___________________________________________________________________
To:  Economy and Regeneration Board 
On:  5 November 2024
___________________________________________________________________
Report by: Chief Executive 
___________________________________________________________________
Heading: Place Based Improvement Programme 2024/25
___________________________________________________________________
1. Summary 
1.1 The purpose of this report is to update members on the 2024/25 allocation of
Scottish Government Place Based Investment Programme (PBIP) and the
projects being developed for delivery.  
___________________________________________________________________ 
2. Recommendations 
2.1 It is recommended that the Board:  
(i) Approves the proposed projects for the 24/25 allocation for the Place
Based Investment Programme (PBIP) set out in this report;
(ii) Notes that progress on delivery of these projects will be reported to the
Board as appropriate.  
___________________________________________________________________
3. Background
3.1 The Economy and Regeneration Board of 19 March 2024 noted progress on
actions to deliver projects from a range of external funding sources and
approved projects to be funded through the 2023/24 allocation of the
Scottish Government’s Place-Based Investment Programme.
3.2 The Place-Based Investment Programme (PBIP) is a capital funding
programme directly allocated to local authorities, available to the Council in
various forms since 2019. This funding supports capital investment and the
delivery of actions within our town centre strategies, community-led
regeneration proposals, and community-led place plans, thereby
accelerating the Council’s broader placeshaping agenda.

Page 2

Page 2 of 4 
3.3 The 2023/24 allocation of the fund approved at Board has recently supported
a range of projects including delivery of landscape enhancements at the
Wallace Monument, Elderslie as well as the Retail Improvement Grant
Scheme and Historic Buildings in Villages Grant Scheme.
___________________________________________________________________
4. Place Based Investment Programme – 2024/25 
4.1 In early summer 2024 the Scottish Government announced that in view of
wider public finance constraints, national funding streams such as the
Regeneration Capital Grant Fund and Vacant and Derelict Land Fund were
to be paused.  
4.2 In respect of PBIP, the Scottish Government indicated that allocations would
be restricted to support projects already underway.  In addition, funding
would be limited to a maximum value of 50% of the allocation the Council
had anticipated (based on previous announcements) in order to protect the
value for money of projects already in progress. 
4.3 In view of the above, a strategic review was undertaken by officers to identify
those projects most advanced and at risk of stalling, in the event funding was
withdrawn.  Two projects were identified as those most at risk in this context,
as set out in Table 1 below.
Table 1:  Place Based Investment Fund Projects 2024/25 
Project summary Estimated
Cost
Estimated
Completion
Ferguslie Green Line:  Neighbourhood Centre
Activity Hub 
Transformation of 1.55 hectares of long term vacant
and derelict land to provide an active recreational
hub within the heart of Ferguslie Park, Paisley,
delivering a key element of the community led
Making of Ferguslie Local Place Plan.   
The project provides a new multi-use games area 
and community space as well as enhancing active
travel connections within the neighbourhood.   
£500,000 Autumn 2025
Castle Semple enhancements: Visitor Facility 
Demolition of an existing toilet block which is in a
poor state of repair and construction of a new cycle
hub facility as well as providing new accessible toilet
facilities. 
The project delivers a key element of the Strategic
Tourism Infrastructure Development Plan (STIPD)
for Clyde Muirshiel Regional and Castle Semple
Country Parks and aligns closely with
Renfrewshire’s Tourism Plan 2024-27. 
£500,000 Early Winter
2025

Page 3

Page 3 of 4 
4.4 Following the consideration of information provided by officers, the Scottish
Government has recently advised that an allocation of £300,000 will be
provided to the Council under PBIP for 2024/25. Subject to Board approval,
it is anticipated that this allocation will be used to match fund and support the
delivery of projects identified in Table 1.
___________________________________________________________________
5.   Next Steps  
5.1 Officers will continue to monitor national funding programmes and external
funding sources to support delivery of the variety of additional projects under
development and which align with the Council’s Placeshaping ambitions.
___________________________________________________________________
Implications of the Report
1. Financial – PBIP allocation will be utilised to match fund the projects
identified in Table 1 above. 
2. HR & Organisational Development – None 
3. Community/Council Planning –  
Creating a sustainable Renfrewshire for all to enjoy – The delivery of
projects supports the Council’s wider placeshaping agenda, improving
quality of place, our neighbourhoods and town centres. 
4. Legal – None 
5. Property/Assets – None 
6. Information Technology – None  
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and
human rights. No negative impacts on equality groups or potential for
infringement of individuals’ human rights have been identified arising from
the recommendations contained in the report.  If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website. 
8. Health & Safety – None 
9. Procurement – None
10. Risk – None 
11. Privacy Impact – None

Page 4

Page 4 of 4 
12. Climate Risk – Implementation of the project within Renfrewshire will
support the Council’s Plan for Net Zero through enhanced active travel
linkages and supporting living well locally.
13. Children’s Rights – None
14. Cosla Policy Position – None 
_______________________________________________________
List of Background Papers 
(a) Regeneration Funding Bids Update.  Economy and Development Policy
Board, 19 March 2024 
___________________________________________________________________ 
Author: Euan Shearer, Regeneration and Place Manager
euan.shearer@renfrewshire.gov.uk Tel: 07483 136235