Page 1

MINUTES of MEETING of OBAN LORN & THE ISLES AREA COMMITTEE held  BY
MICROSOFT TEAMS AND IN AN FURAN GAELIC CENTRE, CORRAN HALLS, OBAN 
on WEDNESDAY, 10 DECEMBER 2025 
Present: Councillor Kieron Green (Chair) 
Councillor Amanda Hampsey
Councillor Willie Hume
Councillor Andrew Kain 
Councillor Jim Lynch (from Item 5)
Councillor Luna Martin (from Item 4)
Councillor Andrew Vennard 
Attending: Michelle Mundie, ACHA Chief Executive
Melissa Stewart, Democratic Services Manager
Mark Calder, Project Manager, Roads and Infrastructure
Elsa Simoes, Infrastructure Design Manager
Victoria Weir, Project Officer, Roads and Infrastructure 
1. APOLOGIES FOR ABSENCE 
The Chair welcomed everyone to the meeting. 
Apologies were received on behalf of Councillor Julie McKenzie. 
2. DECLARATIONS OF INTEREST 
There were no declarations of interest intimated. 
3. MINUTES 
(a) Oban, Lorn and the Isles Area Committee - 10 September 2025 
The Minute of the meeting of the Oban, Lorn and the Isles Area
Committee, held on 10 September 2025 was approved as a correct
record. 
(b) Oban, Lorn and the Isles Area Community Planning Group - 12
November 2025 
The Minute of the meeting of the Oban, Lorn and the Isles Area
Community Planning Group, held on 12 November 2025 was noted. 
(c) Oban Common Good Fund - 11 August 2025 
The Minute of the meeting of the Oban Common Good Fund, held on 11
August 2025 was noted.   
(d) Special Meeting of the Oban Common Good Fund - 10 October 2025 
The Minute of the special meeting of the Oban Common Good Fund, held

Page 2

on 10 October 2025 was noted.   
4. PUBLIC QUESTION TIME 
The Chair advised, with agreement of the Committee, and subject to governance
advice, that he intended to have two public question time sessions to provide a
further opportunity for supplementary questions later in the meeting.  The
Democratic Services Manager advised on procedure and the committee agreed that
they would take questions now and would then continue the session until later in the
meeting. 
The first 5 questions were received in advance of the meeting and submitted to the
relevant departments for responses. 
Question 1 – Phil Hamerton 
Should responsibility for decision-making in regard to Control Areas in Argyll &
Bute be delegated to local Area Committees, as is done in Highland Council areas? 
The Chair advised that Argyll and Bute Council are in the process of drawing up a
consultation on Control Areas within the Local Authority.  It would, in his view, be
important that any Control Areas introduced in the area are based on the responses
to the consultation and evidence based as this would give a degree of confidence
should there be any legal challenge. Any suggested delegation could be fed in
through that consultation process. 
Councillor Vennard advised that there is nothing decided concerning Control Areas
and these would fall under the remit of Planning and Licensing Committee and full
Council. 
It was agreed that the next 4 questions which were submitted prior to the start of the
meeting would be taken together as they related to the same issues of flooding. 
Question 2, 3 & 4 – Alison Rennie, Oban Community Council 
2.    What is the clearance work referred to in para 4.2 of the Oban Flooding Update
report to the Area Committee, as follows: "Subject to the necessary permissions it is
proposed that some clearance work is carried out." 
3.    Does the Council accept the statements in the 2019 Flood Study that:
• “The Black Lynn has been identified as the only reach where vegetation or
sediment accumulations currently have potential to impact upon flood risk.”
(Argyll & Bute Council - Oban Flood Study; Report 3A: Options Appraisal -
Long-List to Short-List: Waterbody Engineering); and
• "water levels in the channel may have been elevated (in 2018) by 0.3m or
more due to this effect." (Argyll & Bute Council - Oban Flood Study; Report
2B: Black Lynn Flood Modelling 5.4.2)? 
4.    Regarding the meeting referred to in the Oban Flooding Update report to the
Area Committee states in para 4.10 (the first one numbered thus) that: "An Oban
Local Flood Resilience Group has been established by volunteers with an initial
meeting held with Council officers.":

Page 3

• who was involved;
• when did  this take place;
• is there a record of the meeting; and,
•  what were the outputs? 
Question 5 – Lachie Strathern 
The business premises which I lease from the Council continue to flood with surface
water and sewage, which runs from Crannog Lane whenever we have heavy rain. 
On 8th April 2024 a survey was conducted of the surface water drainage of
Lochavullin Road and Crannog Lane by an external contractor on behalf of the
Council.  This clearly identified an obstruction of the surface water drain in Crannog
Lane, and a further possible obstruction of the larger drain downstream in
Lochavullin Road. 
Can the Committee please enquire what remedial action has been taken to clear
these obstructions to allow surface water to drain properly, and is the survey and
report to be considered under Agenda item 6 at this meeting? 
Ms Stewart advised the Committee that in regard to question 5 from Mr Strathern,
this was not a question for the infrastructure design team and due to officer leave
there was no-one available at this time to provide a response.  On this basis a
response would be pursued and sent on to Mr Strathern in due course.  
Elsa Simoes advised that modelling of the Black Lynn was carried out to establish if
it could be dredged.  It turned out after the modelling that it could not be dredged and
if it could then it was not known the how the existing walls etc would hold up as there
are no records available of the existing structures.  It would be a very costly exercise
to search out culverts as the existing culverts under the car park and out to the South
of the Bay would not cope with the excess water. 
Ms Simoes went on to say that the only solution would be to create ponds and
storage areas above the business park area and below the Hospital grounds to
collect the rainwater and discharge when the tide is low. 
The Japanese Knotweed will be cleared under a different fund which was not part of
the flooding work. 
Ms Simoes went on to say it is a Council obligation to clear the burn, and it was
cleared late 2024 from the South Bay up to Jackson’s Quarry. Further clearance will
take place early in the new year to remove obstructions within the burn. 
Regarding the Resilience Group, Ms Simoes stated that she was made aware that a
meeting took place in 2024 but has no further information available of who was
involved. 
The Chair went back to the members of the public who had asked the questions if
they had any further queries? 
Mr Strathern advised that he had seen mention of a Resilience Flood Group but had
no idea who they were and if he had been he would very much have liked to attend
the meeting.  He also advised that he did not agree with the negatives that Ms

Page 4

Simoes mentioned, and he thought that the dredging of the burn’s built-up silt would
go a long way to alleviate the flooding issue. 
Councillor Martin spoke regarding the removal of Japanese Knotweed this would not
be removed under the current funding but funding of £104k had been allocated from
the Nature Restoration fund and Mr Murphy had assured Councillor Martin that
members of his team were currently undergoing training on the injection of Japanese
Knotweed with a view to undertaking works in March. 
Ms Simoes responded to the further comment about dredging and advised that early
next year she would come back to the Area Committee with the modelling which will
be a visual of what would exactly happen if the sediment in the burn was removed
and making the burn deeper.   
Councillor Martin advised that the Cabinet Secretary had been invited to attend on
the issue of flooding last year but declined.   Councillor Martin indicated that she
would raise this again later in the month at the Economic Development and
Infrastructure Committee. 
Mr Hamerton advised that the Flood Resilience Group was mentioned in a report to
the Environment, Development and Infrastructure Committee in June 2024, and that
this was not accurate.  Oban Community Council had previously invited Councillors
and Council Officers to a flood resilience meeting with a view to forming a group but
there had been no response. Mr Hamerton questioned the existence of a group
commenting that if there was information of a meeting taking place then it was not in
the scope of Oban Community Council.   
There being no further questions at this time, the Committee agreed to continue the
item until later in the meeting. 
5. ARGYLL COMMUNITY HOUSING ASSOCIATION (ACHA) UPDATE 
Consideration was given to a presentation by the Chief Executive of ACHA, which
provided an update on a number of areas including the investment programme for
2025/26, that delivered replacement kitchens and bathrooms and the upgrade of
lighting and decoration in common closes; the Scottish Government Grant of
£750,000 which has allowed the progression of 25 adaptations and essential aids for
the most vulnerable customers across Argyll and Bute with a further 11 due to be
completed by end of December; and how they had successfully obtained £13m
through the Energy Efficiency Programme allowing the improvement on energy
efficiencies within home that are EPC rated E, D and Low C.  Further information
was provided on the extensive renovations at Dunallan House in Connel, that has
now been leased to the HSCP for visiting staff; The Welfare Rights Team’s success
in securing unpaid benefits and grants to tenants of up to £2.4m, and awards
totalling £68,355 for 472 tenants from the Housing Association Community Trust
(HACT) fuel fund; major improvements are planned for the gypsy travellers site at
Bayview Ledaig; and distributions of funding from the ACHA’s 10-10-10 initiative,
and ACHA’s  Community Action Fund to Rockfield Primary School and Oban’s
Riding for the Disabled Group respectively. 
Decision

Page 5

The Oban, Lorn and the Isles Area Committee considered and noted the information
provided in the presentation. 
(Reference: Presentation by Chief Executive, Argyll Community Housing Association
Ltd, dated December 2025 submitted) 
Due to an issue with the connection, it was agreed that the items on the agenda
would be taken out of sequence.  The minute reflects the order which items were
taken at the meeting. 
6. ELECTRIC VEHICLE CHARGING STRATEGY 
The Committee gave consideration to a presentation by the Project Manager on the
Electric Vehicle Charging Strategy, and the list of current and proposed locations for
electric vehicle chargers. 
Discussion followed during which concerns were outlined as to maintenance of the
equipment and generating sufficient capacity, with the Project Officer responding by
outlining the modelling tool used to help inform decisions subsequently fed into area
energy plans used to inform SSEN.  The Project Manager advised that more
information on costs would be submitted to the Economic Development and
Infrastructure Committee in March, followed by a further report to Area Committees
which would give opportunity for a more informed discussion. 
Decision 
The Oban, Lorn and the Isles Area Committee noted the information provided. 
(Presentation by Executive Director with responsibility for Roads and Infrastructure
Services, dated 20 October 2025, submitted) 
7. OBAN FLOODING UPDATE 
The Committee gave consideration to an update on Flooding within Oban as a result
of coastal, fluvial (water course), surface water and combined sewer overflows.  The
report highlighted a localised hotspot at Lochavullin Car Park bounded by Soroba
Road, Tesco and Lochavullin Road and that preventing future flooding would require
significant works, for which there was no funding identified. 
Decision 
The Oban, Lorn and the Isles Area Committee:- 
1. considered and noted the submitted report; 
2. endorsed the proposals by officers to lobby for funding and to explore
external funding opportunities, and 
3. agreed that quarterly progress updates be provided to future meetings
of the Oban, Lorn and the Isles Area Committee. 
(Reference: A report by Executive Director with responsibility for Roads and
Infrastructure Services, dated 10th November 2025, submitted)

Page 6

8. ROADS AND INFRASTRUCTURE UPDATE 
The Committee gave consideration to a report which provided links to the recent
activities of Roads and Infrastructure Services. 
Decision 
The Oban, Lorn and the Isles Area Committee noted the contents of the report. 
(Reference: Report by Executive Director with responsibility for Roads and
Infrastructure Services, dated 30 October 2025, submitted) 
9. AREA COMMITTEE QUARTERLY PERFORMANCE REPORTS – FQ2 2025/26 
The Committee gave consideration to the Area Performance Report for financial
quarter 2 of 2025/26 (July to September 2025) which illustrated the agreed
performance measures for this period. 
Decision 
The Oban, Lorn and the Isles Area Committee noted the performance and
supporting commentary as presented and commended the local planning team on
their exceptional performance in achieving an average 5.1 week determination of
householder planning applications during the FQ2 period. 
(Reference: Report by Executive Director with responsibility for Customer Support
Services, dated 7 November 2025, submitted) 
10. APPOINTMENT TO OBAN & LORN COMMUNITY ENTERPRISE LTD
(ATLANTIS LEISURE) 
The Committee considered a verbal update from the Democratic Services Manager
on this item, which was continued from the September Area Committee meeting. Ms
Stewart advised the Committee on the dates and timings of board meetings and that
they were in person meetings, although the Board may be open to review this on the
basis that there were two categories of Directors, with council appointments being
ex-officio.  Nominations were sought for an additional Member to sit on the Board of
Oban & Lorn Community Enterprise Ltd. 
Decision 
No nomination was forthcoming and it was agreed that the vacancy would remain
unfilled at this time. 
11. CHARITABLE TRUSTS, BEQUESTS AND TRUST FUNDS 
The Committee gave consideration to a report which provided details on proposals
relating to the ongoing management and proposed distribution arrangements for
Charitable Trusts, Bequests and Trust Funds for which the Oban, Lorn and the Isles
Area Committee are Trustees. 
Decision

Page 7

The Oban, Lorn and the Isles Area Committee: 
1. noted the financial position of the Charitable Trusts, Bequests and
Trust Funds as of August 2025; 
2. agreed that the charities and trust funds, that have historically been
awarded to Council Departments and Allied Partners, are awarded on
the basis outlined in paragraph 5.5 and defined within appendix 1; 
3. agreed to make available all unrestricted funds from the Dugald
McPhail Memorial Fund to Roads and Infrastructure and thereafter to
place a moratorium on the fund; 
4. agreed to invite representatives from the Health and Social Care
Partnership to consider submitting an application form to the Miss Flora
McLucas and Miss M M Cameron Bequests; and 
5. noted that the Mrs Mellors Bequest has no identified beneficiaries and
that this fund is subject to ongoing consideration by officers. 
(Reference:  Report by Executive Director with Responsibility for Legal & Regulatory
Support, dated November 2025, submitted) 
12. HEALTH & SOCIAL CARE PARTNERSHIP - PERFORMANCE REPORT FQ1
2025/26 (APRIL- JUNE) 
Consideration was given to the Health and Social Care Partnership Performance
Report for financial quarter 1 of 2025/26 (April to June). 
Decision 
The Oban, Lorn and the Isles Area Committee noted the: 
1. revised suite of 77 Key Performance Indicators within the Integrated Performance
Management Framework for 2025/26; 
2. performance for FQ1 2025/26 (April – June 2025); 
3. Delayed Discharge Sitrep as of 30 Jun 2025, as at Appendix 1 of the report and 
4. latest performance against the National Health & Wellbeing Outcomes and
Ministerial Steering Group Integration Indicators, as at Appendix 2 of the report. 
(Reference: Report by Senior Manager Performance and Improvement, Argyll and
Bute Health and Social Care Partnership, dated 10 December 2025, submitted) 
13. SAKURA CHERRY TREE PROJECT UPDATE 
A report providing an update on the next stage of Argyll and Bute’s Sakura Cherry
Tree Project was before members for information.
Decision

Page 8

Oban, Lorn and the Isles Area Committee noted the contents of the report.
(Report by Executive Director with responsibility for Legal and Regulatory Support,
dated 7 November 2025, submitted) 
14. OBAN, LORN AND THE ISLES AREA COMMITTEE WORKPLAN 
The Oban, Lorn and the Isles Area Committee workplan was before members for
information. 
Decision 
The Oban, Lorn and the Isles Area Committee noted the contents of the workplan. 
(Reference: Oban, Lorn and the Isles Area Committee workplan, dated 10 December
2025, submitted) 
PUBLIC QUESTIONS PART 2
The Chair asked if there were any further questions from the public. 
Mr Frank Roberts, Oban Community Council 
Mr Roberts referred to Mr Strathern’s previous question which mentioned a survey
report that was published about 20 months ago which clearly identified drainage of
surface water and clearance of obstructions from the drains around Lochavullin
Business Park, and questioned whether anything had actually been done on the
results of that report? 
Mr Calder advised that he was not aware of the specifics of the report but his
colleague, Ms Simoes may be in a position to respond.  With regard to road side
verges those were regularly attended to to ensure gullies are running clearly. 
In noting Ms Simoes was not attending at that time, Ms Stewart advised that Ms
Simoes had confirmed that this was not a question she could answer and it would
have to be referred back to Estates and/or Property Services for their input. 
Mr Strathern advised that the report from 20 months ago states that the main drains
have collapsed and/or blocked and he is surprised that no one is aware of this
report.  He continued it is all very well clearing the gullies but the surface water has
no where to run as these main drains are blocked and he has highlighted this for
sometime now. What is required is a high pressure washer to go through the drains
or the road dug up to ascertain how these blockages could be cleared, until this is
done the water cannot go anywhere except back up into business premises. 
Mr Calder advised again that if the question is referring to specific premises that are
rented from the Council, then he is not in a position to respond to that as it does not
fall under the remit of Roads and Infrastructure.   
Mr Phil Hamerton

Page 9

Mr Hamerton asked if the Community Council was to attempt to reconvene a Flood
Resilience Group meeting again, to whom within the Council should the invitation be
sent? 
The Chair advised that the Community Council would be welcome to invite
Councillors directly and as for invitations to Council Officers the best avenue would
be to roadsandinfrastucture@argyll-bute.gov.uk which would then allow the service
to identify the an available person to attend. 
Mr Hamerton then asked does the benefit cost ratio take into account the wider
community of Argyll, particularly the Islands who shop at the supermarkets in the
flood area and recognise the true cost? 
The Chair advised his understanding of how funding is allocated is that residential
property is prioritised. 
Mr Calder agreed with the Chair’s view and stated that he understood that the
economic impact of flooding to the wider community and that was an important point,
but he was unsure how it feeds into the National Flood Fund process.   
Mrs Alison Rennie, Oban Community Council 
Mrs Rennie stated that this would have been a question for Ms Simoes who has now
left the meeting, regarding her earlier statement with reference to the development of
ponds or storage tanks above the business park.  Is anyone aware of the offer of
land from the developers of a large development at Arinagour, South of Oban, where
trees were being planted. 
The Chair advised that there would need to be a detailed study of the best place to
store rainfall, it wasn’t possible to just accept a site just because it was offered, the
site would be required to intercept rainfall.  In his view, the most appropriate
locations to intercept were behind the hospital or alternatively putting in a raised car
park at Lochavullin, with storage below, given nature had suggested that this is
where the water wanted to go. 
Councillor Hume had raised a question earlier in the meeting which Mr Calder had
suggested Ms Simoes, who was not present at the time, may be able to pick up
under the reconvened Public Question Time session.  In Ms Simoes absence he
asked that his question regarding the timescale for opening of the B8035 and
whether this would be in time for 2 main events next year, that had already submitted
through Member Zone, be picked up and responded to as a priority. 
15. JOHN OF LORN BEQUEST FUND AWARD RECOMMENDATIONS 
The Committee gave consideration to a report providing information on the
number of applications that have been received for support from the John of
Lorn Bequest. 
Decision 
The Oban, Lorn and the Isles Area Committee noted the number of awards
made from the John of Lorn Bequest since the last meeting of the Area

Page 10

Committee in September 2025. 
(Reference:  Report by Executive Director with responsibility for Legal and
Regulatory Support dated 10 December 2025, submitted)