To:  Economy and Regeneration Policy Board
On:  26 August 2025
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: AMIDS South Update
___________________________________________________________________
1. Summary 
1.1. To provide an update on the progress being made with the AMIDS South
Project which will link AMIDS and Paisley Town Centre.
___________________________________________________________________ 
2. Recommendations 
Board members are asked to:
2.1  Note the contents of the progress update.
2.2 Note the Chief Executive approved the award of the construction
contract and final business case under delegated authority authorised
at the Renfrewshire Council meeting on 26 June and that the
construction contract will be presented and noted to FRCS on 11
September.
_________________________________________________________
3. AMIDS South Project
3.1  The AMIDS South project was awarded £38.7million from the UK
Government’s Levelling Up Fund, with the Council committing
£18.8million, to create a new road bridge across Paisley Harbour, a
1.7km gateway route along the White Cart river and a network of roads,

Page 2

cycling, wheeling and walking links from the town centre train station
and bus interchange to AMIDS, Glasgow Airport and Inchinnan. 
3.2  In addition, a new east-west link road from Renfrew Road to the new
bridge crossing will be created which will connect into the new Paisley
Grammar School Community Campus, as will dedicated walking and
cycling routes. Additionally, a safe access route from Gallowhill using
the underpass on the former railway line will be constructed using an
additional £1.5million provided by Transport Scotland. 
3.3  This project provides infrastructure to better connect communities to
education and employment opportunities at AMIDS, but it will also
significantly improve the offer to organisations looking to locate here
with enhanced access to the airport and the fourth-busiest train station
in Scotland. 
3.4  Specifically, the project includes: 
 A road bridge crossing at Paisley Harbour for pedestrians, cyclists and
road traffic. 
 A gateway route from Paisley town centre along Abercorn Street,
Harbour Road and Inchinnan Road to the manufacturing district AMIDS
and Glasgow Airport – includes new cycle routes and landscaping
 An east-west road link from Renfrew Road joining onto the new route,
increasing connectivity to the manufacturing district and improving
access to the proposed new Paisley Grammar School Community
Campus. 
- It will also connect into the Gallowhill Link which will use the
former railway underpass to provide a safe crossing of Renfrew
Road.
 Traffic calming works on Love Street will improve the environment for
local residents and pedestrians, the area benefiting from a reduction in
traffic flow due to the new routes.
 Improved walking and cycling on Greenock Road between Inchinnan
Business Park and AMIDS. 
4. Procurement Process
4.1  The Council used the competitive procedure with negotiation in
accordance with the Public Contract Scotland Regulations 2015 and
the Council’s Standing Orders relating to Contracts to procure a
suitable Contractor to undertake the Construction works for the AMIDS
South project. 
4.2  The procurement commenced with publication of a Contract Notice on
27 March 2024. Final tenders were invited in July 2025.

Page 3

4.3  The AMIDS South project team includes Amey OW Limited the
appointed Lead Consultant. The evaluation of Final Tenders identified
that the submission by Farrans Construction trading as Northstone (NI)
Limited was the most economically advantageous tender and therefore
a Contract for the Construction Works for the Advanced Manufacturing
and Innovation District Scotland South (AMIDS S) Project (RC-CPU-22-
352) was awarded by the Chief Executive to Farrans Construction
trading as a division of Northstone (NI) Limited as authorised by
Council at its meeting on 26 June 2025.
4.4  A report notifying award of this contract will be presented to the
Finance Resources and Customer Services Policy Board at its meeting
on 11 September 2025. 
5. Business Case
5.1  Economic projections have estimated the project could boost the local
economy by an additional £136million and cut carbon emissions by
21,700 tonnes, while creating new job opportunities and helping
existing and new companies to grow and expand. 
5.2  A compulsory purchase process was followed to acquire the land for
the scheme and notices have now been issued confirming the Vesting
Date. 
5.3  The AMIDS South investment including the previously delivered
Inchinnan Cycleway Link and contingency allowances totals £59M. 
This is funded from the following sources:
 Levelling Up Fund (LUF) £38.7M
 Council Funding of up to £18.8M, including reallocation of existing
resources as approved by Council on 26 June 2025.
 Transport Scotland, Active Travel Infrastructure funding of £1.5M 
6. Construction phase 
6.1  Construction related activities are due to commence in September
2025, with overall opening programmed for Spring 2028 with earlier
phases tying in with the adjacent Paisley Grammar Community
Campus project.
6.2  Aspects such as public utilities diversions and overall bridge
construction are crucial to realising this milestone completion date.

Page 4

6.3  Lead Consultant, Amey Consulting Limited, are commissioned to
provide contract management and site supervision services relating to
delivery of the project.  A full-time site presence of 5/6 individuals will
be provided to undertake the required duties, with Amey Consulting
ultimately responsible for management of overall delivery of the project
within the terms of the contract, having been involved in this capacity
from early conception. 
7. Governance 
7.1  The project will be report to the City Deal and Infrastructure
Programme Board, chaired by the Chief Executive. This officer board
will provide oversight, monitoring and governance to the project.
Update reports will be brought to the Economy and Regeneration
Policy Board as required. 
8. Next Steps
8.1  A further update report will be brought to a future Economy and
Regeneration Policy Board to update the board on site progress. The
award of the construction contract under Chief Exec delegation will be
reported to the next FRCS Board.
___________________________________________________________________
Implications of the Report
1. Financial – The AMIDS South project is funded through Levelling Up
Funding of £38.7M, approved Council Contribution of up to £18.8M and
£1.5M from Transport Scotland via the Active Travel Infrastructure
Fund – therefore allocating a total project budget of £59milllion.   
2. Financial – none 
3. HR & Organisational Development – none 
4. Community/Council Planning –  
 Our Renfrewshire is thriving – The AMIDS South project will link our
communities and deliver an economic boost. The project aligns with the
outcomes of the Renfrewshire Economic Strategy 2020 -2030 and the
Renfrewshire Economic Recovery Plan.

Page 5

 Our Renfrewshire is well – The new safer walking and cycling infrastructure
will help encourage active travel by children and young people, as well as
adults. 
 Reshaping our place, our economy and our future AMIDS South will link
to AMIDS and other investment in cycling infrastructure and education and will
provide connectivity and access to new and existing jobs for people in our
communities. During the project construction period new jobs will be created. 
 Tackling inequality, ensuring opportunities for all – AMIDS South links our
less advantaged communities with education and job opportunities at AMIDS
and provides healthy transport options 
 Creating a sustainable Renfrewshire for all to enjoy – The completed
infrastructure will include segregated provision for walking and cycling and will
also enable improved public transport links. 
 Working together to improve outcomes – Officers and contractors will
work closely with local businesses and a business engagement programme
will be established 
5. Legal – a compulsory purchase process was undertaken to progress
the land requirements for this project. 
6. Property/Assets – once completed the new road and bridge will be
adopted by the Council’s statutory roads team. 
7. Information Technology – none 
8. Equality & Human Rights - 
(a) The Recommendations contained within this report have been
assessed in relation to their impact on equalities and human rights. 
No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report because it is for noting only. If
required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website. 
9. Health & Safety – all health and safety legislation and standards will
be followed during construction. 
10. Procurement – all contracts are tendered in accordance with Council
procurement procedures and will be awarded under Chief Exec
delegation (see Council delegation from 26 June 2025) and reported to
the next FRCS Board.

Page 6

11.   Risk – Project specific and Programme level risk registers have been
established. These are kept under regular review and reported to the
Council’s officer City Deal and Infrastructure Programme Board,
chaired by the Chief Executive. 
12. Privacy Impact – None. 
13. Children’s Rights – None
14. COSLA Policy Position – Not applicable. 
15. Climate Risk –Active travel is a key component of the project and links
with wider active travel routes and investment in Renfrewshire. A new
active travel “safe route to school” will be constructed as part of this
project. 
___________________________________________________________________ 
Author:         Barbara Walker, City Deal and Infrastructure Programme Director