2024-25 P03 Eco and Regen PB Budget Monitoring Report

Renfrewshire Council · 27 August 2024
Back to Economy and Regeneration Policy Board — 27 August 2024 and its agenda

Text extracted from the council's PDF. Layout and reading order may differ from the original.

Original council PDF · Download plain text

Page 1

___________________________________________________________________
To: Economy and Regeneration Policy Board
On: 27 August 2024
___________________________________________________________________
Report by: Chief Executive and Director of Finance and Resources
___________________________________________________________________
Heading: Revenue and Capital Budget Monitoring 2024/25 at 21 June 2024
___________________________________________________________________
1. Summary
1.1 At the close of reporting Period 3 on 21 June 2024, the projected revenue
outturn at 31 March 2025 for those services reporting to the Economy and
Regeneration Policy Board was an underspend position of £0.066m (3.0%)
against the revised budget for the year. 
1.2 The projected capital outturn at 31 March 2025 for projects reporting to the
Economy and Regeneration Policy Board is a break-even position. 
1.3  This is summarised in the table below and further analysis is provided in the
report and appendices. 
Revised
Annual
Budget
£000
Projected
Outturn
£000
Budget
Variance
(Adv)/Fav
£000
Budget
Variance
%
Revenue    
Economy and Development 2,228 2,162 66 3.0%
Capital    
Economy and Development 22,862  22,862  0  0.0% 
2. Recommendations
2.1 Members are requested to: 
a) Note the projected Revenue outturn underspend position of £0.066m;
b) Note the projected Capital outturn break-even position;

Page 2

c) Agree to homologate the budget adjustments detailed at section 6.2;
d) Note the budget adjustments detailed at section 6.3; and
e) Approve the budget adjustment detailed at section 6.4. 
3. Revenue Budget Projection – underspend of £0.066m by 31 March 2025
3.1 The tables in Appendix 1 present the projected year-end position for all
services reporting to this board, by both subjective analysis (what the budget
is spent on) and objective analysis (which division is spending the budget).
Significant variances affecting the projected position are analysed further
below. 
3.2 It should be noted that the projected outturn position reported here is based
on the latest information available, which is subject to change during the
financial year. The impact of any change on this projection will be updated at
each board cycle until the close of reporting Period 10. Budget holders are
obliged to seek mitigating action to minimise significant budget variances. 
4. Objective Analysis – Significant Variances
4.1 Regeneration - £0.066m underspend
This forecast position reflects the impact of vacancies within the team at the
start of the financial year. 
5. Subjective Analysis – Significant Variances
5.1 Employees - £0.065m underspend by 31 March 2025
This projected underspend represents vacancies in the Regeneration team
at the start of the financial year. Recruitment to these posts is expected to
complete over the course of the next quarter. 
6. Revenue Budget Virements
6.1. Under the Council’s financial regulations, Directors and their nominated
officers, in consultation with the Director of Finance and Resources, have
certain delegated authority to transfer sums between subjective budget
headings within a service division to enable budget management throughout
the financial year. This is known as ‘budget virement’. 
6.2. Transfers between divisions of the same service / department in excess of
£100,000, and transfers between services / departments must be authorised
by the respective service Director/Chief Executive and the Director of

Page 3

Finance and Resources for submission to the relevant policy board for
approval.   
Since the budget was approved in February 2024, the Chief Executive now
seeks homologation from the Board for the following affected virements: 
Revenue Budget Adjustments
Service Amount
(£m)
Reason
Economy and Development (0.001) Regeneration project budget reallocated
to Environment, Housing &
Infrastructure for delivery
Economy and Development (0.750) Right for Renfrewshire savings realised 
6.3. The following budget adjustment reflects changes to superannuation rates
for employers and is therefore for noting only: 
Revenue Budget Adjustments
Service Amount
(£m)
Reason
Economy and Development (0.188) Contribution to reserves re reduction in
employers’ superannuation 
6.4. The Scottish Government issued an offer of grant to Renfrewshire Council of
£2.182m in connection with the delivery of No One Left Behind employability
support, which was accepted on 18 June 2024. The Board is therefore asked
to approve the following virement to reflect the realignment of budgets
required to deliver the programme, to be reflected in the next report: 
Revenue Budget Adjustments
Objective
Heading
Subjective
Heading
Amount
(£m)
Reason
Economy and
Development
Employee Costs 1.166 Temporary realignment of costs
funded by external income
streams. Project Costs* 1.016
Income (2.182)
* Project costs can include supplies and services contracts and payments to external bodies 
7. Capital Budget Projection – break-even position by 31 March 2025
7.1 The Capital Investment Programme 2024/25 to 2028/29 of £21.720m for
Economy and Regeneration was approved by the Council on 29 February
2024. The revised capital spend for 2024/25 is £22.862m.

Page 4

7.2 The in-year Capital budget is forecast to break-even by 31 March 2025 after
a number of budget adjustments between years have taken place, to reflect
revised programming of some capital projects. Details of these adjustments,
which amount to £1.142m, are as follows: 
Project Amount
(£m)
Budget brought forward into 2024/25 to reflect updated timing
Paisley Art Centre Redevelopment 0.128
Paisley Town Hall Redevelopment (0.250)
Paisley Learning & Cultural Hub 0.280
Paisley Museum (0.634)
Paisley Junctions and Charging Hub 0.194
Public Realm 1.163
Sports Development – St James Playing Fields Redevelopment 3.075
Sports Development – Ferguslie Pavilion Upgrade 0.460
Sports Development – Hockey Pitch at On-X 0.600
Town Centre Capital Fund 0.035
Place Based Investment Fund 0.366
Town Centre Regeneration 0.009
Shared Prosperity Fund 0.028
RCGF PACE Theatre (0.210)
Townscape Heritage CARS 2 0.223
Budget carried forward into 2025/26
Town Centre Regeneration (0.069)
Public Realm (4.256)
Total 1.142 
Implications of the Report
1. Financial
The projected budget outturn position for Finance, Resources and Customer
Services’ Revenue budget is an underspend of £0.066 (3.0%) at 31 March
2025.  Income and expenditure will continue to be monitored closely for the rest
of the financial year and as far as possible, steps will be taken to mitigate any
overspend.   
The projected outturn position for Economy and Regeneration Capital budget is
break-even, after the adjustments outlined at section 6.

Page 5

2. HR & Organisational Development 
While staffing budgets form a significant proportion of the Council’s revenue
budgets, there are no direct implications arising from the recommendations in
this report. 
3. Community/Council Planning
Community Plan
Our Renfrewshire is thriving The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Our Renfrewshire is well 
Our Renfrewshire is fair 
Our Renfrewshire is safe
Council Plan
Reshaping our place, our
economy and our future The Council’s revenue and capital spend
ensures that its facilities are fit for
purpose and safe for the community, to
maximise accessibility.
Building strong, safe and resilient
communities
Tackling inequality, ensuring
opportunities for all
Creating a sustainable
Renfrewshire for all to enjoy
Ongoing revenue and capital budget
monitoring is a tool to enable good
financial management so that the Council
has resources now and in the future for
continued service delivery.
Working together to improve
outcomes 
4. Legal 
There are no direct implications arising from the recommendations in this
report. 
5. Property/Assets 
The capital expenditure noted in this report will result in improvements to
Culture and Heritage assets and delivery of strategic place-shaping and
regeneration. 
6. Information Technology 
There are no direct implications arising from the recommendations in this
report. 
7. Equality & Human Rights 
While new areas of spend may impact on particular groups, any such impact
would be assessed prior to the spend being incurred, therefore there are no
direct implications arising from the recommendations in this report.

Page 6

8. Health & Safety 
There are no direct implications arising from the recommendations in this
report. 
9. Procurement 
While Procurement is an important consideration prior to the Council incurring
any revenue or capital spend, there are no direct implications arising from the
recommendations in this report. 
10. Risk 
The potential financial risk that the Council will overspend its approved revenue
budgets for the year is managed at a Council-wide level by the Chief Executive
and Directors. 
11. Privacy Impact 
There are no direct implications arising from the recommendations in this
report. 
12. Cosla Policy Position 
N/a 
13. Climate Change
The Council aims to reduce its carbon and other emissions to net zero by 2030,
however there are no direct implications arising from the recommendations in
this report. 
14. Children’s Rights
There are no direct implications arising from the recommendations in this
report. 
List of Background Papers 
• Revenue Budget and Council Tax 2024/25, Council 29 February 2024
• The Capital Investment Programme 2023/24 to 2027/28, Council 29
February 2024 
Author:           Valerie Howie, Finance Business Partner; and Linsey McGregor,
Senior Accountant (Capital)

Page 7

Appendix 1
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2024/25
1 April 2024 to 21 June 2024              
POLICY BOARD:  ECONOMY AND REGENERATION              
Objective Summary
Approved
Annual Budget 
Budget
Adjustments
Revised Annual
Budget at Period
3
Projected
Outturn
Budget Variance 
(Adverse) or Favourable  
£000 £000 £000 £000 £000 %
Economy and Regeneration Management 160 (125) 35 35 0 0.0%
Economic Development 1,947 (812) 1,135 1,135 0 0.0%
Regeneration 1,066 (8) 1,058 992 66 6.2%
NET EXPENDITURE 3,172  (944) 2,228  2,162  66 3.0%              
Subjective Summary
Approved
Annual Budget 
Budget
Adjustments
Revised Annual
Budget at Period
3
Projected
Outturn
Budget Variance 
(Adverse) or Favourable  
£000 £000 £000 £000 £000 %
Employees 2,586 (854) 1,732 1,666 66 3.8%
Premises Related 22 0 22 21 1 4.5%
Transport Related 3 0 3 4 (1) (33.3%)
Supplies and Services 30 (7) 23 24 (1) (4.3%)
Third Party Payments 0 0 0 0 0 0.0%
Transfer Payments 842 (69) 773 772 1 0.1%
Support Services 40 (15) 25 26 (1) (4.0%)
Depreciation and Impairment Losses 0 0 0 0 0 0.0%
GROSS EXPENDITURE 3,523  (945) 2,578  2,513  65 2.5%
Income (351) 1 (350) (351) 1 0.3%
NET EXPENDITURE 3,172  (944) 2,228  2,162  66 3.0%

Page 8

Appendix 2 
Prior Years Approved  Budget Revised Projected
Expenditure Budget Adjustments Budget Outturn Total Approved Projected
to 31/03/2024 2024-25 in 2024-25 2024-25 2023-24 Budget Outurn
Project Title to 31-Mar-29 to 31-Mar-29
£000 £000 £000 £000 £000 £000 £000
ECONOMY & DEVELOPMENT
Paisley Art Centre Redevelopment 2,881 741 128 869 869 0 0% 3,750 3,750 0 0%
Paisley Town Hall Redevelopment 24,747 1,250 -250 1,000 1,000 0 0% 25,747 25,747 0 0%
Paisley Learning & Cultural Hub 6,654 66 280 346 346 0 0% 7,000 7,000 0 0%
Paisley Museum 39,228 13,527 -634 12,893 12,893 0 0% 52,122 52,122 0 0%
Paisley Junctions and Charging Hub 431 0 194 194 194 0 0% 625 625 0 0%
Public Realm 494 3,393 -3,093 300 300 0 0% 5,050 5,050 0 0%
Sports Development - St James Playing Fields Redevelopment 426 0 3,075 3,075 3,075 0 0% 3,500 3,500 0 0%
Sports Development - Ferguslie Pavillion Upgrade 531 0 460 460 460 0 0% 992 992 0 0%
Sports Development - Hockey Pitch at On-X 0 0 600 600 600 0 0% 600 600 0 0%
Town Centre Capital Fund 766 74 35 109 109 0 0% 876 876 0 0%
Place Based Investment Fund 1,842 2,219 366 2,585 2,585 0 0% 4,428 4,428 0 0%
Town Centre Regeneration 1 240 -60 180 180 0 0% 2,050 2,050 0 0%
Shared Prosperity Fund 197 0 28 28 28 0 0% 225 225 0 0%
RCGF PACE Theatre 1,084 210 -210 0 0 0 0% 1,084 1,084 0 0%
Townscape Heritage CARS 2 3,876 0 223 223 223 0 0% 4,099 4,099 0 0%
Total Economy & Development 83,158 21,720 1,142 22,862 22,862 0 0% 112,148 112,148 0 0%
TOTAL ECONOMY & DEVELOPMENT 83,158 21,720 1,142 22,862 22,862 0 0% 112,148 112,148 0 0%
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY - NON-HOUSING SERVICES
1 April 2024 to 21 June 2024
POLICY BOARD: ECONOMY & REGENERATION
Current Year 2024-25 Full Programme - All years
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable