1. Historic Buildings in Villages Grants Scheme - Update - Report

Renfrewshire Council · 27 August 2024
Back to Economy and Regeneration Policy Board — 27 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy and Regeneration Policy Board
On: 27 August 2024
___________________________________________________________________
Report by: Chief Executive
___________________________________________________________________
Heading: Historic Buildings in Villages Grants Scheme - Update
___________________________________________________________________
1. Summary 
1.1 Following the paper to Board on 29 August 2023, this report provides a further
update on the Council Motion of 3 March 2022 to create a £0.250million
conservation and heritage grants scheme for property owners in and around
the centres of Renfrewshire’s villages. 
1.2 Available across the eleven Renfrewshire villages which previously benefited
from the Villages Investment Fund, two complementary grant schemes were
launched in November 2023 under the “Historic Buildings in Villages Grants”
scheme: “Maintenance Planning Grants”; and “Repairs Grants”. 
 
1.3 The application process for both schemes has followed a similar model to the
online process successfully established for the Retail Improvement Scheme,
with applications scored on a range of criteria which assess impact, quality and
deliverability.   
1.4 To date nearly 50 applications have been received under the scheme, with a
geographical spread across Renfrewshire’s villages.  To date, 19 grants have
been offered, totalling over £186,000.
___________________________________________________________________
2. Recommendations 
2.1 It is recommended that the Board: 
(i) Notes the progress to date in respect of the number applications received
for the scheme. 
(ii) Approves a second round of the Scheme should any of the current
allocation remain unspent.

Page 2

(iii) Authorises the Head of Economy and Development to seek sources of
funding for future rounds of the Scheme. 
_________________________________________________________
3. Background 
3.1 The Council meeting of 3 March 2022 agreed to commit £0.250million of capital
resources committed to town centre regeneration and underpin a conservation
and heritage grants scheme for property owners in and around Renfrewshire’s
village centres. 
 
3.2 The Historic Buildings in Villages Grants scheme focuses on preserving and
enhancing the historic built environment in Renfrewshire’s villages,
complementing the existing Villages Investment Fund, to support projects which
strengthen the character, identity and heritage of Renfrewshire’s village
communities. 
3.3 In aligning with the Villages Investment Fund, the Historic Buildings in Villages
Grants scheme has been available to property owners in Bishopton, Bridge of
Weir, Brookfield, Crosslee, Elderslie, Houston, Howwood, Inchinnan, Kilbarchan,
Langbank and Lochwinnoch. 
4. Historic Buildings in Villages Grants Scheme 
4.1 In devising an application and assessment process, lessons were learned from
Renfrewshire Council’s Retail Improvement Scheme and the Paisley TH.CARS2
regeneration project. Research was also undertaken into similar schemes
offered by councils and heritage trusts nationally. 
4.2 The Historic Buildings in Villages Grants scheme has been targeted primarily at
private owner occupiers (including shared owners), but third sector organisations
and commercial businesses (who are more likely to be lessees) have also been
eligible to apply. 
4.3 Properties dating from 1945 or earlier have been eligible for funding. Applications
have been scored according to a range of criteria weighted to prioritise listed
buildings, buildings at risk, buildings within conservation areas, and buildings in
shared ownership. 
4.4 Grants have been available through two complementary schemes: 
(i) Maintenance Planning Grants support a conservation accredited
professional advisor to undertake an external survey and prepare an
illustrated, costed maintenance plan for a privately owned historic property.
Grants of up to 80% of eligible costs (excluding VAT) - up to a maximum
value of £1,500 per property – were available, with applications closing on
29 January 2024.  
 
(ii) Repairs Grants support the repair of a privately owned historic property.
Small Grants of up to 60% of eligible costs (excluding VAT) have been 
available for works valued between £3,000 and £8,000 (excluding VAT).

Page 3

Standard Grants of up to 50% of eligible costs (excluding VAT) have also
been available; these support works valued over £8,000 (excluding VAT).
The maximum amount awarded for Standard Grants is typically £25,000
however in exceptional circumstances, larger grants have been considered.
Applications for the Repairs Grants closed on 29 April 2024.  
 
4.5 The criteria for the Historic Buildings in Villages Grants scheme assess the
impact, quality and deliverability of proposed works.  Criteria will include:- 
 Whether the property is listed, within a village conservation area or is
identified on the Buildings at Risk Register; 
 Ownership and evidence of commitment of owners to repair and maintain
the property; 
 Whether the property is currently occupied and has a long-term, sustainable
function; 
 Evidence of a level of input from a suitably experienced professional
advisor; 
 Whether quotes have been obtained from Renfrewshire based contractors
and their experience working on older properties. 
5. Outcomes to date 
5.1 In total, officers received 94 enquiries about the scheme. Of the 11 eligible
villages, enquiries were received from all but 2: Elderslie; and Inchinnan. 
5.2 Those 94 enquiries translated into: 
(i) 13 applications for Maintenance Planning Grants, requesting nearly
£16,000 of support. 12 grants were offered, and of those, 8 grants totalling
£8,400 were accepted by property owners in Bridge of Weir, Houston,
Kilbarchan and Lochwinnoch. 7 Maintenance Plans are now complete. 
(ii) 36 applications for Repairs Grants from seven villages, requesting over
£466,000 of support. To date, 19 grants have been offered, totalling over
£186,000. This includes two offers of grant for over £25,000: one for a
historically significant listed building in Kilbarchan; and one for a building in
shared ownership in the centre of Lochwinnoch, occupying a prominent
corner site. A further 11 grant offers, totalling £110,000 are pending, subject
to applicants providing clarification on their proposals. 
5.3 Applications for Repairs Grants have largely been for roof repair or
replacement, and window refurbishment or replacement. 
5.4 Part of the purpose of the scheme is to stimulate demand for traditional building
skills locally. Applicants obtained quotes from 9 Renfrewshire-based
businesses.

Page 4

6. Next Steps   
6.1 Offers of grant are conditional until Council officers issue grantees with
Permission to Start letters. For those grantees who have not yet received their
Permission to Start letter, officers continue to advise on, for example, consents
and issues with contractors. 
6.2 Given the challenge of implementing repair works, while c.£300,000 has
potentially been allocated in Repairs Grants, it’s highly likely that a % of this will
not translate into completed works and will need reallocated. 
6.3 On completion of works, grantees will be asked for feedback to help determine
where officer can make improvements in the scheme. For example, should
funding for the scheme continue to be allocated in the future, to improve the
process for applicants - and improve the quality of applications – future
applicants may wish the scheme to be available on a rolling basis, rather than
having a fixed submission deadline. 
6.4 Once the Council motion funds have been expended, officers will continue to
explore other alternative funding routes to allow the Scheme to continue.  As
noted in the Regeneration Funding Bids Update 2024 paper to board on 19th
March 2024, there may scope for the Place Based Investment Fund to provide
funding for future runs of the Scheme.
___________________________________________________________________
Implications of the Report 
1. Financial – Funding for both schemes utilise an approved Council budget. 
2. HR & Organisational Development – None. 
3. Community/Council Planning – 
 Our Renfrewshire is thriving – The schemes support development which will
protect and enhance the built heritage of Renfrewshire’s village centres,
contributing to the creation of thriving places which support individuals,
communities, and businesses. 
 Reshaping our place, our economy and our future – The schemes will help
support the restoration and productive re-use of buildings in the centres of
Renfrewshire’s villages, improving the built environment, helping to create job
opportunities and contribute to economic growth. 
4. Legal – Third party grants will be awarded within the relevant Council policies and
will be subject to the Council’s approved conditions. 
5. Property/Assets – None. 
6. Information Technology – ICT will help develop and maintain the online
application process for both schemes. 
7. Equality & Human Rights – The Recommendations contained within this report
have been assessed in relation to their impact on equalities and human rights.

Page 5

No negative impacts on equality groups or potential for infringement of individuals’
human rights have been identified arising from the recommendations contained in
the report. 
8. Health & Safety – None. 
9. Procurement – None. 
10. Risks – None. 
11. Privacy Impact – None. 
12. COSLA Policy Position – None. 
13. Climate Risk – With cognisance of Historic Environment Scotland’s ‘A Guide to
Climate Change Impacts: On Scotland’s Historic Environment, Our Place in Time,
2019’, the repair and maintenance of Renfrewshire’s historic fabric will contribute
to the restoration and repair of buildings and will improve the performance of these
properties over time. 
14. Children’s Rights – None.
_________________________________________________________
Author: Euan Shearer; Regeneration and Place Manager