Democracy Spraffa

4 - Renfrewshire Council Community Benefits (Community Wealth Building) - AM reviewed

Renfrewshire Council · 26 August 2025
Back to Economy and Regeneration Policy Board — 26 August 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy and Regeneration Policy Board
On:    26 August 2025
___________________________________________________________________
Report by:  Chief Executive
___________________________________________________________________
Heading:  Renfrewshire Council Community Benefits (Community Wealth 
Building) 
1.  Summary 
1.1 This report provides a background to the Council’s community benefits
programme and summarises current economic development activity
supporting the delivery of community added value from Council contracted
spend. 
1.2 This paper sets out how community benefits link to the Council’s Community
Wealth Building [CWB] agenda for Renfrewshire and highlights some of the
opportunities that community benefits can create for local organisations,
people and places to thrive and prosper because of the added value created. 
___________________________________________________________________ 
2. Recommendations 
2.1 Board members are asked to: 
• Note the current activity undertaken to maximise community added value
for local people, communities and organisations from the Council’s
community benefits programme.  
• Note that further updates on the Council’s community benefits programme
will be reported to a future board.
___________________________________________________________________

Page 2

3. Background
3.1  Community benefits are the method by which local communities and good
causes can receive additional value from public spending and provides a
means of achieving sustainability in public contracts. Renfrewshire Council
mandates community benefits on regulated procurements above the threshold
of £50k and has a forum of local delivery partners, led by the Economic
Development Team, in place to help suppliers to meet their community benefit
requirements. 
3.2  The obligation to include community benefits in our procurement process
comes from legal requirements from the Sustainable Procurement Duty within
the Procurement Reform (Scotland) Act 2014. 
3.3 Renfrewshire Council fully supports this method of achieving sustainability in
contracts and has identified one of its key objectives to be the exploring of ‘all
opportunities to use its procurement activities to promote its wider policy
objectives, including social, economic and environmental objectives’ in its
Procurement Strategy.
3.4  Over the past few years, officers from the Economic Development and
Procurement teams have worked closely together to strategically and
intentionally promote progressive procurement of goods and services, as a
means through which greater social, economic and environmental benefits can
be achieved for our local people, businesses and communities as part of the
Council’s wider Community Wealth Building agenda. 
3.5  In response to the introduction of the Community Wealth Building (Scotland)
Bill (March 2025) which sets out the ‘use of public procurement to facilitate or
support such generation, circulation and retention of wealth to local
communities’ as a key measure, it is vital the Council uses its purchasing power
as a critical lever to deliver added economic, social, and environmental value
through its community benefits programme. 
___________________________________________________________________ 
4.  Current Economic Development Activity
4.1 The community benefits forum, is a key lever for the delivery of benefits from
existing contracts. The forum comprises of core delivery partners from the
Council’s Invest in Renfrewshire, Education and Business Gateway services
as well as Engage Renfrewshire.
4.2  As chair of the forum, the CWB Coordinator has grown the forum membership
to include representation from wider council services such as HSCP, Housing,
ICT and Connected Communities ensuring that benefits are focused on
supporting the right people in the right places across Renfrewshire and, most
importantly, that benefits reach those most in need. 
4.3  The forum’s remit has also been extended to build a range of social, economic,
or environmental conditions into the delivery of Council contracts from pre-

Page 3

tender stage to address local priorities and to ensure that the Council focuses
on maximising the benefits of large infrastructure projects on localities.
Operational delivery sub-groups formed of suppliers, sub-contractors, delivery
partners and coordinated by the CWB Coordinator have been formed to ensure
delivery is managed across the life of the contract. 
4.4  To help direct community benefits to where they make the most impact, relevant
officers are seeking to input at pre-tender stage to examine where we think
benefits are required and are achievable under the contract. This work is
essential in ensuring benefits are relevant to the social and economic conditions
of our localities and are deliverable for suppliers under the terms of the contract. 
4.5 Improved supplier guidance and greater input from delivery partners at a much
earlier stage has led to a more meaningful approach to understanding the
needs of priority groups. This shifted focus from community benefits as a tick
box for suppliers to a means of delivering good quality engagements that have
a real impact for communities.
4.6  In the past there were many community benefits offered by suppliers, however
these were tracked manually and, therefore, challenging to quantify. As a result,
it was difficult to measure and report on what local benefit was delivered and
how much impact this had on improving outcomes for local people. As such it
presented a huge opportunity lost.
4.7 In order to strengthen tracking and monitoring of community benefits, Economic
Development have purchased the Cenefits system for use across the Council.
Cenefits enables the Council to measure whether and how well these benefits
are being achieved, and report on value added to local people, organisations
and communities. Cenefits is now fully embedded in the community benefits
process allowing tighter management and monitoring of the suppliers’
community benefit obligations and providing fully reportable quantative and
qualitative information on outcomes achieved.
4.8  To support the implementation of the system and to meet reporting
requirements, Economic Development part funded a role within the
Procurement team to strengthen ongoing work. As part of our joint approach to
improving communication with suppliers and to add energy and momentum to
the community benefits delivery process, Economic Development and
Procurement have worked together to deliver community benefits webinar
sessions in partnership with the Supplier Development Programme and
Cenefits. These sessions have been very well attended and have received
positive feedback from our supply chain. In addition, the CWB Coordinator
attends several HSCP, communities and other strategic planning forums to
raise awareness of the Council’s community benefits work.
___________________________________________________________________ 
5. Key community benefits outcomes delivered in FY24/25  
5.1  As a result of some of the significant changes brought in, this is the first year
that we have been able to report on the impact of community benefits, with FY
2024/25 producing the first fully reportable activity.

Page 4

5.2  The figures in this report represent financial year 2024/25, taken from the period
of 1st April 2024 to 31st March 2025.  As community benefits are delivered on
a rolling programme these figures reflect a single point in time and may change
subject to reporting period and reporting criteria. 
5.3  In FY24/25, 179 benefits were realised across 64 Council contracts delivering
added value and improving outcomes in real terms for Renfrewshire
communities: 
5.4  Figures shown represent benefits fully delivered during 2024-25. Some
community benefit outcomes can take a period of years to complete and/ or
may have been committed on projects which span across several years,
therefore, may not be included in this period. 
5.5  Appendix A to this report provides a range of case studies which illustrate some
of the positive outcomes that can be realised for local people, communities and
businesses from each type of community benefit noted in the figures above. 
5.6  Appendix B offers a case study for the Paisley Grammar Community Campus
and illustrates the scope, range and scalability of the community benefits offer

Page 5

on a large capital project delivered over a period of several years. In this case,
the contractors in the supply chain are involved in leaving a positive legacy
through their community benefit commitments across the life on the contract
and beyond.
___________________________________________________________________ 
6. Next Steps 
6.1  Further work is being undertaken by the community benefits forum to identify
opportunities to bring in to scope some contracts and frameworks such as ICT
and Early Years & Childcare where community benefits have not previously
been sought. 
6.2  The close relationship between Economic Development and Procurement
teams in the Council has fostered joint responsibility for the delivery of
community added value. This work will be strengthened by implementing a
robust end to end process for the management of the community benefits
programme going forward. 
6.3  The Community Wealth Building (Scotland) Bill compels the Council to take on
more responsibility for the strategic planning of the economic and social impact
of contracted spend and other Council activity which generates community
added value. In addition, recent changes to the National Planning Framework 
4 (NPF4) seeks to encourage, promote and facilitate the maximisation of added
social value in local government decision making. The key policies influencing
this agenda are Policies 11C (Energy) and policy 25 (CWB), both have a direct
reference to added value in development proposals with reference to the
community wealth building agenda. 
6.4  To ensure that we maximise economic, social and community added value
across all areas of Council activity and spend, the Economic Development team
are exploring a range of opportunities and approaches to harness significant
additional benefits for the local area. These include benefits to be sought from
renewable energy projects, planning applications, benefits accrued through
Scotland Excel frameworks and regionally funded projects, along with the
potential opportunity to pilot delivery of Scottish Government (procurement)
benefits. 
6.5  Further reports on community benefits, as part of the Council’s approach to
community wealth building, will be brought back to Board at a future date.
___________________________________________________________________
Implications of the Report
1. Financial – There are no implications to identify at present other than the
community benefits highlighted in this report 
2. HR & Organisational Development – There are no implications

Page 6

3. Community/Council Planning – CWB is a key feature of the current Council
Plan, Procurement Strategy and Community Learning and Development Plan. 
4. Legal- There are no immediate implications however, going forward new
community wealth building legislation is likely to be published in Scotland. 
5. Property/Assets- There are no new implications however, land and assets
are a key theme of CWB with a particular focus on community asset transfer
and the inclusion of a CWB provision within the National Planning Framework
4 (NPF4) published in 2024. 
6. Information Technology – There are no implications 
7. Equality & Human Rights- There are no implications 
8. Health & Safety- There are no implications 
9. Procurement - There are no new implications however, procurement and the
tracking of the public pound and local spend are a key focus of the spending
pillar of CWB. 
10. Risk - There are no implications 
11. Privacy Impact - There are no implications 
12. Climate Risk -There are no implications 
13. Children’s Rights - There are no implications 
14. COSLA Policy Position- COSLA strongly supports the concept of community
wealth building (CWB), advocating for its implementation across Scotland
through legislation and collaborative efforts with local authorities, businesses,
third sector organisations, and communities to ensure wealth generated within
communities is redistributed and benefits local residents; essentially seeing
local government as a key "anchor institution" to drive CWB initiatives.
_________________________________________________________
List of Background Papers - None 
___________________________________________________________________
Chief Executive’s
MD
25 July 2025 
Author: 
Morag Doig, Community Wealth Building Coordinator, Renfrewshire Council
Email: morag.doig@renfrewshire.gov.uk

Page 7

Appendix A: Community Benefit Case Studies 
New Entrant Job Created
Luke was taken on as a Window Cleaning Technician by Caledonian Maintenance
Services Limited as part of their Community Benefit requirement. He was taken on
full time at a minimum of 30 hours per week. Prior to this, Luke had been
unemployed for 4 years, though he was a caring for elderly relatives as a full-time
carer. Since joining the team, he has completed a number of training courses
including CSCS, IPAF, First Aid etc and in just the first 2 months of his employment he
also progressed to Team Leader.     
Community Engagement: Funding Opportunity 
For their Community Benefit Robertson-Acom Limited, donated £5000 to a local
charity called 'Lisa's Gift'. This charity is run on a completely voluntary basis with every
penny raised going to those who need it most. The charity offers financial assistance
to students attending Renfrewshire schools, who may require support, to allow them
to take part in the full range of school based and extra-curricular activities. For
example, the money donated was used to fund breakfast clubs, warm winter clothing,
pe kits, trips home and abroad, emergency food parcels and fuel for families. 
Graduate Job
As part of the new Paisley Grammar Community Campus build, local Gallowhill resident
Sophie was taken on in a permanent position as a ‘Communities and Social Impact
Trainee’. This was to fulfil supplier, Morrison Construction Ltd Community Benefit to
deliver a ‘New Graduate Job’. Sophie has been supported to complete a 4-year graduate
apprenticeship in business management using the paisley grammar project as a learning
tool to support her through university. Now over a year on Sophie continue to thrive and
is enjoying her role. 
Local Supply Chain Development Opportunities
As part of their Community Benefits requirements John McGeady Ltd provided 4
subcontracting opportunities for 4 Renfrewshire based SME’s.
➢ SME - MTEC Construction 
➢ Social Enterprise - Scotland's Bravest
➢ SME – WRC Recycling 
1. SME - CMC Electrical (Scotland) Ltd.

Page 8

Appendix B: New Paisley Grammar School Community Benefits  
Paisley Grammar School Build Community Benefits
(across all 6 contracts)
Total Number of Benefits to be delivered
2022-2027
180  
Benefit Type Total benefits committed 2022-27
(180)
New Entrant Jobs Created 14
Graduate Jobs Created 8
Modern Apprenticeships 4
Work Experience Placements 51
Workplace Visits and Career Events 39
Upskilling of the Workforce 16 
Local Supply Chain Development
Opportunities
19
Community Engagement: Funding
Opportunities
18
Community Engagements
(donation of time, expertise, materials and
equipment)
11