Democracy Spraffa

2024-25 P08 Eco and Regen PB Budget Monitoring Report

Renfrewshire Council · 21 January 2025
Back to Economy and Regeneration Policy Board — 21 January 2025 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy and Regeneration Policy Board
On: 21 January 2025
___________________________________________________________________
Report by: Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring 2024/25 at 8 November 2024
___________________________________________________________________
1. Summary
1.1 At the close of reporting Period 8 on 8 November 2024, the projected
revenue outturn at 31 March 2025 for those services reporting to the
Economy and Regeneration Policy Board was an underspend position of
£0.092m (4.0%) against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2025 for projects reporting to the
Economy and Regeneration Policy Board is a break-even position. 
1.3  This is summarised in the table below and further analysis is provided in the
report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Economy and Development 2,306 2,214 92 4.0%
Capital    
Economy and Development 17,302  17,302  0  0.0% 
2. Recommendations
2.1 Members are requested to: 
a) Note the projected Revenue outturn underspend position of £0.092m; and
b) Note the projected Capital outturn break-even position.

Page 2

3. Revenue Budget Projection – underspend of £0.092m by 31 March 2025
3.1 The tables in Appendix 1 present the projected year-end position for all
services reporting to this board, by both subjective analysis (what the budget
is spent on) and objective analysis (which division is spending the budget).
Significant variances affecting the projected position are analysed further
below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle until the close of reporting Period 10. Budget holders are
obliged to seek mitigating action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances
4.1 Regeneration - £0.092m underspend
This forecast position reflects the impact of vacancies within the team over
the course of the financial year. 
5. Subjective Analysis – Significant Variances
5.1 Employees - £0.091m underspend by 31 March 2025
This projected underspend represents vacancies in the Regeneration team
which are in the process of recruitment. 
6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director/Chief Executive and the Director of
Finance and Resources for submission to the relevant policy board for
approval. Future reports may therefore ask the board to approve budget
adjustments that are deemed necessary for good budget management.   
No budget adjustments have been processed since the previous report to
board.

Page 3

7. Capital Budget Projection – break-even position by 31 March 2025
7.1 The approved Capital Investment Programme 2024/25 to 2028/29 for
Economy and Regeneration was £16.612m. The revised capital spend for
2024/25 is £17.302m. 
7.2 The in-year Capital budget is forecast to break-even by 31 March 2025 after
a number of budget adjustments between years have taken place, to reflect
revised programming of some capital projects. Details of these adjustments,
which amount to £0.690m, are as follows: 
Project Amount
(£m)
Budget brought forward into 2024/25 to reflect updated timing (adjustment)
Paisley Town Hall (0.482)
Budget carried forward into 2025/26 for updated cashflows
Town Centre Regeneration (0.085)
Budget Increases in 2024/25 
Paisley Junction & Charging Hub (grant award) 0.347
Shared Prosperity Fund (grant award) 0.815
Retail Improvement Scheme (approved by Council on 29/02/24) 0.070
Budget accelerated from 2025/26 into 2024/25
Place Based Investment Fund 0.025
Total 0.690 
Implications of the Report
1. Financial
The projected budget outturn position for Finance, Resources and Customer
Services’ Revenue budget is an underspend of £0.092m (4.0%) at 31 March
2025. Income and expenditure will continue to be monitored closely for the rest
of the financial year and as far as possible, steps will be taken to mitigate any
overspend.   
The projected outturn position for Economy and Regeneration Capital budget is
break-even, after the adjustments outlined at section 7.   
2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report.

Page 4

3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in improvements to
Culture and Heritage assets and delivery of strategic place-shaping and
regeneration. 
6. Information Technology 
There are no direct implications arising from the recommendations in this
report. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report. 
8. Health & Safety 
There are no direct implications arising from the recommendations in this
report.

Page 5

9. Procurement 
While Procurement is an important consideration prior to the Council incurring
any revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Cosla Policy Position 
N/a 
13. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report. 
14. Children’s Rights
There are no direct implications arising from the recommendations in this
report. 
List of Background Papers 
• Revenue Budget and Council Tax 2024/25, Council 29 February 2024
• The Capital Investment Programme 2023/24 to 2027/28, Council 29
February 2024 
Author:           Valerie Howie, Finance Business Partner; and Geoff Borland,     
Finance Manager.

Page 6

Appendix 1
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 8 November 2024                  
POLICY BOARD :  ECONOMY AND REGENERATION                  
Objective Summary
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Budget Variance 
(Adverse) or Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Economy and Regeneration Management 35 0 35 35 0 0.0% 0 0
Economic Development 1,213 0 1,213 1,213 0 0.0% 0 0
Regeneration 1,058 0 1,058 966 92 8.7% 76 16
NET EXPENDITURE 2,306  0 2,306  2,214  92  4.0% 76  16                  
Subjective Summary
Annual
Budget at
Period 6
Budget
Adjustments
Revised
Annual
Budget at
Period 8
Projected
Outturn
Budget Variance 
(Adverse) or Favourable
Previous
Projected
Outturn
Variance
Movement  
£000 £000 £000 £000 £000 % £000 £000
Employees 4,571 0 4,571 4,480 91 2.0% 75 16
Premises Related 84 0 84 83 1 1.2% 1 0
Transport Related 3 0 3 4 (1) (33.3%) (1) 0
Supplies and Services 127 0 127 128 (1) (0.8%) 0 (1)
Third Party Payments 0 0 0 0 0 0.0% 0 0
Transfer Payments 2,347 0 2,347 2,345 2 0.1% 1 1
Support Services 45 0 45 46 (1) (2.2%) (1) 0
Depreciation and Impairment Losses 0 0 0 0 0 0.0% 0 0
GROSS EXPENDITURE 7,177  0 7,177  7,086  91  1.3% 75 16 
Income (4,871) 0 (4,871) (4,872) 1 0.0% 1 0
NET EXPENDITURE 2,306  0 2,306  2,214  92  4.0% 76  16

Page 7

Appendix 2 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2024 2024-25 since previous 2024-25 2023-24 Budget Outurn
Project Title to 31-Mar-29 to 31-Mar-29
£000 £000 £000 £000 £000 £000 £000
ECONOMY & DEVELOPMENT
Paisley Art Centre Redevelopment 2,881 869 0 869 869 0 0% 3,750 3,750 0 0%
Paisley Town Hall Redevelopment 24,747 1,000 (482) 518 518 0 0% 25,265 25,265 0 0%
Paisley Learning & Cultural Hub 6,654 346 0 346 346 0 0% 7,000 7,000 0 0%
Paisley Museum 39,228 8,893 0 8,893 8,893 0 0% 53,001 53,001 0 0%
Paisley Junctions and Charging Hub 431 194 347 541 541 0 0% 972 972 0 0%
Public Realm 494 0 0 0 0 0 0% 4,050 4,050 0 0%
Sports Development - St James Playing Fields Redevelopment 425 3,075 0 3,075 3,075 0 0% 3,500 3,500 0 0%
Sports Development - Ferguslie Pavillion Upgrade 531 460 0 460 460 0 0% 992 992 0 0%
Sports Development - Hockey Pitch at On-X 0 600 0 600 600 0 0% 600 600 0 0%
Place Based Investment Fund 1,214 635 25 660 660 0 0% 2,628 2,628 0 0%
Town Centre Capital Fund 766 109 0 109 109 0 0% 876 876 0 0%
Town Centre Regeneration 1 180 (85) 95 95 0 0% 2,050 2,050 0 0%
Shared Prosperity Fund 197 28 815 843 843 0 0% 1,040 1,040 0 0%
Retail Improvement Scheme 0 0 70 70 70 0 0% 70 70 0 0%
Townscape Heritage CARS 2 3,876 223 0 223 223 0 0% 4,099 4,099 0 0%
Total Economy & Development 81,445 16,612 690 17,302 17,302 0 0% 109,893 109,893 0 0%
TOTAL ECONOMY & DEVELOPMENT 81,445 16,612 690 17,302 17,302 0 0% 109,893 109,893 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1 April 2024 to 8th November 2024
POLICY BOARD: ECONOMY & REGENERATION
Current Year 2024-25 Full Programme - All years
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable