4 - Regeneration Funding Bids Update 2022

Renfrewshire Council · 14 June 2022
Back to Economy and Regeneration Policy Board — 14 June 2022 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy and Regeneration Policy Board
On: 14 June 2022
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Regeneration Funding Bids Update 2022
___________________________________________________________________
1. Summary 
1.1 National government funding of regeneration projects and programmes has
expanded over the last year as both the Scottish and UK Governments have
announced new funding programmes. The Leadership Board of June 2021
agreed to a set of priorities for projects that officers will pursue the delivery of
through applications to appropriate funding programmes and by utilising capital
budget available from the Council budget. This report updates the Board on
progress over 2021 in delivering on these priorities and presents the
programmes being developed in 2022.
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that Board: 
(i) Homologates the decision of the Director of Finance and Resources to
accept the grant offer from the Scottish Government Place Based
Investment Programme of £1.038 million for 2022/23. 
(ii) Notes the progress and continuing actions to deliver projects from the range
of regeneration funds identified in the report. 
(iii) Notes the submission of the Kibble/St Mirren Foundation wellbeing project
to this year’s round of applications for the Scottish Government’s
Regeneration Capital Grant Fund.
_________________________________________________________

Page 2

3. Background 
3.1 The funding of regeneration projects and programmes has been reliant on
support from national government, often with ‘match-funding’ coming from the
Council. The main and longest running fund is the Regeneration Capital Grant
Fund (RCGF) through which the Council has secured support for the Russell
Institute, Paisley Learning and Cultural Hub and for Paisley Museum. The
RCGF also supports projects run by other organisations (with the grant being
passed to the Council to manage), with the projects promoted by Linwood
Community Development Trust, Active Communities, Johnstone and PACE
Youth Theatre being supported very recently. 
3.2 The RCGF is an annual competitive fund with applications coming from all 32
Scottish local authorities plus the Clyde Gateway Urban Regeneration
Company. The fund is always substantially over subscribed, meaning that many
projects that are put forward are not funded. As a response to this the Scottish
Government in 2019 launched the Town Centre Fund which was quickly
superseded by the Place Based Investment Programme (PBIP). This is a five
year programme to enable projects to be funded at a local authority level. In
2021/22 £1.195m was awarded with in £1.038m being available for 2022/23. 
3.3 Earlier this year the Scottish Government announced that the RCGF application
for PACE Youth Theatre’s ‘Exchange’ Theatre in Paisley has been successful.
This followed considerable work over 2020 and 2021 to build up the project, its
business case and its regeneration outcomes. The award of £800,000 now
forms a substantial element of the capital funding required to deliver the project
(based in the former Mannequins nightclub building on New Sneddon Street)
and has had the effect of unlocking at least one further large grant award from
the Garfield Weston Foundation. Officers continue to work closely with PACE
to realise the project. 
3.4 In September 2021 the Leadership Board approved a set of priorities for the
Place Based Investment Programme. Progress is summarised below. 
Table 1 Place Based Investment Fund Projects 2021 awards, summary update at May 2022
Project summary Launch Appl’ns  Awards Complete
1. Renfrewshire Shopfront
Improvement Scheme (2021) -
Grant scheme to support shop
front improvements   
Sep’ 2022 
Design Tender On-site Complete
2. Heritage Renewal Programme
- Support for building restoration
to town centre buildings 
i. 5 George Place, Paisley
restoration and refurbishment   
October
2022

Page 3

Design Tender On-site Complete
ii. 32 High Street (The Liberal
Club), Paisley restoration and
refurbishment  
Sep’ 2022 April 2023
3. Prominent Building Repair -
Urgent repairs to key buildings    
i. Oakshaw Church Tower   July 2022 Oct’ 2022
ii. St Matthews Church, Paisley   July 2022 Sep’ 2022
4. Start-Up Street, Renfrew at
Dunlop Crescent, Renfrew – refit
of vacant shop units   
Aug’ 2022
5. Lighting Programme -
extending work on town centres
lighting - buildings, lanes and
spaces using LED technology    
i. John Neilson Institute, Oakshaw   June 2022 July 2022
6. Active Communities –
supplement to delivery of Health
and Wellbeing hub - capital
costs     
4. Capital funding for regeneration projects 
4.1 The Leadership Board of September 2021 covered in detail the full range of
alternative external capital funds currently available. This range has extended
this year with new funds announced by Government and other agencies. The
current funding environment of relevance to regeneration activities in
Renfrewshire is therefore the: 
 Levelling-Up Fund (UK Government) available to 2024/25. 
 Shared Prosperity Fund (UK Government) see separate report to this Board,
current round to 2024/25. 
 Regeneration Capital Grant Fund (RCGF) (Scottish Government), awards
by application, annual funding rounds. 
 Vacant and Derelict Land Investment Programme (VDLIP) (Scottish
Government), awards by application, annual funding rounds. 
 Place Based Investment Programme (PBIP), (Scottish Government),
annual direct awards to local authorities.

Page 4

 Heritage and Place Programme, (Historic Environment Scotland), new
programme round open in 2022. 
 National Heritage Lottery Fund – various programmes that can combine with
the Heritage and Place Programme. 
 Water Environment Framework, (SEPA), projects instigated by SEPA as
part of River Basin Management Planning, projects must now have ‘place’
outcomes. 
5. Actions for 2022 
5.1 The recent launches of regeneration funding streams set out above have shown
that being in a strong position to react to opportunities as they arise will give the
Council and other Renfrewshire organisations a much greater chance of
securing funds, mobilising and delivering projects efficiently and effectively.
Projects must tackle quality of place, neighbourhoods, new purposes for town
centres, climate change adaptation, zero carbon infrastructure and the
reprovisioning of property and space at a large scale. 
5.2 In 2022 we are making preparations to: 
i) Submit a LUF bid for Renfrew town centre focussing on the Victory Baths
and former Renfrew Police Station. 
ii) Submit a RCGF bid in support of Kibble and the St Mirren Foundation’s
proposals for a Wellbeing Centre on vacant land adjacent to the St Mirren
Stadium. 
iii) Submit an ‘Expression of Interest’, and if accepted a Stage 1 application,
for a Heritage and Place Fund programme focussing on the heritage of
Renfrewshire’s villages. 
iv) Support a SEPA Water Environment Framework feasibility study for the
deculverting of the Candren Burn and associated landscape works in
Ferguslie. 
v) Prepare programmes for the VDLIP for projects associated with ‘The
Making of Ferguslie Park’, and potentially other communities, for
submission in 2023. 
vi) Advance feasibility work through the Shared Prosperity Fund to develop
business cases for future Place Based Investment Programme and Council
capital programme work, particularly relating to climate resilience projects
in town centres, energy efficiency in community assets and the potentials
for redevelopment and future funding bids for Johnstone town centre.

Page 5

vii) Deliver a 2022/23 programme of projects from the Place Based Investment
Programme – continuing the work to support heritage building repairs, town
centre/architectural low carbon lighting and specific projects this year to
include: 
 Ferguslie ‘Green Line’ walking and active travel route
 The Sculpture House – refurbishment of Craigielea House as artists
studios, Blackstoun Road, Paisley
 Projects emerging from work on improving active travel links to major
employment locations around Renfrewshire 
5.3 A separate report on this agenda deals with the submission of the LUF bid for
Renfrew. 
5.4 Further reports will be brought to the Economy and Regeneration Board as and
when grants offers are made from funders. 
___________________________________________________________________ 
Implications of the Report 
1. Financial – 
Government grants awarded to the Council are monitored in accordance with the
terms and conditions of grant. The Council will liaise with the Scottish Government
to comply with drawdown and financial reporting requirements.   
2. HR & Organisational Development – None. 
3. Community Planning – 
 Reshaping our place, our economy and our future: Renfrewshire Council is
working with stakeholders to maximise the opportunities for regeneration and
economic recovery/growth. 
 Building strong, safe and resilient communities: working in partnership with
local groups and organisations to achieve positive outcomes. 
4. Legal – None. 
5. Property/Assets 
Any acquisitions, leases or licenses required to enable project delivery using any
funding awarded will progress through the recognised Council processes and with
relevant Board approvals. 
6. Information Technology – None. 
7. Equality and Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights.

Page 6

No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report.  If required following
implementation, the actual impact of the recommendations and the mitigating
actions will be reviewed and monitored, and the results of the assessment will
be published on the Council’s website. An Equality Impact Assessment is
being prepared as part of the project requirements. 
8. Health and Safety – None. 
9. Procurement – A programme of contract processes will be developed with the
advice of the Council’s Procurement team to secure effective and best value
project delivery. 
10. Risks - None. 
11. Privacy Impact – None. 
12. Cosla Policy Position - Not applicable. 
13. Climate Risk - No identified impacts at present.
__________________________________________________________________ 
List of Background Papers 
1. Report to Leadership Board, 15th September 2021 - Place Based Investment
Fund 2021/22
2. Report to Leadership Board, 16th June 2021 – Regeneration Funds, Bids
Update – Priority Themes
3. Report to Leadership Board, 2nd December 2020 - Extension to the Scottish
Government Town Centre Fund 2020 – 2021.
4. Report to Leadership Board, 19th June 2019 – Town Centre Capital Fund.
___________________________________________________________________ 
Author: Stuart McMillan, Regeneration Manager
Tel: 07958 009520