Democracy Spraffa

Cultural Infrastructure Programme Update

Renfrewshire Council · 24 January 2023
Back to Economy and Regeneration Policy Board — 24 January 2023 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy & Regeneration Policy Board
On: 24 January 2023
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Cultural Infrastructure Programme Update
___________________________________________________________________
1. Summary 
1.1. This report is to update the Board on the progress of Renfrewshire Council’s
Cultural Infrastructure Programme, being delivered on behalf of the Council by the
City Deal & Infrastructure Team (with project management expertise from the
Council’s Property Services team) with the Paisley Museum Project being
delivered by OneRen. 
1.2. The Cultural Infrastructure Programme investment in Paisley town centre will use
our internationally significant cultural and heritage story to transform our future for
visitors and events within Scotland. This programme of work will bring new footfall
and life to the town centre, new homes for top class events and life-changing
cultural experiences whilst preserving the heritage of the town. 
1.3. Since the beginning of the Cultural Infrastructure Programme, the scale of the
economic shock we have since experienced from global events such as the
pandemic and war in Ukraine has been unforeseeable introducing significant
pressure on the Council and its contractor’s in delivering these ambitious plans.
Completion of these projects are central to the recovery and inclusive growth of
the Renfrewshire economy and Paisley Town Centre. 
1.4. Given the very significant scale of the cultural infrastructure programme a
managed programme of phased venue openings over a defined period has been
planned since the commencement of the construction phase. Delivering a
managed and coordinated opening programme is key to securing a successful go
live phase where each venue is provided with the opportunity to be launched in its
own right and contribute both individually and collectively to maximise the impact
on Renfrewshire’s cultural, events and heritage opportunities.

Page 2

1.5. In addition, there are significant operational demands involved in planning,
preparing and delivering each venue opening and consequently there is a need to
actively manage the opening programme to ensure organisational capacity of both
the Council and OneRen is able to appropriately support the associated demands
of each individual venue opening. 
1.6. The very significant scale of the construction phase, coupled with the
unprecedented challenges faced across the wider construction sector over the
past number of years, has meant there has been an inevitable shift in the
construction completion dates of each venue in contrast to that planned at the
outset of the programme.  Notwithstanding, greater confidence is being
increasingly secured in relation to anticipated construction completion dates which
will allow a firm opening schedule to be finalised and in line with the planning
principles outlined above it this will not necessarily be directly driven by the
completion dates of each individual construction contractor.  A paper outlining the
detail of the planned opening programme will be brought to the next board.
2. Recommendations 
2.1  The Economy & Regeneration Board is asked to: 
i) Note the progress and current stage of construction of the projects
outlined in this paper.
ii) Note that OneRen will bring details of the cultural infrastructure opening
programme and marketing plans to the next meeting of this board as
detailed in paragraph 13.
________________________________________________________________________
3. Project Updates 
3.1. Whilst each of the Cultural Infrastructure projects individually contribute to
economic growth in Renfrewshire, it is important to note that the combined social
and economic outcomes from across these investments are greater than the sum
of the individual parts. Coupled with the Councils wider economic investments in
City Deal, AMIDS, housing and other regeneration projects these social and
economic outcomes for our local residents and visitors is enhanced further. 
3.2. On all project sites planned progress has been difficult to maintain in line with
programmes whilst contractors manage the ongoing difficulties of construction
materials and supply chain with current global issues outing significant pressure
on costs. The Council continues to work closely with contractors to monitor and
provide any reasonable support to ensure the successful delivery of these
important projects. 
3.3. The Council and OneRen teams are currently working together to finalise opening
plans for these venues and an update will be brought to the next meeting of this
board. 
4. Paisley Town Hall Redevelopment 
4.1. Paisley Town Hall is being transformed into a landmark entertainment venue for
the West of Scotland, to preserve its place at the heart of life in Paisley for future
generations.

Page 3

The Paisley Town Hall Redevelopment project includes replacement of all
mechanical, electrical and plant, as well as a full fit out and redecoration of the
existing building. In addition, internal modernisation to increase the quality and
range of services offered by improving the main hall auditorium, increased
dressing room provision, acoustic and lighting improvements, new function suite,
extended kitchen and new bar provision, additional toilets, and all-round
improvements to the landmark building are currently being constructed. 
4.2. The design preserves the same classic look and grand features which make the
town hall so distinctive – but creates the 21st century facilities required for a
successful modern venue. 
4.3. Redevelopment of significant and historic buildings is always challenging, and the
team are ensuring that quality and care is taken to deliver the building to the high
standards to meet the vision and expectations for this building. The contractor,
Morrison Construction, has now completed most of the required internal structural
changes and is transitioning to the fit-out works. One of the most prominent areas
of construction has been the erection of an 18m high scaffolding structure that
covered the entirety of the main hall, used to completely refurbish the historic
ceiling decoration, and install new machinery in the attic space above the main
hall. This scaffold has now largely dropped, marking the completion of a significant
area of work, and showcasing the ornate ceiling that brings the main hall to life. 
4.4. Work will continue at pace into 2023 where mechanical and electrical upgrades
will complete in the early part of the year and will see the finalisation of a new
heating and water system as well as new accessible lift installations. Along with
the full electrical replacement, the building will also have new fibre installed to
bring improved network capacity and allow the installation of a new Wi-Fi service
that will provide connectivity for both staff and the public. 
4.5. Finishing works will then take place across all rooms including kitchens, toilets,
office spaces and event rooms which will conclude the construction works. It is
anticipated that construction works will be complete at the end of May 2023. This
will then be followed by an intense period of internal fit out of items including
furniture, ICT, and high-quality stage sound and lighting equipment to ensure
Paisley Town hall can deliver top class entertainment events. 
4.6. OneRen are preparing an operational readiness programme concurrently for the
internal fit out works, involving staff training and implementation of operating
procedures. The PTH venue will be marketed by OneRen through a pre-planned
strategy to attract events, performers, and bookings. The operational readiness
programme will be implemented commencing in spring 2023, with the building
opening in advance of the Royal National Mòd 2023, which will take place in
Paisley from 13th to 21st of October. 
5. Paisley Learning and Cultural Hub 
5.1. Paisley Learning and Cultural Hub is a 21st century community hub and a modern
home for library services at the heart of Paisley High Street, bringing new footfall
into the town centre. The construction of this building is taking place in a previously
vacant and derelict building in the centre of the High Street and will become a
modern educational resource for people of all ages to learn and be inspired.

Page 4

5.2. Construction of the building has seen a significant amount of the existing building
stripped out whilst preserving the historic characteristics of the building. The
building has been transformed with a complex network of new steel installed to
create the foundation of what will be four floors of learning and collaboration
space. On site, steelwork and structural changes are largely complete with the
final new staircases being installed imminently to allow the works to progress to
the fitout phase. 
5.3. Early in 2023 the front of the building will be installed which will be a significant
milestone towards completion. Work has already commenced to prepare the fitout
of the building with mechanical and electric works started, and internal walls now
being constructed. Every element of this building will be newly installed, and this
will include new fibre and Wi-Fi to the building for both staff and the public who
use the building. 
5.4. Construction works are scheduled to complete by the end of May 2023, and this
will deliver; a children’s library including a new play structure integrated with digital
learning mechanisms, various touch down spaces to work and learn, meeting
rooms and event space, ICT suites, all combined with the Paisley Central Library
collection throughout. 
5.5. OneRen will deliver an operational readiness programme that will involve the
transition of the temporary Paisley Central Library from its existing location in the
Lagoon car park, to the new building on Paisley High Street. This transition will
take place in the second half of 2023 after which the PLCH will be opened to the
public. 
6. Paisley Arts Centre 
6.1. Paisley Arts Centre is being extended and upgraded into a unique and intimate
performance venue and creative hub, driving new life and footfall into the heart of
the town centre. This refurbishment project includes a complete replacement of
the building’s mechanical, electrical and plant equipment, a full refurbishment
throughout, new retractable seating, accessibility improvements and a new
extension to improve the number of covers in the bar. These improvements will be
further supplemented by the creation of a new public realm space externally to
provide event space. 
6.2. The existing historic building has been stripped inside to enable the main works to
take place. This is enabling the contractor to make final structural alterations and
complete the removal of existing material no longer required. Work is beginning to
pick up now with reinforcements to the internal structure taking place and progress
being made on the strengthening of the roof. Foundations are in place for the new
extension to the front of the building which will then progress to the construction
of the additional space. 
6.3. Construction will then move to internal fit out works in early 2023, bringing the
refurbishment of all spaces. The final element will see the installation of a ‘tensile
wire grid’ which is a permanent working platform that will allow access to the audio-
visual equipment including stage lighting.

Page 5

This structure will allow ease of access to an otherwise hard to reach area, to
ensure performances can receive the best technical support available, resulting in
higher demand for using the venue. This building will also benefit from the
installation of new fibre and Wi-Fi for the use of staff and public. 
6.4. It is anticipated that construction work will complete in summer 2023, where the
venue will then progress into a OneRen led operational readiness programme.
This will include the training of staff and implementation of operating procedures,
as well as readying for performances, and marketing the venue. The operational
readiness and marketing programme by OneRen will be delivered in advance of
the building opening which is expected to be late 2023 / early 2024. 
7. Paisley Museum Reimagined 
7.1. Paisley Museum Reimagined will deliver a world-class destination telling the
inspirational stories of Paisley’s people and pattern and showcasing its
internationally significant collections. This project includes repairing and
renovating all buildings on the museum campus delivering a 20% increase in the
overall area. The construction also includes a new extension housing a visitor
reception and café, the installation of new mechanical, electrical and plant
systems, as well as the introduction of a public courtyard. Importantly, this work
enables an increase in the interpretation of the collections and number of objects
on display, with a strong focus on digital interpretation. 
7.2. Construction work is well underway and bulk excavation to form Level 0 and the
new entrance courtyard is nearing completion. Temporary steelwork previously
supporting the corner of the new gable opening has been removed and the
building is now supported by the permanent columns. Roof works are ongoing at
the main museum building and Oakshaw with completion of the main south roofs
now largely complete. The new west extension steelwork has been erected on
Level 3 and 2 and roof decking is progressing well. 
7.3. Work has now begun on planning the exhibition fitout for the museum with award-
winning specialist consultants ‘The Hub’ appointed to lead this piece of work. Work
is taking place to design and create samples and mock-ups of the show cases and
displays with this work progressing well. 
7.4. With the project moving into the final part of delivery, work is ongoing with content
and interactive development with three digital companies appointed to work on the
following: 
 Joi Polloi – a double BAFTA award winning independent studio has been
commissioned to produce digital interactives for the museum. 
 Media Co-op - a multi award winning company has been contracted to co-
produce films working with local communities.
 Freakworks Ltd - one of Scotland’s leading film making companies has been
commissioned to produce films and animations for museum displays. 
7.5. Work to conserve the collection is well underway in readiness for redisplay.
Conservation treatment of all Paisley Pattern shawls, sculptures and works on
paper, selected for display is already complete. Conservation work continues on
paintings, ship models, frames, costume, natural history and looms.

Page 6

To assist with conservation treatments, we have been successful in securing
external grants including contributions from the Art Fund, National Museums
Scotland’s National Fund for Acquisitions, Museums Galleries Scotland and the
Pilgrim Trust. As part of the conservation works programme, we have also
established partnerships with organisations such as Centre for Textile
Conservation at University of Glasgow and the Natural History Museum in New
York. 
7.6. A Museum Careers Day at Paisley Lagoon has also taken place to highlight the
benefits of a career in museums and show potential new colleagues, what the new
venue will bring when it re-opens in 2024. The target audience included school
children and adults with additional support needs. Participants were offered
interactive activities, competitions, films, slideshows, and hands-on experiences
as well as opportunities to discuss skills and qualifications associated with various
roles within the sector. In total there were 224 attendances, of which, 151 were
school children. 
7.7. Construction work on site is due to be complete late summer 2023 which will then
transition to the building and exhibition fitout process over a number of months
which will see the building open to the public in summer 2024. 
8. Abbey Quarter 
8.1. Abbey Quarter is a high quality public realm project to support the investment in
the Town Hall facilities and provide an accessible outdoor events space for our
Town Centre. The project extends over the area in front of the Town Hall across
the grass area adjacent to the Abbey to Cotton St and includes the grass area to
the side of the Town Hall in front of the Abbey to the bridge at Cotton St. 
8.2. Design of the area in front of the Town Hall extending into the Green is at RIBA
Stage 3 (ready for planning). This area also incorporates the entrance to the
Abbey to ensure this is fully accessible. It had previously been anticipated that this
area could be undertaken as part of the Town Hall project and so a public
consultation was carried out for this element November and December 2021 which
obtained wide public support. However, when undertaking investigative
archaeological surveys in the area potential human remains were encountered
and so a court order will be sought in order to deal with this in an appropriate and
sympathetic manner. Historical ownership of this area is also being reviewed. The
paperwork required for the court order has now been prepared and is being
reviewed for our in-house lawyers, before being submitted to the Sheriff Court
early in the New Year. 
8.3. The design of the garden area adjacent to the river is also at RBA Stage 3 (ready
for planning). No public consultation has yet been carried out in this area. This
consultation is being prepared and will be launched in March 2023. 
8.4. The area around the Cotton Street/Gauze Street junction forms part of the aim to
create an additional town centre event space. The design proposals in this area
are also at RIBA Stage 3 (ready for planning). The design is currently being
reviewed with the Council’s roads team to ensure alignment with their Bus
Partnership project. This consultation is being prepared and will be launched in
March 2023.

Page 7

9. Townscape Heritage and Conservation Area Regeneration Scheme 2
(TH.CARS2) 
9.1. Paisley TH.CARS2 is now entering its final year and is delivering Building Repair
projects, Shopfront improvements and a Small Grant programme to historic
properties in Paisley Town Centre. The project is funded by the National Lottery
Heritage Fund (NLHF), Historic Environment Scotland (HES) and Renfrewshire
Council, with combined project funding of over £4.1 million, and additional
contributions from owners. The project is also delivering public realm
improvements with a successful programme of heritage related activities and
events now completed. NLHF and HES have agreed an extension to the project
completion date to the end of September 2023, to allow the completion of the final
projects and evaluation. 
9.2. Grant support for external repairs has been awarded to ten larger building repair
projects with eight projects completed, one project on site at 5 George Place and
works to the final project, 32 High St, (the former Liberal Club), due to commence
in January 2023. This has made a significant difference to the condition and
appearance of a number of prominent properties in Paisley Town Centre including:
2/3 County Place opposite Paisley Gilmour St, now restored and converted to flats;
20 New St (Viennas night club), 41 High St, (Right Way Credit Union offices), Sma
Shot Cottages, 9 Gilmour St (Walker Laird’s offices), 28 High St, 18 Georges Gate
and 10 Shuttle St. The works to 5 George Place are due to complete in February
2023. The external works to the Liberal Club are expected to complete by August
2023 and will greatly improve the condition and appearance of this prominent town
centre property.   
9.3. Shopfront Improvements grants have been awarded to eleven projects in the High
St with five projects completed at 30 High St (White Cart Company and Sinclair
Jewellers), 36 High St, (Shelter), 61 High St (Print and Copy it), 41 High St (Right
Way Credit Union) and 44 High St (Uptown Barbers). A further four projects are
programmed to start in the New Year. The TH.CARS2 project has also supported
a Small Grants programme mainly for traditional window repair projects in the
Town Centre. 
9.4. Public realm works have also been funded through the project with works
completed at George Place. Public Realm works to pavements opposite the High
St are currently on site. Works at Weighhouse Close are almost complete and
footpath works have also been carried out at Storie Street.  The High Street
pavement works have been a complex project with private basements below the
pavements and additional structural repairs required. However, the works will
make a significant difference to the quality of the public realm in this area and
support the improvements to the Museum.   
9.5. TH.CARS2’s community engagement programme of Heritage Education, Training
and Events has also now concluded. Comprising 42 projects, it has seen delivery
of 630 workshops and over 115 separate events. Over 2,500 participants, trainees
and volunteers have been engaged and estimated audiences of over 50,000
reached. More than 100 partners have been involved locally and nationally, and
over 150 job opportunities have been created for consultants and freelancers.

Page 8

Final projects included: ‘Paisley Pioneers’ a short film made with Pachedu,
exploring historical and contemporary stories of migration to and from
Renfrewshire; ‘Monumental’, a project with ReMode for International Women’s
Day 2022 in which participants worked with a costume designer to make
historically accurate costumes for significant women from Paisley’s past;   and a
paid work placement for a Renfrewshire 16 year old with a stone sub-contractor
at Paisley Museum who has recently progressed to a permanent job with a civil
engineering company. 
10. St James Playing Fields & Ferguslie Sports Centre 
10.1. These projects will work towards delivering Renfrewshire’s vision to ‘make sport
a way of life’. In 2018, Council approved the upgrading of changing facilities at
Ferguslie Sports Centre and for the demolition and replacement of the existing
pavilion at St James Playing Fields. When the Covid-19 pandemic hit, a decision
was made to put these projects on hold until such time that it was appropriate to
proceed. 
10.2. In July 2022, approval was given to resume the planning of the Ferguslie Sports
Centre upgrades. This work has now gathered pace with designs now agreed
and progressing through the appropriate stages. This work will completely
refurbish all existing changing facilities to the sports centre, bringing a greater
experience to the already well utilised facility. It is currently projected that
procurement for a contractor to complete these works can be completed and
presented to the August 2023 Finance, Resources and Customer Services Policy
Board for approval. This will then allow a contractor to complete the works during
the first half of 2024. 
10.3. With regards to St James Playing Fields, a design was previously approved for
the construction of a new pavilion to accommodate changing facilities for four
existing football pitches, with the aim of making this a desirable destination for
football bookings within Renfrewshire. The tender process unfortunately resulted
in only one bid being received and this was significantly over budget and
therefore not viable as no best value obligations could be met. The project team
are currently considering options to de-risk the tender in light of the current
market volatility and a new tender process will be conducted. It is envisaged that
following completion of redesign work in early 2023, and the development of
construction planning stages, this project can go back out to tender for a
contractor in the first half of 2023. 
11. Programme Community Benefits 
11.1. Across the cultural infrastructure programme, we have secured 207 community
benefit commitments of which 95 have been delivered. Benefits delivered include
new entrant jobs, modern apprenticeships and graduate roles at Paisley Museum
and Town Hall as well as supply chain development events and training.
Community Engagement has been delivered through training sessions, financial
donations and support from contractors and professional services for local social
enterprises and third sector organisations. Educational support has included site
visits, career events, specific have been supported through site visits, work
experience placements for school leavers, support with CVs and applications,
donations of PPE and support to secure CSCS cards.

Page 9

The contractors and design teams will continue working with the Council’s
community benefit forum to deliver the remaining benefits before completion of
the programme. 
12. Programme Marketing, Communications and Engagement 
12.1. With the significant capital investment being made across the cultural
programme, and the benefits this will bring to Renfrewshire, it is important that
marketing, communication, and engagement is delivered in a timely and effective
manner. To achieve this, the following activities are being delivered: 
12.2. A communications strategy has been developed by the Council’s marketing and
communication service and continues to inform key stakeholders about
construction progress and end-dates for the cultural programme. Public
communication is also taking place to notify on relevant progress for other
projects until such time that they progress further. 
12.3. Marketing, communication, and business engagement to support the reopening
and programming of the new cultural venues will be delivered by OneRen and is
expected to commence in early 2023. To supplement this process, a programme
of business engagement to drive town readiness for the scheduled reopening of
the venues will begin in January 2023. 
13. Operational Readiness 
13.1. For the four Paisley Town Centre cultural buildings (Paisley Town Hall, Paisley
Arts Centre, Paisley Learning & Cultural Hub, and Paisley Museum), a joint
operational readiness process is required between Renfrewshire Council and
OneRen. The Council will assist in the fit out of all furniture, fixtures and
equipment required to meet the operational needs of these buildings. It is
however, for OneRen to deliver a detailed operational readiness programme for
each of these buildings. Plans are currently under development and will be used
to define a managed and achievable opening schedule for the four buildings. 
13.2. This process of operational readiness will comprise of elements such as: 
 Furniture and equipment installation with some of the specific requirements
including: 
o Bespoke library equipment and shelving for the Learning & Cultural Hub.
o For the Town Hall and Arts Centre, the technical fit out of all theatre and
performance audio visual equipment.
o Finally, for the Museum, this will include the bespoke exhibition fit out. 
 ICT fit out including all devices, network access, staff and public Wi-fi. There are
also a number of new digital interactions being installed in particular in the
Learning & Cultural Hub and Museum. 
 Confirmation of operational procedures and policies.
 Recruitment and training of OneRen staff.
 Specific venue marketing and bookings.

Page 10

13.3. The operational readiness process for each venue requires time and resource to
ensure it is a success. The planning of this process is also the key component to
confirming exact opening dates. In early 2023, a detailed plan will be finalised
which will show the opening programme for each of the cultural venues in a
staggered way. Details of this opening programme, supplemented with
operational readiness information and a marketing plan by OneRen will be
brought to the next Economy and Regeneration Policy Board. 
_____________________________________________________________ 
Implications of the Report 
1. Financial – None. 
2. HR & Organisational Development – None. 
3. Community/Council Planning –  
 Our Renfrewshire is thriving – These projects will link our communities and
facilitate a significant increase in footfall to Paisley and surrounding areas. The
infrastructure will enable Renfrewshire to host world class performances and
attract new footfall from far beyond the local area. 
 Our Renfrewshire is well - The outputs of these projects will enable safe and
inspiring locations for all. From arts and performances to learning and
educational space, Renfrewshire will offer anyone the ability to engage and
take interest in either a new subject matter or an existing passion that is now
much more accessible. Driving world class performances to the area and
having 21st century work and education spaces will support people from
Renfrewshire to engage in beneficial activities that will in turn support
education and interest. 
 Reshaping our place, our economy and our future – These infrastructure
projects allow access to new and existing jobs for people in our communities.
Significant increase in footfall will benefit local businesses who can grow as a
result and in turn support their ongoing viability in the area. An increase in arts
and performances will allow a platform for Paisley becoming a cultural hub in
Scotland which can be used to drive new educational agendas with greater
access to this subject matter. 
 Tackling inequality, ensuring opportunities for all – A specific focus has been
applied to the redevelopment and construction of these projects to ensure
accessibility is a key feature. A significant amount of thought has gone into
making historic, and predominantly inaccessible buildings, available for
anyone to enjoy and utilise. There are no barriers to utilising any of these
buildings, and One Ren will continue to deliver an events programme that
caters for everyone including those in more deprived areas. 
 Creating a sustainable Renfrewshire for all to enjoy – With these buildings
being in the heart of Paisley Town centre, it means they are accessible by
train, on foot, or by bus thanks to the well-connected nature of the town centre.

Page 11

Limited town centre parking will force the use of public transport which will
work towards the net zero ambitions of the Council. Recently completed
infrastructure through AMIDS, including the shared cycle and walkway, also
enhances the connectivity, and in future years with the opening of the Clyde
Waterfront and Renfrew Riverside bridge, Paisley will become a vastly
accessible route by sustainable travel. 
 Working together to improve outcomes - Officers and contractors continue to
work closely with local businesses and a business engagement programme
will commence shortly to bring this to focus. Throughout the development of
these projects, several organisations were engaged to design the outputs
including accessibility groups, the Scottish Government, Historic Environment
Scotland, multiple private sector organisations and the local community. 
4. Legal – None. 
5. Property/Assets – Note the improvements being delivered to current assets. 
6. Information Technology – None. 
7. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. No negative
impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations
contained in the report because it is for noting only. If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety – None. 
9. Procurement – all contracts are tendered in accordance with Council
procurement procedures and where relevant taken to FRCS Board for approval. 
10. Risk – Project specific and Programme level risk registers have been established
for all projects. These are kept under regular review and reported to the Council’s
internal City Deal and Infrastructure Programme Board. 
11. Privacy Impact – None. 
12. COSLA Policy Position – Not applicable. 
13. Climate Risk – these projects will significantly improve all mechanical, electrical
and plant systems within existing and new buildings affected. This, coupled with
improved efficiency in windows and doors will drive down the requirement for
heating, in turn lowering the carbon footprint from key council buildings. 
_________________________________________________________

Page 12

List of Background Papers 
None.
__________________________________________________________________ 
Author: Barbara Walker, City Deal and Infrastructure Programme Director; Email
Barbara.walker@renfrewshire.gov.uk