Page 1

To: Economy and Regeneration Policy Board
On: 14 March 2023 
Report by:  Chief Executive and Director of Finance and Resources
Heading:  Revenue and Capital Budget Monitoring as at 6 January 2023 
1. Summary of Financial Position
1.1. The projected revenue outturn at 31 March 2023 for those services reporting
to the Economy and Regeneration Board is a breakeven position. 
1.2. The projected capital outturn at 31 March 2023 for projects reporting to the
Economy and Regeneration Policy Board is a breakeven position against the
revised budget for the year of £26.048 million.
1.3. This is summarised in the table below and further analysis is provided in the
Appendices. 
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn
£000
Budget
Variance
(Adv) / Fav
£000
Budget
Variance 
%
Economy and Development 3,075 3,075 0 0.0% 
Division
Revised
Annual
Budget
£000
Projected
Annual
Outturn 
£000
Budget
Variance
(Adv) / Fav
£000
Budget
Variance 
%
Economy and Development 26,048 26,048 0 0%

Page 2

Recommendations
1.4. Members are requested to:
(a) Note the projected Revenue outturn position detailed in Table 1 above; 
(b) Note the projected Capital outturn position detailed in Table 2 above; and 
(c) Note the budget adjustments detailed at sections 4 and 6. 
2. Revenue
2.1. The Revenue Budget Monitoring report at Appendix 1 identifies a projected
breakeven position for all services reporting to this Policy Board.  Detailed
division service reports can also be found here, together with an explanation
of any significant projected variances.
2.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.  Any changes to these
projections will be detailed in future reports to the Board.
2.3. The main reasons for the projected outturn position are indicated below the
tables showing both the subjective analysis (what the budget is spent on) and
the objective analysis (which division is spending the budget). 
3. Revenue Budget Adjustments
3.1. Members are requested to note from Appendix 1 that budget adjustments
totalling £0.079 million have been processed since the previous report to
board, which mainly relate to pay award inflation.   
4. Capital
4.1. The Capital Investment Programme 2022/23 to 2026/27 was approved by the
Council on 3 March 2022. For Economy and Regeneration the approved
capital spend for 2022/23 is £26.048m.
4.2. The Capital Monitoring report at Appendix 2 indicates net budget adjustments
to date in the 2022/23 approved capital programme for Economy and
Regeneration of £19.823m, largely as a result of reprofiling budget from
2022/23 into 2023/24 for Paisley Town Hall and Paisley Museum to reflect
updated cashflows. 
4.3. Further detail, including reasons for significant variances (where applicable),
can be found at Appendix 2.

Page 3

Capital Budget Adjustments
4.4. Since the last report, budget changes totalling £4.770m have arisen which
reflect the following:
Budget carried forward into 2023/24 from 2022/23 for updated cashflows
(£4.770m):
• Paisley Art Centre (£1.004m);
• Paisley Museum (£1.500m);
• Paisley Learning & Cultural Hub (£0.750m);
• Paisley Junctions and Charging Hub (£1.116m);
• Townscape Heritage CARS 2 (£0.400m).
______________________________________________________________ 
Implications of this report 
1.  Financial – The projected budget outturn position for the revenue budget
reported to the Economy and Regeneration Policy Board is breakeven. 
Income and expenditure will continue to be monitored closely for the rest of
the financial year and, where necessary, steps will be taken to mitigate any
overspend.   
The projected outturn position for capital budgets reported to the Economy
and Regeneration Policy Board is breakeven.  The Capital programme will
continue to be monitored closely for the rest of the financial year.   
Any changes to current projections in either Revenue or Capital budgets
will be reported to the board as early as possible, along with an explanation
for the movement. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
None directly arising from this report. 
4.  Legal 
None directly arising from this report.

Page 4

5.  Property/Assets 
The Capital expenditure in this board will result in improvements to Culture
and Heritage assets and delivery of strategic place-shaping and
regeneration. 
6.  Information Technology 
None directly arising from this report. 
7.  Equality and Human Rights 
The recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website.   
8. Health and Safety
None directly arising from this report. 
9. Procurement 
None directly arising from this report. 
10. Risk 
The potential risk that the Council will overspend its approved budgets for
the year will be managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact
None directly arising from this report. 
12. 
13.
Cosla Policy Position 
N/a. 
Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers
__________________________________________________________________ 
Authors: Valerie Howie, Finance Business Partner (Revenue) and Geoff
Borland, Finance Manager (Capital)

Page 5

Appendix 1   
Objective Summary
Approved
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Economy and Regeneration Management 127 11 138 141 (3) (2.2%) (2) (1)
Economic Development 1,932 45 1,977 1,981 (4) (0.2%) 11 (15)
Regeneration 937 23 960 953 7 0.7% (9) 16
NET EXPENDITURE 2,996 79 3,075 3,075 0 0.00% 0 0
Objective Heading
Economy and Regeneration Management
Economic Development
Regeneration
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  ECONOMY AND REGENERATION
Key Reasons for Projected Variance
No significant projected year end variances to report.
No significant projected year end variances to report.
No significant projected year end variances to report.

Page 6

Appendix 1   
Subjective Summary
Approved
Annual
Budget at
Period 8
Budget
Adjustments
Revised
Annual
Budget at
Period 10
Projected
Outturn
Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 4,609 (14) 4,595 4,541 54 1.2% 53 1
Premises Related 52 0 52 53 (1) (1.9%) (1) 0
Transport Related 3 0 3 3 0 0.0% 0 0
Supplies and Services 29 0 29 30 (1) (3.4%) (1) 0
Third Party Payments 0 0 0 0 0 0.0% 0 0
Transfer Payments 721 88 809 860 (51) (6.3%) 1 (52)
Support Services 39 0 39 40 (1) (2.6%) (1) 0
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 5,453 74 5,527 5,527 0 0.0% 51 (51)
Income (2,457) 5 (2,452) (2,452) 0 0.0% (51) 51
NET EXPENDITURE 2,996 79 3,075 3,075 0 0.0% 0 0
REVENUE BUDGET MONITORING STATEMENT 2022/23
1 April 2022 to 6 January 2023
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
POLICY BOARD :  ECONOMY AND REGENERATION

Page 7

Appendix 2   
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2022* 2022-23 in 2022-23 2022-23 2021-22 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
ECONOMY & DEVELOPMENT
Paisley Art Centre Redevelopment 574 1,774 (774) 1,000 1,000 0 0% 3,050 3,050 0 0%
Paisley Town Hall Redevelopment 8,284 11,729 (4,469) 7,260 7,260 0 0% 22,050 22,050 0 0%
Flexible Outdoor Facility/Travel & Accessibility Infrastructure 447 1,283 (1,223) 60 60 0 0% 7,050 7,050 0 0%
Playing Fields and Sports Development 779 1,040 (860) 180 180 0 0% 5,600 5,600 0 0%
Paisley Museum 12,117 20,109 (7,542) 12,567 12,567 0 0% 45,522 45,522 0 0%
Town Centre Capital Fund 1,793 2,250 (2,007) 243 243 0 0% 4,037 4,037 0 0%
Paisley Learning & Cultural Hub 2,755 3,642 (1,994) 1,648 1,648 0 0% 7,000 7,000 0 0%
Place Based Fund 25 0 1,195 1,195 1,195 0 0% 4,427 4,427 0 0%
Paisley Junctions and Charging Hub 211 2,520 (1,301) 1,219 1,219 0 0% 3,346 3,346 0 0%
Townscape Heritage CARS 2 2,523 1,524 (848) 676 676 0 0% 4,099 4,099 0 0%
Total Economy & Development 29,508 45,871 (19,823) 26,048 26,048 0 0% 106,181 106,181 0 0%
TOTAL ECONOMY & DEVELOPMENT 29,508 45,871 (19,823) 26,048 26,048 0 0% 106,181 106,181 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1st April to 6th January 2023
POLICY BOARD: ECONOMY & REGENERATION
Current Year 2022-23 Full Programme - All years
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable