To: Communities and Housing Policy Board
On: 31 October 2023 
Report by:  Director of Finance and Resources
Heading:  General Services Revenue, Housing Revenue Account (HRA) and
Capital Budget Monitoring as at 15 September 2023 
1. Summary of Financial Position
1.1. The projected outturn at 31 March 2024 for all services reporting to the
Communities and Housing Policy Board, including the Housing Revenue
Account, is an overspend position of (£0.005m) (0.0%) against the revised
budget for the year. This can be further analysed as a projected underspend in
General Services activities of (£0.005m) and a break-even position in the HRA.
1.2. The projected capital outturn at 31 March 2024 for projects reported to the
Communities and Housing Policy Board is a break-even position against the
revised budget of £21.495m for the year.  
1.3. This is summarised over the relevant services in the table below and further
analysis is provided in the appendices. 
Table 1: Revenue
Division / Department Revised
Annual
Budget
£000
Projected
Outturn 
£000
Budget
Variance 
£000
Budget
Variance 
%
Housing Revenue Account (HRA) 0 0 0 0%
Housing – General Services (Not HRA) 4,682 4,682 0 0%
Communities and Public Protection 6,047 6,052 (5) (0.1%)
Criminal Justice 3,190 3,190 0 0%
Board Total – Revenue 13,919 13,924 (5) 0.0%

Page 2

1 
Table 2: Capital
Division / Department Revised
Annual
Budget
£000
Projected
Outturn 
£000
Budget
Variance 
£000
Budget
Variance 
%
Housing Revenue Account (HRA) 20,378 20,378 0 0%
Other Housing PSHG 1,117 1,117 0 0%
Board Total – Capital 21,495 21,495 0 0% 
2. Recommendations 
Members are requested to: 
2.1.  Note the projected Revenue outturn position detailed in Table 1 above
2.2. Note the projected Capital outturn position detailed in Table 2 above; and 
2.3. Approve the budget adjustments detailed at sections 4 and 6. 
3. Revenue 
3.1. The Revenue Budget Monitoring Statement at Appendix 1 identifies a projected
overspend of (£0.005m) (0.0% of total budget) for all services reporting to this
Policy Board. Detailed division service reports can also be found here, along
with an explanation of each significant projected variance.
3.2. The projected outturn is based on information currently available, and
assumptions made by service budget holders.  Projections are subject to
continuous review, and any changes will be detailed in future reports to the
Board.
3.3. The main reason for the projected outturn positions are indicated below the
Appendix tables, showing both the subjective analysis (what the budget is spent
on) and the objective analysis (which division is spending the budget).
3.4. The projected overspend of (£0.005m), is due to a small overspend in employee
costs within the Community Learning & Development Service. 
4. Revenue Budget Adjustments 
4.1. Members are requested to note, from Appendix 1, budget adjustments totalling
£0.239m have been processed since the budget was approved in March 2023.
The most significant adjustment being: 
 (£0.205m) – Transfer to Private Sector Housing Reserve from General
Services to support future investment priorities.

Page 3

2 
5. Communities and Housing Services Capital 
5.1. The Capital Investment Programme 2023/24 to 2027/28 was approved by the
Council on 2 March 2023. For Communities and Housing Services the approved
capital spend for 2023/24 is £30.795m.
5.2. The Capital Monitoring report at Appendix 2 indicates net budget adjustments
in the approved capital programme for Communities and Housing Services of
(£9.300m), as explained in 6.1 below. 
6. Capital Budget Adjustments 
6.1. Since the last report on the 22 August 2023, budget changes within HRA capital
projects totalling £9.300m have arisen, which reflect the following: 
 Budget carried forward into 2024/25 from 2023/24 of (£8.960m) due to timing
in works being started:
o External Improvements Framework Year 1 (£3.000m)
o Architectural Design Fees (£1.000m)
o Regeneration and Renewal programme (£4.610m)
o Gallowhill Council House New Build (£0.350m) 
 Budget decrease of (£0.340m) due to fee reduction:
o Multi Storey Flats General (£0.140m)
o Housing Investment Team Fees (£0.200m) 
___________________________________________________________________

Page 4

3 
Implications of this report 
1.  Financial – The projected budget outturn position for Communities and
Housing Services Revenue budget is an overspend of (£0.005m) (0.0% of
total budget). Income and expenditure in all services within the department
will continue to be monitored closely for the rest of the financial year and,
where necessary, steps will be taken to mitigate any significant overspend.   
The projected outturn position for Communities and Housing Services’
Capital budget is break-even. The Capital programme will continue to be
monitored closely for the rest of the financial year and, where necessary,
steps will be taken to mitigate any significant overspend.   
Any changes to current projections in either Revenue or Capital budgets will
be reported to the Board as early as possible, along with an explanation for
the movement. 
2.  HR and Organisational Development 
None directly arising from this report. 
3. Community/Council Planning
None directly arising from this report. 
4.  Legal 
None directly arising from this report. 
5.  Property/Assets 
Capital projects will result in new build Council housing stock and
improvements to existing stock. 
6.  Information Technology 
None directly arising from this report.
7.  Equality and Human Rights 
None directly arising from this report.
8. Health and Safety
None directly arising from this report.
9. Procurement 
None directly arising from this report.
10. Risk 
The potential risk that the Council will overspend its approved budget for the
year will be managed at a Council-wide level by the Chief Executive and
Directors.

Page 5

4 
11. Privacy Impact
None directly arising from this report. 
12. 
13.
Cosla Policy Position 
N/a. 
Climate Risk
None directly arising from this report.
__________________________________________________________________ 
List of Background Papers 
Housing Revenue Account Budget & Rent Levels 2023/24 and Housing Capital
Investment Plan 2023/24 to 2027/28, Council, 2 March 2023; 
Non-housing Capital Investment Programme, Prudential Framework and Treasury
Management Strategy, and Capital Strategy 2023/24 – 2027/28, Council, 2 March
2023. 
___________________________________________________________________ 
Authors: John Kilpatrick, Finance Business Partner 
Linsey Mcgregor, Capital Accountant

Page 6

Appendix 1   
Objective Summary
Annual Budget at
Period 3
Budget
Adjustments
Revised Annual
Budget at Period 6
Projected Outturn Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000
Housing Revenue Account (HRA) 0 0 0 0 0 0.0% 0 0
Housing - General Services (Not HRA) 4,906 (224) 4,682 4,682 0 0.0% 0 0
Communities and Public Protection (including
Regulatory Services) 6,062 (15) 6,047 6,052 (5) (0.1%) 343 (348)
Criminal Justice 3,190 0 3,190 3,190 0 0.0% 0 0
NET EXPENDITURE 14,158 (239) 13,919 13,924 (5) 0.0% 343 (348)
Objective Heading
Housing Revenue Account (HRA)
Housing - General Services (Not HRA)
Communities and Public Protection
Criminal Justice
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 15 September 2023
Budget Variance
(Adverse) or Favourable
POLICY BOARD :  COMMUNITIES AND HOUSING - All SERVICES
A projected underspend in employee costs is due to the timing of recruitment of vacancies within the service. Property costs are projected to
overspend, reflecting ongoing demands for repair and maintenance provision, particularly in void properties. Transfer payments continue to
forecast an overspend, owing to the impact of repairs pressures on void rent loss, as well as additional Council Tax costs for these properties.
These overspends are expected to be offset by additional interest income due to higher than budgeted interest rates. Overall, the HRA is
therefore still projected to break-even at year-end.
Key Reasons for Projected Variance
There is a continuing increased demand for homelessness accommodation, impacting on rental costs, Council Tax and furniture for temporary
accommodation units. The forecasted overspends are expected to be offset by additional rental income received in relation to these units. All
budget lines are being closely monitored with an aim to mitigate the overspends anticipated as a result of these demand pressures.
This area is projecting a small overspend within the Community Learning & Development service. Following the recent restructure, the Head of
Service is developing plans to use the previously identified underspend to fund one-off pressures this year, and reviewing the overall budget
with Finance to both ensure it is appropriately allocated going forward and to identify any savings opportunities.
No significant projected year end variances to report.

Page 7

Appendix 1   
Subjective Summary
Annual Budget at
Period 3
Budget
Adjustments
Revised Annual
Budget at Period 6
Projected Outturn Previous
Projected
Outturn
Variance
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 12,379 (182) 12,197 12,249 (52) (0.4%) 135 (187)
Premises Related 1,990 (45) 1,945 2,239 (294) (15.1%) (227) (67)
Transport Related 170 1 171 206 (35) (20.3%) (27) (8)
Supplies and Services 3,241 53 3,294 3,449 (155) (4.7%) 38 (193)
Third Party Payments 87 0 87 89 (2) (2.3%) 3 (5)
Transfer Payments 2,635 (194) 2,441 2,509 (68) (2.8%) (44) (24)
Support Services 56 (2) 54 13 41 76.6% 28 13
Depreciation and Impairment Losses (23) 0 (23) (18) (5) (21.7%) (5) 0
GROSS EXPENDITURE 20,535 (369) 20,166 20,735 (569) (2.8%) (101) (470)
Income (6,377) 130 (6,247) (6,811) 564 9.0% 444 122
NET EXPENDITURE 14,158 (239) 13,919 13,924 (5) 0.0% 343 (348)
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
1 April 2023 to 15 September 2023
POLICY BOARD :  COMMUNITIES AND HOUSING - GENERAL SERVICES (excluding HRA)
Budget Variance
(Adverse) or Favourable

Page 8

Appendix 1   
Subjective Summary
Annual Budget at
Period 3
Budget
Adjustments
Revised Annual
Budget at Period 6
Projected Outturn Previous
Projected
Outturn
Movement
£000 £000 £000 £000 £000 % £000 £000
Employees 11,007 91 11,098 10,839 259 2.3% 290 (31)
Premises Related 20,397 (109) 20,288 21,589 (1,301) (6.4%) (925) (376)
Transport Related 103 0 103 51 52 50.5% 52 0
Supplies and Services 792 (59) 733 683 50 6.8% (54) 104
Third Party Payments 49 0 49 49 0 0.0% (88) 88
Transfer Payments 4,190 209 4,399 5,139 (740) (16.8%) (479) (261)
Support Services 2,492 0 2,492 2,500 (8) (0.3%) 45 (53)
Depreciation and Impairment Losses 19,089 0 19,089 19,089 0 0.0% 0 0
GROSS EXPENDITURE 58,119 132 58,251 59,938 (1,687) (2.9%) (1,158) (529)
Income (58,119) (132) (58,251) (59,938) 1,687 2.9% 1,158 529
NET EXPENDITURE 0 0 0 0 0 0.0% 0 0
Budget Variance
(Adverse) or Favourable
RENFREWSHIRE COUNCIL
REVENUE BUDGET MONITORING STATEMENT 2023/24
POLICY BOARD :  COMMUNITIES, HOUSING AND PLANNING SERVICES - Housing Revenue Account  (HRA) Only
1 April 2023 to 15 September 2023

Page 9

Appendix 2   
Prior Years Annual Budget Budget Revised Projected
Expenditure at P3 Adjustments Budget Outturn Total Approved Projected
to 31/03/2023 2023-24 2023-24 2023-24 Budget Outurn
Project Title to 31-Mar-27 to 31-Mar-27
£000 £000 £000 £000 £000 £000 £000
HOUSING(HRA)
Improvements To Existing Properties 0 13,390 (3,140) 10,250 10,250 0 0% 113,885 113,885 0 0%
Regeneration 7,045 9,378 (4,610) 4,768 4,768 0 0% 106,953 106,953 0 0%
Other Assets 0 1,815 0 1,815 1,815 0 0% 12,500 12,500 0 0%
Non Property Expenditure 0 1,550 (1,000) 550 550 0 0% 1,550 1,550 0 0%
Council House New Build 41,358 1,680 (350) 1,330 1,330 0 0% 74,599 74,599 0 0%
Professional Fees 0 1,865 (200) 1,665 1,665 0 0% 9,415 9,415 0 0%
Total Housing(HRA) Programme 48,403 29,678 (9,300) 20,378 20,378 0 0% 318,902 318,902 0 0%
HOUSING(PSHG)
Private Sector Housing Grant Programme 0 1,117 0 1,117 1,117 0 0% 1,117 1,117 0 0%
Total Housing(PSHG) Programme 0 1,117 0 1,117 1,117 0 0% 1,117 1,117 0 0%
TOTAL COMMUNITIES, HOUSING & PLANNING
BOARD 48,403 30,795 (9,300) 21,495 21,495 0 0% 320,019 320,019 0 0%
*Rolling programmes have a prior year year expenditure of £0 as the expenditure is not directly linked from one year to the next as a singular project.
RENFREWSHIRE COUNCIL
CAPITAL INVESTMENT STRATEGY
1st April to 15th September 2023
POLICY BOARD: COMMUNITES & HOUSING
Current Year 2023-24 Full Programme - All years
Budget Variance (Adverse) or
Favourable
Budget Variance (Adverse) or
Favourable