To:  Economy and Regeneration Policy Board
On:  26 August 2025
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Paisley Museum – update on construction progress
___________________________________________________________________
1. Summary 
1.1 Paisley Museum will be a world-class destination telling the
inspirational stories of Paisley’s people and pattern and showcasing its
internationally significant collections. 
1.2 This report gives an update on the construction progress as Kier
Construction Ltd enter the final stages of the first major refurbishment
in the building’s 150-year history nears completion. 
1.3 Whilst the pandemic significantly affected the original timeline, post
pandemic availability of resource in a number of trades, including
specialist conservation resource and supplies has continued to impact
the project throughout. 
1.4 In addition, more recent delays have been due to a combination of
factors, for example; unforeseen structural and conservation issues
uncovered during renovation of the historic buildings (many areas were
inaccessible and could not be fully identified until later in the
construction programme); complex utility infrastructure problems,
where services were installed incorrectly and unrecorded by utility
companies and required significant rectification and latent defects
which were worse than anticipated from pre-construction surveys.
There have also been significant works required to previously

Page 2

inaccessible areas that could not have been identified earlier in the
programme. 
1.5 This is an extremely complex project and whilst it was always expected
that unforeseeable issues would be encountered during construction
the scale of these has been much more than anticipated. These issues
reflect the challenges in managing a historic building undergoing its
first major modernisation. 
1.6 The work undertaken will significantly expand, renew, remodel and
transform the building from its previous footprint whilst simultaneously
bringing the historic aspects of the building up to modern standards,
protect its long-term future, and attract thousands of visitors to Paisley
town centre each year. 
1.7 This project has included the repair and renovation of all historic
buildings on the museum campus and will deliver a net 20% increase
in the overall usable area reflecting the scale of demolition, renewal
and remodelling incorporated into the project. The construction
incorporates a significant new extension which will provide an iconic
visitor entrance and reception as well as an on-site café, the installation
of new mechanical, electrical and plant systems, and the introduction of
a public courtyard. 
1.8 The newly extended galleries will allow more of the museum’s
remarkable items to be displayed than ever before and we look forward
to continuing to work closely with the community and our partners to
create an outstanding visitor experience. 
1.9 Having already won awards for its design, the construction period is
now progressing towards completion which is expected by the end of
this year followed by a complex fit-out period to ready the Museum for
its official reopening in the second half of 2026. 
1.10 Once completed, the project will deliver a truly transformed cultural
asset not just in terms the condition of the historic buildings but a
transformation in the scale of the overall facility and the quality and
depth of the cultural experience that visitors will enjoy, placing Paisley
Museum within the very top cohort of museum facilities across Europe.
___________________________________________________________________ 
2. Recommendations

Page 3

2.1 Board members are asked to:
i) Note the contents of the progress update.
ii) Note that a further update report will be brought to a future Economy
and Regeneration Policy Board to provide further detail on the fit-out
process. 
_________________________________________________________
3. Construction progression  
3.1 Kier Construction Ltd continue to
deliver the construction contract
for the museum, and are
progressing into the final stages
of work, after which the fit-out
period to install the collections
will commence.
3.2 New oak flooring has been completed on Level 1 of the Factory Hall,
East Extension, West Extension, and Gallery 1. OneRen and a vehicle
specialist will be completing the final parts of the fire tender restoration
once Kier have completed the decoration of the wall and ceiling in the
area where the fire tender was previously boxed in.
3.3 Oak flooring has been completed in the Introductory Gallery and a
crash deck scaffold has been erected to enable completion of all high-
level decoration. High Level decoration is also complete in the Pillar
Gallery and decoration of the main Rotunda 1, Sculpture Court and
Factory Hall 1 and 2 is progressing well. 
3.4  Kier are planning the final
redecoration of galleries 2-5
ahead of final commissioning of
the underfloor trench heating
this month. 
3.5  The acoustic ceilings have been
completed above the main
entrance and lift lobby on Level
1 and the HeartFelt modular felt
ceiling system and lighting in the West Extension has commenced. The

Page 4

brass handrails leading up the stairs from the main entrance have been
installed together with the handrails along the Factory Hall balcony. 
3.6  The crash deck scaffold in the shop will be dismantled shortly following
completion of all ceiling void, high-level plaster cornice and decoration
works.
3.7  The library lift installation is planned to get underway in August. This lift
and the ‘night entrance’ introduces contained access from the High
Street to the Factory Hall gallery and Learning Space 1 on Level 2 and
will allow possibility of evening event or activities without opening the
rest of the museum.  
3.8  Works in all Oakshaw properties, including Transit House and the
Observatory, are almost complete and snagging benchmark
inspections will take place in mid-August.
3.9  Soft landscaping is complete in all
areas around the museum, with the
exception of the garden area
adjacent the former Territorial Army
Centre site boundary. This will be
completed in September 2025.
3.10  The public realm hard landscaping
works just outside the Museum were delayed due to existing utility
services installed over many previous years by various utility providers
not being installed correctly and requiring rectification before
landscaping could be completed.
This was outside the control of
Kier, the Council or OneRen.
Works are now progressing well,
and all services have now been
lowered successfully, allowing the
installation of new kerbing and
Caithness slabs. A new bus-
shelter and street lighting will be
installed during August which will allow the removal of temporary traffic
and pedestrian management.
4. Exhibition fit out and object installation
4.1  Following the completion of the construction contract, the exhibition
fitout and object installation will follow as we prepare the Museum for
reopening.

Page 5

4.2 This will be carried out by “The Hub”, a contractor renowned for their
work with heritage and cultural landmarks, including some of the UK’s
most iconic museums including, The V&A, The Natural History
Museum, Royal Shakespeare Company, and Tate Modern. With more
than 20 years’ experience, they will curate the fit out the museum
enabling us to showcase our internationally significant collections. 
4.3  The exhibition fit-out contract will only commence when Kier
Construction Ltd have completed the main works to the standard
specified and quality expected. The sensitive and specialist nature of
museum exhibition installations can only progress when the gallery
spaces are fully complete, dust free and include fully commissioned
services that meet the specific environmental parameters required to
house our collections. 
4.4  The Hub and their sub-contractors will be
on site in September 2025 to begin
familiarisation of the building systems
and operation in advance of the
handover at the end of the construction
contract. The Hub have commenced their
mobilisation process preparation and are
looking to firm up their site management
and wider fit-out resources. They expect
to have their site manager on site in
September 2025.

Page 6

4.5  The Hub have already completed production of the majority of the
display components, including flexible display systems, display cases
and interactives, and these are in storage until they are required. All
prototyping and samples have been approved and the finished displays
are of high quality. The final specialist joinery items and in-built display
cases are now planned for manufacture as we reach the conclusion of
construction. 
4.6  We are now in the final stages of delivering all digital interpretations,
including AV shows, films and digital game interactives, with our
specialist contractors. We have already won the Smiley Charity Bronze
award for one of our co-produced films with local organisation Kairos. 
4.7 More than 1,000 objects have been conserved by more than 20 experts
and are now ready for installation. The final pieces – including an
Indian chainmail shirt and archival glass slides – will be complete in the
coming months.
4.8  The object installation programme and resource review are complete
and has been shared with The Hub and their mount-maker Orbis ready
for implantation following exhibition fitout. 
5. Next steps
5.1  A further update report will be brought to a future Economy and
Regeneration Policy Board which will provide further detail on the fit-out
process for the Museum.
___________________________________________________________________
Implications of the Report
1. Financial – the financial implications of the updated constructions and fit out
programme will be reported in detail in the financial overview report to be
presented to the September Council board cycle.   
2. HR & Organisational Development - None 
 Our Renfrewshire is thriving – The Museum is the flagship of our
Cultural Infrastructure investment in our heritage assets. Together these
will facilitate a significant increase in footfall to Paisley and surrounding
area and enable Renfrewshire to host world class performances and
attract new footfall from far beyond the local area. 
 Our Renfrewshire is well - The outputs of these projects will enable safe
and inspiring locations for all.

Page 7

From arts and performances to learning and educational space,
Renfrewshire will offer anyone the ability to engage and take interest in
either a new subject matter or an existing passion that is now much
more accessible. Driving world class performances to the area and
having 21st century work and education spaces will support people from
Renfrewshire to engage in beneficial activities that will in turn support
education and interest. 
 Reshaping our place, our economy and our future – Significant increase
in footfall will benefit local businesses who can grow as a result and in
turn support their ongoing viability in the area. An increase in arts and
performances will allow a platform for Paisley becoming a cultural hub in
Scotland which can be used to drive new educational agendas with
greater access to this subject matter. 
 Tackling inequality, ensuring opportunities for all – A specific focus has
been applied to the redevelopment and construction to ensure
accessibility is a key feature. A significant amount of thought has gone
into making historic, and predominantly inaccessible buildings, available
for anyone to enjoy and utilise. There are no barriers to utilising the
Museum, and One Ren will continue to deliver an events programme
that caters for everyone including those in more deprived areas. 
 Creating a sustainable Renfrewshire for all to enjoy – With the Museum
being in the heart of Paisley Town centre, it is accessible sustainably
due to the well-connected nature of the town centre. Limited town centre
parking will encourage the use of public transport which will work
towards the net zero ambitions of the Council. Recently completed
infrastructure through AMIDS, including shared cycle and walkways,
also enhances the connectivity, and with the opening of the Renfrew
Bridge, Paisley has become a more accessible route by sustainable
travel. 
 Working together to improve outcomes - Officers and contractors
continue to work closely with local businesses and a business
engagement programme is ongoing to bring this to focus. 
3. Legal - none 
4. Information Technology – None. 
5. Equality & Human Rights - 
(a) The Recommendations contained within this report have been assessed
in relation to their impact on equalities and human rights. 
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the

Page 8

recommendations contained in the report because it is for noting only. If
required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
6. Health & Safety – None 
7. Procurement – None 
8. Risk – Project specific risk registers are in place. These are kept under
regular review and reported to the Council’s internal City Deal and
Infrastructure Programme Board. 
9. Privacy Impact – None. 
10. COSLA Policy Position – Not applicable. 
11. Climate Risk – these projects will significantly improve all mechanical,
electrical and plant systems. This, coupled with improved efficiency in
windows and doors will drive down the requirement for heating, in turn
lowering the carbon footprint from the building. 
Author:         Barbara Walker, City Deal and Infrastructure Programme
Director