To: Communities and Housing Policy Board
On: 31 October 2023
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Renfrewshire’s Local Air Quality Management Update –
2023 Air Quality Annual Progress Report
___________________________________________________________________
1. Summary
1.1 This report provides an update in relation to air quality within Renfrewshire
and details the findings of the Council’s most recent Local Air Quality
Management report, Renfrewshire’s 2023 Annual Progress Report. 
1.2 The 2023 Annual Progress Report reviewed air quality monitoring data from
2022. There were no exceedances of any quality objectives identified within
Renfrewshire during 2022 with concentrations of nitrogen dioxide (NO2) and
particulate matter (PM) continuing to show a downward trend. 
1.3 There have now been three consecutive years of compliance with statutory
objective levels throughout all of Renfrewshire and eight years of compliance
within Paisley and the Paisley Town Centre Air Quality Management Area.
The legislative framework permits Air Quality Management Areas to be
amended or revoked and Scottish Government Policy Guidance recommends
that, as a minimum there will normally be at least three consecutive years
where the pollutants of concern are complying with the relevant objective
levels. Environment, Housing and Infrastructure will continue with the current
monitoring programme throughout 2023/24 before consideration will be given
to amending or revoking any of the Council’s three Air Quality Management
Areas. 
___________________________________________________________________
2. Recommendations 
It is recommended that the Infrastructure, Land and Environment Policy Board:
2.1 Notes the outcome of Renfrewshire’s 2023 Air Quality Annual Progress
Report and that there were no exceedances of any quality objectives
identified within Renfrewshire during 2022. 
_________________________________________________________

Page 2

3. Background
3.1 Air quality is directly related to a number of key Scottish Government National
Outcomes and policy priorities, notably those focussed on the environment,
sustainable places, environmental impact and healthier lives. 
3.2 In accordance with the Local Air Quality Management statutory process
introduced by the Environment Act 1995, all local authorities are required to
undertake a regular review and assessment of air quality within their area and
submit their findings by means of an Annual Progress Report to the Scottish
Government by the end of June each year for approval. Environment,
Housing and Infrastructure have submitted the Annual Progress Report which
has now been approved by the Scottish Government. 
3.3 The Annual Progress Report provides an overview of air quality within
Renfrewshire during 2022. It includes a review of 2022 pollutant monitoring
data and atmospheric emissions sources within Renfrewshire and compares
the available data to national air quality standards. 
3.4 The main pollutants of concern within Renfrewshire are NO2 and PM. There
are currently three Air Quality Management Areas (AQMAs) declared within
Renfrewshire; the Paisley Town Centre AQMA declared August 2009 and the
Johnstone High Street and Renfrew Town Centre AQMAs declared August
2016. 
3.5 In 2022 the Council operated three automatic monitoring sites (Cockels Loan,
Renfrew, Inchinnan Road, Renfrew and High St, Johnstone) which measured
NO2 or PM concentrations. Concentrations recorded at all automatic
monitoring sites were below the annual mean and short-term objective levels
for both pollutants. 
3.6  Monitoring of NO2 was also undertaken via a network of sixty-two NO2
diffusion tube sites throughout Renfrewshire with no exceedances recorded at
any of these sites. A largely downward trend in concentrations continues to be
observed across the Council’s 2022 monitoring data, with only seven NO2
diffusion tube sites experiencing an increase in annual mean NO2
concentration from 2021 to 2022, with the remaining experiencing a decrease. 
Broadly, over the past five years, the majority of the diffusion tube monitoring
sites have shown a decrease in NO2 concentrations.
3.7  Within the Paisley Town Centre Air Quality Management Area there have now
been eight consecutive years of compliance with statutory objective levels
within Paisley. The legislative framework permits Air Quality Management
Areas to be amended or revoked and Scottish Government Policy Guidance
recommends that, as a minimum there will normally be at least three
consecutive years where the pollutants of concern are complying with the
relevant objective levels. There are various reasons why the Paisley Town
Centre AQMA has not been revoked yet and presently we are awaiting
finalisation of significant infrastructure projects to the north of the Paisley
AQMA which may impact on road traffic in that area.

Page 3

3.8 In terms of the Johnstone High Street AQMA and Renfrew Town Centre
AQMA, there have now been three consecutive years of compliance with
statutory objective levels throughout these areas. In Johnstone, we have had
no exceedances of NO2 since 2018 when there was a reading of 40ug/m3 (the
objective level being 40ug/m3) at one diffusion tube site. Within Renfrew,
there was one marginal exceedance at a diffusion tube site in 2019 with a
reading of 41.4ug/m3. Environment, Housing and Infrastructure will continue
with the current monitoring programme throughout 2023/24 and collate a
further years’ worth of monitoring data before consideration will be given to
amending or revoking the Johnstone and Renfrew Air Quality Management
Areas. 
3.9 No further action is required by the Council other than to progress with
updating the 2019 Renfrewshire Air Quality Action Plan. An update to this is
due by spring 2024 and will be submitted to the Board for approval in due
course.  
___________________________________________________________________
Implications of the Report
1. Financial - none   
2. HR & Organisational Development - none 
3. Community/Council Planning – 
 Our Renfrewshire is well - by reviewing and assessing air quality
throughout Renfrewshire and producing our annual Local Air Quality
Management report we aim to improve air quality and provide a clean
and safe environment for all of Renfrewshire’s residents, workers and
visitors.  
 Creating a sustainable Renfrewshire for all to enjoy - improving air
quality will have a beneficial impact on Renfrewshire’s natural
environment.
4. Legal - none
5. Property/Assets - none
6. Information Technology - none 
7. Equality & Human Rights - The Recommendations contained within this
report have been assessed in relation to their impact on equalities and human
rights. No negative impacts on equality groups or potential for infringement of
individuals’ human rights have been identified arising from the
recommendations contained in the report. 
8. Health & Safety - none
9. Procurement - none
10. Risk - none

Page 4

11. Privacy Impact - none 
12. COSLA Policy Position - none
13. Climate Risk - The interactions between air pollution and climate change are
complex which is recognised within the Scottish Government’s 2015 air
quality strategy Cleaner Air for Scotland – The Road to a Healthier Future
(CAFS). An action measure within this government strategy recommends all
Scottish local authorities which have or are currently developing a Sustainable
Energy Action Plan to ensure that air quality considerations are also covered.
_________________________________________________________
List of Background Papers
a) Background Paper 1 - 2023 Air Quality Annual Progress Report for
Renfrewshire Council 
The foregoing background papers will be retained within Environment, Housing
and Infrastructure for inspection by the public for the prescribed period of four
years from the date of the meeting.  
The contact officer within the service is Colin Hunter, Environmental Health
Manager (Public Health) Tel: 07768831482, Email:
colin.hunter@renfrewshire.gov.uk
___________________________________________________________________ 
Author:    Gerard Hannah, Head of Climate, Public Protection and Roads (email:
gerard.hannah@renfrewshire.gov.uk

Page 5

Renfrewshire Council
Annual Progress Report (APR) 
2023 Air Quality Annual Progress Report (APR) for Renfrewshire Council
In fulfilment of Part IV of the Environment Act 1995, as amended by the
Environment Act 2021
Local Air Quality Management
June, 2023

Page 6

Renfrewshire Council 
Information Renfrewshire Council Details
Local Authority Officer Karen McIndoe
Department Environment, Housing and Infrastructure
Address
Renfrewshire Council
Renfrewshire House
Cotton Street
Paisley
PA1 1BR
Telephone 07768 988028 
E-mail karen.mcindoe@renfrewshire.gov.uk 
Report Reference Number APR2023
Date June 2023

Page 7

Renfrewshire Council
LAQM Annual Progress Report 2023 i
Executive Summary: Air Quality in Our Area
Air Quality in Renfrewshire Council
There are currently three Air Quality Management Areas (AQMAs) within Renfrewshire
Council. The AQMAs are located within Paisley Town Centre (PTC), Johnstone High Street
(JHS) and Renfrew Town Centre (RTC). The AQMAs have been declared due to exceedances
of the air quality objective (AQO) levels for nitrogen dioxide (NO2) and particulate matter
(PM10, PTC only). There continue to be no exceedances of either the NO2 or PM10 AQOs at
the automatic and passive monitoring locations within any of the AQMAs as reported in this
APR. Renfrewshire Council monitor NO2, PM10 and PM2.5 at a number of locations. 
Renfrewshire Council undertook automatic (continuous) monitoring at three sites during 2022
– REN1 (Renfrew Cockels Loan), REN02 (Renfrewshire Johnstone), REN03 (Renfrew
Inchinnan Road). REN1 and REN03 monitor NO2 while REN02 monitors PM10 and PM2.5.
The monitored concentrations of NO2 continue to show the downward trend observed across
Renfrewshire for the majority of the past decade, and there were no exceedances of the
relevant AQOs reported during 2022. Concentrations of the annual mean and relevant short-
term objectives for NO2, PM10 and PM2.5 recorded at all automatic monitoring sites during 2022
were below AQO levels.
There were a total of 62 diffusion tube monitoring sites across Renfrewshire in 2022, six sites
were either added to the diffusion tube monitoring network or changed in the network from
2021. The details of these are as follows: Paisley88 was removed in August due to low return
rates and was not replaced; Paisley95 was removed in February due to building works and
was replaced by Paisley106; Johnstone106 was removed in March due to building works and
was replaced by Johnstone107; Paisley104 was removed in June due to low return rates and
was replaced by Paisley108. Three additional new sites were introduced in 2022 – Paisley102,
Paisley103 and Paisley105.
Actions to Improve Air Quality
Throughout 2022, several sustainable travel-based measures detailed within the 2019 Air
Quality Action Plan (AQAP) have been progressed to improve air quality throughout
Renfrewshire, all measures and their progress are discussed in Section 2.3
Implementation of Air Quality Action Plan(s) and/or measures to address air quality.

Page 8

Renfrewshire Council
LAQM Annual Progress Report 2023 ii
Renfrewshire Council ran three schemes in 2022 to encourage active travel – Better
Points active travel incentive scheme, Living Streets WOW project walk to school
challenge, and Beat the Street competition where competitors tap Beat the Streets cards
on Beat Boxes to record distances walked or cycled. Additionally, the Paisley to Renfrew
and Inchinnan Active Travel Routes were constructed and the Cycle2Work Scheme was
open from March – June 2022.
Fourteen measures are within the existing AQAP, they cover the following topic
categories:
• Transport Planning and Infrastructure;
• Traffic Management;
• Promoting Travel Alternatives;
• Promoting Low Emission Transport;
• Freight and Delivery Management;
• Vehicle Fleet Efficiency;
• Alternatives to Private Vehicle Use;
• Policy Guidance and Development Control; and
• Public Information.
Local Priorities and Challenges
Renfrewshire Council’s priorities following the publication of the 2023 APR are as follows:
• Progress with the significant new road and cycle infrastructure projects which
are part of the City Deals and AMIDS South projects;
• Publication of a new Renfrewshire Local Transport Strategy and development of
a Paisley Town Centre Transport Strategy;
• Continuation with the upgrade and development of the cycling network as per
the Renfrewshire Council Cycle Strategy priorities;
• Improvement of the council’s fleet, funded via the Council’s Vehicle
Replacement Capital Programme. £2.2 million has been set aside for the VRC
Programme in 2023-24 for the purchase of new fleet vehicles. This includes the
replacement of older fossil vehicles with newer fleet vehicles with better
emission standards and the introduction of HVO as an alternative fuel for some
of the fleet;

Page 9

Renfrewshire Council
LAQM Annual Progress Report 2023 iii
• Reopening the Cycle2Work scheme in April 2023 and keeping it available for
the full financial year;
• Upgrading fleet tracking telemetric system fitted to all Council vehicles to
optimise utilisation of fleet. This will be completed by end of May 2023;
• Refresh the local transport strategy and active travel strategy/action plan;
• Full review of the 2019 Renfrewshire Council AQAP in summer 2023 in order to
have the review completed by next Spring which is in accordance with the new
requirements of the Scottish Government’s Policy Guidance 2023 whereby the
Scottish Government now requires all action plans are reviewed and
republished on a five-yearly cycle from date of initial publication, which will be
March 2024. This process will involve consultation with steering group members
and a full update of the action plan measures. The updated AQAP will include
new measures that are not listed within the 2019 AQAP such as Beat the
Streets, Better Points Ltd.;
• Continue to monitor NO2, PM10 and PM2.5 at all relevant locations throughout
Renfrewshire; and
• Submit the 2024 Annual Progress Report.
Renfrewshire Council has no comment on challenges faced as air quality in the area has
been steadily improving over the years.
How to Get Involved
The general public can find further information about air quality within Renfrewshire on the
Renfrewshire Council website https://www.renfrewshire.gov.uk/airquality.

Page 10

Renfrewshire Council
LAQM Annual Progress Report 2023 iv
Table of Contents
Executive Summary: Air Quality in Our Area ................................................................... i
Air Quality in Renfrewshire Council .............................................................................................. i
Actions to Improve Air Quality ...................................................................................................... i
Local Priorities and Challenges ................................................................................................... ii
How to Get Involved ....................................................................................................................iii
1 Local Air Quality Management ................................................................................... 1
2 Actions to Improve Air Quality ................................................................................... 2
2.1 Air Quality Management Areas .............................................................................................. 2
2.2 Cleaner Air for Scotland 2 ...................................................................................................... 3
2.2.1 Placemaking – Plans and Policies .................................................................................................... 3
2.2.2 Transport – Low Emission Zones (LEZs) ......................................................................................... 4
2.3 Implementation of Air Quality Action Plan(s) and/or measures to address air quality ............. 5
3 Air Quality Monitoring Data and Comparison with Air Quality Objectives .......... 16
3.1 Summary of Monitoring Undertaken .................................................................................... 16 
Automatic Monitoring Sites ...................................................................................................... 16 
Non-Automatic Monitoring Sites .............................................................................................. 16 
Other Monitoring Activities ....................................................................................................... 17
3.2 Individual Pollutants ............................................................................................................. 23
3.2.1 Nitrogen Dioxide (NO2) ................................................................................................................... 23
3.2.2 Particulate Matter (PM10) ................................................................................................................ 24
3.2.3 Particulate Matter (PM2.5) ............................................................................................................... 24
3.2.4 Sulphur Dioxide (SO2) .................................................................................................................... 25
3.2.5 Carbon Monoxide, Lead and 1,3-Butadiene ................................................................................... 25
4 New Local Developments ......................................................................................... 26
4.1 Road Traffic Sources ...................................................................................................... 26
4.2 Other Transport Sources ..................................................................................................... 27
4.3 Industrial Sources ................................................................................................................ 27
4.4 Commercial and Domestic Sources ..................................................................................... 27

Page 11

Renfrewshire Council
LAQM Annual Progress Report 2023 v
4.5 New Developments with Fugitive or Uncontrolled Sources .................................................. 27
5 Planning Applications ............................................................................................... 28
6 Conclusions and Proposed Actions ........................................................................ 29
6.1 Conclusions from New Monitoring Data ............................................................................... 29
6.2 Conclusions relating to New Local Developments ............................................................... 29
6.3 Proposed Actions ................................................................................................................ 30
Appendix A: Monitoring Results .................................................................................... 31
Appendix B: Full Monthly Diffusion Tube Results for 2022 ......................................... 50
Appendix C: Supporting Technical Information / Air Quality Monitoring Data QA/QC
........................................................................................................................................... 53
New or Changed Sources Identified Within Renfrewshire Council During 2023 ......................... 53
Additional Air Quality Works Undertaken by Renfrewshire Council During 2023........................ 53
QA/QC of Diffusion Tube Monitoring ......................................................................................... 53
Diffusion Tube Annualisation ................................................................................................................... 54
Diffusion Tube Bias Adjustment Factors ................................................................................................. 54
NO2 Fall-off with Distance from the Road ................................................................................................ 55
QA/QC of Automatic Monitoring ................................................................................................ 55
PM10 and PM2.5 Monitoring Adjustment ................................................................................................... 56
Automatic Monitoring Annualisation ........................................................................................................ 56
NO2 Fall-off with Distance from the Road ................................................................................................ 56
Glossary of Terms ........................................................................................................... 59
References ....................................................................................................................... 61

Page 12

Renfrewshire Council
LAQM Annual Progress Report 2023 vi
List of Tables
Table 1.1 – Summary of Air Quality Objectives in Scotland ................................................. 1
Table 2.1 – Declared Air Quality Management Areas .......................................................... 2
Table 2.2 – Progress on Measures to Improve Air Quality................................................... 8 
Table A.1 – Details of Automatic Monitoring Sites ............................................................. 31
Table A.2 – Details of Non-Automatic Monitoring Sites ..................................................... 32
Table A.3 – Annual Mean NO2 Monitoring Results (µg/m3) ............................................... 36
Table A.4 – 1-Hour Mean NO2 Monitoring Results, Number of 1-Hour Means > 200µg/m3
........................................................................................................................................... 46
Table A.5 – Annual Mean PM10 Monitoring Results (µg/m3) .............................................. 46
Table A.6 – 24-Hour Mean PM10 Monitoring Results, Number of PM10 24-Hour Means >
50µg/m3 ............................................................................................................................. 48
Table A.7 – Annual Mean PM2.5 Monitoring Results (µg/m3) ............................................. 48 
Table B.1 – NO2 2022 Monthly Diffusion Tube Results (µg/m3) ......................................... 50 
Table C.1 – Bias Adjustment Factor .................................................................................. 55
Table C.2 – Annualisation Summary (concentrations presented in µg/m3) ........................ 57
Table C.3 – Local Bias Adjustment Calculations ............................................................... 57
Table C.4 – NO2 Fall off With Distance Calculations (concentrations presented in µg/m3) 58 
List of Figures
Figure 1. Map of Automatic Monitoring Sites ..................................................................... 18
Figure 2. Map of Non-Automatic Monitoring Sites in Renfrew ........................................... 19
Figure 3. Map of Non-Automatic Monitoring Sites in Paisley ............................................. 20
Figure 4. Map of Non-Automatic Monitoring Sites in Kilbarchan and Johnstone ............... 21
Figure 5. Map of Non-Automatic Monitoring Sites in Lochwinnoch .................................... 22
Figure 6. Annual Mean NO2 Concentrations at Automatic Monitoring Sites ...................... 39

Page 13

Renfrewshire Council
LAQM Annual Progress Report 2023 vii
Figure 7. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Urban
Centre, Urban Background, Kerbside) ............................................................................... 40
Figure 8. Annual mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside
1) ....................................................................................................................................... 41
Figure 9. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside
2) ....................................................................................................................................... 42
Figure 10. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside
3) ....................................................................................................................................... 43
Figure 11. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside
4) ....................................................................................................................................... 44
Figure 12. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside
5) ....................................................................................................................................... 45
Figure 13. Annual Mean PM10 Concentrations at Automatic Monitoring Sites ................... 47
Figure 14. Annual Mean PM2.5 Concentrations at Automatic Monitoring Sites ................. 49

Page 14

Renfrewshire Council
LAQM Annual Progress Report 2023 1
1 Local Air Quality Management
This report provides an overview of air quality in Renfrewshire Council during 2023. It
fulfils the requirements of Local Air Quality Management (LAQM) as set out in Part IV of
the Environment Act (1995), as amended by the Environment Act (2021), and the relevant
Policy and Technical Guidance documents. 
The LAQM process places an obligation on all local authorities to regularly review and
assess air quality in their areas, and to determine whether or not the air quality objectives
are likely to be achieved. Where an exceedance is considered likely the local authority
must declare an Air Quality Management Area (AQMA) and prepare an Air Quality Action
Plan (AQAP) setting out the measures it intends to put in place in pursuit of the objectives.
This Annual Progress Report (APR) summarises the work being undertaken by
Renfrewshire Council to improve air quality and any progress that has been made.
Table 1.1 – Summary of Air Quality Objectives in Scotland
Pollutant Air Quality Objective
Concentration
Air Quality
Objective
Measured as
Date to be
Achieved
by
Nitrogen
dioxide (NO2)
200 µg/m3 not to be exceeded
more than 18 times a year 1-hour mean 31.12.2005
Nitrogen
dioxide (NO2) 40 µg/m3 Annual mean 31.12.2005
Particulate
Matter (PM10)
50 µg/m3, not to be exceeded
more than 7 times a year 24-hour mean 31.12.2010
Particulate
Matter (PM10) 18 µg/m3 Annual mean 31.12.2010
Particulate
Matter (PM2.5) 10 µg/m3 Annual mean 31.12.2021
Sulphur dioxide
(SO2)
350 µg/m3, not to be exceeded
more than 24 times a year 1-hour mean 31.12.2004
Sulphur dioxide
(SO2)
125 µg/m3, not to be exceeded
more than 3 times a year 24-hour mean 31.12.2004
Sulphur dioxide
(SO2)
266 µg/m3, not to be exceeded
more than 35 times a year 15-minute mean 31.12.2005
Benzene 3.25 µg/m3 Running annual
mean 31.12.2010
1,3 Butadiene 2.25 µg/m3 Running annual
mean 31.12.2003
Carbon
Monoxide 10.0 mg/m3 Running 8-Hour
mean 31.12.2003

Page 15

Renfrewshire Council
LAQM Annual Progress Report 2023 2
2 Actions to Improve Air Quality
2.1 Air Quality Management Areas
Air Quality Management Areas (AQMAs) are declared when there is an exceedance or
likely exceedance of an air quality objective. After declaration, the authority must prepare
publish and implement an Air Quality Action Plan (AQAP) within the shortest possible time
and no later than 12 months of the date of AQMA Designation Order. The AQAP must set
out measures the local authority intends to put in place in pursuit of the objectives within
the shortest possible time. Measures should be provided with milestones and a final date
for completion. The action plan itself should have a timescale for completion and for
revocation of the AQMA. Where measures to reduce air pollution may require a longer
timescale an action plan shall be reviewed and republished within five years of initial
publication and then five-yearly thereafter.
A summary of AQMAs declared by Renfrewshire Council can be found in Table 2.1.
Further information related to declared or revoked AQMAs, including maps of AQMA
boundaries are available online at
https://www.scottishairquality.scot/laqm/aqma?id=382#!/la/462.
Table 2.1 – Declared Air Quality Management Areas
AQMA
Name
Pollutants
and Air
Quality
Objectives
City /
Town Description Action Plan
Paisley
Town
Centre
(PTC)
NO2 annual
mean
NO2 1-hour
mean
PM10 24-
hour mean
Paisley
An area encompassing
a large part of central
Paisley and extending a
short distance along
some radial roads
Renfrewshire Council Air
Quality Action Plan
2019:
http://www.renfrewshire
.gov.uk/airquality
Johnston
e High
Street
(JHS)
NO2 annual
mean
Johnst
one
From the junction of
High Street and
Peockland Place; thence
along High Street to the
junction of Barrochan
Road and Napier Street
Renfrewshire Council Air
Quality Action Plan
2019:
http://www.renfrewshire
.gov.uk/airquality
Renfrew
Town
Centre
(RTC)
NO2 annual
mean
NO2 1-hour
mean
Renfre
w
From the junction of
Paisley Road, Inchinnan
Road, Hairst Street and
Glebe Street; thence
Renfrewshire Council Air
Quality Action Plan
2019:

Page 16

Renfrewshire Council
LAQM Annual Progress Report 2023 3
AQMA
Name
Pollutants
and Air
Quality
Objectives
City /
Town Description Action Plan
along Glebe Street to
property number 4
Glebe St; thence along
Paisley Road to the
junction of Donaldson
Drive; thence along
Inchinnan Road to the
junction of Longcroft
Drive; thence along
Hairst Street to the
junction with Canal
Street and High Street;
thence along Canal St to
the junction with Ferry
Road
http://www.renfrewshire
.gov.uk/airquality
2.2 Cleaner Air for Scotland 2
Cleaner Air for Scotland 2 – Towards a Better Place for Everyone (CAFS2) is Scotland’s
second air quality strategy. CAFS2 sets out how the Scottish Government and its partner
organisations propose to further reduce air pollution to protect human health and fulfil
Scotland’s legal responsibilities over the period 2021 – 2026. CAFS2 was published in
July 2021 and replaces Cleaner Air for Scotland – The Road to a Healthier Future (CAFS),
which was published in 2015. CAFS2 aims to achieve the ambitious vision for Scotland "to
have the best air quality in Europe". A series of actions across a range of policy areas are
outlined, a summary of which is available on the Scottish Government’s website. 
Progress by Renfrewshire Council against relevant actions for which local authorities are
the lead delivery bodies within this strategy is demonstrated below.
2.2.1 Placemaking – Plans and Policies
Local authorities with support from the Scottish Government will assess how effectively air
quality is embedded in plans, policies, City Deals and other initiatives, and more generally
in cross departmental working, identifying and addressing evidence, skills, awareness and
operational gaps.

Page 17

Renfrewshire Council
LAQM Annual Progress Report 2023 4
Renfrewshire Council has relevant initiatives in Transport and Climate Change, as detailed
below:
Transport – Avoiding Travel – T1
Renfrewshire Council has included a measure within their 2019 AQAP to develop a
Corporate Travel Plan (Measure 14, Table 1.3) together with ongoing detailed reviews of
transport plans within Paisley and Johnstone. A draft travel plan and travel directories
were prepared and provided by a consultant at the end of 2019. The steering group had
been planned for spring 2020 to finalise the travel plan, however due to the pandemic, this
has now been put on hold. It is not yet known when the steering group may be
established, as the pandemic has had a significant effect on staff work habits with the
majority of non-frontline workers still working from home.
The council has recently created and filled a permanent Active Travel Officer post within
the councils Transportation and Development team. The post was created to assist
delivery on a wide range of priority active travel and public transport infrastructure related
projects within Renfrewshire as well as develop and deliver a Renfrewshire Active Travel
Strategy. This will be aimed at all residents, business etc. across Renfrewshire and not
solely for staff as per the Corporate Travel Plan. 
Climate Change – Effective co-ordination of climate change and air quality policies to
deliver co-benefits – CC2
The Scottish Government expects any Scottish local authority which has or is currently
developing a Sustainable Energy Action Plan to ensure that air quality considerations are
covered. In addition to the Council’s 2014 Carbon Management Plan, and as discussed in
the Council’s AQAP, Renfrewshire Council commissioned a study during 2019 to review
the AQAP measures in line with CAFS objectives. As such, it was found that within the 16
AQAP measures listed, the decarbonising transport and low emission vehicle use aspects
were strongly aligned with the CAFS strategy.
2.2.2 Transport – Low Emission Zones (LEZs)
Local authorities working with Transport Scotland and SEPA will look at opportunities to
promote zero-carbon city centres within the existing Low Emission Zones (LEZs) structure.

Page 18

Renfrewshire Council
LAQM Annual Progress Report 2023 5
Renfrewshire Council has no LEZs established within the Local Authority area.
Renfrewshire Council undertook a National Low Emission Framework Stage 1 Screening
Appraisal as part of the 2020 APR and determined that the proposed air quality measures
were sufficient as declared AQMAs either reported no exceedances in 2019, or LEZs were
not considered appropriate due to AQMAs being restricted along a stretch of road. This
position is not considered to have changed since the appraisal and LEZs remain to not be
considered appropriate in Renfrewshire.
2.3 Implementation of Air Quality Action Plan(s) and/or
measures to address air quality
In order to ensure that local authorities implement the measures within an action plan by
the timescales stated within that plan, the Scottish Government expects authorities to
submit updates on progress through the APR process. Renfrewshire Council has taken
forward a number of measures within the action plan during the current reporting year of
2022 in pursuit of improving local air quality and meeting the air quality objectives within
the shortest possible time. Details of all measures completed, in progress or planned are
set out in Table 2.2. More detail on these measures can be found in the Air Quality Action
Plan relating to each AQMA.
Key completed measures for this reporting year are: 
• Measure 1 – Gaia Works are now substantially complete and the completed
infrastructure is in use;
• Measure 1 – Two AMIDS (Advanced Manufacturing Innovation District Scotland)
buildings are now complete and occupied;
• Measure 15 – Construction of Paisley to Renfrew and Inchinnan Active Travel
Routes; and
• Measure 16 – Cycle2Work Scheme open from 24 March 2022 to 17 June 2022. 
New measures for this reporting year that were not included within the 2019 AQAP but will
be detailed in the 2024 AQAP update include the following:
• Better Points active travel incentive scheme ran for 12 months from Spring
2022. Headline results include:
• 654 users out of 917 replaced their last car journey with an active travel
option;

Page 19

Renfrewshire Council
LAQM Annual Progress Report 2023 6
• 75.9% of respondents agreed they used the car less than usual to get from
place to place;
• 73% of respondents agreed they would likely use the car less to get from
place to place in the future;
• 75.2% of respondents said they are more likely to walk or cycle to get from
place to place in the future;
• 66.4% of respondents said they are likely to use public transport to get from
place to place in future; and
• 76.7% of respondents said that the scheme has made them leave the car at
home.
• Living Streets WOW project is a year-round walk to school challenge undertaken
within Renfrewshire in 2022/23 which rewards children and young people with
badges for choosing an active travel method in going to school. Headline results
include:
• 6455 children engaged with the project; and
• 259,208 sustainable and active travel journeys undertaken.
• Beat the Street empowers communities to increase activity levels and improve
health with a walking and cycling competition where participants tap their Beat
the Street cards on Beat Boxes on lampposts to record distances walked or
cycled. Headline results for 2021/22:
• 6313 players; 
• 37% activity undertaken during typical commute travel periods thus the game
encouraged people to use active modes of travel to get to school and work; 
• 2% decrease in car proportion travelling to school by car each day following
the scheme; 
• 68% players reported walking more and 11% reported cycling or wheeling
more; and
• 79% players said they were likely or very likely to continue walking, cycling or
wheeling for travel in future.
• Scootability is a training programme aimed at P3/4 allowing children to learn the
skills and knowledge to ride safely. 5 primary schools took part in 2022/23 and
292 pupils completed training.
Progress on the following measures has been slower than expected due to:

Page 20

Renfrewshire Council
LAQM Annual Progress Report 2023 7
• Measure 1 – Effective acquisition of land required to implement the AMIDS
South project is considered a potential barrier to implementation.
• Measure 6 – Phase 3 is ongoing but delayed due to the impact the pandemic
has had on the number of staff working from home.
• Measure 9 – Funding has been secured for PTC transportation improvements
and a prioritised programme of works has been identified but modelling has not
yet been undertaken and a timeline for implementation has not yet been
decided.
• Measure 14 – Council steering group established to finalise the travel plan has
been put on hold since Spring 2020 due to the pandemic.
Renfrewshire Council expects the following measures to be completed over the course of
the next reporting year: 
• Measure 3 - £2.2 million set aside for purchase of new fleet vehicles in 2023/24.
• Measure 5 – new fleet tracking telematic system installed from 31st May 2023.
• Measure 11 – Further meeting will be undertaken with local bus operators as
part of the 2024 update to the AQAP.
• Measure 15 – Refresh of local transport strategy and active travel
strategy/action plan.
• Renfrewshire Council will be commencing a full review of the 2019 Renfrewshire
Council AQAP this summer in order to have the review completed by next
Spring which is in accordance with the new requirements of the Scottish
Government’s Policy Guidance 2023 whereby the Scottish Government now
requires all action plans are reviewed and republished on a five-yearly cycle
from date of initial publication, which will be March 2024. This process will
involve consultation with steering group members and a full update of the action
plan measures.

Page 21

Renfrewshire Council
LAQM Annual Progress Report 2023 8
Table 2.2 – Progress on Measures to Improve Air Quality
No. Measure Category
Expected /
Actual
Completion
year
Measure
Status Funding Status Key Milestones Progress Barriers to
Implementation
1
Glasgow City Region City
Deal Projects
- Clyde Waterfront &
Renfrew Riverside Project
(CWRR)
- Glasgow Airport
Investment Area Project
(GAIA)
UK Government Levelling
Up Fund Project
- Advanced Manufacturing
Innovation District Scotland
(AMIDS) South 
Transport
Planning and
Infrastructure
Traffic
Management
Promoting
Travel
Alternatives
CWRR –
expected
completion early
2025
GAIA –
completed 2022
AMIDS South –
expected
completion
March 2025 
CWRR – in
progress
GAIA –
completed
AMIDS South
– in progress 
Partially funded.
UK Government funding 90% of
the capital costs of the project.
Renfrewshire council
contribution is 10% of costs.
Government funding will be
unlocked in 5 yearly Gateway
Reviews. If the City Deal meets
agreed outputs and outcomes at
each review, the full £1 billion of
funding from the UK and
Scottish Governments will be
unlocked. 
CWRR
Nov 2018 – planning
consent granted
Autumn 2019 – tenders
published
Nov 2021 – Contract Start
Date
Early 2025 – Anticipated
construction completion.
GAIA
Nov 2017 – planning
consent granted
Spring 2019 – tender
contracts awarded
June 2019 – start of
construction
March 2022 – Works
opened to the public.
AMIDS South
March 2023 – planning
consented
Nov 2022 to Oct 2023 –
Contractor procurement
and land acquisition
Nov 2023 to March 2025 –
Construction period.
CWRR site works are
progressing, and off-site
manufacture of the bridge
structure underway. It is
anticipated that the project will
open to the public in early
2025.
GAIA Works are now
substantially complete with
rectification of defects on-
going. The completed
infrastructure is in use.
The GAIA project has been
the catalyst for AMIDS which
is now progressing well, with
the first two buildings complete
and occupied.
Detailed design for AMIDS
South is progressing in parallel
with landowners and
stakeholder liaison.
AMIDS South –
Effective
acquisition of the
land required to
implement the
project is
considered a
potential barrier
to
implementation

Page 22

Renfrewshire Council
LAQM Annual Progress Report 2023 9
2
Upgrades & Improvements
to the Council’s Urban
Traffic Control (UTC)
system
Replacement of UTC system
with externally hosted UTC-
X system from Yunex with
guaranteed updates for the
next 10 years. 
Traffic
Management
(UTC,
congestion
management)
Expected
completion year
- 2023
In progress Not funded (from external
sources).
Original defective loops
repaired/ replaced in June
2017. Validation of traffic
signals & PROM updates
completed in November
2017.
Spring 2023 - 66 sites’
communications improved
to prevent dropouts and
minimise frequency of
traffic delay.
Feasibility of extending
UTC control to Johnstone
being pursued but will be
dependent on funding.
66 sites across 30 junctions
throughout the council area
have been upgraded to an
externally hosted UTC system
between 2020 and 2023. This
is then followed with a 10-year
maintenance contract at these
sites to ensure signals remain
as efficient as possible.
The work to replace life-
expired traffic signals
continues.
4G communications between
the signals and the system are
being superseded by
connections to the council’s
fibre network and priority
junctions continue to have
their equipment replaced as
needs and funding arise 
3
Council Fleet
Improvements
- Continue to improve the
standard of fleet
Promoting
Low
Emission
Transport
(Company
vehicle
procurement -
Prioritising
uptake of low
emission
vehicles)
Ongoing.
There is an
annual vehicle
replacement
programme
(VRP) whereby
vehicles at the
end of their
service life are
replaced with an
improved EURO
standard or an
electric
alternative.
In progress
Not funded (from external
sources).
Funded via the Council’s Vehicle
Replacement Capital
Programme.
Through the VRP programme
we are always looking to invest
in our fleet – 2.2m has been set
aside for 2023-24 for purchase
of new fleet vehicles, this will
incorporate replacing older fossil
vehicles with newer fleet
vehicles with better emission
standards
The Council fleet consists
of approx 500 vehicles of
which >70% are of EURO
V or VI standard.
We have recently
introduced HVO as an
alternative fuel for some of
our fleet – and are looking
to expand the project to
come in line with more
vehicles on the fleet.
Ongoing.
The Council will continue to
improve the standard of fleet
and introduce greener vehicles
where opportunities and
funding permits.
There are approx 80 HGV
vehicles, 32 of which are
EURO VI standard with the
remaining 48 being of EURO
V standard. The EURO V
HGVs are prioritised for
replacement with EURO VI
vehicles. 
4
Council Fleet
Improvements
- Increase numbers of
electric vehicles (EVs) &
associated charging
infrastructure
Promoting
Low
Emission
Transport
(Company
vehicle
procurement
Ongoing.
The Council will
continue to
introduce EVs &
charging points
where
In progress
Funded mainly via the Council’s
Replacement Vehicle
Programme and Transport
Scotland’s Switched On Fleets
funding.
First Council EVs and
charging points purchased
and installed in 2012.
The Council now have 115
EVs (cars/vans) in the
Contract awarded for
£250,000 investment in
Underwood Road Waste
Depot during 2023 with a new
2.3MVA power supply and
transformer to support the
further expansion of EV

Page 23

Renfrewshire Council
LAQM Annual Progress Report 2023 10
- EV Fleet Strategy
Feasibility Study
prioritising
uptake of low
emission
vehicles &
Procuring
alternative
refuelling
infrastructure
to promote low
emission
vehicles, EV
recharging)
opportunities
and funding
permits. As
technology
evolves the
Council will
extend the EV
Fleet Strategy to
include all
vehicles
including HGVs
and buses.
fleet or 27% of overall
fleet.
There are now 124 council
operated publicly available
charging points in
Renfrewshire and 89
charging bays for council
vehicles across 14 council
depots /buildings.
charging infrastructure for light
vans, HGVs and refuse
collection vehicles
In addition to pool cars, the
council have 10 pool bikes for
staff to use for business travel
as part of the Business Travel
Hierarchy.
5
Masternaut Connect Fleet
Telemetric System
- Upgrade of fleet tracking
telemetric system fitted to all
Council vehicles to optimise
utilisation of fleet. The
tracking system allows close
monitoring of movement and
operating status of all fleet
vehicles. 
Freight and
Delivery
Management
(Route
management
plans/
Strategic
routing
strategy for
HGV's)
Vehicle Fleet
Efficiency
(other)
Masternaut
Connect
installed/
completed 2017.
However new
fleet tracking
system being
installed 31st
May 2023
In progress Not funded (from external
sources).
Masternaut was originally
installed in all council
vehicles in 2009-10.
This was upgraded to a
newer Masternaut
Connect version early
2017 which provided an
easier reporting system
and focused in more detail
on driver behaviour,
vehicle utilisation etc.
A new fleet tracking
system is being installed
from 31st May 2023
System operational from April
2017.
Dedicated member of staff
employed from Autumn 2018.
Masternaut is getting replaced
on the 31st of May and a new
supplier - UK Telematics - will
be the fleet tracker system for
the council. This will provide
real time, web-based asset
tracking system using GPS.
This should improve fuel
economy and provide
departments with more in-
depth reports about driver
behaviour when in a fleet
vehicle. 
6
Renfrewshire Council
Sustainable Travel
Planning Scheme
- Supply high mileage users
with council cars and
introduce a fleet of pool
vehicles to replace business
mileage for employees.
- Pool bikes are available for
staff to use to carry out
Council business.
Alternatives
to Private
Vehicle Use
(Car clubs/
sharing
schemes)
Promoting
Low
Emission
Transport
Ongoing
Phase 1 of
scheme -
introduced Oct
2018 and now
complete.
Phase 2 -
introduced Jan
2019 and
complete.
Phase 3 –
ongoing but
delayed,
Funded.
The majority of funding for the
EVs has come from Transport
Scotland Switched On Fleet
funding.
Phase 1 of the scheme
was introduced in 2018.
This involved 35 vehicles
being available for staff
use within Environmental
Services. Staff required to
use the fleet cars in
replacement of their own
cars.
Phase 2 was introduced
Jan 2019 and involved
pool cars being available
for all other relevant staff
Currently, there are 47 electric
pool vehicles with 23 charger
units located in Renfrewshire
HQ. 300,000 miles have been
travelled by pool vehicles
since October 2018.
Phase 3 – locating pool
vehicles at other council
buildings has started with EV
charging units now installed at
HCSP office in Paisley for
Care at Home teams.  Further

Page 24

Renfrewshire Council
LAQM Annual Progress Report 2023 11
-Encouraging staff to walk or
use public transport where
appropriate to carry out
Council business. 
mainly due to
the impact that
the pandemic
has had on
increased
numbers of
staff working
from home.
There is
currently not
the need for
significant
numbers of
pool cars to be
stationed at
other council
buildings.
members across
Renfrewshire House HQ.
By the end of 2019 all pool
cars based at
Renfrewshire House were
EVs and over 300 HQ staff
are now using pool
vehicles.
Phase 3 involves locating
pool vehicles at other
Council buildings.
EVs were delivered March
2021.
8
Renfrewshire’s Local
Transport Strategy
- Publication of a new
Local Transport Strategy
(LTS) to replace the
Council’s 2007 LTS will be
undertaken.
Policy
Guidance and
Development
Control
(Other policy)
New
Renfrewshire
LTS – expected
completion
2024/25
In progress Not funded (from external
sources).
The Council’s 2007 LTS
set out key objectives and
vision for transport over
10-20 yrs.
A refresh of this 2007 LTS
was undertaken in Feb
2017.
A new Renfrewshire LTS
will be prepared following
the policy guidelines in the
National Transport
Strategy 2020 and the
Regional Transport
Strategy 2023, which is
currently awaiting Scottish
Ministers approval.
New Renfrewshire LTS is
currently out to tender for
consultancy support. A
detailed scope of the council’s
requirements includes
consideration of its plan for net
zero emissions by 2030. 
9
Paisley Town Centre
Transportation
Improvements
- Undertake a feasibility
study of potential transport
interventions for Paisley
town centre e.g. reinstating
two-way traffic flows,
amending key junctions,
Policy
Guidance and
Development
Control
(Other policy)
Traffic
Management
(Congestion
management)
To be confirmed
following further
modelling
In progress
The feasibility study has been
funded via SPT.
Funding of any future proposed
measures will be subject to
availability of capital funding with
the potential of funding from
external partners also e.g. SPT.
Procurement process for
feasibility study awarded
2017.
2019 - first draft of the
feasibility study produced
which establishes initial
proposals and reports on
potential areas of
improvement, their
Ongoing. The proposed
options are intentionally high
level, providing ideas of key
potential transport
interventions for Paisley.
Some of these measures will
now be developed from the
current concept phase taking
into account traffic modelling
and allowing for appropriate
Funding of
measures.

Page 25

Renfrewshire Council
LAQM Annual Progress Report 2023 12
review of lining & signage
and trial removal of certain
traffic lights on ring road.
technical feasibility,
benefits and deliverability.
The development of a
Transport Strategy for
Paisley Town Centre
(PTC) was identified as a
key action within the
Renfrewshire LTS and
PTC 2016-2026 Action
Plan. The conclusions of
this feasibility study may
feed into any PTC
Transport Strategy.
The conclusions will then
be subject to senior
management review,
Board approval and
consultation with
stakeholders before any
decisions are made on
potential action measures.
Implementation of final
proposals will thereafter
be subject to identification
of funding streams.
assessment, design and
eventual delivery.
Whilst a prioritised programme
of works has been identified
for the short to medium term,
further modelling has yet to be
undertaken and a timeline for
implementation of the
measures yet to be decided.
Some long-term improvements
are also identified in line with
the PTC 10yr Action Plan, but
these require further
investigation.
The draft feasibility study
details a programme of
phased interventions covering
the short, medium and long
term.
10
Johnstone Town Centre
Transportation
Improvements
Policy
Guidance and
Development
Control
(Other policy)
Traffic
Management
(Parking
enforcement
on Highway)
Temporary
measures have
been completed.
Permanent TRO
changes to be
pursued after
the
Renfrewshire
consolidated
digital TRO is
made in 2023.
In progress Not funded (from external
sources).
Yellow line restrictions and
bus stop
closures/relocations have
been carried out under
TTRO to enable a turning
facility for buses around
Houston Square.
Permanent TRO changes to
be pursued after the
Renfrewshire consolidated
digital TRO is made in 2023.
Consideration is being given to
Johnstone as an extension to
the UTC system to better link
and control signal junctions on
High Street.
.

Page 26

Renfrewshire Council
LAQM Annual Progress Report 2023 13
11 Improvements in the Bus
Fleet Standard
Vehicle Fleet
Efficiency
(Promoting
Low
Emission
Public
Transport)
Ongoing In progress
The purchase of these by the
operator has been aided by the
Scottish Ultra Low Emission Bus
Scheme.
An initial meeting was held
in April 2019 with the
management of the largest
bus operator in
Renfrewshire and staff
from Renfrewshire Council
to discuss the potential
improvements in bus
operations.
The operator has since
invested significantly in
their EV fleet brining in 23
EV buses at the end of
2021 and used for local
residential routes,
therefore improving
emissions locally. In
addition, EV charging
infrastructure has been
installed in Johnstone and
Inchinnan Depots.
Further engagement
required with other
operators.
Further meeting will be
undertaken with local bus
operators as part of the 2024
update to the Air Quality
Action Plan 
12
Vehicle Idling Awareness
Raising
- Regular targeted
campaigns to raise
awareness regarding idling
vehicles & air pollution.
Campaigns aimed at specific
categories of drivers or in
areas where vehicles idle
unnecessarily e.g. schools,
bus terminals, taxi ranks or
in response to complaints. 
Traffic
Management
(Anti-idling
enforcement)
Public
Information
(via other
mechanisms
Ongoing.
General idling
awareness
campaigns have
been ongoing
since 2011.
On hold Not funded (from external
sources).
A School Parking
Campaign was introduced
in April 2018 aimed at
road safety around
schools including safe
parking and an anti-idling
message.
Banners were erected at
school entrances and
every pupil received a
school parking pledge
leaflet which contained a
message regarding no
idling and encouraging
parents to sign up to safe
parking pledges around
schools.
By August 2019, all 49
Primary schools in
Renfrewshire were engaged in
the campaign.
Regarding the second phase
of the scheme, four primary
schools have been identified
to introduce an exclusion zone
in the streets around their
entrances as we aim to create
a safer, healthier school
environment for pupils. This
was due to commence in April
2020 but has been put on
hold. When it is next able to
commence, it will consist of a
six-month pilot scheme and
will introduce a part-time

Page 27

Renfrewshire Council
LAQM Annual Progress Report 2023 14
A second phase of the
campaign will consider the
closure of surrounding
roads around selected
primary schools. A
feasibility study for this
was undertaken in 2019.
vehicle exclusion zone at the
start and end of the school day
in some of the surrounding
streets of the four schools.
14 Renfrewshire Council
Corporate Travel Plan
Promoting
Travel
Alternatives
(Workplace
Travel
Planning)
Uncertain On hold Not funded (from external
sources).
Jan 2019 - Consultant
undertook site visits to
relevant council offices to
determine existing
facilities.
June 2019 - staff travel
survey issued to
determine current
transport modes etc. A
Roadshow event was also
held on Clean Air Day in
June 2019 at
Renfrewshire House.
Council staff and the
consultants were in
attendance to provide
travel planning advice, info
on pool cars, promotion of
the travel survey etc. Dr
Bikes and Scotrail were
also in attendance. A staff
commuter challenge was
undertaken in August
2019.
Nov 2019 – draft plan
provided by consultant
A draft travel plan and travel
directories were prepared and
provided by the consultant
during Nov 2019.
A council steering group
requires to be established to
finalise the plan and then
consultation of this with other
relevant services/
organisations. This had been
planned for spring 2020 but
has now been put on hold due
to the current pandemic. It is
unclear when this stage will
recommence.
Once the plan is published
and measures implemented a
second staff survey is planned
to determine any change in
travel behaviour.

Page 28

Renfrewshire Council
LAQM Annual Progress Report 2023 15
15
Renfrewshire Council
Cycle Strategy & Action
Plan 2016-2025
- The strategy contains a
Cycling Action Plan which
sets out a programme of
activities and network
interventions for the coming
ten years including upgrades
and expansion of cycle
networks, upgrading the
Council’s facilities for
cyclists and updating the
Council’s Travel Plan. 
Promoting
Travel
Alternatives
(Promotion of
cycling)
The Cycle
Strategy and
Action Plan runs
from 2016-2025.
Upgrades and
development of
the cycling
network is
ongoing as per
the strategy
priorities.
Council will
refresh Local
Transport
Strategy and
Active Travel
Strategy / Action
Plan during
2023/24.
In progress
Funding is applied for each
financial year from the Scottish
Government under the Cycling,
Walking and Safer Routes fund.
At least 36% of this fund must
be allocated to cycling including
for example infrastructure or
design works.
Renfrewshire used 49.4% of
CWSR budget in 2022/23 on
new infrastructure to encourage
cycling.  Projects included
construction of Paisley to
Renfrew and Inchinnan Active
Travel Routes.  Designs for
Erskine and Inchinnan Business
Park.
Sustrans funded projects
completed in 22/23 include NCN
improvements at Jennyswell,
Miller Street Johnstone.
The Cycle Strategy was
approved by Board in Dec
2016.
Measures contained within
the action plan will be
implemented dependant
on funding. 
There are several cycling
infrastructure projects which
are currently at concept design
/public consultation design
stage. The routes for these are
–
1.Southolm Roundabout
Erskine
2.Linside Avenue
3.Hawkhead Rd/ Glasgow Rd
junction
4.Linclive Roundabout
5. Inchinnan Business Park
6. Barnsford Road, Glasgow
Airport 
16
Renfrewshire Council Staff
Cycling Incentives
- Staff Cycle to Work
Scheme.
Cycle2Work
Council employees can
participate in this
Government approved
salary sacrifice scheme
which allows them to
purchase a bike and cycle
accessories with tax free
benefits.
Promoting
Travel
Alternatives
(Promotion of
cycling)
Ongoing In progress
Not funded (from external
sources).
Staff can apply for anything
between £100 and £2000
towards the cost of bike or cycle
accessories which could
potentially save up to £960 per
person.
The scheme was
previously open from 24
March 2022 to 17 June
2022.
Given its previous
popularity, the
Cycle2Work scheme was
reopened in April 2023
and is now available all
year round.
Scheme currently open for
uptake

Page 29

Renfrewshire Council
LAQM Annual Progress Report 2023  16
3 Air Quality Monitoring Data and Comparison with
Air Quality Objectives
3.1 Summary of Monitoring Undertaken 
Automatic Monitoring Sites
This section sets out what monitoring has taken place and how local concentrations of the
main air pollutants compare with the objectives.
Renfrewshire Council undertook automatic (continuous) monitoring at three sites during
2022. Table A.1 in Appendix A shows the details of the sites. National monitoring results
are available at https://www.scottishairquality.scot/data. Two sites monitor NO2 – REN1
Renfrew Cockels Loan and REN03 Renfrew Inchinnan Road, with the final site REN02
Renfrewshire Johnstone monitoring PM2.5 and PM10. No exceedances of the relevant air
quality objectives were recorded for any pollutant at any automatic monitoring station in
2022. No changes occurred to Renfrewshire Council’s automatic monitoring network in
2022.
Gordon Street automatic continuous monitor was decommissioned in November 2021.
The continuous monitor was old and required continual repairs and experienced issues
with its main electrical feed prior to closure. No exceedances had been recorded in Paisley
Town Centre for over five years, from either this continuous monitoring site or diffusion
tube monitoring sites. Therefore, it was decided that this site was to be decommissioned
rather than paying for continual repairs.
A map showing the location of the monitoring sites are provided in Figure 1. Further details
on how the monitors are calibrated and how the data has been adjusted are included in
Appendix C. 
Non-Automatic Monitoring Sites
Renfrewshire Council undertook non- automatic (passive) monitoring of NO2 at 60 sites
during 2022, including three triplicate sites. Table A.2 in Appendix A shows the details of
the sites.

Page 30

Renfrewshire Council
LAQM Annual Progress Report 2023 17
The following changes to Renfrewshire Council’s diffusion tube network occurred during
2022:
• Paisley88 was removed in August due to low return rates.
• Paisley95 was removed in February due to building works and was replaced by
Paisley106
• Johnstone106 was removed in March due to building works and was replaced by
Johnstone107
• Paisley104 was removed in June due to low return rates and was replaced by
Paisley108.
Of the 60 diffusion tube monitoring sites across Renfrewshire in 2022, following bias
adjustment and prior to the application of distance correction, there were no exceedances
of the NO2 annual mean air quality objective recorded in 2022.
Maps showing the location of the monitoring sites are provided in Figure 2 to Figure 5.
Further details on Quality Assurance/Quality Control (QA/QC) for the diffusion tubes,
including bias adjustments and any other adjustments applied (e.g. annualisation and/or
distance correction), are included in Appendix C. 
Other Monitoring Activities
No other monitoring activities have been undertaken.

Page 31

Renfrewshire Council
LAQM Annual Progress Report 2023 18
Figure 1. Map of Automatic Monitoring Sites

Page 32

Renfrewshire Council
LAQM Annual Progress Report 2023 19
Figure 2. Map of Non-Automatic Monitoring Sites in Renfrew

Page 33

Renfrewshire Council
LAQM Annual Progress Report 2023 20
Figure 3. Map of Non-Automatic Monitoring Sites in Paisley

Page 34

Renfrewshire Council
LAQM Annual Progress Report 2023 21
Figure 4. Map of Non-Automatic Monitoring Sites in Kilbarchan and Johnstone

Page 35

Renfrewshire Council
LAQM Annual Progress Report 2023 22
Figure 5. Map of Non-Automatic Monitoring Sites in Lochwinnoch

Page 36

Renfrewshire Council
LAQM Annual Progress Report 2023 23
3.2 Individual Pollutants
The air quality monitoring results presented in this section are, where relevant, adjusted
for annualisation and bias. Further details on adjustments are provided in Appendix C.
3.2.1 Nitrogen Dioxide (NO2)
Table A.3 in Appendix A compares the ratified and adjusted monitored NO2 annual mean
concentrations for the past five years with the air quality objective of 40 µg/m3.
For diffusion tubes, the full 2022 dataset of monthly mean values is provided in Appendix
B. There were six new sites established in 2022. Two diffusion tubes recorded a data
capture below 25% and therefore could not be annualised, this data is still shown in
(monthly table). Two diffusion tubes required annualisation as their data capture was
between 25% and 75% - Renfrew70 and Paisley108. Distance correction was undertaken
for two monitoring sites to estimate the concentration at the nearest receptor, with
calculations provided in Table C.4 – Paisley21 (triplicate site) and Renfrew48. All diffusion
tube monitoring locations in Renfrewshire Council achieved NO2 AQO compliance in 2022.
The highest concentration was 30.9 µg/m3 reported at Johnstone59 (High Street).
The observed downward trend in concentrations continues for the majority of monitoring
sites in 2022. Only seven sites experienced an increase in annual mean NO2
concentration from 2021 to 2022, compared to 49 sites experiencing a decrease, these
include REN03 – Renfrew Inchinnan Road automatic monitoring site and five diffusion
tube locations (Paisley2, Renfrew8, Renfrew17, Renfrew68, Renfrew70 and
Johnstone86). These increases range from +0.2 µg/m3 (at Johnstone86) to +2.3 µg/m3 (at
Paisley2). The decreases observed range from -0.6 µg/m3 (Paisley3, Paisley44 and
Paisley50) to -9.7 µg/m3 (Johnstone99). The remaining six sites were commissioned in
2023. Broadly, over the past five years, the majority of the diffusion tube monitoring sites
have shown a decrease in NO2 concentrations.
Table A.4 in Appendix A compares the ratified continuous monitored NO2 hourly mean
concentrations for the past five years with the air quality objective of 200 µg/m3, not to be
exceeded more than 18 times per year. No exceedances of the hourly mean air quality
objective for NO2 were recorded at any of the automatic monitoring sites. None of the diffusion
tube monitoring sites reported concentrations exceeding 60 µg/m3 which indicates that there
are no exceedances of the short-term air quality objective.

Page 37

Renfrewshire Council
LAQM Annual Progress Report 2023 24
3.2.2 Particulate Matter (PM10)
Table A.5 in Appendix A compares the ratified and adjusted monitored PM10 annual mean
concentrations for the past five years with the air quality objective of 18 µg/m3 showing the
ratified data and the ratified corrected data for REN02 (Renfrewshire, Johnstone).
following the Scottish Government Guidance Note in relation to the measurement of
ambient Particulate Matter (PM) and the LAQM reporting of measured concentrations
issued in May 2023. REN02 (Renfrewshire, Johnstone) has shown variations in
concentrations ranging from 10.2 µg/m3 to 16.3 µg/m3 for the ratified data and 11.3 µg/m3
to 17.9 µg/m3 in the ratified corrected data in the past five years. It should be noted that
the PM10 annual mean in 2020 and 2021 may have been impacted by COVID-19 related
lockdowns. The concentration in 2022 is a reduction of 0.8 – 0.9 µg/m3 compared to the
concentration recorded in 2021. This site has not recorded an exceedance of the annual
mean AQO since at least 2018.
Table A.6 in Appendix A compares the ratified continuous monitored PM10 daily mean
concentrations for the past five years with the air quality objective of 50 µg/m3, not to be
exceeded more than seven times per year. In 2022, REN02 (Renfrewshire Johnstone)
monitor reported no instances of 24-hour mean AQO exceedances. The 24-hour PM10
AQO was last exceeded in 2019 at REN02 – Renfrewshire Johnstone, this exceedance
has been attributed to localised buildings works undertaken in summer 2019. 
3.2.3 Particulate Matter (PM2.5)
Table A.7 in Appendix A compares the ratified and ratified corrected monitored PM2.5
annual mean concentrations for the past five years with the air quality objective of 10
µg/m3. In 2022, REN02 (Renfrewshire Johnstone) recorded a concentration of 6.1 µg/m3
or a corrected value of 6.5 µg/m3, these both show a slight increase (+0.1 µg/m3 and +0.2
µg/m3 respectively) compared to the concentration reported in 2021 (6.0 µg/m3 and 6.3
µg/m3 respectivey) but a reduction compared to the concentrations in 2018 and 2019 (7.3
µg/m3 and 7.9 µg/m3 for the ratified annual mean and 7.7 µg/m3 and 8.4 µg/m3 for the
corrected annual mean). However, it should be noted that the PM2.5 annual mean in 2020
and 2021 may have been impacted by COVID-19 related lockdowns. The site has not
recorded an exceedance of the annual mean AQO since at least 2018.

Page 38

Renfrewshire Council
LAQM Annual Progress Report 2023 25
3.2.4 Sulphur Dioxide (SO2)
No monitoring of SO2 was undertaken in 2022.
3.2.5 Carbon Monoxide, Lead and 1,3-Butadiene
No monitoring of Carbon Monoxide, Lead or 1,3-Butadiene was undertaken in 2022.

Page 39

Renfrewshire Council
LAQM Annual Progress Report 2023  26
4 New Local Developments
4.1 Road Traffic Sources
There are a number of developments within the local authority that may affect air quality,
The following developments that will affect road traffic sources are outlined below: 
• 22/0363/PP - Advanced Manufacturing Innovation District Scotland (AMIDS) South
project. Formation of 2 lane road, including a bridge crossing over the White Cart
Water, road and footpath upgrades and other associated works. Site Linking Inchinnan
Road and Harbour Road with Abercorn Street, Paisley. 
Two detailed air quality assessments were submitted for the application – the first being a
Preliminary Air Quality Assessment relating to the construction phase of the development
and then an Air Quality Addendum report for the operational phase road traffic impacts of
the scheme. Both reports were found to be satisfactory with mitigation measures
recommended in order to address potential dust issues from the construction phase.
Development approved January 2023. 
• 22/0345/PP - Erection of residential development comprising eighty flats and thirty-nine
dwellinghouses and formation of roads, infrastructure, and open space amenity. Site
On Southern Edge of Roundabout Junction with Laymoor Avenue, King's Inch Road,
Renfrew. 
A detailed air quality assessment was submitted with the application and found to be
satisfactory. The assessment concluded there were no significant effects on air quality as
a result of the development and therefore no requirement for mitigation measures.
Development approved April 2023.
• 22/0142/PP - Demolition of existing office building and erection of sixty-seven flats with
associated access, landscaping, open space and parking. 2 Lonend Paisley PA1 1SS.  
A simple air quality assessment was submitted with this application (in accordance with
relevant air quality and planning guidance based on the proposed number of traffic vehicle
movements). The assessment determines that further quantitative assessment of local air
quality is not required for the proposed future use of the scheme and that the air quality
impact of the development was not considered to be significant. Development approved
August 2022.

Page 40

Renfrewshire Council
LAQM Annual Progress Report 2023 27
• 21/1668/PP - Mixed Use Redevelopment of The Paisley Centre to include Class 1
(Shops), Class 2 (Financial, Professional & Other Services), Class 3 (Food & Drink),
Class 4 (Business), Class 7 (Hotel), Class 10 (Non-residential Institutions), Class 11
(Assembly & Leisure), Residential, Healthcare, Sui Generis (Hot Food Takeaway),
Demolition and Other Ancillary Uses (Planning Permission in Principle).  Paisley Centre
23 High Street Paisley PA1 2AF. This is a large-scale redevelopment of Paisley Town
Centre proposal which was approved March 2022. 
An air quality assessment has still to be received for this as the main application is a
masterplan with further supporting documents, such as air quality assessments, to be
submitted at the detailed planning application stage. 
4.2 Other Transport Sources
No planning applications were received by Renfrewshire Council during 2022 that
identified any new or significantly changed other transport sources.
4.3 Industrial Sources
A statutory consultation notification was received from SEPA in March 2022 of the
following:
• Pollution Prevention and Control (Scotland) Regulations 2012 Application for a New
Pollution Prevention and Control, Part B Permit Application by: Scottish Leather Group
Operations Ltd, Bridge of Weir
An air quality and odour dispersion modelling assessment was submitted with the
application. The air quality aspect of the assessment screened out any human health
concerns or impacts on vegetation and ecosystems as a result of the proposals.
4.4 Commercial and Domestic Sources
No planning applications were received by Renfrewshire Council during 2022 that
identified any new or significantly changed commercial and domestic sources.
4.5 New Developments with Fugitive or Uncontrolled Sources
No planning applications were received by Renfrewshire Council during 2022 that
identified any new developments with fugitive or uncontrolled sources.

Page 41

Renfrewshire Council
LAQM Annual Progress Report 2023 28
5 Planning Applications
The transport project within Paisley town centre known as AMIDS South was granted
planning approval in January 2023.  The project will create new routes between Paisley
town centre and the Advanced Manufacturing Innovation District Scotland (AMIDS) and
Glasgow Airport. The project involves a road bridge crossing the White Cart and an east-
west link road, all with accompanying walking and cycling options. This is 90% funded by
the UK Government Levelling Up Fund, with the rest paid by Renfrewshire Council.
Two detailed air quality assessments were submitted with the application, a Preliminary Air
Quality Assessment relating to the construction phase of the development and an Air
Quality Addendum report for the operational phase road traffic impacts of the scheme.
Both reports were found to be satisfactory. With regards to the operational phase, the
assessment determines that there will be no exceedances of air quality objectives as a
result of the development. There will also be a beneficial effect on annual mean NO2, PM10
and PM2.5 concentrations at the majority of locations assessed. 
In terms of public support for the development, more than 260 people completed a public
survey with their thoughts on the project proposals. The survey found:
• 90% would use the riverside route
• 86% confirmed that they would be more likely to walk or cycle here following the
infrastructure improvements
• More than two-thirds of people would use the walking and cycling route between
Gallowhill Road and Inchinnan Road
• 70% indicated that they would consider leaving the car at home and walk or cycle
instead
A contractor for the development should be appointed by the end of 2023 with completion
expected in 2025.
Further information on AMIDS South can be found at
https://www.renfrewshire.gov.uk/transport-links-amids-south-paisley

Page 42

Renfrewshire Council
LAQM Annual Progress Report 2023  29
6 Conclusions and Proposed Actions
6.1 Conclusions from New Monitoring Data
There were no AQO exceedances identified in Renfrewshire Council during 2022.
Historically, the Renfrew 8 diffusion tube monitoring site has exceeded the annual mean
NO2 AQO however in 2021 the reported concentration was 29.8 µg/m3 and so this
monitoring site fell below the AQO for the first time in at least five years. In 2022, the
reported concentration was 30.2 µg/m3 and so still fell significantly below the AQO.
89% of existing monitoring sites recorded a decrease in annual mean NO2 concentrations
from 2021 to 2022. The remaining sites experienced an increase in NO2 concentrations,
including the REN03 Renfrew Inchinnan Road automatic monitoring site and five diffusion
tube monitoring sites. 
PM10 annual mean concentrations at REN02 – Renfrewshire Johnstone decreased from
2021 to 2022 by 0.8 µg/m3 or by 0.9 µg/m3 for the corrected annual mean concentrations.
REN02 – Renfrewshire Johnstone also records PM2.5 and experienced a small increase
(+0.1 μg/m3 for the ratified annual mean concentrations or +0.3 µg/m3 for the corrected
annual mean concentrations) from 2021 to 2022, both pollutants monitored at REN02
recorded concentrations below their respective annual mean AQOs. 
6.2 Conclusions relating to New Local Developments
Any new developments that are likely to impact local air quality, or potentially introduce
new receptors into areas of poor air quality, have been adequately assessed during the
planning process.
No planning applications were received by Renfrewshire Council in 2022 that identified
any new or significantly changed Non-Road, Industrial, Commercial or Domestic Sources
or developments with fugitive or uncontrolled sources that had any human health concerns
or impacts on vegetation or ecosystems.
The air quality impacts were assessed to be not significant for two Road Traffic source
planning applications submitted to Renfrewshire Council. The planning application reports
relating to AMIDS South project were found to be satisfactory with construction phase dust

Page 43

Renfrewshire Council
LAQM Annual Progress Report 2023 30
mitigation measures. Renfrewshire Council are still awaiting an air quality assessment for
the Mixed Use Redevelopment of Paisley Centre to be submitted.
6.3 Proposed Actions
Renfrewshire Council’s proposed actions following the publication of the 2023 APR are as
follows:
• Progress with the significant new road and cycle infrastructure projects which
are part of the City Deals and AMIDS South projects;
• Publication of a new Renfrewshire Local Transport Strategy and development of
a Paisley Town Centre Transport Strategy;
• Continuation with the upgrade and development of the cycling network as per
the Renfrewshire Council Cycle Strategy priorities;
• Improvement of the council’s fleet, funded via the Council’s Vehicle
Replacement Capital Programme. £2.2 million has been set aside for the VRC
Programme in 2023-24 for the purchase of new fleet vehicles. This includes the
replacement of older fossil vehicles with newer fleet vehicles with better
emission standards and the introduction of HVO as an alternative fuel for some
of the fleet; 
• Reopening the Cycle2Work scheme in April 2023 and keeping it available for
the full financial year;
• Upgrading fleet tracking telemetric system fitted to all Council vehicles to
optimise utilisation of fleet. This will be completed by end of May 2023;
• Refresh the local transport strategy and active travel strategy/action plan;
• Full review of the 2019 Renfrewshire Council AQAP commencing summer 2023
in order to have the review completed by next Spring which is in accordance
with the new requirements of the Scottish Government’s Policy Guidance 2023
whereby the Scottish Government now requires all action plans are reviewed
and republished on a five-yearly cycle from date of initial publication, which will
be March 2024. This process will involve consultation with steering group
members and a full update of the action plan measures;
• Continue to monitor NO2, PM10 and PM2.5 at all relevant locations throughout
Renfrewshire; and
• Submit the 2024 Annual Progress Report.

Page 44

Renfrewshire Council
LAQM Annual Progress Report 2023  31
Appendix A: Monitoring Results
Table A.1 – Details of Automatic Monitoring Sites
Site ID Site Name Site Type X OS
Grid Ref
Y OS
Grid Ref
Pollutants
Monitored
In
AQMA?
Which
AQMA?
Monitoring
Technique
Distance to
Relevant
Exposure (m)
(1)
Distance to
kerb of
nearest road
(m) (2)
Inlet
Height
(m)
REN1 Renfrew,
Cockels Loan Roadside 250464 665933 NO, NO2 N Chemiluminescent 5 18 2.2
REN02 Renfrewshire,
Johnstone Roadside 242984 663178 PM2.5, PM10 Y – JHS FIDAS 200 0.5(3) 2.9 1.9
REN03
Renfrew,
Inchinnan
Road
Roadside 250567 667558 NO, NO2 Y – RTC Chemiluminescent 7.1 3.9 1.6
Notes:
(1) 0m if the monitoring site is at a location of exposure (e.g. installed on the façade of a residential property).
(2) N/A if not applicable.
(3) The distance of 0.5 m is to the façade of the closest building, these are commercial units at ground level and residential units on the
first floor

Page 45

Renfrewshire Council
LAQM Annual Progress Report 2023  32
Table A.2 – Details of Non-Automatic Monitoring Sites
Site ID Site Name Site Type X OS
Grid Ref
Y OS
Grid Ref
Pollutants
Monitored
In
AQMA?
Which
AQMA?
Distance to
Relevant
Exposure (m)
(1)
Distance to
kerb of
nearest road
(m) (2)
Tube co-
located with a
Continuous
Analyser?
Tube
Height
(m)
Paisley1 Gilmour
Street Urban Centre 248350 664082 NO2 Y – PTC 70 68 N 2.7
Paisley2 Oakshaw
Street
Urban
Background 247925 664052 NO2 Y – PTC 11 35 N 2.4
Paisley3 Lochfield
Drive
Urban
Background 249002 662138 NO2 N 8 1.5 N 2.4
Renfrew8 Inchinnan
Road Kerbside 250589 667547 NO2 Y – RTC  0.1 2.64 N 2.4
Renfrew17 Tanar Way Roadside 251524 666287 NO2 N 0 28 to M8 N 2.3
Paisley19 Linwood
Road Roadside 245701 663603 NO2 N 5 2.5 N 2.5
Johnstone20 High Street Kerbside 242675 663286 NO2 Y – JHS  0.45 1.4 N 2.3
Paisley21
Causeyside
Street
(triplicate)
Roadside 248316 663612 NO2 Y – PTC -6.3 9.9
(Causeyside St) N 2.3
Paisley33
76
Causeyside
Street
Roadside 248277 663524 NO2 Y – PTC 1.1 2.76 N 2.8
Paisley35
Old
Sneedon
Street
Roadside 248360 664272 NO2 Y – PTC 0.4 3.4 N 2.7
Paisley36 Caledonia
Street Roadside 247948 664774 NO2 Y – PTC 4.5 3.3 N 2.5
Renfrew40 Hairst Street Roadside 250763 667631 NO2 Y – RTC 0.25 6.18 N 2.5
Paisley43 Smithhills
Street (East) Roadside 248481 664154 NO2 Y – PTC 0 2.45 N 2.5
Paisley44 Love Street Roadside 248209 664474 NO2 Y – PTC 0.17 2.17 N 2.5
Renfrew45 Xscape Kerbside 251803 667365 NO2 N 18 2 N 2.5
Renfrew48 Glen Sax
Drive Roadside 251264 666217 NO2 N -22 45 to M8 N 2.6
Paisley50 Renfrew
Road Roadside 248985 665494 NO2 N 7 12 N 2.5

Page 46

Renfrewshire Council
LAQM Annual Progress Report 2023 33
Site ID Site Name Site Type X OS
Grid Ref
Y OS
Grid Ref
Pollutants
Monitored
In
AQMA?
Which
AQMA?
Distance to
Relevant
Exposure (m)
(1)
Distance to
kerb of
nearest road
(m) (2)
Tube co-
located with a
Continuous
Analyser?
Tube
Height
(m)
Renfrew52 Glasgow
Road Roadside 251515 666955 NO2 N 4 3 N 2.3
Renfrew56 Paisley
Road Roadside 250579 667488 NO2 Y – RTC 3.45 4.5 N 2.4
Renfrew57 Paisley
Road Roadside 250597 667473 NO2 N 1.2 6 N 2.4
Johnstone59 High Street Kerbside 242656 663281 NO2 Y – JHS 0.1 1.7 N 2.5
Paisley60 Underwood
Road Roadside 247525 664326 NO2 N 7.8 0.5 N 2.4
Kilbarchan61 High
Barholm Roadside 240584 663007 NO2 N 0.1 1.1 N 2.4
Renfrew62
Cockels
Loan
(triplicate)
Roadside 250463 665934 NO2 N 5 18 to M8 Y 3
Paisley63 Renfrew
Road Roadside 249159 665710 NO2 N 6.8 3.7 (12 to
Renfrew Rd) N 2.4
Kilbarchan65 High
Barholm Roadside 240599 663000 NO2 N 0.42 2 N 2.2
Kilbarchan66 High
Barholm Roadside 240573 663021 NO2 N 0.43 1.64 N 2.2
Kilbarchan67 High
Barholm Roadside 240512 663027 NO2 N 1.75 2.95 N 2.3
Renfrew68 Paisley
Road Roadside 250522 667419 NO2 Y – RTC 0.2 3 N 2.3
Renfrew69 Inchinnan
Road Roadside 250537 667602 NO2 Y – RTC 0.12 2.87 N 2
Renfrew70 Inchinnan
Road Roadside 250599 667561 NO2 Y – RTC 4.5 3.71 N 2
Renfrew71 Braille Drive Roadside 251729 666360 NO2 Y – RTC
0 (equivalent
distance to
nearby housing)
26.5 to M8 slip
road N 2
Johnstone72 High Street Roadside 243080 663140 NO2 Y – JHS 0.45 3 N 2.3
Paisley73 Lawn Street Roadside 248566 664072 NO2 Y – PTC 0.19 1.95 N 2.45
Paisley74 Causeyside
Street Roadside 248313 663621 NO2 Y – PTC 0.19 3.3 N 2.2

Page 47

Renfrewshire Council
LAQM Annual Progress Report 2023 34
Site ID Site Name Site Type X OS
Grid Ref
Y OS
Grid Ref
Pollutants
Monitored
In
AQMA?
Which
AQMA?
Distance to
Relevant
Exposure (m)
(1)
Distance to
kerb of
nearest road
(m) (2)
Tube co-
located with a
Continuous
Analyser?
Tube
Height
(m)
Renfrew75 Canal Street Roadside 250853 667747 NO2 N 0.17 5 N 2.45
Paisley78 Neilston
Road Roadside 248339 662576 NO2 Y  0.15 2.63 N 2.5
Paisley79 Incle Street Roadside 248632 664212 NO2 N 0.18 2.8 N 2.16
Paisley80 Glasgow
Road Roadside 249653 664123 NO2 N 1.9 2.1 N 2.35
Paisley82 Well Street Roadside 247513 664024 NO2 Y – PTC 0.2 2.27 N 2.36
Paisley83 Wellmeadow
Street Kerbside 247671 663913 NO2 N 0.4 3.32 N 2.46
Renfrew84 Ferry Village Roadside 251254 667876 NO2 Y – PTC 18 0.5 N 2.4
Johnstone85 High Street Roadside 242622 663306 NO2 Y – JHS 0.62 1.1 N 2.4
Johnstone86 High Street Roadside 242495 663358 NO2 Y – JHS 0.14 2.7 N 2.41
Paisley88 Hawkhead
Road Roadside 249850 663991 NO2 Y - PTC 7 2.05 N 2.39
Paisley89 Abercorn
Street Roadside 248467 664303 NO2 Y– PTC 0.14 3.5 N 2.3
Renfrew90
Renfrew
Monitor
(triplicate)
Roadside 250567 667558 NO2 Y – RTC 7 3.9 Y 1.63
Lochwin92 Newton of
Barr Roadside 234904 658634 NO2 N 0.45 2 N 2.35
Lochwin93 Main Street Roadside 235280 658877 NO2 N 0.43 1.15 N 2.55
Paisley94 New Street Roadside 248186 663925 NO2 Y – PTC 2.1 0.47 N 2.37
Paisley96
McDonalds
Renfrew
Road
Roadside 248998 665204 NO2 N 19 2.23 N 2.23
Renfrew97 Inchinnan
Road Kerbside 250610 667534 NO2 Y – RTC  2.1 0.57 N 2.42
Johnstone98 High Street Roadside 242540 663323 NO2 Y – JHS 0.5 1.37 N 2.3
Johnstone99 High Street Roadside 242584 663307 NO2 Y – JHS 0.45 1.3 N 2.36
Johnstone100 High Street Roadside 242643 663285 NO2 Y – JHS 0.1 1.85 N 2.24
Renfrew101 Glebe Street Roadside 250656 667457 NO2 N 4.5 2.5 N 2.3
Paisley102 Orchard
Street Roadside 248363 663752 NO2 Y – PTC 0.58 2.32 N 2.1

Page 48

Renfrewshire Council
LAQM Annual Progress Report 2023 35
Site ID Site Name Site Type X OS
Grid Ref
Y OS
Grid Ref
Pollutants
Monitored
In
AQMA?
Which
AQMA?
Distance to
Relevant
Exposure (m)
(1)
Distance to
kerb of
nearest road
(m) (2)
Tube co-
located with a
Continuous
Analyser?
Tube
Height
(m)
Paisley103 Greenock
Road Roadside 247486 665285 NO2 N 18 0.8 N 2.24
Paisley105 Central
Road 2 Roadside 248425 664192 NO2 Y – PTC 55 4 N 2.25
Paisley106 Smithhills
Street Roadside 248477 664186 NO2 Y – PTC 5.59 0.59 N 2.17
Johnstone107 High Street Roadside 242503 663335 NO2 Y – JHS 6 2.8 N 2.24
Paisley108 Central
Road Roadside 248355 664180 NO2 Y – PTC 0.51 6.84 N 2.41
Notes:
(1) 0m if the monitoring site is at a location of exposure (e.g. installed on/adjacent to the façade of a residential property).
(2) N/A if not applicable.
PTC – Paisley Town Centre, RTC – Renfrew Town Centre, JHS – Johnstone High Street

Page 49

Renfrewshire Council
LAQM Annual Progress Report 2023  36
Table A.3 – Annual Mean NO2 Monitoring Results (µg/m3)
Site ID Site Type Monitoring Type Valid Data Capture for
Monitoring Period (%)(1)
Valid Data Capture
2022 (%) (2) 2018 2019 2020 2021 2022
REN1 Roadside Automatic 99.7 99.7 31.2 31.1 20.9 24.5 22.4
REN03 Roadside Automatic 98.2 98.2 - 24.1 19.9 19.0 19.7
Paisley1 Urban Centre Diffusion Tube 100.0 100.0 20.3 21.3 16.1 14.9 13.5
Paisley2 Urban
Background Diffusion Tube 84.6 84.6 14.4 14.6 10.9 9.6 11.9
Paisley3 Urban
Background Diffusion Tube 92.3 92.3 12.0 11.6 8.9 7.4 6.8
Renfrew8 Kerbside Diffusion Tube 92.3 92.3 41.1 41.4 40.2 29.8 30.2
Renfrew17 Roadside Diffusion Tube 92.3 92.3 33.7 32.0 26.3 22.9 23.5
Paisley19 Roadside Diffusion Tube 100.0 100.0 28.3 24.9 24.1 22.5 17.9
Johnstone20 Kerbside Diffusion Tube 92.3 92.3 29.7 28.7 25.5 20.2 19.3
Paisley21 (1),
Paisley21 (2),
Paisley21 (3)
Roadside Diffusion Tube 100.0 100.0 28.9 27.6 25.7 21.9 18.6
Paisley33 Roadside Diffusion Tube 92.3 92.3 31.7 28.8 27.7 24.1 19.4
Paisley35 Roadside Diffusion Tube 92.3 92.3 34.7 31.1 31.5 25.7 21.9
Paisley36 Roadside Diffusion Tube 100.0 100.0 30.4 28.2 27.7 26.5 20.5
Renfrew40 Roadside Diffusion Tube 100.0 100.0 27.4 25.8 21.6 18.7 16.4
Paisley43 Roadside Diffusion Tube 100.0 100.0 28.9 26.7 20.4 20.5 15.0
Paisley44 Roadside Diffusion Tube 100.0 100.0 23.6 21.9 16.3 16.1 15.5
Renfrew45 Kerbside Diffusion Tube 90.4 90.4 25.8 21.5 20.3 18.4 14.9
Renfrew48 Roadside Diffusion Tube 100.0 100.0 30.9 29.1 24.8 20.9 17.7
Paisley50 Roadside Diffusion Tube 90.4 90.4 29.4 24.3 21.8 17.9 17.3
Renfrew52 Roadside Diffusion Tube 100.0 100.0 31.8 25.3 24.9 21.2 17.3
Renfrew56 Roadside Diffusion Tube 92.3 92.3 30.3 26.3 24.4 20.9 19.5
Renfrew57 Roadside Diffusion Tube 100.0 100.0 24.1 24.4 18.1 19.0 12.9
Johnstone59 Kerbside Diffusion Tube 100.0 100.0 40.0 37.9 39.5 34.4 30.9
Paisley60 Roadside Diffusion Tube 100.0 100.0 34.4 33.6 30.1 24.5 22.3
Kilbarchan61 Roadside Diffusion Tube 100.0 100.0 32.4 30.2 26.0 26.1 18.7
Renfrew62 (1),
Renfrew62 (2),
Renfrew62 (3)
Roadside Diffusion Tube 100.0 100.0 36.8 34.3 30.5 25.3 21.9
Paisley63 Roadside Diffusion Tube 92.3 92.3 33.2 29.4 25.2 25.2 20.9
Kilbarchan65 Roadside Diffusion Tube 100.0 100.0 28.2 30.3 25.8 20.9 16.9

Page 50

Renfrewshire Council
LAQM Annual Progress Report 2023 37
Site ID Site Type Monitoring Type Valid Data Capture for
Monitoring Period (%)(1)
Valid Data Capture
2022 (%) (2) 2018 2019 2020 2021 2022
Kilbarchan66 Roadside Diffusion Tube 75.0 75.0 19.3 22.3 18.1 15.9 14.1
Kilbarchan67 Roadside Diffusion Tube 92.3 92.3 18.6 17.5 18.6 13.2 10.3
Renfrew68 Roadside Diffusion Tube 100.0 100.0 27.4 23.8 21.0 16.4 17.4
Renfrew69 Roadside Diffusion Tube 82.7 82.7 30.7 29.9 25.0 32.4 25.3
Renfrew70 Roadside Diffusion Tube 57.7 57.7 31.7 25.4 26.9 17.4 18.1
Renfrew71 Roadside Diffusion Tube 92.3 92.3 28.5 29.2 26.2 24.4 19.1
Johnstone72 Roadside Diffusion Tube 100.0 100.0 22.9 23.4 20.2 19.9 13.6
Paisley73 Roadside Diffusion Tube 100.0 100.0 32.0 26.1 27.0 22.5 17.7
Paisley74 Roadside Diffusion Tube 100.0 100.0 30.9 27.8 28.6 23.0 18.7
Renfrew75 Roadside Diffusion Tube 100.0 100.0 22.6 22.1 21.1 20.2 13.9
Paisley78 Roadside Diffusion Tube 100.0 100.0 28.9 26.6 24.4 24.0 16.8
Paisley79 Roadside Diffusion Tube 100.0 100.0 32.5 27.8 32.0 24.6 20.0
Paisley80 Roadside Diffusion Tube 92.3 92.3 24.9 23.9 23.7 18.4 14.9
Paisley82 Roadside Diffusion Tube 100.0 100.0 33.2 28.9 36.1 28.1 24.3
Paisley83 Kerbside Diffusion Tube 100.0 100.0 31.1 33.2 25.1 22.7 21.8
Renfrew84 Roadside Diffusion Tube 100.0 100.0 24.3 23.1 16.8 14.9 13.1
Johnstone85 Roadside Diffusion Tube 92.3 92.3 26.1 25.0 30.2 24.5 19.9
Johnstone86 Roadside Diffusion Tube 92.3 92.3 28.1 27.0 29.9 19.0 19.2
Paisley89 Roadside Diffusion Tube 100.0 100.0 22.4 30.4 24.9 23.2 20.0
Renfrew90 (1),
Renfrew90 (2),
Renfrew90 (3)
Roadside Diffusion Tube 100.0 100.0 - 24.4 21.4 20.1 17.2
Lochwin92 Roadside Diffusion Tube 100.0 100.0 - - 14.8 14.3 13.5
Lochwin93 Roadside Diffusion Tube 100.0 100.0 - - 14.1 16.7 11.1
Paisley94 Roadside Diffusion Tube 84.6 84.6 - - 21.0 19.0 17.9
Paisley96 Roadside Diffusion Tube 100.0 100.0 - - 24.2 21.2 16.9
Renfrew97 Kerbside Diffusion Tube 100.0 100.0 - - - 30.5 28.5
Johnstone99 Roadside Diffusion Tube 82.7 82.7 - - - 35.4 25.7
Johnstone100 Roadside Diffusion Tube 100.0 100.0 - - - 31.8 24.3
Renfrew101 Roadside Diffusion Tube 90.4 90.4 - - - 19.5 17.8
Paisley102 Roadside Diffusion Tube 92.3 92.3 - - - - 19.1
Paisley103 Roadside Diffusion Tube 100.0 100.0 - - - - 13.1
Paisley105 Roadside Diffusion Tube 100.0 100.0 - - - - 16.6
Paisley106 Roadside Diffusion Tube 81.0 75.0 - - - - 17.7
Johnstone107 Roadside Diffusion Tube 100.0 84.6 - - - - 20.6
Paisley108 Roadside Diffusion Tube 86.7 50.0 - - - - 14.7

Page 51

Renfrewshire Council
LAQM Annual Progress Report 2023 38
Notes:
Exceedances of the NO2 annual mean objective of 40µg/m3 are shown in bold.
NO2 annual means exceeding 60µg/m3, indicating a potential exceedance of the NO2 1-hour mean objective are shown in bold and
underlined.
Means for diffusion tubes have been corrected for bias. All means have been “annualised” as per LAQM.TG(22) if valid data capture for
the full calendar year is less than 75%. See Appendix C for details.
(1) Data capture for the monitoring period, in cases where monitoring was only carried out for part of the year.
(2) Data capture for the full calendar year (e.g. if monitoring was carried out for 6 months, the maximum data capture for the full calendar
year is 50%).

Page 52

Renfrewshire Council
LAQM Annual Progress Report 2023 39
Figure 6. Annual Mean NO2 Concentrations at Automatic Monitoring Sites 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO
2
Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective REN1 REN03

Page 53

Renfrewshire Council
LAQM Annual Progress Report 2023 40
Figure 7. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Urban Centre, Urban Background, Kerbside) 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO
2
Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective Paisley1 Paisley2 Paisley3
Renfrew8 Johnstone20 Renfrew45 Johnstone59
Paisley83 Renfrew97

Page 54

Renfrewshire Council
LAQM Annual Progress Report 2023 41
Figure 8. Annual mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside 1) 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO
2
Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective Renfrew17 Paisley19
Paisley21 (1), Paisley21 (2), Paisley21 (3) Paisley33 Paisley35
Paisley36 Renfrew40 Paisley43
Paisley44 Renfrew48 Paisley50

Page 55

Renfrewshire Council
LAQM Annual Progress Report 2023 42
Figure 9. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside 2) 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO
2
Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective Renfrew52 Renfrew56
Renfrew57 Paisley60 Kilbarchan61
Renfrew62 (1), Renfrew62 (2), Renfrew62 (3) Paisley63 Kilbarchan65
Kilbarchan66 Kilbarchan67

Page 56

Renfrewshire Council
LAQM Annual Progress Report 2023 43
Figure 10. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside 3) 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO2 Concentrations (µg/m
3 )
Year
Annual Mean Air Quality Objective Renfrew68 Renfrew69 Renfrew70
Renfrew71 Johnstone72 Paisley73 Paisley74
Renfrew75 Paisley78 Paisley79

Page 57

Renfrewshire Council
LAQM Annual Progress Report 2023 44
Figure 11. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside 4) 
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO2 Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective Paisley80 Paisley82
Renfrew84 Johnstone85 Johnstone86
Paisley89 Renfrew90 (1), Renfrew90 (2), Renfrew90 (3) Lochwin92
Lochwin93 Paisley94

Page 58

Renfrewshire Council
LAQM Annual Progress Report 2023 45
Figure 12. Annual Mean NO2 Concentrations at Non-Automatic Monitoring Sites (Roadside 5)
0
5
10
15
20
25
30
35
40
45
2018 2019 2020 2021 2022
Annual Mean NO
2
Concentrations (µg/m
3 )
Year
Annual Mean Air Quality Objective Paisley96 Johnstone99 Johnstone100
Renfrew101 Paisley102 Paisley103 Paisley105
Paisley106 Johnstone107 Paisley108

Page 59

Renfrewshire Council
LAQM Annual Progress Report 2023  46
Table A.4 – 1-Hour Mean NO2 Monitoring Results, Number of 1-Hour Means > 200µg/m3
Site ID Site Type Monitoring Type Valid Data Capture for
Monitoring Period (%) (1)
Valid Data Capture 2022
(%) (2) 2018 2019 2020 2021 2022
REN1 Roadside Automatic 99.7 99.7 0 0 0 0 0
REN03 Roadside Automatic 98.2 98.2 - 0 0 0 0
Notes:
Exceedances of the NO2 1-hour mean objective (200 µg/m3 not to be exceeded more than 18 times/year) are shown in bold.
If the period of valid data is less than 85%, the 99.8th percentile of 1-hour means is provided in brackets.
(1) Data capture for the monitoring period, in cases where monitoring was only carried out for part of the year.
(2) Data capture for the full calendar year (e.g. if monitoring was carried out for 6 months, the maximum data capture for the full calendar year is
50%).
Table A.5 – Annual Mean PM10 Monitoring Results (µg/m3)
Site ID Site Type Valid Data Capture for
Monitoring Period (%) (1)
Valid Data Capture 2022
(%) (2) 2018 2019 2020 2021 2022
REN02 Roadside 82.3 82.3 13.4 16.3 10.2 13.7 12.9
REN02
Corrected Roadside 82.3 82.3 14.8 17.9 11.3 15.1 14.2
Notes:
Exceedances of the PM10 annual mean objective of 18 µg/m3 are shown in bold.
All means have been “annualised” as per LAQM.TG(22), valid data capture for the full calendar year is less than 75%. See Appendix C for details.
(1) Data capture for the monitoring period, in cases where monitoring was only carried out for part of the year.
Data capture for the full calendar year (e.g. if monitoring was carried out for 6 months, the maximum data capture for the full calendar year is
50%).

Page 60

Renfrewshire Council
LAQM Annual Progress Report 2023 47
Figure 13. Annual Mean PM10 Concentrations at Automatic Monitoring Sites
0
2
4
6
8
10
12
14
16
18
20
2018 2019 2020 2021 2022
Annual Mean PM10 Concentration (µg/m
3 )
Year
Annual Mean Air Quality Objective REN02 REN02 Corrected

Page 61

Renfrewshire Council
LAQM Annual Progress Report 2023  48
Table A.6 – 24-Hour Mean PM10 Monitoring Results, Number of PM10 24-Hour Means > 50µg/m3
Site ID Site Type Valid Data Capture for
Monitoring Period (%) (1)
Valid Data Capture 2022
(%) (2) 2018 2019 2020 2021 2022
REN02 Roadside 82.3 82.3 1 14 0 1 0
Notes: 
Exceedances of the PM10 24-hour mean objective (50 µg/m3 not to be exceeded more than seven times/year) are shown in bold.
If the period of valid data is less than 85%, the 98.1st percentile of 24-hour means is provided in brackets.
(1) Data capture for the monitoring period, in cases where monitoring was only carried out for part of the year.
(2) Data capture for the full calendar year (e.g. if monitoring was carried out for 6 months, the maximum data capture for the full calendar year is
50%).
Table A.7 – Annual Mean PM2.5 Monitoring Results (µg/m3)
Site ID Site Type Valid Data Capture for
Monitoring Period (%) (1)
Valid Data Capture 2022
(%) (2) 2018 2019 2020 2021 2022
REN02 Roadside 82.3 82.3 7.3 7.9 5.5 6.0 6.1
REN02
Corrected Roadside 82.3 82.3 7.7 8.4 5.9 6.3 6.5
Notes:
Exceedances of the PM2.5 annual mean objective of 10 µg/m3 are shown in bold.
All means have been “annualised” as per LAQM.TG(22), valid data capture for the full calendar year is less than 75%. See Appendix C for details.
(1) Data capture for the monitoring period, in cases where monitoring was only carried out for part of the year.
Data capture for the full calendar year (e.g. if monitoring was carried out for 6 months, the maximum data capture for the full calendar year is
50%).

Page 62

Renfrewshire Council
LAQM Annual Progress Report 2023 49
Figure 14. Annual Mean PM2.5 Concentrations at Automatic Monitoring Sites
0
2
4
6
8
10
12
2018 2019 2020 2021 2022
Annual Mean PM2.5 Concentrations (µg/m
3 )
Year
Annual Mean Air Quality Objective REN02 REN02 Corrected

Page 63

Renfrewshire Council
LAQM Annual Progress Report 2023  50
Appendix B: Full Monthly Diffusion Tube Results for 2022
Table B.1 – NO2 2022 Monthly Diffusion Tube Results (µg/m3)
Site ID Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Mean: Raw
Data
Annual
Mean: Bias
Adjusted (1)
Paisley1 8.2 11.4 17.8 13.2 4.5 8.3 5.8 11.9 11.0 14.5 12.5 34.2 12.8 13.5
Paisley2 - 23.6 6.9 10.1 5.4 - 4.9 8.3 8.1 8.5 16.2 20.7 11.3 11.9
Paisley3 - 6.7 4.5 8.6 2.1 2.3 3.4 5.5 5.8 6.5 6.4 18.8 6.4 6.8
Renfrew8 31.7 39.2 14.9 23.6 15.3 31.8 29.9 23.5 22.1 34.4 - 47.0 28.5 30.2
Renfrew17 20.7 24.2 13.3 27.0 12.1 16.0 14.6 16.3 - 27.4 34.6 37.7 22.2 23.5
Paisley19 9.3 14.6 13.2 19.8 11.3 12.8 12.0 10.2 19.8 20.8 27.5 31.9 16.9 17.9
Johnstone20 14.0 15.9 15.9 24.7 18.8 10.3 14.2 12.3  13.0 25.7 36.0 18.3 19.3
Paisley21 (1) 16.9 17.5 15.6 24.1 11.8 11.8 13.3 - 15.6 14.1 26.6 37.3 -(2) -(2)
Paisley21 (2) 15.6 18.0 12.1 23.6 10.7 14.2 8.5 16.0 12.1 20.7 22.2 32.8 -(2) -(2)
Paisley21 (3) 11.4 18.8 11.8 25.1 9.8 13.3 12.2 8.7 - 18.2 28.2 36.0 17.5(2) 18.6(2)
Paisley33 10.5 13.3 15.8 26.6 20.1 11.9 18.2 11.6 22.9 13.7 - 36.8 18.3 19.4
Paisley35 15.4 12.3 15.9 29.0 21.5 16.0 18.6 14.0 26.4 16.3 - 41.9 20.7 21.9
Paisley36 19.7 18.0 7.1 21.6 12.1 11.7 15.5 13.6 22.1 23.5 33.2 34.5 19.4 20.5
Renfrew40 12.0 7.2 12.1 16.4 13.9 12.7 9.5 11.6 12.1 17.7 23.7 36.2 15.4 16.4
Paisley43 12.3 8.0 10.7 18.1 10.2 9.2 8.9 11.7 10.4 14.8 20.3 35.3 14.2 15.0
Paisley44 9.6 7.5 12.9 17.7 10.7 8.8 8.5 15.6 17.3 15.1 23.8 28.0 14.6 15.5
Renfrew45 11.6 8.4 19.8 17.4 7.4 10.2 13.1 7.1 17.3 16.9 25.7 - 14.1 14.9
Renfrew48 13.6 10.2 14.9 10.4 7.7 13.6 11.5 7.5 20.0 23.7 29.0 38.1 16.7 17.7
Paisley50 14.2 11.1 10.7 - 15.3 11.9 12.2 7.5 21.0 18.5 21.5 35.9 16.3 17.3
Renfrew52 15.8 9.9 15.0 9.1 13.6 14.3 10.7 10.7 15.7 18.0 28.5 35.1 16.4 17.3
Renfrew56 18.0 9.5 14.0 23.1 10.4 15.9 10.7 17.3 - 21.9 28.1 33.8 18.4 19.5
Renfrew57 11.7 6.9 12.8 16.2 10.6 6.6 9.1 7.6 18.1 18.5 25.4 2.9 12.2 12.9
Johnstone59 34.1 16.5 21.4 31.9 29.2 20.4 10.6 29.7 29.2 42.0 41.0 44.3 29.2 30.9
Paisley60 21.6 8.8 17.3 15.6 15.3 12.0 16.9 20.9 25.6 21.1 34.1 42.9 21.0 22.3
Kilbarchan61 19.5 12.0 16.4 12.8 16.5 6.8 13.1 14.8 23.7 15.0 27.9 33.4 17.7 18.7
Renfrew62 (1) 28.8 16.0 14.5 18.1 15.3 11.8 16.8 14.8 24.2 26.5 31.8 40.1 -(3) -(3)
Renfrew62 (2) 25.2 11.4 14.1 15.9 19.9 9.5 - 19.3 22.6 30.0 32.6 38.1 -(3) -(3)
Renfrew62 (3) 24.3 17.2 12.8 18.5 8.6 11.1 2.0 - 28.0 28.8 27.6 39.8 20.6(3) 21.9(3)

Page 64

Renfrewshire Council
LAQM Annual Progress Report 2023 51
Site ID Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Mean: Raw
Data
Annual
Mean: Bias
Adjusted (1)
Paisley63 19.8 18.7 15.5 17.2 17.6 6.2 16.3 17.9 - 24.4 25.9 37.3 19.7 20.9
Kilbarchan65 20.6 9.0 15.6 12.1 15.1 7.3 12.1 14.8 19.3 16.8 17.1 31.3 15.9 16.9
Kilbarchan66 10.2 - 10.5 - 9.4 - 6.4 11.5 15.4 11.5 17.8 26.9 13.3 14.1
Kilbarchan67 7.3 - 9.0 6.4 7.5 3.7 5.7 8.5 10.3 11.2 14.2 23.6 9.8 10.3
Renfrew68 12.7 10.4 13.7 10.6 7.3 7.1 10.9 14.1 17.8 18.7 32.6 40.8 16.4 17.4
Renfrew69 15.1 22.2 18.3 17.1 - - 14.3 18.6 26.8 28.0 51.4 26.9 23.9 25.3
Renfrew70 - - 14.9 9.0 15.2 7.9 13.0 - 20.5 - 28.1 - 15.5 18.1
Renfrew71 10.4 - 16.4 9.9 10.0 7.7 11.9 12.0 21.3 25.5 35.7 37.3 18.0 19.1
Johnstone72 10.0 5.3 12.6 8.6 12.0 5.2 10.0 13.4 23.3 11.6 19.6 22.6 12.9 13.6
Paisley73 11.7 7.9 13.4 14.7 16.3 7.5 16.9 15.8 18.1 16.7 20.5 41.2 16.7 17.7
Paisley74 8.9 6.3 14.1 27.1 17.8 8.1 11.4 19.2 15.7 21.0 26.2 35.6 17.6 18.7
Renfrew75 12.6 9.0 11.4 8.2 5.9 6.8 10.1 12.0 5.3 18.7 23.0 34.3 13.1 13.9
Paisley78 13.3 12.3 17.3 15.6 8.4 10.8 15.7 14.2 9.3 13.6 23.9 35.4 15.8 16.8
Paisley79 17.5 10.9 16.5 19.0 9.5 9.9 12.8 17.1 16.4 20.7 30.9 45.4 18.9 20.0
Paisley80 9.3 8.7 13.3 21.5 11.5 4.3 10.6 12.3 - 12.8 17.8 32.4 14.0 14.9
Paisley82 16.3 36.0 20.0 22.1 11.6 5.5 11.3 27.4 23.1 31.4 28.8 41.8 22.9 24.3
Paisley83 20.2 9.3 29.3 21.7 18.8 12.6 16.6 17.4 12.5 20.8 29.9 38.0 20.6 21.8
Renfrew84 6.5 5.7 10.3 11.4 9.4 7.5 10.9 11.8 11.9 14.7 22.4 26.1 12.4 13.1
Johnstone85 12.5 6.7 - 25.3 17.8 9.4 14.7 20.4 16.1 20.0 27.2 36.6 18.8 19.9
Johnstone86 16.0 10.6 13.2 22.1 19.6 6.7 12.1 19.4 - 20.6 24.8 34.4 18.1 19.2
Paisley88 - - - 11.8 - - 10.2 - - - - - - -
Paisley89 18.2 19.3 12.5 24.8 15.4 9.7 16.7 18.3 14.7 14.3 23.5 38.7 18.8 20.0
Renfrew90 (1) 7.4 8.0 18.8 14.4 13.3 10.4 10.9 15.6 9.6 15.2 28.6 38.3 -(4) -(4)
Renfrew90 (2) 6.2 5.1 12.7 20.6 8.6 7.5 11.0 12.8 11.1 17.8 31.5 35.2 -(4) -(4)
Renfrew90 (3) 12.6 8.0 27.9 18.7 14.6 6.5 10.9 15.1 10.6 19.9 30.3 37.6 16.2(4) 17.2(4)
Lochwin92 11.2 4.6 16.1 11.3 12.9 7.8 12.1 16.2 13.2 10.7 15.7 20.7 12.7 13.5
Lochwin93 8.4 6.0 17.2 10.8 10.7 4.5 7.6 7.8 6.0 10.4 16.6 19.8 10.5 11.1
Paisley94 12.1 4.2 24.7 22.3 15.1 - - 13.9 8.5 11.6 21.5 34.6 16.9 17.9
Paisley96 20.9 11.2 25.3 12.1 11.3 9.5 10.3 10.3 7.1 19.3 20.6 33.7 16.0 16.9
Renfrew97 37.8 24.7 38.2 27.0 23.9 12.8 16.9 20.9 11.0 31.5 34.6 43.1 26.9 28.5
Johnstone98 36.0 - - - -  - - - - - - - -
Johnstone99 - 12.3 26.8 - 27.6 18.4 16.4 29.0 17.0 18.6 31.5 44.6 24.2 25.7
Johnstone100 26.8 16.2 30.6 18.8 18.9 22.1 14.6 16.8 15.9 23.8 31.8 38.8 22.9 24.3
Renfrew101 18.1 9.3 25.8 - 13.8 9.8 5.9 9.7 15.1 18.7 23.5 35.5 16.8 17.8
Paisley102 13.6 8.2 28.2 13.6 16.3 7.8 - 27.7 10.2 14.7 22.4 35.3 18.0 19.1

Page 65

Renfrewshire Council
LAQM Annual Progress Report 2023 52
Site ID Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Annual
Mean: Raw
Data
Annual
Mean: Bias
Adjusted (1)
Paisley103 11.8 5.3 21.8 9.6 9.5 6.1 8.3 11.6 10.8 12.4 14.6 26.3 12.3 13.1
Paisley105 10.5 9.7 28.0 12.5 8.7 6.9 10.1 17.9 11.4 17.3 20.7 34.6 15.7 16.6
Paisley106 - 12.5 27.5 17.7 - 9.1 - 8.5 9.3 15.1 22.3 28.0 16.7 17.7
Johnstone107 - - 31.5 23.4 10.3 15.9 9.4 10.7 13.4 19.3 28.6 31.6 19.4 20.6
Paisley108 - - - - - 5.2 3.6 10.1 15.5 13.3 - 29.6 12.9 14.7
Notes:
(1) See Appendix C for details on bias adjustment
(2) Triplicate Site with Paisley21 (1), Paisley21 (2) and Paisley21 (3) - Annual data provided for Paisley21 (3) only
(3) Triplicate Site with Renfrew62 (1), Renfrew62 (2) and Renfrew62 (3) - Annual data provided for Renfrew62 (3) only
(4) Triplicate Site with Renfrew90 (1), Renfrew90 (2) and Renfrew90 (3) - Annual data provided for Renfrew90 (3) only

Page 66

Renfrewshire Council
LAQM Annual Progress Report 2023  53
Appendix C: Supporting Technical Information / Air
Quality Monitoring Data QA/QC
New or Changed Sources Identified Within Renfrewshire
Council During 2023
Renfrewshire Council has not identified any new sources relating to air quality within the
reporting year of 2022.
Additional Air Quality Works Undertaken by Renfrewshire
Council During 2023
Renfrewshire Council has not completed any additional works within the reporting year of
2022.
QA/QC of Diffusion Tube Monitoring
The diffusion tubes for the reporting year of 2022 were supplied and analysed by Glasgow
Scientific Services (GSS) using the 20% TEA in water preparation method. All results have
been bias adjusted and annualised (where required) before being presented in Appendix
A: Monitoring Results.
GSS is a UKAS accredited laboratory and participates in the AIR-PT Scheme (a
continuation of the Workplace Analysis Scheme for Proficiency (WASP)) for NO2 tube
analysis and the Annual Field Inter-Comparison Exercise. These provide strict
performance criteria for participating laboratories to meet, thereby ensuring NO2
concentrations reported are of a high calibre.
The latest AIR-PT results were as follows:
• AIR-PT AR037 (May – June 2020) – No Results (NR)
• AIR-PT AR039 (July – August 2020) – No Results (NR)
• AIR-PT AR040 (September – October 2020) – 100%
• AIR-PT AR042 (January – February 2021) – 50%
• AIR-PT AR043 (May – June 2021) – 100%

Page 67

Renfrewshire Council
LAQM Annual Progress Report 2023 54
• AIR-PT AR045 (July – August 2021) – 100%
• AIR-PT AR046 (September – October 2021) – No Results (NR)
• AIR-PT AR049 (January – February 2022) – 100%
• AIR-PT AR050 (May – June 2022) – 100%
Diffusion Tube Annualisation
Two diffusion tube monitoring locations within Renfrewshire Council required annualisation
as their data capture was less than 75% but greater than 25%: Renfrew70 and
Paisley108, details are provided in Table C.2. Two diffusion tube monitoring locations
recorded a data capture below 25% and therefore could not be annualised: Paisley88 and
Johnstone98. The remainder of the sites recorded a data capture greater than 75% and
therefore did not require annualisation.
Diffusion Tube Bias Adjustment Factors
Renfrewshire Council have applied a local bias adjustment factor of 1.06 to the 2022
monitoring data. A summary of bias adjustment factors used by Renfrewshire Council over
the past five years is presented in Table C.1.
The 2022 national bias adjustment factor was taken from the National Diffusion Tube Bias
Adjustment Factor Spreadsheet (version 03/23) of which reports six studies analysed by
Glasgow Scientific Services in 2022 to give a national bias adjustment factor of 1.05.
There were two locations which provided opportunity for input to local bias adjustment
calculation. The local bias adjustment factor for 2022 was 1.06 from Cockels Loan co-
location site, which reported good overall precision and overall data capture. Renfrew
Inchinnan Road co-location site reported a poor overall precision for the diffusion tubes
and therefore was not used to calculate the local bias adjustment factor as per
LAQM.TG(22) which states “Where results show poor precision, then they should be
treated with caution, and they may not be suitable for their intended purpose… The aim
should be to use results from tubes that are giving good precision, as this will improve the
overall reliability of the annual mean concentrations derived from the diffusion tubes to
which the locally derived bias adjustment factors have been applied.” 
The local adjustment factor was used as it was larger than the national adjustment factor
and was considered to provide a more conservative, worst case approach; this is
consistent with the Council’s previous years’ choice of bias adjustment factors. Bias

Page 68

Renfrewshire Council
LAQM Annual Progress Report 2023 55
adjustment was carried out using the Defra Diffusion Tube Data Processing Tool v3.0
(https://laqm.defra.gov.uk/air-quality/air-quality-assessment/diffusion-tube-data-
processing-tool/).
Table C.1 – Bias Adjustment Factor
Year Local or National If National, Version of National
Spreadsheet Adjustment Factor
2022 Local - 1.06
2021 National 03/22 1.12
2020 Local - 1.20
2019 Local - 0.89
2018 Local - 0.91
NO2 Fall-off with Distance from the Road
Two monitoring sites (Paisley21 and Renfrew48) were not representative of exposure and
so the NO2 fall-off with distance calculator was used to estimate the NO2 concentration at
the nearest receptor with relevant exposure for each site. The calculations are shown in
Table C.4. NO2 Fall-off with Distance from the Road was carried out using the Defra
Diffusion Tube Data Processing Tool (https://laqm.defra.gov.uk/air-quality/air-quality-
assessment/diffusion-tube-data-processing-tool/).
QA/QC of Automatic Monitoring
Automatic monitoring of NOX, PM10 and PM2.5 is completed within Renfrewshire using
Chemiluminescence (NOX) and FIDAS 2000 (PM2.5 and PM10) analysers. Local Site
Operator (LSO) duties are carried out by an Officer from Renfrewshire Council on a
monthly basis. Automatic monitoring data is available on the Scottish Air Quality website
(https://www.scottishairquality.scot/) both in real-time and following ratification by Ricardo
Energy and Environment to AURN standards. The continuous monitoring sites are audited
every six monthly by Ricardo and are serviced every six months by ACOEM who maintain
the Service and Maintenance Contract. REN1 and REN03 NO2/NOx monitors are visited
and calibrated once a month by an LSO from Renfrewshire Council and reports from these
calibrations are sent to Ricardo to use in the QA/QC process.

Page 69

Renfrewshire Council
LAQM Annual Progress Report 2023 56
PM10 and PM2.5 Monitoring Adjustment
PM10 and PM2.5 data have been corrected in line with the Scottish Government Guidance
Note in relation to the measurement of ambient Particulate Matter (PM) and the LAQM
reporting of measured concentrations, issued in May 2023. PM10 data have been
corrected by dividing the ratified data by 0.909. PM2.5 data have been corrected by
multiplying the ratified data by 1.06. Both the corrected and uncorrected values have been
reported for completeness, as per the Scottish Government Guidance Note.
Automatic Monitoring Annualisation
Annualisation is required for any site with data capture less than 75% but greater than
25%. All automatic monitoring locations within Renfrewshire Council recorded data
capture of greater than 75% therefore it was not required to annualise any monitoring
data.
NO2 Fall-off with Distance from the Road
No automatic NO2 monitoring locations within Renfrewshire Council required distance
correction during 2022.

Page 70

Renfrewshire Council
LAQM Annual Progress Report 2023  57
Table C.2 – Annualisation Summary (concentrations presented in µg/m3)
Site ID
Annualisation
Factor
Glasgow
Anderston
Annualisation
Factor
Glasgow
Townhead
Annualisation
Factor Site 3
Name
Annualisation
Factor Site 4
Name
Average
Annualisation
Factor
Raw Data
Annual Mean
Annualised
Annual Mean Comments
Renfrew70 1.0604 1.1452 - - 1.1028 15.5 17.1 
Paisley108 1.0911 1.0564 - - 1.0737 12.9 13.8 
Table C.3 – Local Bias Adjustment Calculations 
Local Bias Adjustment
Input 1 (Renfrew
Cockels Loan)
Local Bias Adjustment
Input 2 (Inchinnan
Road)
Local Bias Adjustment
Input 3
Local Bias Adjustment
Input 4
Local Bias Adjustment
Input 5
Periods used to
calculate bias
9 7   
Bias Factor A 1.06 (0.86 – 1.37) 1.12 (0.95 – 1.36)   
Bias Factor B -6% (-27% - 16%) -10% (-26% - 5%)   
Diffusion Tube Mean
(µg/m3)
23.1 19.8   
Mean CV (Precision) 9.3% 8.4%   
Automatic Mean
(µg/m3)
24.5 22.1   
Data Capture 100% 100%   
Adjusted Tube Mean
(µg/m3)
25 (20 – 32) 22 (19 – 27)   
Notes:
Local bias adjustment input 2 (Inchinnan Road) has been disregarded due to poor diffusion tube precision so a single local bias
adjustment factor (Renfrew Cockels Loan) has been used to bias adjust the 2022 diffusion tube results.

Page 71

Renfrewshire Council
LAQM Annual Progress Report 2023 58
Table C.4 – NO2 Fall off With Distance Calculations (concentrations presented in µg/m3)
Site ID
Distance (m):
Monitoring
Site to Kerb
Distance (m):
Receptor to Kerb
Monitored
Concentration
(Annualised and
Bias Adjusted)
Background
Concentration
Concentration
Predicted at
Receptor
Comments
Paisley21 (1),
Paisley21 (2),
Paisley21 (3)
9.9 3.6 18.6 11.1 21.4 
Renfrew48 45.0 23.0 17.7 16.4 18.4 Receptor is more than 20m further from the kerb
than the monitor - treat result with caution.

Page 72

Renfrewshire Council
LAQM Annual Progress Report 2023  59
Glossary of Terms
Abbreviation Description
AMIDS Advanced Manufacturing Innovation District Scotland South
APR Air Quality Annual Progress Report
AQAP
Air Quality Action Plan - A detailed description of measures,
outcomes, achievement dates and implementation methods,
showing how the LA intends to achieve air quality limit
values’
AQMA
Air Quality Management Area – An area where air pollutant
concentrations exceed / are likely to exceed the relevant air
quality objectives. AQMAs are declared for specific pollutants
and objectives
AQO Air Quality Objective
AURN Automatic Urban and Rural Network (UK air quality
monitoring network)
CAFS2 Cleaner Air for Scotland 2
CWRR Clyde Waterfront & Renfrew Riverside
DEFRA Department for Environment, Food and Rural Affairs
DMRB Design Manual for Roads and Bridges – Air quality screening
tool produced by Highways England
EV Electric Vehicle
FDMS Filter Dynamics Measurement System
GAIA Glasgow Airport Investment Area
GSS Glasgow Scientific Services
HGV Heavy Goods Vehicle
HVO Hydrotreated Vegetable Oil
JHS Johnstone High Street
LA Local Authority
LAQM Local Air Quality Management
LEZ Low Emission Zone

Page 73

Renfrewshire Council
LAQM Annual Progress Report 2023 60
LSO Local Site Operator
LTS Local Transport Strategy
NO2 Nitrogen Dioxide
NOx Nitrogen Oxides
PM10
Airborne particulate matter with an aerodynamic diameter of
10µm (micrometres or microns) or less
PM2.5
Airborne particulate matter with an aerodynamic diameter of
2.5µm or less
PTC Paisley Town Centre
REN1 Renfrew Cockels Loan
REN02 Renfrewshire Johnstone
REN03 Renfrew Inchinnan Road
RTC Renfrew Town Centre
QA/QC Quality Assurance and Quality Control
SEPA Scottish Environment Protection Agency
SO2 Sulphur Dioxide
SPT Strathclyde Partnership for Transport
TEA Triethanolamine
TRO Traffic Regulation Order
TTRO Temporary Traffic Regulation Order
UTC Urban Traffic Control
VPR Vehicle Replacement Programme
VRC Vehicle Replacement Capital

Page 74

Renfrewshire Council
LAQM Annual Progress Report 2023  61
References
Air Quality in Scotland website (2022 Monitoring data), available at
http://www.scottishairquality.co.uk/ 
AIR-PT-Rounds 37 to 50 (May 2020 to June 2022) available at
https://laqm.defra.gov.uk/diffusion-tubes/qa-qc-framework/ 
AMIDS South - https://www.renfrewshire.gov.uk/transport-links-amids-south-paisley.
Cleaner Air for Scotland 2. July 2021. Published by the Scottish Government.
Defra LAQM helpdesk – https://laqm.defra.gov.uk/ 
Diffusion Tube Data Processing Tool v3.0 available at https://laqm.defra.gov.uk/air-
quality/air-quality-assessment/diffusion-tube-data-processing-tool/
Local Air Quality Management Policy Guidance LAQM.PG(S)23. March 2023. Published
by the Scottish Government. 
Local Air Quality Management Technical Guidance LAQM.TG(22). August 2022.
Published by Defra in partnership with the Scottish Government, Welsh Assembly
Government and Department of the Environment Northern Ireland. 
National Diffusion Tube Bias Adjustment Factor Spreadsheet version 03/22 available at
https://laqm.defra.gov.uk/bias-adjustment-factors/national-bias/
Renfrewshire Air Quality Action Plan 2019. 
Renfrewshire Council (2016-2021) Annual Progress Reports.