PUBLIC 
___________________________________________________________________
To:  Economy and Regeneration Policy Board
On:  17 March 2026
___________________________________________________________________
Report by: Chief Executive
____________________________________________________________
Heading: Steeple Buildings Kilbarchan - Update
___________________________________________________________________
1. Summary
1.1 The purpose of this report is to provide members with an update on the
proposed refurbishment and potential reuse of the Steeple Buildings in
Kilbarchan. It offers an update on recently completed essential repairs and
progress on a further phase of repairs to allow the building to be brought back
into use.
_________________________________________________________________
2         Recommendations
2.1 It is recommended that the Board: 
(i) Notes the contents of this update report
(ii) Authorises the Head of Economy and Development to progress with the
procurement of the Phase 2 repairs programme if sufficient funding can
be secured.
_________________________________________________________
3    Background
3.1 The 18th-century Steeple Buildings, located in Kilbarchan's Conservation Area
and jointly owned by Renfrewshire Council and the Kilbarchan General Society
(KGS), hold cultural significance as a Category A listed property and forms the
centre of the village's annual Lilias Day celebrations. OneRen currently leases
the building as a community hall, though it has remained closed since the Covid
pandemic. While the building saw limited community use pre-pandemic, other

Page 2

PUBLIC
venues are available in Kilbarchan. Prior to 2025, repairs have been conducted
by Renfrewshire Council as needed. The last major refurbishment took place in
the 1950s.
___________________________________________________________________ 
4 Current position 
4.1 Reports to the Economy and Regeneration Board in January 2024 and
November 2024 provided updates on Council motion (4 May 2023) and the
allocation of £705,000 to support refurbishment. These reports highlight
extensive stakeholder engagement, particularly with Kilbarchan Community
Council (KCC). This led to the formation of the Friends of the Steeple sub-
group, to support decision-making regarding the Steeple Buildings.
4.2 Updates on the findings of a detailed Options Appraisal were also provided,
highlighting the preferred future use of the Steeple Buildings, including using
the ground floor hall as licensed café/restaurant and maintaining the first floor
as community hall for hire.
4.3 After reviewing the Options Appraisal, the sub-group confirmed its voluntary
role in sustaining the Steeple Buildings and continues to operate as part of
KCC. 
4.4 Since 2024, officers have received several informal enquiries from third parties
about potentially leasing the ground floor hall and kitchen, for use as a
café/restaurant, once refurbishment works are complete.
___________________________________________________________________ 
5 Repairs Programme 
5.1 Based on costings from conservation specialists John Gilbert Architects’ 2023
condition survey, in January 2024 the Economy and Regeneration Board
approved the implementation of a first phase of major repairs, valued at
£310,000+VAT, prioritising “immediate” and “urgent” work on the roof,
leadwork, and rainwater systems.
5.2 Conservation specialists MAST Architects were subsequently appointed in
September 2024 to develop the programme for this first phase of major repairs. 
5.3 Following more intrusive surveys in autumn 2024, MAST categorised additional
internal works, to address dampness on the ground floor and improve the safety
of services, as “immediate” and “urgent”. 
5.4 In light of MAST’s reassessment of the internal condition of the building and
after discussion with stakeholders, it was agreed that a meantime use for the
building, following completion of Phase 1 repairs, was not a viable option.
5.5 Following a competitive tender process, Contract Authorisation for Steeple
Buildings Phase 1 Repairs (RC-CPU-23-316) was granted at the June 2025
Finance, Resources and Customer Services Policy Board, with W H Kirkwood
subsequently appointed to deliver Phase 1 repairs at a cost of £332,913.87
excluding VAT.

Page 3

PUBLIC
5.6 Phase 1 repairs were complete in February 2026 at a cost of c.£359,970
excluding VAT. Additional spend was required to complete necessary electrical
works and rebuild (as opposed to simply repoint) two stone chimneys. With the
additional chimney works needing scaffolding to remain in position longer and
with pointing to the steeple structure found to be in worse condition than
anticipated, it was decided to instruct repointing of stonework to the entire
steeple structure while the scaffolding remained on site, rather than just at the
highest levels.
5.7 The procurement process has been initiated with CPU to appoint a
conservation architect to develop the detailed programme for Phase 2 repairs.
While Phase 1 focused on making the building wind and watertight i.e. on
external repairs to replace materials that had reached the end of their life and
internal repairs to address damp issues, Phase 2 will focus on the repair and
reconfiguration of the interior (including accessibility improvements) to enable
the building to come back into public use.  It is anticipated that this will include
the installation of new toilets, a refurbished kitchen space and a lift.
5.8 At the start of Phase 1 repairs, the clock mechanism was removed and placed
in safe storage. Repairs to the clock mechanism and its strike controller have
been instructed prior to reinstallation, as has the repair of the structure from
which the bell hangs. Repair of the structure will mean the bell no longer needs
to be tied back for safety.
___________________________________________________________________
6 Funding
6.1 Total expenditure to date on the Steeple Buildings, including preparatory
surveys, professional fees, legal searches, and Phase 1 works is £434,083.
6.2 Of the original £705,000 budget, £270,917 remains.
6.3 The current estimated cost of Phase 2 works (including clock and bell repairs)
is £420,913, giving a total cost for Phase 1 and Phase 2 of £854,996 and an
estimated budget shortfall for Phase 2 of £149,996. It should be noted that
repointing of the stonework of the main steeple building is currently excluded
from Phase 2 repairs as it has been designated neither “urgent” nor
“immediate”. 
6.4 Officers are exploring funding options to address the Phase 2 budget shortfall.
The Scottish Government’s Place Based Investment Programme and the UK
Government’s Local Growth Fund may be options, depending on the
application process. Enquiries have also been made to Historic Environment
Scotland (HES), however with additional external works having taken place as
part of Phase 1 and Phase 2 focused on the interior, there are relatively few
costs in Phase 2’s programme which would be considered grant eligible by
HES.
___________________________________________________________________

Page 4

PUBLIC
7 Next Steps  
7.1 Officers are working with CPU on the tender process to appoint a conservation
architect who will develop designs for Phase 2, support the tender process to
appoint a main contractor (if funding can be secured) and oversee
implementation of the works.
7.2 Officers will also investigate opportunities to secure funding and enable delivery
of Phase 2 works.
___________________________________________________________________
Implications of the Report
1. Financial - £705,000 has been allocated by Renfrewshire Council for the
refurbishment of the Steeple Buildings. Additional funds will be required to
deliver Phase 2 repairs which will enable the building to be brought back into
use. 
2. HR & Organisational Development - None 
3. Community/Council Planning –  
• Our Renfrewshire is thriving – The project supports development which will
protect and enhance the built heritage of Renfrewshire’s village centres,
contributing to the creation of thriving places which support individuals,
communities, and businesses. 
• Reshaping our place, our economy and our future – The project will help
support the restoration and productive re-use of a landmark building in the
centre of a Renfrewshire village, improving the built environment, helping
to create job opportunities and contribute to economic growth. 
• Working together to improve outcomes - The project is working in
partnership with local groups and organisations to achieve positive
outcomes. 
4. Legal – The Steeple Buildings are jointly owned with local charity, Kilbarchan
General Society (who own a single room on the first floor). 
5. Property/Assets - Property Services were Client Advisor for the Phase 1
repair programme 
6. Information Technology - None
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report because for example it is for noting
only.   If required following implementation, the actual impact of the

Page 5

PUBLIC
recommendations and the mitigating actions will be reviewed and monitored,
and the results of the assessment will be published on the Council’s website. 
(Report author to arrange this). 
8. Health & Safety – MAST Architects were Principal Designer for the Phase 1
repair programme.
9. Procurement – The appointment of a conservation architect and a main
contractor for the Phase 2 repair programme will be managed by CPU.
10. Risk – Phase 1 repairs have stabilised the fabric of the building and Phase 2
repairs will bring the building back into a use which is sustainable.
11. Privacy Impact - None 
12. Climate Risk – With cognisance of Historic Environment Scotland’s ‘A Guide
to Climate Change Impacts: On Scotland’s Historic Environment, Our Place in
Time, 2019’, the repair and maintenance of the Steeple Buildings will
contribute to the restoration and repair of Renfrewshire’s historic fabric and
will improve the performance of this property over time.
13. Children’s Rights - None
14. Cosla Policy Position – None
________________________________________________________________ 
List of Background Papers 
(a) Steeple Buildings Kilbarchan – Update - Economy and Regeneration
Policy Board, 23 January 2024
(b) Steeple Buildings Kilbarchan – Update - Economy and Regeneration
Policy Board, 5 November 2024
(c) Contract Authorisation Report for Steeple Buildings Kilbarchan
Phase 1 Repairs (RC-CPU-23-316) - Finance, Resources and Customer
Services Policy Board – 12 June 2025 
___________________________________________________________________ 
Author: Euan Shearer; Regeneration and Place Manager
Email: euan.shearer@renfrewshire.gov.uk