen’s Winter Programme will focus on a range of exciting activity in the
venues that complements the existing programming in Paisley around this
period.   
3.10 Public Programming Paisley Town Hall 2024 
The proposed public programme for the townhall in 2024 includes: 
• Commercial Festivals - A diverse programme of carefully curated
commercial festivals that animate the interior and exterior of the venue,
linking OneRen’s venues in the centre of Paisley. 
• Collaborations - A broad range of experiences that are developed with
operators and stakeholders from bespoke dance experiences to immersive
larger scale ticketed events, allowing OneRen to present a unique offer that
attracts a range of audiences to Paisley.  
• Seasonal Programming - This programme forms the backbone of the offer at
the venue, following the traditional pattern of performance venues in offering
a range of public programming that is advertised in distinct seasons including
music gigs, theatre shows, dance and comedy. 
• Special commercial events - The refurbishment of the venue presents a
premium venue for weddings and other life events to the Scottish market.

Page 9

• Corporate hire - A range of corporate events from gala dinners to award
ceremonies and bespoke experiences for the incentive market will be a key
offer, along with corporate offers linked into other programming strands e.g.
corporate tickets for an immersive Winter performance.  
• Private hire - The flexibility of the venue layout and capacity will be presented
to a range of private clients as an attractive proposition for hire including
concerts, touring theatre and film & television.   
3.11 Paisley Learning and Cultural Hub 
3.11.1 Work is ongoing on the creation of a new, modern community and educational
facility housing library services in a formerly vacant High Street unit. Paisley
Central Library used to be located within Paisley Museum.

Page 10

In its new home, it will stand as an icon on the High Street, with the aim of
attracting more people into the town centre and the venue.  The new central
learning and cultural hub complements other investment by the Council in the
town centre, such as the nearby Secret Collection - museum store, improved
transport links and outdoor spaces, and ongoing work to help property owners
restore historic buildings. 
3.11.2 The timescale is outlined in the table below:

Page 11

No embedded text on this page.

Page 12

3.12 Paisley Learning and Cultural Hub - Public Programming Approach 
Pre-opening events 
OneRen will invite groups from local nursery, primary and secondary schools
as test visits for the schools’ programme, and to arrange a test visit from the
day care centre for adults with learning disabilities who already have a strong
relationship with the library. The library team will also run some pre-opening
Bookbug sessions. 
Opening events
Although not yet confirmed, OneRen will look at a number of author events, as
part of Book Week Scotland in November for inclusion in part of the opening
programme. 
Post-opening events
The main focus of the programme will be for activities which promote reading
and digital inclusion, and for regular activities which encourage repeat visits and
create opportunities for the development of friendships, community and social
groups.  In addition to the activity which already happens in Paisley Central
Library such as Bookbug, the library team are also looking at initiatives including
a children’s reader in residence, film screenings, storytelling sessions (adult
and children), Dip into Digital sessions, magic table sessions and an increase
in our digital assistance sessions which support those who may be digitally
excluded. 
3.13 Paisley Arts Centre 
3.13.1 The construction phase of the refurbished Paisley Arts Centre will also be
completed in 2023, improving both performance facilities and visitor
experience at the popular venue.

Page 13

The Paisley Arts Centre stage has hosted some of Scotland’s biggest names in
the three decades since the 250-year-old former church building was converted
into one of the country’s most vibrant small entertainment venues. 
3.13.2 Paisley Arts Centre has an excellent reputation within the theatre community
for programming a wide and varied range of performances. The centre will offer
a platform for emerging artists and performers which will reinforce Paisley and
Renfrewshire’s place in Scotland’s cultural scene. The facility will be modern
and welcoming, while retaining the incredible character of the historic building.
The refreshed venue will be flexible enough for small, intimate performances
as well as the capacity for larger gigs that we know will attract a range of
performers and audiences. 
3.13.3 The timescale is outlined in the table below:

Page 14

No embedded text on this page.

Page 15

3.14 Paisley Arts Centre - Public Programming Approach 
The Arts Centre will be a much loved performance venue that continues to
support the creative arts industry in Paisley offering a platform for emerging
talent. This will include: 
• Festivals - An intimate performance venue that offers a performance and
workshop space for a lower capacity activity, as part of a wider festival in
the town centre. 
• Seasonal programming - Innovative and experimental ticketed
performances from theatre to comedy and dance that offers opportunities
for emerging artists and production companies to develop and present
ideas with accessibility being at the heart of the venue.  
• Learning - Development of a programme of workshops and courses
available at weekends, evenings and holiday periods.  
• Private hire - Studio and performance space available for local groups and
individuals to hire for classes and creative development. 
3.15 Paisley Museum 
3.15.1 Opening in 2024, the world-class museum refurbishment is the flagship
project in the regeneration of Paisley and Scotland’s biggest cultural heritage
capital development. Home to galleries, an observatory, heritage centre,
public gardens, events, and more, the reimagined museum will be at the
heart of the local community – and open for everyone to learn, discover,
create and connect. 
3.15.2 The new museum will be a vibrant and accessible cultural hub providing
welcoming facilities to the community whilst attracting visitors to Paisley from
across Scotland and beyond. The stories behind the museum and the
treasures it holds have been extensively and collaboratively researched and
will be shared more widely in the months ahead – building excitement as we
look forward to revealing the jewel in our cultural crown. 
3.15.3 The current timescale is outlined in the table below:

Page 16

No embedded text on this page.

Page 17

3.15.4 The PMR master programme includes three key stages of site works through
to opening in 2024; Main Works construction, Exhibition Fit-out and Direct
Works/Object Installation: 
Main Works - underway (2021-2023)
The Main Works contract is currently being undertaken by Kier Construction
Ltd who are due to complete this year. The work being undertaken to the
buildings is ambitious, complex and transformative with wholesale renovation
of external and internal fabric and major structural interventions including a
new build extension and entrance building and landscaped garden.   
The commissioning phase of the main work contract will commence in July
with final testing activities programmed in October/November. This phase will
involve attendance from the Exhibition Fit-out PMR project team, OneRen
operations/asset teams, Council FM and Exhibition fit-out Contractor to ensure
familiarisation with the new building systems. 
Exhibition Fitout – underway (2022-2024)
The Exhibition Fit Out (EFO) contract with The Hub Ltd started with a letter of
appointment on 13/05/2022 with a tendered programme of 76 weeks. The
exhibition fit-out contract includes a pre-construction phase ahead any site
installations. This involves a year of technical design by the contractor,
prototyping of the displays and offsite fabrication. They are currently
undertaking pre-construction services to execute contractor design portions
(CDP) for aspects of the flexible display system (FDS), plinths and showcases,
and bespoke display elements. 
Once site becomes available – galleries must be dust-free for building display
cases - the EFO contractor will take ownership of the site and begin to build
the individual displays.  Once the EFO contractor has completed their work,
and we have installed all the objects, the Museum team would move onto the
Direct Works installation, of FF&E, and onto pre-opening activities. 
Object Install – scheduled (2024)
Object install is the final delivery phase and will involve the move of display
objects from the Secret Collection to the museum for mounting and installation
ahead of opening. Object install will also include the return of the Heritage
Centre from its current temporary location to its permanent location within the
museum. Object Install, like EFO, will be completed sectionally with the
museum campus split into four sections. 
The other direct works include the installation of AV hardware, interactive
software and films in the digital displays. The remaining objects will be
installed in the Object Install phase following completion of EFO. Install teams
will be composed of both PMR/OneRen staff and EFO contracted mount
makers who will install mounts alongside the object mounts to secure them in
place in their display. A contracted art handler will provide additional support
for larger objects being installed during the Object Install phase.

Page 18

Operational Planning Pre & Post-Handover Planning (underway) 
An Operations Task Force group for PMR has been formed which comprises of
the Musuem team members and OneRen Assets Management and Operations
staff.  In the period prior to building handover, the group will concentrate on the
creation or development of standard operating procedures ranging from
collection incident reporting, pest management and gallery procedures to
security incidents and bomb threat response, as well as a programme of staff
training, skills development and recruitment. The group is tasked with
identifying and developing all of the Operational plans and procedures required
for PMR and to review and where required, respond to architectural plans,
proposed operating systems and other plans required by the external
consultants/contractors.  To date, the group has identified 40 policies and
procedures that are required for the new museum, of which 25% have been
created.   
3.16 Paisley Museum - Public Programming Approach 
To offer audiences a truly new experience of the museum and its collections,
OneRen is creating a new approach to programming; an embedded culture
which places audiences at the centre, and a framework to support this. Over
the last five years, OneRen has explored many new approaches to working with
audiences, through content creation, audience research, active listening
exercises and stakeholder engagement at all levels of the project. 
Simultaneously, through OneRen’s active commitment to unlocking the stories
of Renfrewshire’s collections, the team has amassed a huge volume of
collections’ research and newfound knowledge which has relevance, interest
and huge engagement potential for our audiences. The development of the
public programme offers the opportunity to draw together these different
threads of the PMR project and create a powerful and sustainable legacy for
the project. Between March and August 2023 OneRen will work with staff and
partners through a series of vision and values workshops and thinking space
discussions to create an outline public programme which truly exemplifies the
ambitions of what promises to be a world-class destination. 
___________________________________________________________________
Implications of the Report 
1. Financial - Financial modelling of the operational and opening phase of the
projects has been undertaken and is being continually updated to reflect emerging
factors. 
2. HR & Organisational Development - staffing training and recruitment
requirements are outlined in this report in the pre and post handover phases of the
projects.

Page 19

3. Community/Council Planning –  
• Our Renfrewshire is thriving – These projects will link our communities and
facilitate a significant increase in footfall to Paisley and surrounding areas. The
infrastructure will enable Renfrewshire to host world class performances and
attract new footfall from far beyond the local area.
• Our Renfrewshire is well - The outputs of these projects will enable safe and
inspiring locations for all. From arts and performances to learning and
educational space, Renfrewshire will offer anyone the ability to engage and
take interest in either a new subject matter or an existing passion that is now
much more accessible. Driving world class performances to the area and
having 21st century work and education spaces will support people from
Renfrewshire to engage in beneficial activities that will in turn support
education.
• Reshaping our place, our economy and our future – These infrastructure
projects allow access to new and existing jobs for people in our communities.
Significant increase in footfall will benefit local businesses who can grow as a
result and in turn support their ongoing viability in the area. An increase in arts
and performances will allow a platform for Paisley becoming a cultural hub in
Scotland.
• Tackling inequality, ensuring opportunities for all – A specific focus has been
applied to the redevelopment and construction of these projects to ensure
accessibility is a key feature. A significant amount of thought has gone into
making historic, and predominantly inaccessible buildings, available for
anyone to enjoy and utilise. There are no barriers to utilising any of these
buildings, and One Ren will continue to deliver an events programme that
caters for everyone including those in more deprived areas.
• Creating a sustainable Renfrewshire for all to enjoy – With these buildings
being in the heart of Paisley Town centre, it means they are accessible by
train, on foot, or by bus thanks to the well-connected nature of the town centre.
Limited town centre parking will force the use of public transport which will
work towards the net zero ambitions of the Council. Recently completed
infrastructure through AMIDS, including the shared cycle and walkway, also
enhances the connectivity, and in future years with the opening of the Clyde
Waterfront and Renfrew Riverside bridge, Paisley will become a vastly
accessible route by sustainable travel.
• Working together to improve outcomes - Officers and contractors continue to
work closely with local businesses and a business engagement programme
will commence shortly to bring this to focus. Throughout the development of
these projects, several organisations were engaged to design the outputs
including accessibility groups, the Scottish Government, Historic Environment
Scotland, multiple private sector organisations and the local community. 
4. Legal – not applicable. 
5. Property/Assets - the investment in the four premier cultural assets will enhance
and sustain the properties for the future.

Page 20

6. Information Technology - ICT actions are included within a specific workstream
for the four cultural venues and are managed by project partners. 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report. If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website.   
8. Health & Safety – all health and safety documents are being prepared for the
operational delivery of the venues. 
9. Procurement – contracts are being entered into in line with contract standing
orders to meet legislatory regulatory requirements. 
10. Risk – a risk register is being maintained for the cultural infrastructure programme
which is actively, updated, monitored and managed. 
11. Privacy Impact – not applicable. 
12. Cosla Policy Position – not applicable.
_________________________________________________________ 
List of Background Papers – None 
___________________________________________________________________ 
Author:           Barbara Walker – Programme Director (City Deal & Infrastructure)  