To:  Economy and Regeneration Policy Board 
On:  27 August 2024
___________________________________________________________________
Report by: Chief Executive and City Deal and Infrastructure Programme
Director 
___________________________________________________________________
Heading: Update on AMIDS and AMIDS South Projects
___________________________________________________________________
1. Summary 
1.1 In May 2023 the Council approved the appointment of the Development Partner,
Tarras Park Properties Limited (TPPL) to form a joint venture partnership with
Renfrewshire Council and to progress the Council’s Advanced Manufacturing
Innovation District Scotland (AMIDS) to the next stage. 
1.2 Progress is being made by TPPL to attract interest from suitable advanced
manufacturing facilities and occupiers, supporting the Council’s ambitious vision
to deliver long term economic growth and high quality jobs. 
1.3 The Advanced Manufacturing Innovation District Scotland South (AMIDS South)
project comprises a new transport link from Paisley town centre to AMIDS and
Glasgow Airport, together with a new link from Shortroods to Renfrew Road,
crossing the White Cart via a new bridge. The Project includes cycling, walking
and vehicle infrastructure as well as sustainable drainage and landscape works.
The Outline Business Case (OBC) for the Advanced Manufacturing Innovation
District Scotland South (AMIDS South) was approved on 16th June 2021. 
1.4 Design activities are completed and the procurement exercise to appoint a
contractor is underway. 
1.5 This report provides an update on progress made to date with AMIDS and AMIDS
South Projects
___________________________________________________________________

Page 2

2. Recommendations 
2.1 To note the progress of AMIDS towards establishing a world class advanced
manufacturing cluster delivering long term economic benefits to Renfrewshire. 
2.2  To note the progress with AMIDS South Project.
_________________________________________________________
3. Background 
3.1 The foundations of the AMIDS vision commenced back in 2014 when the
Glasgow City Region City Deal Infrastructure Fund enabled the Council to
progress the Glasgow Airport Investment Area (GAIA) project which provided the
enabling infrastructure for the AMIDS Netherton Campus.  
 
3.2 The GAIA Business Case noted the City Deal benefits anticipated. 
AMIDS will capitalise on the advanced engineering and manufacturing expertise
that exists across multiple technologies in both industry and academia in
Renfrewshire and Scotland and will further strengthen that capability to create
competitive advantage for existing and new companies to remain globally
competitive, and drive inclusive, sustainable growth in the Scottish economy. The
development of AMIDS has the potential to create thousands of new jobs in
Renfrewshire, if managed well and with active support and cooperation of all
partners. 
3.3 Throughout the development and delivery of the AMIDS the Council has had
advice and support from our partners on the AMIDS Strategic Advisory Group
(SAG) which includes senior representatives from the Council, Scottish
Government, Scottish Enterprise, SDS, NMIS, MMIC, Strathclyde University and
West College Scotland. These representatives have collaborated to determine
the potential target innovation sectors and organisations to locate at AMIDS and
ensure Renfrewshire residents and businesses are given maximum opportunity
for skills development and long-term high quality, sustainable employment. 
 
3.4 The limited liability partnership agreement between TTPL and Renfrewshire
Council was formally concluded in August 2023 under the name AMIDS
(Renfrewshire) LLP. The partnership with TTPL has brought specialist expertise
in property marketing and development to deliver the AMIDS project objectives
with the 50:50 constitution of the LLP board allowing the Council to appropriately
and directly influence the project outcomes. 
3.5 The AMIDS South project will provide a 1.7km ‘gateway route’ along the White
Cart River with a network of road, cycling and walking links from the town centre
train station and bus interchange to Glasgow Airport, AMIDS and onto Inchinnan.
The project includes landscaping as well as a new bridge crossing around
Paisley Harbour for pedestrians, cyclists and road traffic. AMIDS South is a high-
impact local transport scheme which will reduce carbon emissions, improve air
quality, cut congestion, support economic growth and improve the experience of
transport users.

Page 3

3.6  Economic analysis demonstrates the project could bolster the local economy
by an additional £136 million, cut carbon emissions by 21,700 tonnes and help
existing and new companies to grow creating new job opportunities for years to
come. 
3.7  A new east-west road linking Renfrew Road to the new Gateway route is also
included and will increase connectivity to and from the new manufacturing
district and improve accessibility to the proposed new Paisley Grammar
community campus, West College Scotland and the Gallowhill area. An
extension to the new Renfrew – Paisley active travel route into the Gallowhill
catchment area will provide a new safe active travel route to the education
facilities. The funding also enables improved walking and cycling on Greenock
Road between Inchinnan Business Park and AMIDS, which has already been
delivered. 
4.      Update on Progress at AMIDS 
4.1 The National Manufacturing Institute Scotland’s flagship facility opened at
AMIDS in June 2023, and acts as a magnet to support advanced
manufacturing, engineering and associated technology businesses of all sizes.
Innovative R&D will help them to become more productive, tap into emerging
markets, embrace new technologies and achieve net-zero targets. The NMIS
building accommodates the NMIS Manufacturing Skills Academy, Digital
Factory, and publicly accessible collaboration hub. 
4.2  Adjacent to NMIS the Medicine Manufacturing Innovation Centre is bringing
world leading science and technology expertise to help accelerate state of the
art solutions to challenges in medicines development and manufacturing. An
extension to the facility will create the Oligonucleotides Manufacturing
Innovation Centre of Excellence (OMICE). Construction works are programmed
to commence on site in October 2024. 
4.3  The joint venture between TPPL and Renfrewshire Council has now completed
is first year of partnership. Good progress is being made with strong interest
from potential suitable occupiers to locate at AMIDS. There are twelve ongoing
enquiries at different stages of development with significant work being
undertaken to engage with potential occupiers and develop projects. Most
enquiries are subject to non-disclosure agreements but from organisations in
sectors fitting the AMIDS criteria, including life sciences, green energy, space
and aviation. A team of design consultants have been appointed with four
interested organisations progressing preliminary design works to inform their
decisions on location and costs with encouraging progress towards the release
of the first site. 
4.4   TPPL as Development Partner are also progressing the development of Tech
Terrace with the design team. Tech Terrace will comprise of units ranging from
200 – 3,200 sqm providing much needed speculative space for spin out
organisations and those looking to scale up in a supportive, collaborative and
entrepreneurial environment. Designs are being finalised to allow a submission
for planning permission in September 2024.

Page 4

4.5  In the promotion of AMIDS, TPPL have attended conferences and events in the
Glasgow area, wider in Scotland and the UK. Marketing strategies have
included a successful agents event held at NMIS in June 2024 for Glasgow and
Edinburgh property agents. Marketing brochures have now been produced and
are in circulation with a Linkedin strategy is being developed. The AMIDS
website is operational at www.amids.co.uk . 
4.6  The Team are hopeful that AMIDS will benefit from the GCR Investment Zone
though announcements on this are now not expected until the UKG Autumn
Statement in October. 
4.7   Other progress incudes work by Skills Development Scotland who are
undertaking qualitative research into skills shortages. Survey work includes
carrying out interviews with businesses in the wider AMIDS area with a report
of findings to be completed by October 2024. 
5.  Update on Progress at AMIDS South 
5.1  A Planning Application was submitted to Renfrewshire Council in May 2022 and
consent was granted at the Planning and Climate Change Policy Board meeting
on 24th January 2023. 
5.2  The alignment for the Project runs north from Weir Street along Abercorn St,
Harbour Road, across the White Cart Water (just south of Paisley Harbour),
linking to Inchinnan Road at the northern end of the Project. A new bridge will
be constructed across the White Cart Water (the White Cart Crossing). 
5.3  The alignment of the Project and location of the bridge was driven by a detailed
multistage options appraisal. This process considered options for delivering the
targeted outcomes, potential corridors and then specific alignments to ensure
the Project specific objectives were delivered. This appraisal process was
further assessed during the stakeholder and public consultation process. 
5.4 The planned Project alignment performed best in terms of being considered
most suitable for delivery of the targeted benefits, promoting potential for growth
of existing businesses, development potential, accommodating the revised
traffic flows in the area and minimising impact on existing residential areas. 
5.5 A detailed transport modelling exercise has been undertaken to assess and
report on the predicted impact of the Project on future traffic flows and was
included in the planning application. 
5.6  The detailed design has been finished and the procurement exercise to appoint
a contractor is underway, which will enable the completion and submission of
the Full Business Case (FBC) in early 2025. 
5.7 A Compulsory Purchase Order has been applied for and one objection was
received.

Page 5

A Public Local Inquiry will take place at the end of August and the Reporter
will thereafter make a decision on whether the Council can proceed with the
Order or otherwise. Successful completion of the Project is dependent on the
Order being confirmed. 
5.8  A two-stage procurement process in underway. Stage 1 has been completed
and Stage 2 will commence in August 2024 with the completion date expected
to be March 2025. 
5.9 Construction work is scheduled to start during the summer 2025 with an
expected construction period of 30 months. 
__________________________________________________________________
Implications of the Report 
1. Financial - The Council’s financial contribution to the AMIDS (Renfrewshire) LLP
for Phase 1 is zero (£0) in monetary terms. The Council’s investment in the LLP is
by way of non-cash capital investment of the AMID Land subject to business case
agreement by the LLP Board. 
Financial outlay to progress future development will be returned out of future
profits generated through the LLP. Subject to the Council not defaulting on any
contractual obligations through the LLP, financial risk rests with the Development
Partner 
2. HR & Organisational Development -Two officers of Renfrewshire Council are
continuing to serve the LLP board 
3. Community/Council Planning –  
 Our Renfrewshire is thriving – This project will provide properties for
advanced manufacturing employers to locate. This will facilitate business
growth and improve skills development for people within the local
communities. The projects align with and aid the outcomes of the
Renfrewshire Economic Strategy 2020 -2030 and the Renfrewshire
Economic Recovery Plan 
 Our Renfrewshire is well - Increased employment opportunities will aid health
and social outcomes within Renfrewshire. 
 Reshaping our place, our economy and our future - The progression of the
Advanced Manufacturing Innovation District directly aligns with the council’s
policies and ambitions.  
During the project construction period jobs will be created and existing jobs
supported. The new occupiers of buildings created will result in additional
employment within Renfrewshire, which will be accessible by people in our
communities

Page 6

 Tackling inequality, ensuring opportunities for all - The location of AMIDS,
adjacent to residential communities and the infrastructure and active travel
links to education and skills development centres will ensure our less
advantaged communities are able to access the opportunities provided 
 Creating a sustainable Renfrewshire for all to enjoy - The design ethos
adopted at AMIDS is one which relies on sustainable transport, active travel,
includes a District Heating Network and all property designs will align with
the Councils net Zero Carbon target 
 Working together to improve outcomes - Officers are working closely with
local communities, neighbouring councils, private sector organisations,
Scottish Government, Scottish Enterprise and other partners to ensure the
maximisation of positive outcomes from the AMIDS and AMIDS south
projects 
4. Legal – No legal implications as report is for noting only.  
 
5. Property/Assets - The land area included in the LLP Agreement will be drawn
down in parcels. Once the land is made available to the LLP, the Council will
retain some control over the land through a 150 year ground lease.  Renfrewshire
Council will only make available to the LLP land parcels upon agreement by the
LLP of a business plan for each development. 
6. Information Technology – None. 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report because for example it is for noting only.   If required following
implementation, the actual impact of the recommendations and the
mitigating actions will be reviewed and monitored, and the results of the
assessment will be published on the Council’s website.   
8. Health & Safety - Tarras Park Properties Limited health and safety credentials
were evaluated by Corporate Health and Safety and met the Council’s minimum
requirements regarding health and safety. 
9. Procurement –  Ongoing  procurement process will continue to ensure that the
Council meets its statutory requirements in respect of procurement procedures,
efficiency and modern Government. 
10. Risk - Project and Programme level risk registers have been established for the
project. These are kept under regular review and reported to the Council’s
internal City Deal and Infrastructure Programme Board.

Page 7

The Council is not contractually obliged to provide any capital to funding the
LLP other than the land injection in parcels as outlined in this report. In the event
of a default or winding up situation affecting the LLP situation the Council would
have the option to purchase the interests of the LLP, independently valued at
Fair Value. 
11. Privacy Impact - No Privacy Impact implications have been identified or are
anticipated. 
12. Climate Risk - The level of impact associated with the AMIDS Development
has been assessed using the Scottish Government Sustainability Test and is
considered High Risk. 
The Development Partner is required to develop a Carbon Reduction Plan
under the PDSC and confirmed that all Contractors, Designers etc appointed
by the LLP will have suitable ISO 14001 or equivalent Environment
Management System accreditations. 
13. COSLA Policy Position – None. 
14. Children’s Rights – Not applicable.
_______________________________________________________
List of Background Papers 
(a) Appointment of Advanced Manufacturing Innovation District Scotland
Development – Full Council, 4 May 2023 
(b) City Deal and AMIDS Projects Update report, Leadership Board, November
2022 
(c) Renfrewshire’s City Deal Projects – Final Delivery Phase report, Leadership
Board, February 2021
___________________________________________________________________ 
Author:           Barbara Walker, City Deal and Infrastructure Programme Director; 