Page 1

___________________________________________________________________
To: Communities and Housing Policy Board
On: 16 May 2023
___________________________________________________________________
Report by: Director of Environment, Housing and Infrastructure
___________________________________________________________________
Heading: Private Sector Housing Investment Programme 2023/24
___________________________________________________________________
1. Summary
1.1 On 2 March 2023 the Council approved a report entitled ‘Non Housing Capital
Investment Programme 2022/23 – 2026/27’ which includes funding provision for
capital and revenue Private Sector Housing Grant (PSHG) expenditure for
2023/24.
1.2 Based on the Council budget approval and taking account of the most up to date
expenditure projections, this report updates the programme requirements of
£1.116m for the period 2023/24 to support owner participation on a range of
programmes.
1.3 As noted by the Communities, Housing and Planning Policy Board on 12 March
2019, there are funds held in reserve to support owners involved in the Orchard
Street Housing Renewal Area tenement refurbishment project and to support
owner participation in the eight approved Housing Regeneration areas. 
1.4 There is a requirement to manage PSHG resources in a flexible manner in terms
of the drawdown of funds, to reflect the timing of the settlement of final accounts
associated with owners in the both the Housing Investment and Housing
Regeneration programmes, as well as the renewal of the contract for private
sector adaptations.
___________________________________________________________________
2. Recommendations 
It is recommended that the Communities and Housing Policy Board:
2.1 Approve the Private Sector Housing Grant Investment Programme for the period
2023/24 as set out in appendix 1 of the report.
___________________________________________________________________

Page 2

3. Background
3.1 The Private Sector Housing Grant supports a range of services to private sector
owners. This includes Adaptation grants, support costs for Care & Repair
Renfrewshire, support for the pilot project to pay ‘Missing Shares’ and support
for homeowners involved in Council Housing Investment and Housing
Regeneration programmes involving common works carried out as part of
external works programmes. 
3.2 Appendix 1 sets out the proposed programme for 2023/2024 showing proposed
expenditure of £1.116m. The key elements of the proposed programme currently
are as follows: 
(i) Adaptation Grants (Assistance to older and disabled owners) 
The Council provides grant to assist owners who require adaptations to make
dwellings suitable for a member of the household who is older or disabled.  
The strategy for support for disabled adaptations across all tenures (excluding
Housing Associations) is the responsibility of Renfrewshire Health & Social Care
Partnership (HSCP) Integration Joint Board. 
The Council is required by legislation to provide a minimum of 80% grant support
to homeowners referred by HSCP, Occupational Therapy Services. Demand for
adaptation grants continues to grow with the number of referrals for adaptations
continuing to put strain on the available budget.  An annual allowance of
£550,000 to support the delivery of private sector adaptations has been included
in the available grants budget for 2023/24. The Council, in conjunction with the
Health & Social Care Partnership will continue to monitor demand pressures on
available grant during the year. 
As in previous years, Bridgewater Housing Association (Care & Repair
Renfrewshire) will manage private sector adaptations and small repairs services
in Renfrewshire and East Renfrewshire Councils during this financial year. An
allowance of £230,000 is included within the budget for Renfrewshire’s costs
associated with this contract. 
(ii) Housing Investment Programme 
Since achieving compliance with the Scottish Housing Quality Standard (SHQS)
in April 2015, there has been an ongoing requirement to ensure our housing
stock continues to be maintained at this standard.  In addition to SHQS, there is
an over-arching emphasis on improving the housing stock to the latest energy
efficiency standards as set out in the Energy Efficiency Standards for Social
Housing post 2020 (EESSH2).  However, this standard has been suspended
whilst the Scottish Government carries out a review during 2023, to ensure it
aligns with new net zero requirements.   
The Housing Investment Programme is focussed on common works in blocks of
mixed ownership and accordingly the PSHG programme will continue to support
future external improvement works in mixed tenure blocks and offer grants to
homeowners involved in these programmes.

Page 3

The PSHG programme will also support investment in retained housing stock
within the eight Housing Regeneration areas, for which the Policy Board
approved a report on 7 March 2023 enhancing the level of grant support to
participating private homeowners in the regeneration areas.
Energy efficiency grants also continue to be made available to eligible
households through the Scottish Government’s EES: ABS (Energy Efficient
Scotland: Area Based Schemes) programme and the Energy Company
Obligation (ECO) scheme, where applicable.
An allowance of £150,000 is proposed to support grants to homeowners.  As
noted within this report, uncertainties around the exact timing of projects and the
application of grants to owners will require programme flexibility to be maintained
with this and future years. 
(iii) ‘Missing Shares’ Pilot Project 
On 21 August 2018 the Communities, Housing and Planning Policy Board
approved an allowance of up to £100,000 for the development of a “missing
shares” pilot project, initially open to owners of older traditional privately owned
tenement flats. 
This pilot is to assist owners in pre 1919 private blocks to get essential common
repairs done where they are having difficulty receiving contributions from other
owners who are unable or unwilling to pay their share.
The Council will to pay up to £10,000 per missing share for eligible works and
will seek to recover these and associated administrative costs from non-paying
owners.
The Council has, since the inception of the pilot project, paid out £52,000 in
missing share payments for seven tenement block repair projects that have been
completed. The Council has recovered £23,758 of these missing share
payments leaving an available balance in 2023/24 of £71,758. 
(iv)  Salaries
Salaries for staff engaged on private sector investment within the Owner
Services team are funded through this budget. The annual allowance of
£105,000 is included, reflecting the structure within the staff grouping
responsible for delivery of the programme and including agreed pay settlements.
The Private Sector Housing Grant also part funds the Council’s More Homes
Officer post. 
(v)   Support to the Private Rented Sector / Miscellaneous Fees 
An allowance of £10,000 is included to fund training events for private landlords
undertaken in Partnership with Landlord Accreditation Scotland. These events
are currently delivered online. These funds also support membership of
Scotland’s Housing Network who provide online training and networking
meetings for Council Officers.

Page 4

3.3 The nature of the Private Sector Housing Investment Programme means that
flexibility is required to adjust spend between projects during the financial year
for a number of reasons, for example because of differences between the
estimated and actual grant required once the test of resources is applied to
individual owners, slippage in projects, difficulties securing the participation of
some owners, increased demand for private sector adaptations to ensure that
full spend is achieved and thus best use is made of the resource available. 
___________________________________________________________________ 
Implications of the Report
1. Financial – The PSHG programme for 2023/24 totals £1.116 million.
2. HR & Organisational Development - None
3. Community/Council Planning – 
 Our Renfrewshire is thriving – the support offered to private owners will
help to improve housing conditions, making Renfrewshire a great place to
live 
 Our Renfrewshire is well – the support provided to older and disabled
owners will help enable people to live healthier, for longer, in their own
homes 
 Reshaping our place, our economy and our future – investment in the
refurbishment of housing stock will create jobs and contribute to the
economy
4. Legal - None
5. Property/Assets - None
6. Information Technology - None 
7. Equality & Human Rights 
(a) The Recommendations contained within this report have been assessed in
relation to their impact on equalities and human rights. No negative impacts
on equality groups or potential for infringement of individuals’ human rights
have been identified arising from the recommendations contained in the
report.  If required following implementation, the actual impact of the
recommendations and the mitigating actions will be reviewed and
monitored, and the results of the assessment will be published on the
Council’s website.
8. Health & Safety - None
9. Procurement - None
10. Risk - None
11. Privacy Impact - None

Page 5

12. COSLA Policy Position – N/A.
13. Climate Risk – Grant funding to private homeowners to support their
participation in housing investment programme works will help to improve energy
efficiency in privately owned properties, which will contribute to residents using
less energy, thus reducing emissions.
_________________________________________________________
List of Background Papers
1. Report to Communities and Housing Policy Board on 7 March 2023 – Proposed
Change to Scheme of Assistance in Regeneration Areas. 
2. Report to Council on 2 March 2023 – Non-Housing Capital Investment
Programme, Prudential Framework and Treasury Management Strategy, and
Capital Strategy 2023/24 – 2027/28 
3. Report to Communities, Housing and Planning Policy Board on 12 March 2019 –
Private Sector Housing Investment Programme 2019/20 
4. Report to Communities, Housing and Planning Policy Board on 21 August 2018
– Scheme of Assistance for private owners and missing shares pilot project
 
The foregoing background papers will be retained within Environment, Housing & Infrastructure
for inspection by the public for the prescribed period of four years from the date of the meeting.
The contact officer within the service is Ian Mackinnon, Mixed Tenure Manager, 07483 376
245, ian.mackinnon@renfrewshire.gov.uk
___________________________________________________________________ 
Author: Ian MacKinnon, Mixed Tenure Manager, 07483 376245, 
ian.mackinnnon@renfrewshire.gov.uk

Page 6

APPENDIX 1 
PROPOSED PRIVATE SECTOR HOUSING PROGRAMME 2023/2024 
Category 2023/2024
Adaptation Grants £550,000
Care and Repair – Revenue Support - Contracted £230,000
Capital Programmes – Owners Grants £150,000
Missing Share Tenement Pilot Scheme   £71,758
Capitalised Salaries £105,000
Miscellaneous Costs (including support for the private
rented sector)   £10,000
Total £1,116,758